RECOMMENDED ACTION:
Approve Change Order No. 8 in the not to exceed amount of $36,120 for four field changes: (1) resolving a conflict at a storm drain connection point, (2) resolving a storm drain conflict with an existing sewer line, (3) a new service meter on a previously unknown waterline, and (4) installing a temporary bypass line for a storm drain line that was in conflict with a PG&E gas line (funding sources: Water, Sewer and Storm Enterprise Capital Funds).
BACKGROUND:
The Stockton Avenue Rehabilitation Project was awarded to D.A. Wood Construction, Inc. at the February 9, 2021 City Council meeting for an amount of $4,747,866.50. The Stockton Avenue Rehabilitation Project will involve a complete road reconstruction from Second St. to Doak Blvd, including the repair and replacement of several underground utilities along with the installation of concrete pavers, new streetlights, and 6-foot sidewalks.
At the April 13, 2021 City Council meeting, Council approved Change Order No. 1 in the not to exceed amount of $189,062.81 for the truck detour improvements required on private property and changes to the scope of the project at the request of Ripon Manufacturing Company.
At the June 8, 2021 City Council meeting, Council approved Change Order No. 2 in the not to exceed amount of $28,174.31 for the increase in price of PVC pipe material due to a national material shortage.
At the August 10, 2021 City Council meeting, Council approved Change Order No. 3 in the not to exceed amount of $135,904.03 for various unforeseen field conditions that required changes to the contract documents.
At the September, 14, 2021 City Council meeting, Council approved Change Order No. 4 in the not to exceed amount of $38,764.98 to locate a water lateral and for additional work needed for storm drain conflicts on Stockton Avenue between Doak Boulevard and Fifth Street.
At the November 9, 2021 City Council meeting, Council approved Change Order No. 5 in the not to exceed amount of $60,265.77 for additional work necessary to lower the elevation of 48” Storm Drain Pipe installed to avoid an existing PG&E transmission line.
At the December 14, 2021 City Council meeting, Council approved Change Order No. 6 in the not to exceed amount of $11,351.00 to adjust catch basins to eliminate conflicts with an MID electrical line and PG&E gas transmission line.
At the January 11, 2022 City Council meeting, Council approved Change Order No. 7 in the not to exceed amount of $24,300.00 for three field changes required to install the water line.
DISCUSSION:
When preparing to connect to the existing 36” storm drain line on East Fourth Street, an approximately 8” thick steel reinforced concrete guard was found attached to the top of the existing pipe which required the use of additional equipment and time for demolition. This additional cost covers the breaker used for demolition and the extra time required.
During the installation of the 48” storm drain adjacent to the Diamond Pet Food property driveway, a conflict with the sanitary sewer was found. Due to the path of the sewer line, readjustment of its depth was not possible. To bypass this sewer line, an additional manhole was poured and the sewer line was cased with a 14” steel casing with skids to protect it per city standards. Additional costs are for the labor of one additional manhole plus the material and labor cost to protect the 12” sanitary sewer.
During investigation of the water line near the Thompson Building Materials property, an unknown water line connection was located and determined to be a needed service for the facilities onsite. The connection required a new backflow prevention device installed and a new meter installed on the service. The additional cost covers the material and labor for the installation of the 2" meter on the new backflow device.
During construction, a 4” PG&E gas distribution line was found to be in conflict with the proposed 48” storm drain line at the intersection of East Fourth Street and Stockton Avenue.
While waiting for PG&E to redirect their line and remove the conflict, a temporary bypass between the storm drain line and industrial sewer line on East Fourth Street was installed to drain storm water during November/December. The additional costs covers the price of material and labor to install this temporary bypass.
FISCAL IMPACT:
The attached Change Order No. 8 is in the amount of $36,120 and will be funded through the Water, Sewer and Storm Enterprise Capital Funds.
To summarize the funding sources to date for the Stockton Avenue Rehabilitation project, please see table below.
Amount Fund Balance
(12/31/21)
Original Contract Price $4,747,866.50 n/a
Change Orders (No. 1-8) $ 523,942.90 n/a
Current Contract Price $5,271,809.40
Funding Sources:
RSTP Grant $1,777,000.00 $1,777,000
Measure K Regional Arterial a $1,979,830.76 $2,200,000
Water Enterprise Capital $ 624,368.93 $6,812,083
Sewer Enterprise Capital $ 813,068.94 $1,443,813
Stormwater Enterprise Capital $ 77,540.77 $409,416
Allocated Funding (as of 1/31/22) $5,271,809.40
a. The City of Ripon was allocated $2.2 million of Measure K Regional Arterial funding. As of 1/31/22, $220,169.24 is available to be allocated to future change orders.