CITY OF RIPON
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 2 DATE: 5/10/2022
PROJECT: Well 19 Pump Station SHEET 1 OF 1 SHEETS
TO: Soracco, Inc.
You are hereby directed to make the herein described changes from the plans and specifications or do the following described work not included in the plans and specifications on this contract.
NOTE: This change order is not effective until approved by the CITY ENGINEER.
Change requested by the Engineer.
Description Cost
Deletion of the following items:
2.1 - Site reduction of asphalt, fencing, sidewalk and concrete generator pad. Add curb -$49,326.34 under all sides of fencing.
Addition of the following items:
2.2 - Adjust the alignment of the water line to avoid existing utlities in conflict and replacement of an existing faulty 12inch water valve. $28,560.46
2.3 - Upgrade the contract specified doors from steel to fiberglass chemical resistant doors for the chlorination and electrical control building. $8,915.09 Total: -$11,850.79
All work shall be in accordance with City Standards.
Estimated Cost: -$11,850.79 Decrease
By reason of this order the time of completion will be adjusted as follows: Pursuant to Calendar Day Statements Approval Recommended: Date:
Approval Senior - Kevin Werer
Approved: Date:
Approval Chief - Dean Uecker
We, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above, and perform all services necessary for the work above specified, and will accept as full Accepted, Date Contractor
By Title
If the contractor does not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified.