Cities Index.
2025 08 19 sr res agmt Staff Report - WCW_RMSD_COR Biosolids Operating Agreement_mp1_rda_ja_FINAL.pdf

Richmond City Council
August 26, 2025

Document
2025 08 19 sr res agmt Staff Report - WCW_RMSD_COR Biosolids Operating Agreement_mp1_rda_ja_FINAL.pdf
Meeting
August 26, 2025
Body
Richmond City Council
Pages
3
Original file
181 KB
Text extracted from the city's file for reading and search. Open the original on pub-richmond.escribemeetings.com. That file is the official record.
Page 1 of 3 ends

August 26, 2025

Public Works

DATE: August 26, 2025
TO: Mayor Martinez and Members of the City Council
FROM:

Daniel Chavarria, PE, Director of Public Works
Robert Armijo, PE, Deputy Director of Public Works / City Engineer
Mary Phelps, Water Resource Division Manager

SUBJECT:

Resolution Approving the Operating Agreement with
West County Wastewater for Joint Biosolids Treatment
and Cost Allocation
FINANCIAL IMPACT: The City’s share of the annual cost for biosolids treatment under the Operating Agreement is $1,743,259
for Fiscal Year 2025–26. This includes Richmond’s 40%
share of capital costs, operations and maintenance, and disposal associated with the new biosolids treatment
process at the West County Wastewater facility. Future
costs will be adjusted annually based on the Consumer
Price Index and actual treatment costs. Funded from the Wastewater Enterprise Fund (Account String: 40322731-
400202).

PREVIOUS COUNCIL
ACTION:

December 17, 2024

STATEMENT OF THE
ISSUE:

The City must enter into a new Operating Agreement with West County Wastewater (WCW) to ensure continued
treatment of biosolids generated at the Richmond
Wastewater Treatment Plant, following the termination of the existing lease for use of WCW’s sludge lagoons. The proposed agreement outlines the long-term cost-sharing, operational responsibilities, and use of WCW’s new
biosolids treatment facilities.

AGENDA
REPORT

Page 2 of 3 ends

August 26, 2025
RECOMMENDED ACTION:

ADOPT a resolution approving the Operating Agreement
between West County Wastewater (WCW) and the City
of Richmond for the treatment of biosolids generated at the Richmond Wastewater Treatment Plant and for the
allocation of associated capital, operations, and disposal costs - Public Works (Mary Phelps 510-621-1269/Robert
Armijo 510-620-5477).

DISCUSSION:

Background
West County Wastewater (WCW) operates the West County Wastewater District Treatment Plant in North Richmond, California (the “WCW Treatment Plant”). The City operates the Richmond Municipal Sewer District (RMSD) Water Pollution Control Plant (the “Richmond Plant”) at Point Richmond. The two plants separately treat wastewater, but some elements of the treatment processes are connected. WCW sends treated wastewater effluent to the Richmond Plant for dechlorination and ocean discharge, and the City sends anaerobically digested sludge from the Richmond Plant to the WCW Treatment Plant for treatment and disposal via an approximately five-mile 6” sludge pipeline that is owned and operated by the City.

Biosolids Handling and Lease Termination
The City entered into a Ground Lease Agreement (“Lease”) with WCW in June 2010 to send biosolids (via pipeline) to WCW’s East Site Sludge Lagoons for treatment and disposal (Attachment 3). That lease was amended in 2017 with an option to renew for an additional term (Attachment 4). A letter was sent to WCW on June 4, 2020, requesting an extension of the Lease for an additional five (5) years. Richmond City Council adopted the extension of the Lease via Resolution 61-20 on June 16, 2020 (Attachments 5 and 6).

The Lease was set to expire on December 31, 2025, unless one or both parties notified the other party of the intent to terminate the lease earlier. West County Wastewater sent the City of Richmond a Lease Termination Letter on August 28, 2023, with their intent to terminate the lease with the City of Richmond effective December 31, 2024 (Attachment 7).

Currently, WCW processes the City of Richmond's sludge byproduct, including digestion and clarification, at WCW’s biosolids ponds. WCW has developed a new biosolids treatment process that will replace the use of the East Site Sludge Lagoons as of August 1, 2025.

Transition to Operating Agreements
Over the past six months, RMSD and WCW staff have been working closely to negotiate the terms and conditions of the Biosolids Processing Operating Agreement

Page 3 of 3 ends

August 26, 2025
(“Operating Agreement”) to replace the expiring lease and support the new treatment process. The cost terms of the Operating Agreement are based on the results of the Carollo Biosolids Treatment Cost of Service Analysis (Attachment 8).

The terms (as agreed by both parties) of the Operating Agreement provide for the capital costs, continued operation, maintenance, and joint use of the WCW assets associated with biosolids processing.

The projected annual cost allocations for Fiscal Year 2025-26 are summarized in the table below:

2025 Costs Organized by Agency WCW City of
Richmond
Proportion of Total Costs (%) 60% 40%
Capital Cost ($/yr) $ 668,644 $ 445,763
O&M Cost ($/yr) $ 764,532 $ 509,688
Disposal/End-Use Cost ($/yr) $1,125,441 $ 787,809
Total $2,558,617 $1,743,259

These costs will increase annually based on the Consumer Price Index (CPI), and any increased operation and maintenance costs associated with the processing of biosolids, as further detailed in the Operating Agreement.

City staff is requesting that the City Council adopt the resolution approving the Operating Agreement between the City of Richmond and West County Wastewater (Attachments 1 and 2).

The fees payable under the Operating Agreement are included in the fiscal year 2025- 26 Wastewater Budget.

DOCUMENTS ATTACHED:

Attachment 1 – Resolution – Biosolids Operating Agreement Attachment 2 – Biosolids Operating Agreement Final
Attachment 3 – Ground Lease Agreement – June 2010
Attachment 4 – Ground Lease Agreement– Amendment 1
Attachment 5 – Resolution 61-20 Ground Lease Amendment 1 Attachment 6 – Ground Lease Agreement – Letter of Intent – Extension Request Attachment 7 – Lease Termination Notice – August 2023
Attachment 8 – Biosolids Treatment Cost Plan

← All documents from this meeting