Subject: Contract Amendment No. 1 with Bay Hawk, Inc. for Pavement, Curbing, Sidewalk and Walkway Restoration
Services
FINANCIAL IMPACT: The proposed Amendment No. 1 increases the two-year contract with Bay Hawk, Inc. by $360,359, from a
not-to-exceed amount of $275,200 to a not-to-exceed
amount of $635,559. Funding for the additional work will come from a combination of the Housing and Urban
Development (HUD) Capital Fund Grant, RHA’s annual
allocation of operating subsidy, and rental income from public housing tenants. No additional appropriation
outside of these established RHA funding sources is
requested.
PREVIOUS COUNCIL
ACTION:
November 18, 2025
STATEMENT OF THE
ISSUE:
Following commencement of work at Nystrom Village, a
detailed field survey identified substantially more
sidewalk and walkway replacement than originally
estimated, including additional work necessary to
address accessibility-related slope conditions. The
expanded scope requires an additional $360,359,
increasing the total payment limit for the Bay Hawk, Inc. contract to $635,559. Board approval is required to
amend the contract and authorize the additional
expenditure.
AGENDA
REPORT
October 20, 2026
RECOMMENDED ACTION: ADOPT a resolution and APPROVE the first contract amendment with Bay Hawk, Inc. for additional sidewalk
and walkway replacement, increasing the payment limit
by $360,359 to a total payment limit of $635,559, to
include additional sidewalk and walkway replacement,
and AUTHORIZE the executive director or their designee
to execute the contract – Richmond Housing Authority
(Antoinette Terrell/Greg Palomino/Nannette Beacham
510-621-1300).
On November 18, 2025, the Board of Commissioners of the Richmond Housing Authority (RHA) approved a two-year contract with Bay Hawk, Inc. for pavement, curbing, sidewalk, and walkway restoration services at Nystrom Village and the Hacienda Excess Lot, in an amount not to exceed $275,200 (Attachments 1 and 2). The original contract scope was based on an estimated 7,200 square feet of sidewalk and walkway replacement, eight (8) curb ramp replacements, and 80 linear feet of sidewalk grinding.
A more detailed field survey of the sidewalks and walkways at Nystrom Village was created once work commenced. Significant slope corrections were required to bring the walking surfaces into compliance with accessibility standards, which increased the total quantity of sidewalk and walkway requiring replacement from the original estimate of 7,200 square feet to approximately 18,638 square feet for sidewalks and an increase from 695 square feet to 1970 square feet for walkways (Attachment 3).
Bay Hawk, Inc. has submitted the following cost estimate for the additional scope of work:
Item Quantity Cost per Unit Subtotal
Additional sidewalk & walkway
replacement
11,438 sq. ft. $28/sq. ft. $320,264
Interior walkway replacement 1,215 sq. ft. $33/sq. ft. $40,095 Total Contract Increase $360,359
Therefore, City staff is requesting that the Board of Commissioners adopt a resolution to approve amendment no. 1 to the contract with Bay Hawk, Inc., increasing the not-toexceed contract amount by $360,359, from $275,200 to $635,559, with no change to the original contract term.