A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF RICHMOND TO
APPROVE A CONSTRUCTION AGREEMENT WITH BAUMAN LANDSCAPE
AND CONSTRUCTION INC. FOR THE 13TH STREET COMPLETE STREET PROJECT CML-5137(056)
WHEREAS, the City of Richmond is committed to improving pedestrian accessibility and extending the existing Class IV bicycle lane infrastructure through the 13th Street Complete Street Project (CML-5137(056)), which will transform a four-lane arterial street from Harbour Way to Costa Avenue into a multi-modal corridor; and
WHEREAS, the project is supported by the Metropolitan Transportation Commission (MTC) through the One Bay Area Grant 3 (OBAG3) program and closes a critical gap in the City’s active transportation network; and
WHEREAS, the project’s scope of work includes eliminating one vehicular travel lane in each direction to create continuous directional cycle tracks, widening sidewalks where feasible, and constructing bus stop and crosswalk improvements throughout the corridor; and
WHEREAS, this project will further close an active transportation gap between the Active Transportation Program (ATP)–funded Rumrill Boulevard Complete Streets project in the City of San Pablo and the ATP-funded Yellow Brick Road project in the City of Richmond; and
WHEREAS, the City publicly solicited bids for the project via BidsOnline on September 19, 2025, and received five (5) submissions; bids were opened on October 16, 2025; and
WHEREAS, Bauman Landscape and Construction Inc. was determined to be the lowest responsive and a responsible bidder at an amount of $3,993,481.50 following a comprehensive review of all submissions; and
WHEREAS, the contractor is responsive because its bid meets all requirements of the project and the terms and conditions of the contract, and responsible because it possesses the qualifications, experience, reputation, facilities, and financial resources necessary to perform the work; and
WHEREAS, City staff recommends establishing a construction contingency in the amount of $400,000 (10%), to be maintained at the budget level and available for change orders approved by the Director of Public Works for a total not-to-exceed contract amount of $4,393,481.50 ; and
NOW THEREFORE, BE IT RESOLVED by the City Council of the City of Richmond, as follows:
Section 1: The City Council hereby approves a Construction Agreement with Bauman Landscape and Construction Inc. for the 13th Street Complete Street Project (CML-5137(056)) in a base contract amount not to exceed $3,993,481.50.
Section 2: The City Council hereby establishes a construction contingency in the amount of $400,000 (10%) and authorizes the Director of Public Works to approve change orders, as needed, within this contingency amount for a total not-to-exceed contract amount of $4,393,481.50.
Section 3: This resolution shall take effect immediately upon its passage.
**********************
Reso. No. xx-25
DocID #59724v1
I hereby certify that the foregoing Resolution of the City Council of the City of Richmond was duly passed and adopted at a meeting thereof held January xx, 2026 by the following vote:
AYES:
NOES:
ABSTENTIONS:
ABSENT:
CLERK OF THE CITY OF RICHMOND
(SEAL)
Approved:
Mayor
Approved as to form:
City Attorney