CITY OF RIPON

PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 9 DATE: 3/8/2022
PROJECT: Stockton Avenue Rehabilitation Project SHEET 1 OF 1 SHEETS TO: D.A. Wood Construction, Inc.

You are hereby directed to make the herein described changes from the plans and specifications or do the following described work not included in the plans and specifications on this contract.

NOTE: This change order is not effective until approved by the CITY ENGINEER. (ores fense ale as arena euper over any sco me a culment sal ye a a alone it at or al me are scount.

Change requested by the Engineer.

Description Cost
Addition of the following items:

1. Cost for Additional Demolition on Stockton Avenue $19,200.00

2. Cost of Additional Potholing for PGE Requirements $15,675.00

3. Cost of Conduit Size Increase $4,251.00

4. Cost of Demolition of Additional Industrial Sewer Manhole $950.00 Total: $40,076.00
All work shall be in accordance with City Standards.

Estimated Cost: $40,076.00 Increase
Change Order 5 work, (0) working days for Change Order 6 work, (5) working days for Change Order 7 work, and (0) working days for Change Order 8 work. Total number of additional working days added is 97.

Approval Recommended: Date:

Approval Senior - Kevin Werner
Approved: Date:

Approval Chief - Dean Ucker
Accepted, Date Contractor
By Title Project Manager
If the contractor does not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified.

← All documents from this meeting