Cities Index.
Attachment 2 - Bid Report - Terminal 4.pdf

Richmond City Council
October 21, 2025

Document
Attachment 2 - Bid Report - Terminal 4.pdf
Meeting
October 21, 2025
Body
Richmond City Council
Pages
145
Original file
103.0 MB
Text extracted from the city's file for reading and search. Open the original on pub-richmond.escribemeetings.com. That file is the official record.

City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 1 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 2 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 3 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 4 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 5 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 6 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 7 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 8 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 9 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 10 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 11 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 12 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 13 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 14 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 15 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 16 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 17 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 18 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 19 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 20 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 21 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 22 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 23 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 24 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 25 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 26 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 27 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 28 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 29 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 30 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 31 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 32 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 33 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 34 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 35 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 36 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 37 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 38 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 39 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 40 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 41 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 42 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 43 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 44 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 45 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 46 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 47 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 48 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 49 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 50 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 51 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 52 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 53 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 54 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 55 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 56 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 57 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 58 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 59 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 60 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 61 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 62 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 63 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 64 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 65 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 66 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 67 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 68 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 69 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 70 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 71 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 72 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 73 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 74 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 75 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 76 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 77 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 78 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 79 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 80 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 81 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 82 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 83 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 84 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 85 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 86 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 87 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 88 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 89 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 90 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 91 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 92 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 93 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 94 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 95 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 96 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 97 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 98 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 99 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 100 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 101 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 102 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 103 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 104 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 105 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 106 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 107 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 108 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 109 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 110 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 111 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 112 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 113 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 114 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 115 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 116 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 117 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 118 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 119 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 120 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 121 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 122 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 123 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 124 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 125 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 126 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 127 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 128 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 129 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 130 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 131 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 132 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 133 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 134 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 135 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 136 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 137 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 138 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 139 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 140 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 141 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 142 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 143 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 144 of 145 ends

Printed 09/03/2025
PlanetBids
City of Richmond
Long-Term Environmental Monitoring Services - Terminal 4 Wharf, Warehouse, and Piling Removal Project (CD-#06272025), bidding on 08/04/2025 3:00 PM (PDT)

Page 145 of 145 ends

Printed 09/03/2025
PlanetBids

← All documents from this meeting