TASK
city of
• VEOLIA AUTHORIZATION Hiel
2024-25 Grade 5 RAA Line Replacement Project - Ph 1 - Change Order 5 Date: April 14, 2025
Activity Classification
(Check applicable)
VWNA Project #: RE.1660
Administration
Engineering
Planning
Design chand
Construction Proposed by:

Construction Chandrasekar Ven a dian Velia Water. West Operating Services anitary Sewe nels
Storm Sewer Reviewed by:

Sanitary P.S Mary Phelps, Authorized City Dept. Rep. (PO verification) Storm P.S
Wastewater Reviewed by:

Other (specify below) City of Richmont, Fisange Departmen Approved by:

Daniel Chavarria-
City of Richmond, Public Works Direce Lity Evgiwer
Approval Date: Deputy
Original Line Item Approved Cost: S 1,755,800.00
Approved Markup/MarginS 289,707.00
Previously authorized change orders $ 3,152,230.12
Change Order 5$ 865,974.00
Approved Markup/MarginS 142,885.71
Previously Authorized Amount: $5,197,737.12 Total Authorized Amt.: S 6,206,596.83 Scope of Services
In this TA, nine (9) line segments are added per the City's request. Five of the lines among them are easement lines on Yuba St. and Carlston St. for which the City has provided easement maps so the right of entry signatures from the residents are not needed. This TA also includes a credit to the City as Line Segment #11 was properly abandoned The above mentioned costs are summarized on page 2. Further, due to the added lines, additional budget and authority for testing, ESDC, and outreach have been requested.

The total additional authority requested is $1,008,859.71 which includes a 16.5% Veolia markup and brings the total project amount authorization to $6,206,596.83.
2024-25 Grade 5 RAA Line Repl. - Phase I - CO5 Veolia Markup Velia Markup Bids/Estim. SUBTOTAL 16.50% 9.00% TOTAL
APB General Engineering 1,690,800 1,690,800 278,982 1,969,782 Change Order 1a 208,608 208,608 34,420 243,028
Change Order 1b (2,540) (2,540) (419) (2,959)
V.W.Housen 40,000 40,000 6,600 46,600
Questa 25,000 25,000 4,125 29,125
J Majors & Associates (CO 1c) 19,240 19,240 3,175 22,415 Change Order 2 206,296 206,296 34,039 240,335
Change Order 3(@16.5%) see pg. 2 1,552,356 1,552,356 256,139 1,808,495 Change Order 3(@9%) 25,780 25,780 2,320 28,100
Addl V.W. Housen (ESDC) CO3 40,000 40,000 6,600 46,600
Addl Questa (testing) CO3 15,000 15,000 2,475 17,475
Addl J Majors & Assoc. (public outreach) 12,220 12,220 2,016 14,236 Change Order 4 @ 9% 673,858 673,858 60,647 734,505
Change Order 5 820,974 820,974 135,461 956,435
Add'l Costs - Testing, ESDC & Outreach 45,000 45,000 7,425 52,425 TOTAL 5,372,592 5,372,592 771,037 62,967 6.206,597
Attachments
Copy of APB General Engineering Proposals

TASK AUTHORIZATION
• VEOLIA City of
Richmon
(PAGE 2 OF 2)
2024-25 Grade 5 RAA Line Replacement Project - Ph I - Change Order 5 Date: 04/14/25 VWNA Project #: RE: 1660
Scope of Services
(CONT.)
2024-25 GRADE 5 RAA LINE REPLACEMENT - CHANGE ORDER 5 REQUEST SUMMARY PCO #21 H9SF295_H9MH1712 Credit for Line Segment #11 - 750 Bissell Ave. -$6,490.00 PCO #22 J13SF193_J13MH278 Yuba Street $127,875.00
PCO #23 J12MH503_|12MH1155 34th St./Clinton Ave. $139,514.00 PCO #24 E14MH464_E14MH1981 S. 59th Street/Bayview Ave. $148,063.00 PCO #25 K9MH1653_J9MH2708 8th Street $121,283.00
PCO #26 G11MH1228_G10MH15tS. 22nd Street/Cutting Blvd. $93,241.00 PCO #27 I13SF73_|13SF74 Carlston St. Easement #1 $27,038.00 PCO #28 |13SF74_H13MH116 Carlston St. Easement #2 $101,228.00 PCO #29 H13MH118_H13MH119 Carlston St. Easement #3 $26,492.00 PCO #30 H13MH119_H13MH117 Carlston St. Easement #4 $42,730.00 Subtotal $820,974.00
Veolia Markup at 16.5% $135,460.71
TOTAL $956,434.71

Page 2 ends

APB

GENERAL ENGINEERING
Lic. 1038184
Project: 2024-2025 RAA Line Segment Replacement Potential Change Order No.21 Date: March 3rd, 2025
Owner: City of Richmond/Veolia Phone: (925) 989-1453
Contractor: APB General Engineering Address: 2721 Kevin Rd.

San Pablo, CA 94806
Request the following change to be made to the contract:

Description of Change
1) Potholing and dye testing operations showed that the line segment (H9SF295 to H9MH1712) as no active lateral connections. Per the response to RFI #015, we are to properly abando oth line segment and the existing penetration at downstream MH. End of the line cleano was actually a MH and needed to be removed and concrete restored. Credit for pipe material and a half a days' worth of labor/equipment to pull the pipe.

Reason for Change:
1) Response to RFI #015.

Requested by: APB General Engineering
Pricing Data: (-$6,490)
Contract Time: 2 Working Days
The Owner and the Contractor hereby agree that this change order constitutes full and mutual accord and she Contin for al e hali cops, and til and edied te adi semen no th coping this change arder, to waive all rights to file claim with respect to any difficulties arising from, or as a result of this change.

APPROVED:

Engineer
Owner
APB

GENERAL ENGINEERING
Lic. 1038184
Project: 2024-2025 RAA Line Segment Replacement Potential Change Order No.22 Date: March 3rd, 2025
Owner: City of Richmond/Veolia Phone: (925) 989-1453
Contractor: APB General Engineering Address: 2721 Kevin Rd.

San Pablo, CA 94806
Request the following change to be made to the contract:

Description of Change:
1) Remove and replace line segment J13SF193 to J13MH278, approximately 354, with 8" HDPE DR 17. Proposed cost includes all sheeting/shoring, all excavations for all insertion pits, sewer lateral connections, 1 new manhole, utility potholing, engineering/design, landscape/yard restoration and post CCTV. All work to follow City of Richmond Standard Specifications.

Reason for Change:
1) Added pipe replacement footage as requested per City of Richmond/Veolia.

Requested by: APB General Engineering
Pricing Data: $127,875
Contract Time: 5 Working Days
The Owner and the Contractor hereby agree that this change order constitutes full and mutual accord and satisfaction for all time, all costs, and all impacts related to this revision. In accepting this change order, the Contractor agrees that it represents a full and equitable adjustment to the Contract and further agrees to waive all rights to file claim with respect to any difficulties arising from, or as a result of this change.

APPROVED:

Engineer
Owner
APB

GENERAL ENGINEERING
Lic. 1038184
Project: 2024-2025 RAA Line Segment Replacement Potential Change Order No.23 Date: March 19th, 2025
Owner: City of Richmond/Veolia Phone: (925) 989-1453
Contractor: APB General Engineering Address: 2721 Kevin Rd.

San Pablo, CA 94806
Request the following change to be made to the contract:

Description of Change:
1) Remove and replace line segment J12MH503 to I12MH1155, approximately 382, with 8" Reason for Change:
1) Added pipe replacement footage as requested per City of Richmond/Veolia.

Requested by: APB General Engineering
Pricing Data: $139,514
Contract Time: 3 Working Days
The Owner and the Contractor hereby agree that this change order constitutes full and mutual accord and she Conta for ale halt er, and fil and elaid te distino the Coping this change arder, to waive all rights to file claim with respect to any difficulties arising from, or as a result of this change.

APPROVED:

Engineer
Owner
APB

GENERAL ENGINEERING
Lic. 1038184
Project: 2024-2025 RAA Line Segment Replacement Potential Change Order No.24 Date: March 19th, 2025
Owner: City of Richmond/Veolia Phone: (925) 989-1453
Contractor: APB General Engineering Address: 2721 Kevin Rd.

San Pablo, CA 94806
Request the following change to be made to the contract:

Description of Change:
1) Remove and replace line segment E14MH464 to E14MH1981, approximately 340, with 8" HDPE DR 17. Proposed cost includes all sheeting/shoring, all excavations for all insertion pits, sewer lateral connections, utility potholing, engineering/design, traffic control, AC restoration and post CCTV. All work to follow City of Richmond Standard Specifications.

Reason for Change:
1) Added pipe replacement footage as requested per City of Richmond/Veolia.

Requested by: APB General Engineering
Pricing Data: $148,063
Contract Time: 3 Working Days
The Owner and the Contractor hereby agree that this change order constitutes full and mutual accord and satisfaction for all time, all costs, and all impacts related to this revision. In accepting this change order, the Contractor agrees that it represents a full and equitable adjustment to the Contract and further agrees to waive all rights to file claim with respect to any difficulties arising from, or as a result of this change.

APPROVED:

Engineer
Owner
APB

GENERAL ENGINEERING
Lic. 1038184
Project: 2024-2025 RAA Line Segment Replacement Potential Change Order No.25 Date: March 19th, 2025
Owner: City of Richmond/Veolia Phone: (925) 989-1453
Contractor: APB General Engineering Address: 2721 Kevin Rd.

San Pablo, CA 94806
Request the following change to be made to the contract:

Description of Change:
1) Remove and replace line segment K9MH1653 to J9MH2708, approximately 335, with 8" HDPE DR 17. Proposed cost includes all sheeting/shoring, all excavations for all insertion pits, sewer lateral connections, utility potholing, engineering/design, traffic control, AC restoration and post CCTV. All work to follow City of Richmond Standard Specifications.

Reason for Change:
1) Added pipe replacement footage as requested per City of Richmond/Veolia.

Requested by: APB General Engineering
Pricing Data: $121,283
Contract Time: 3 Working Days
The Owner and the Contractor hereby agree that this change order constitutes full and mutual accord and satisfaction for all time, all costs, and all impacts related to this revision. In accepting this change order, the Contractor agrees that it represents a full and equitable adjustment to the Contract and further agrees to waive all rights to file claim with respect to any difficulties arising from, or as a result of this change.

APPROVED:

Engineer
Owner
APB

GENERAL ENGINEERING
Lic. 1038184
Project: 2024-2025 RAA Line Segment Replacement Potential Change Order No.26 Date: March 19th, 2025
Owner: City of Richmond/Veolia Phone: (925) 989-1453
Contractor: APB General Engineering Address: 2721 Kevin Rd.

San Pablo, CA 94806
Request the following change to be made to the contract:

Description of Change:
1) Remove and replace line segment G1 1MH1228 to G1OMH1584, approximately 250, with 8" HDPE DR. 17. Proposed cost includes all sheeting/shoring, all excavations for all insertion pits, sewer lateral connections, utility potholing, engineering/design, traffic control, AC restoration and post CCTV. All work to follow City of Richmond Standard Specifications.

Reason for Change:

Added pipe replacement footage as requested per City of Richmond/Veolia.

Requested by: APB General Engineering
Pricing Data: $93,241
Contract Time: 3 Working Days
The Owner and the Contractor hereby agree that this change order constitutes full and mutual accord and satisfaction for all time, all costs, and all impacts related to this revision. In accepting this change order, the Contractor agrees that it represents a full and equitable adjustment to the Contract and further agrees to waive all rights to file claim with respect to any difficulties arising from, or as a result of this change.

APPROVED:

Engineer
Owner
Carlston Esmt #1
APB

GENERAL ENGINEERING
Lic. 1038184
Project: 2024-2025 RAA Line Segment Replacement Potential Change Order No.27 Date: March 27th, 2025
Owner: City of Richmond/Veolia Phone: (925) 989-1453
Contractor: APB General Engineering Address: 2721 Kevin Rd.

San Pablo, CA 94806
Request the following change to be made to the contract:

Description of Change:
1) Remove and replace line segment I13SF73 to I13SF74, approximately 50', with 6" HDPE DR

17. Proposed cost includes all sheeting/shoring, all excavations for all insertion pits, 1 sewer lateral connection, LH to MH conversion, utility potholing, engineering/design and post CCTV. All work to follow City of Richmond Standard Specifications. *Per the PACF reports provided, there appears to have no live lateral connections. Same cost if we are directed to abandon line segment.

Reason for Change:
1) Added pipe replacement footage as requested per City of Richmond/Veolia.

Requested by: APB General Engineering
Pricing Data: $27,038*
Contract Time: 3 Working Days
The Owner and the Contractor hereby agree that this change order constitutes full and mutual accord and sai Contion for ales hall represend a mi acts related to this teminion. the ceptin ahid hange ander, to waive all rights to file claim with respect to any difficulties arising from, or as a result of this change.

APPROVED:

Engineer
Owner
Carlston Esmt #2
APB

GENERAL ENGINEERING
Lic. 1038184
Project: 2024-2025 RAA Line Segment Replacement Potential Change Order No.28 Date: March 27th, 2025
Owner: City of Richmond/Veolia Phone: (925) 989-1453
Contractor: APB General Engineering Address: 2721 Kevin Rd.

San Pablo, CA 94806
Request the following change to be made to the contract:

Description of Change:
1) Remove and replace line segment I13SF74 to HI3MH116, approximately 316', with 6" HDPE DR 17. Proposed cost includes all sheeting/shoring, all excavations for all insertion pits, sewer lateral connections, L.H to MH converstion, utility potholing, engineering/design and post CCTV. All work to follow City of Richmond Standard Specifications. *Per the PACP reports provided, CCTV efforts were abandoned at 316' due to obstructions.

Additional costs and delay may apply if line segment is longer and/or additional lateral connections are encountered after the point of abandonment.

Reason for Change:
1) Added pipe replacement footage as requested per City of Richmond/Veolia.

Requested by: APB General Engineering
Pricing Data: $101,228*
Contract Time: 3 Working Days
The Owner and the Contractor hereby agree that this change order constitutes full and mutual accord and satisfaction for all time, all costs, and all impacts related to this revision. In accepting this change order, he Contractor agrees that it represents a full and equitable adjustment to the Contract and further agrees to waive all rights to file claim with respect to any difficulties arising from, or as a result of this change.

APPROVED:

Engineer
Owner
Carlston Esmt #3
APB

GENERAL ENGINEERING
Lic. 1038184
Project: 2024-2025 RAA Line Segment Replacement Potential Change Order No.29 Date: March 27th, 2025
Owner: City of Richmond/Veolia Phone: (925) 989-1453
Contractor: APB General Engineering Address: 2721 Kevin Rd.

San Pablo, CA 94806
Request the following change to be made to the contract:

Description of Change:
1) Remove and replace line segment H13MH118 to H13MH119, approximately 84', with 6" HDPE DR 17. Proposed cost includes all sheeting/shoring, all excavations for all insertion its, sewer lateral connections, utility potholing, engineering/design and post CCTV. A ork to follow City of Richmond Standard Specifications. *Per the PACP reports provide CCTV shows only one lateral on this line segment, and it is about 2.5' from the downstream MH. We can eliminate this line segment and put the lateral directly into MH or we can shorten the entire run. APB to bill the entirety of the PCO regardless of which option is Reason for Change:
1) Added pipe replacement footage as requested per City of Richmond/Veolia.

Requested by: APB General Engineering
Pricing Data: $26,492*
Contract Time: 3 Working Days
The Owner and the Contractor hereby agree that this change order constitutes full and mutual accord and APPROVED:

Engineer
Owner
APB Carlston Esmt #4

GENERAL ENGINEERING
Lic. 1038184
Project: 2024-2025 RAA Line Segment Replacement Potential Change Order No.30 Date: March 27th, 2025
Owner: City of Richmond/Veolia Phone: (925) 989-1453
Contractor: APB General Engineering Address: 2721 Kevin Rd.

San Pablo, CA 94806
Request the following change to be made to the contract:

Description of Change:
1) Remove and replace line segment HI3MH119 to HIЗMH117, approximately 117°, with 6" HDPE DR 17. Proposed cost includes all sheeting/shoring, all excavations for all insertion pits, sewer lateral connections, utility potholing, traffic control, engineering/design and post CCTV. All work to follow City of Richmond Standard Specifications.

Reason for Change:
1) Added pipe replacement footage as requested per City of Richmond/Veolia.

Requested by: APB General Engineering
Pricing Data: $42,730*
Contract Time: 3 Working Days
The Owner and the Contractor hereby agree that this change order constitutes full and mutual accord and satisfaction for all time, all costs, and all impacts related to this revision. In accepting this change order, the Contractor agrees that it represents a full and equitable adjustment to the Contract and further agrees to waive all rights to file claim with respect to any difficulties arising from, or as a result of this change.

APPROVED:

Engineer
Owner
TASK
City of
• VEOLIA AUTHORIZATION
[2024-25 Grade 5 RAA Line Replacement Project - Phase 1 - Change Order 4 Date: February 11, 2025
VWNA Project #: RE.1660
Administration
Enginer laning
Design AL short
Construction
Construction Proposed by Chandraseka Vergelraman, Vedia Water West Operating Services Reviewed by: lars
Jeffrey Barioh, Aulhorized City Dept. Rep. (PO verification) Wastewater Reviewed by:

Other (specify below)
Approved by:

Daniel Chavarria
City of Richmond, Public Works Director
3/6/2025
Approval Date:

Original Line Item Approved Cost: $ 1,755,800.00
Approved Markup/MarginS 289,707.00
Previously authorized change orders S 2,417.724.90
Change Order 4 S 673,858.00
Approved Markup/MarginS 60,647.22
Previously Authorized Amount: $4,463,231.90 Total Authorized Amt.: $ 5,197,737.12 Scope of Services
Four line segments on the 2024-2025 Grade 5 RAA Project have been identified as shallow in depth, lacking sufficient coverage to comply with the City's standard specifications. This situation necessitates the use of a stronger pipe material compared to the originally paine HOPE. To adress this changed condition, the use of Ductle Iron Pipe (DIP) with ceramic PA01 lining was proposed to the Gily The total additional authority requested is $734,505.22 which includes a 9% Veolia markup and brings the total project amoun authorization to $5,197,737.12
2024-25 Grade 5 RAA Line Repl. - Phase I - CO4 Veolia Markup Veolia Markup Bids/Estim. SUBTOTAL 16.50% 9.00% TOTAL
APB General Engineering 1,690,800 1,690,800 278,982 1,969,782 Change Order 1a 208,608 208,608 34,420 243,028
Change Order 1b (2,540) (2,540) (419) (2,959)
V.W.Housen 40,000 40,000 6,600 46,600
Questa 25,000 25,000 4,125 29,125
J Majors & Associates (CO 1c) 19,240 19,240 3,175 22,415 Change Order 2 206,296 206,296 34,039 240,335
Change Order 3 (@ 16.5%) see pg. 2 1,552,356 1,552,356 256,139 1,808,495 Change Order 3 (@ 9%) 25,780 25,780 2,320 28,100
Addl V.W. Housen (ESDC) CO3 40,000 40,000 6,600 46,600
Addl Questa (testing) CO3 15,000 15,000 2,475 17,475
Addl J Majors & Assoc. (public outreach) 12,220 12,220 2,016 14,236 Change Order 4@9% 673,858 673.858 60,647 734,505
TOTAL 4,506,618 4,506,618 628,152 62,967 5,197,737
Attachments
Copy of APB General Engineering Proposals
TASK
VEOLIA AUTHORIZATION City of
(PAGE 2 OF 2) Biolore
WATER
2024-25 Grade 5 RAA Line Replacement Project - Phase I - Change Order 4 Date: February 11, 2025 VWNA Project #: RE: 1660
Scope of Services
(CONT.)
2024-25 GRADE 5 RAA LINE REPLACEMENT - CHANGE ORDER REQUEST SUMMARY - Ductile Iron Pipe replacement Approximate length (linear feet)
PCO #17 F8SF202_F7MH2732 Line Segment #16 - 407 Nevada Ave. $ 214,246.00 Credit for the Original Line Item 316 If $ (61,048.00)
PCO #18 G7MH743_F7MH745 Line Segment #18 - Terrace Ave. 476 If $ 299,124.00 Credit for the Original Line Item $ (90,928.00)
PCO #19 G7MH2736_G7MH668 Line Segment #23 - Scenic Ave. 221 If $ 160,307.00 Credit for the Original Line Item $ (36,610.00
PCO #20 G7SF234_G7H2736 Line Segment #24 - Scenic Ave. 2 410 If $ 270,972.00 Credit for the Original Line Item $ (82,205.00)
Subtotal $ 673,858.00
Veolia Markup at 9% $60,647.22
TOTAL $ 734,505.22

Page 2 ends

PENDING W/ THE CITY AS OF 2/11/25
TASK
City of
• VEOLIA AUTHORIZATION Maclamor
2024-25 Grade 5 RAA Line Replacement Project - Phase 1 - Change Order 3 Date: February 7, 2025
ctivity Classificatio
heck applicabl
VWNA Project #: RE.1660
Administration
Engineering
Planning
Design
Construction
Construction Proposed by: Chandrasekar Venkaraman, Veila Water West Operating services anitary Sew X
torm Sew Reviewed by:

Sanitary P.S. Jeffrey Barich, Authorized City Dept. Rep. (PO verification) Wastewaterom P.S. Reviewed by:

City of Richmond, Finance Department
Other (specify below)
Approved by:

Daniel Chavarria
City of Richmond, Public Works Director
Approval Date:

