CITY OF RIPON

PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 10 DATE: 4/12/2022
PROJECT: Stockton Avenue Rehabilitation Project SHEET 1 OF 1 SHEETS TO: D.A. Wood Construction, Inc.

You are hereby directed to make the herein described changes from the plans and specifications or do the following described work not included in the plans and specifications on this contract.

NOTE: This change order is not effective until approved by the CITY ENGINEER.

Does on fios do as rented panel over only s to lime as sument clean use and no alone i be made to are ane tore account.

Change requested by the Engineer.

Description Cost
Addition of the following items:

1. Cost of additional concrete driveway work $19,159.86 Total: $19,159.86
All work shall be in accordance with City Standards.

Estimated Cost: $19,159.86 Increase
By reason of this order the time of completion will be adjusted as follows: (0) working days for the work associated with Change Order 10, in addition to (15) working days for Change Order 1 work, (49) working days for Change Order 2 Order 10. Total number of additional working days added is 97.

Approval Recommended: Date:

Approval Senior - Kevin Werner
Approved: Date:

Approval Chief - Dean Uecker
Ne, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above, and perform all services necessary for the work above specified, and will accept as fu payment therefor the prices shown above.

Accepted, Date Contractor
By Title Project Manager
If the contractor does not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified.