MEMO
To: Honorable City Council
From: Kevin Werner, City Administrator
Date: 07/12/2022
Subject: Stockton Avenue Rehabilitation Change Order 12 RECOMMENDED ACTION:

Approve Change Order No. 12 in the not to exceed amount of $138,799.25 for 6” grind and overlay at the South end of Stockton Avenue and additional pull box installation for street light connection. (Funding source: Street & Road Operating Fund ($57,809.86) and Measure K Renewal Grant ($80,989.39)).

BACKGROUND:

The Stockton Avenue Rehabilitation Project was awarded to D.A. Wood Construction, Inc. at the February 9, 2021 City Council meeting for an amount of $4,747,866.50. The Stockton Avenue Rehabilitation Project will involve a complete road reconstruction from Second Street to Doak Boulevard, including the repair and replacement of several underground utilities along with the installation of concrete pavers, new streetlights, and 6-foot sidewalks.

At the April 13, 2021 City Council meeting, Council approved Change Order No. 1 in the not to exceed amount of $189,062.81 for the truck detour improvements required on private property and changes to the scope of the project at the request of Ripon Manufacturing Company.

At the June 8, 2021 City Council meeting, Council approved Change Order No. 2 in the not to exceed amount of $28,174.31 for the increase in price of PVC pipe material due to a national material shortage.

At the August 10, 2021 City Council meeting, Council approved Change Order No. 3 in the not to exceed amount of $135,904.03 for various unforeseen field conditions that required changes to the contract documents.

At the September, 14, 2021 City Council meeting, Council approved Change Order No. 4 in the not to exceed amount of $38,764.98 to locate a water lateral and for additional work needed for storm drain conflicts on Stockton Avenue between Doak Boulevard and Fifth Street.

At the November 9, 2021 City Council meeting, Council approved Change Order No. 5 in the not to exceed amount of $60,265.77 for additional work necessary to lower the elevation of 48” Storm Drain Pipe installed to avoid an existing PG&E transmission line.

At the December 14, 2021 City Council meeting, Council approved Change Order No. 6 in the not to exceed amount of $11,351.00 to adjust catch basins to eliminate conflicts with an MID electrical line and PG&E gas transmission line.

At the January 11, 2022 City Council meeting, Council approved Change Order No. 7 in the not to exceed amount of $24,300.00 for three field changes required to install the water line.

At the February 8, 2022 City Council meeting, Council approved Change Order No. 8 in the not to exceed amount of $36,120.00 for four field changes required to resolve storm drain conflicts.

At the March 8, 2022 City Council meeting, Council approved Change Order No. 9 in the not to exceed amount of $40,076.00 for additional potholing required to adhere to PG&E internal standards, demolition of an industrial sewer manhole found within the proposed curb and gutter, upsizing street light conduits and the demolition of asphalt found buried beneath existing soil on Stockton Avenue.

At the April 12, 2022 City Council meeting, Council approved Change Order No. 10 in the not to exceed amount of $19,159.86 for additional concrete driveway work.

At the June 9, 2022 City Council meeting, Council approved Change Order No. 11 in the not to exceed amount of $91,644.64 for concrete price escalations and additional frontage work at two properties.

DISCUSSION:

The Stockton Avenue project design included the patching of asphalt trenches at the south end of the project where the extension of the underground utilities extended beyond the limits of the pavers. After considering the condition of the asphalt in this area, staff has requested a change order from the contractor to do a full street width 6” grind and overlay for approximately 200 feet south of the paver limits.

Additionally, during an on-site meeting with the Modesto Irrigation District, staff was notified an additional pull box between their service and the service pedestal on-site was required. This change order also includes the cost of material and additional work needed to install this box.

FISCAL IMPACT:

The attached Change Order No. 12 is in the amount of $138,799.25 and will be funded through Street & Road Operating Fund ($57,809.86) and Measure K Grant ($80,989.39).

To summarize the funding related to this change order, see the tables below.

Amount
Original Contract Price $ 4,747,866.50
Change Orders (No. 1-11) $ 674,823.40
Change Order 12 $ 138,799.25
Current Contract Price $ 5,561,489.15
Funding Sources
Fund Balance
(5/31/22)
Change
Order 12
Fund Balance
(after Change
Order approval)
Measure K Regional Arterial $ 80,989.39 $ 80,989.39 $ 0.00 Street & Road Operating Fund $3,598,722.00 $ 57,809.86 $3,540.912.14 Attachments:

1. CO 12