Original Line Item Approved Cost: S 1,755,800.00
Approved Markup/Margin$ 289,707.00
Previously authorized change orders S 502,818.66
Change Order 3S 1.645,356.00
Approved Markup/MarginS 269,550
Previously Authorized Amount: $2,548,326.00 Total Authorized Amt.:$ 4,463,231.90 Scope of Services
The original scope for the 2024-25 Grade 5 RAA Replacement Project - Phase I was to replace (24) pipelines with an approximate combined length of 7,191 lineal feet in the City of Richmond. Since Construction began, however, two factors have come into play: (1) changed conditions; and (2) added lines (scope). The project has already seen a TA for Change Order 1 to add I10SF827_110MH2277 (476 If) and Change Order 2 to add I13MH48_|13SF893 (522 If). As construction continues, and in order to meet the Baykeeper requirement of completing two (2) miles of pipe each year, additional lines have been added. This TA for Change Order 3 is comprised of thirteen (13) components resulting primarily from either added lines from the City or changed conditions. The thirteen components are summarized on page 2. With the added lines totaling over 3k If, the total linear feet for the project becomes 11,760 If, which is 2.23 miles and puts the City is good standing with the Baykeeper requirements. Further, due to the added lines, additional budget and authority for testing, ESDC, and outreach have been requested. The total additional authority requested is $1,914,906.24 which includes Veolia's markup and brings the total project amount authorization to $4,463,231.90. 2024-25 Grade 5 RAA Line Repl. - Phase I - CO3 Veolia Markup Veolia Markup Bids/Estim.SUBTOTAL16.50%9.00%TOTAL
APB General Engineering 1,690,800 1,690,800 1,969,782
Change Order 1a 208,608 208,608 34,420 243,028
Change Order 1b (2,540) (2,540) (419) (2,959)
V.W.Housen 40,000 40,000 6,600 46,600
Questa 25,000 25,000 4,125 29,125
J Majors & Associates (CO1) 19,240 19,240 3,175 22,415
Change Order 2 206,296 206,296 34,039 240,335
Change Order 3 (@ 16.5%) see pg. 2 1,552,356 256,139 1,808,495 Change Order 3 (@9%) 25,780 2,320 28,100
Add'l V.W. Housen (ESDC) 40,000 6,600 46,600
Add'i Questa (testing) 15,000 2,475 17,475
AddlJ Majors & Assoc. (public outreach) 12,220 2,016 14,236 IOTAL 3,832,760 3,832,760 628,152 2,380,232
Attachments
Copy of APB General Engineering Proposals and other backup TASK
VEOLIA AUTHORIZATION City of
(PAGE 2 OF 2) Mielame
WATER
2024-25 Grade 5 RAA Line Replacement Project - Phase I - Change Order 3 Date: February 7, 2025 VWNA Project #: RE:1660
Scope of Services
(CONT.)
Finally, the Substantial Completion date has been moved to 05/01/2025, and Final Completion has been moved to 05/31/2025.

Veolia mark-up
2024-25 GRADE 5 RAA LINE REPLACEMENT - CHANGE ORDER REQUEST SUMMARY % (per City's approval)
PCO #3 H12MH263_H12MH268 3400 Nevin Ave - Added Intermediate Manhole $ 9,600.00 16.5% PCO #4 112MH605_|12MH602 637 41st St - Added Intermediate Manhole $ 9,600.00 16.5% PCO #5 F10SH405_F10MH1549 1319 Marina Way South - Line abandoned properly. Credit for pipe and labor $ (4,850.00) 16.5% PCO #7 Per RFI #13 ($-7,500) credit offset by chipping existing M/H and connect HDPE pipe +$4,960 $ (2,540.00) 16.5% PCO #8 G11SF941_G11MH1223 2315 Cutting Blvd. - Line abandoned properly. Credit for pipe and labor $ (2,610.00) 16.5% PCO #9 I13MH48_|13SF893 516 McLaughlin - Extend line seg. by approx. 20 If and unforeseen concrete plug $ 25,780.00 9.0% PCO#10 I12SF641_H12MH262 ADDED LINE - 35th Street bet. Barrett Ave. and Nevin Ave. (add'l 470 lt) $ 204,620.00 16.5% PCO #11 I8MH938_I8MH988 ADDED LINE - B Street bet. Barrett Ave and Nevin Ave (add'l 577 If) $ 231,980.00 16.5% PCO #12 K12MH581_K12MH582 ADDED LINE - Moran Ave. (addl 601 If) $ 222,274.00 16.5% PCO#13 J11H1891_11H1892 ADDED LINE - Lincoln Ave. bet. 26th & 28th Street (add 624 In) $ 242,720.00 16.5% PCO #14 J12SF626_K12MH96 ADDED LINE - 32nd Street & McBryde Ave. (addl 536 If) $ 233,038.00 16.5% PCO #15 I10SF820_110MH2295 ADDED LINE - 18th Street & Barrett Ave. (add'l 472 If) $ 217,974.00 16.5% PCO#16 I12SF649_H12MH599 ADDED LINE - 42nd Street & Barrett Ave. (add'l 478 If) $ 190,550.00 16.5% TOTAL CHANGE ORDER 3 (Const.) $ 1,578,136.00
Breakdown of Markup $ 1,552,356.00 16.50%
$ 25,780.00 9%

Page 2 ends

TASK
AUTHORIZATION City of
• VEOLIA Maelmon
2024-25 Grade 5 RAA Line Replacement Project - Phase I - Change Order 2 Date: December 30, 2024
VANA Project #: TBD
Administration
Engineering
Planning
Design
Construction struction Proposed by drasekar Venkalraman, Veolia Water West Operaling Servicer Sanitary Sewer Marys
Storm Sewer Reviewed by:

Jeffrey Barich, AutHorized City Dept. Rep. (PO veriflation) Wastewater Reviewed by:

City of Richmond, Finance Departmeny
Other (specify below)
Approved by:

Robert Armijo Dandel Chavarria
City of Richmond, Depuly Public Works Dir./City Engineer 01-02-2025
Approval Date:

Original Line Item Approved Cost: $ 1,755,800.00
Approved Markup/Margin $ 289,707.00
Previously authorized change orders 262,483.82
Change Order 2 S 206,296.00
Approved Markup/Margin 34,038.84
Previously Authorized Amount: $2,307,990.82 Total Authorized Amt.: 2,548,326 Scope of Services
Line segment 113MH48 - I13SF893 was scheduled to be replaced as part of 2022-23 Grade 5 RAA project back in 2023, but could not be completed as the City was not able to complete the easement process. In the last several months, Veolia received numerous service calls in relation to this line segment, to which Veolia responded by cleaning from both sides of the line, but at some point could not go go more than 10 feet as the line appears to be collapsed. Velia held a meeting with the City on December 12 to discuss options for a permanent fix nd presented a proposal to replace the line on December 16. On December 30, the City gave Veolia direction to submit a TA for this wor ising APB as the general contractor under the current Grade 5 RAA projec he total authorization amount of this Change Order 1 TA is $240,335, which includes Velia's 16.5% markup for added scope. This bring le total project amount authorization to $2,548,32l
2024-25 Grade 5 RAA Line Repl. - Phase 1 - CO1 Veolia Markup Bids/Estim. SUBTOTAL 16.50% TOTAL
APB General Engineering 1,690,800 1,690,800 278,982 1,969,782 PCO 1 208,608 208,608 34,420 243,028
PCO 2 (2,540) (2,540) (419) (2,959)
V.W.Housen 40,000 40,000 6,600 46,600
Questa 25,000 25,000 4,125 29,125
J Majors & Associates 19,240 19,240 3,175 22,415
PCO 3 206,296 206.296 34,039 240,335
TOTAL 2,187.404 2,187,404 360,922 2,548,326
Attachments
Copy of APB General Engineering Proposal
TASK
AUTHORIZATION City of
• VEOLIA
2024-25 Grade 5 RAA Line Replacement Project - Phase I - Change Order 1 Date: November 4, 2024
Activity Classification
(Check applicable)
VWNA Project #: TBD
Administration
Engineering
Planning
Design handhase
Construction
Construction Proposed by Chandrasekar Venkatraman, Veolia Water West Oper, Services Sanitary Sewer
Storm Sewer Reviewed by:

Jeffrey Balich, Authorized City Dept. Rep. (PO verificatior Reviewed by: Resolution 87-24 adopted 07/02/2024. CO within budget City of Richmond, Finance Department
Other (specify below)
Approved by: see brice 7 peyes - authieatin
Robert Armijo
City of Richmond, Deputy Public Works Dir./City Engineer Approval Date: 12-16-24
Original Line Item Approved Cost: 1.755,800.00
Approved Markup/Margin 289,707.00
Change Order 225,308.00
Approved Markup/Margin 37.175.82
Previously Authorized Amount: $2,045,507.00 Total Authorized Amt.: 2,307,991 Scope of Services
Per the City's direction, line segment /10SF827_|10MH2277 (20th Street between Nevin Ave. and Barrett Ave.) is to be added to the project as additional scope. The pipe segment is approximately 476 feet in length and will be replaced along with two (2) new manholes. Also, the Contractor, APB General Engineering, has requested 15 days to be added to the project time which will move Substantial Completion from November 30, 2024 to December 15, 2024; and Final Completion will be January 14. 2025. Please refer to the PCO1 documentation attached.

Per RFI #1, the existing 36" manhole is to remain in place. This credit change to the City accounts for the manhole work which is removed from the scope. Please refer to the attached PCO2 documentation.

Additionally, and also per the City's direction, Veolia is to contract directly with J Majors and Associates for outreach needs on the project including distributing notification flyers prior to contractor work, securing signatures from residents at three designated easement addresses, and preparing and printing notification and easement letters for signatures. See attached proposal from Jacqueline Majors.

The total authorization amount of this Change Order 1 TA is $262,483.82, which includes Velia's 16.5% markup for added scope. This brings the total project amount authorization to $2,307,991 2024-25 Grade 5 RAA Line Repl. - Phase I - CO1 Veolia Markup Bids/Estim. SUBTOTAL 16.50% TOTAL
APB General Engineering 1,690,800 1,690,800 278,982 1,969,782 PCO 1 208.608 208.608 34.420 243.028
PCO 2 (2.540) (2,540) (419) (2.959)
V.W.Housen (design support) 40,000 40,000 6,600 46,600
Questa (testing) 25,000 25,000 4,125 29,125
J Majors & Associates (outreach) 19,240 19.240 3.175 22.415 TOTAL 1.981.108 1,981,108 326,883 2.307.991
Attachments
Copy of APB General Engineering PCOs 1&2
J Majors and Associates Proposal
signature: ba 10,22 423757
Email: [email protected]
TA -2024-25 Grade 5 RAA Change Order 1
signed by Veolia
Final Audit Report 2024-12-16
Created: 2024-12-16
By: Jeffrey Barich ([email protected])
Status: Signed
Transaction ID: CBJCHBCAABAAwTwV5Fi8eixMv5xYPT03gs7sfcnGUx95 "TA -2024-25 Grade 5 RAA Change Order 1 signed by Veolia" H istory
Document created by Jeffrey Barich ([email protected]) 2024-12-16 - 10:18:32 PM GMT
- Document emailed to Daniel Chavarria ([email protected]) for signature 2024-12-16 - 10:18:42 PM GMT
Email viewed by Daniel Chavarria ([email protected]) 2024-12-16 - 10:19:20 PM GMT
oo Document e-signed by Daniel Chavarria ([email protected]) Signature Date: 2024-12-16 - 10:24:13 PM GMT - Time Source: server Agreement completed.
2024-12-16 - 10:24:13 PM GMT
Adobe Acrobat Sign
TASK
AUTHORIZATION ciry of
VEOLIA
WATER
2024-25 Grade 5 RAA Line Replacement Project - Phase I
Dale: May 29. 2024
Ally capelication
VWNA Project #: TBD
Administration
Engineering Proposed by:

Planning
Design
Construction Reviewed by:

Construction Rodrigo Vignau, Vella Waley West Operay)g-services Sanitary Sewer
Storm Sewer Reviewed by: Marix
Sanitary P.S Mary Phelps, Water Resource Division Manager Storm P.S
Waslowater Reviewed by: Resoluton 87/fadated 7/24
City of Richmond, Finance Deprimphl/Funding Soulco
Other (specify below)
Approved by:

Daniel Chavarria
City of Richmond, Direcior of Public Works
Approval Dale: 05/30/2024
Original Line Item Approved Cost: S 1,755,800.00
Approved Markup/MarginS 289,707.00
Prevlously Authorized Amount: $0.00 Total Authorized Amt.:: 2,046,507.00 Scope of Services
The 2023-24 Grade 5 RAA Replacement Project - Phase I replaces (24) pipelines with an approximate combined length of 7,191 lineal feet. This task authorization is submitted based on direction provided by the City of Richmond to perform the following full line replacements:

The pipe segments to be rehabilitaled for this project are identified in Scope of Work Attachment A (see altached). The work will include replacement of deteriorated sewer pipe segments within the collection system using pipe bursting or open cut as discussed further below, including installing new manholes where indicaled on Attachment A. For pipe replacement work, pipe bursting is the preferred method followed by open cut. The Contractor shall conduct a pre-CCTV to locate and reinstate laterals. A complete NASSCO graded post-construction CCTV survey of the entire line segment (manhole to manhole) shall be completed upon completion of the work (no later than one month after the repair or replacement) and provided to Veolia.

This project was competitively bid to be performed on a "design-build" basis, and the Contractor is responsible for engaging the services of an engineering firm to issue design drawings for lines with utility conflicts and other constructability issues and also issue the final as-built drawings. Hence, per the City's direction, no engineered drawings were provided for this pipe replacement project. T&M not to exceed fees are included for compaction testing services as well as engineering support services in this proposal. All services provided for design support by V. W. Housen & Associates and for compaction testing services by Quesia Engineering shall be tracked by Veolla and billed to the City with associated markups. All unused funds and associated Veolla markup shall return to the City.

March 20, 2024, the Cily posted the Request for Bids on Bids Online, and Veolla conducted a mandatory pre-t eeting with ten (10) participants on April 3, 2024. On April 16, 2024, five (5) bids were received from qualified contracto the apparent low bid received was from APB General Engineering in the amount of $1,690,800.00. Vella evaluated all of the bids and found them to be responsive and complete and recommend awarding the contract to APB General Engineering, who is the low bidder. Their bid is attached. 202324 Grade S RA Line Repl Phaseds/Estin. Veolia Markup SUBTOTAL 16.50% TOTAL
APB General Engineering 1,690,800 1,690,800 278,982 1,969,782 V.W. Housen & Assoclales - design
support (estim.) 40,000 40,000 6,600 46,600
Questa Engineering-tesling 25,000 25,000 4,125 29,125
TOTAL 1.755,800 1.755,800 289.707 2.045.507
Copy of APB General Engineering's bid