Cities Index.
Invoice 16_D.A. Wood Construction, Inc

Ripon City Council
July 12, 2022

Document
Invoice 16_D.A. Wood Construction, Inc
Meeting
July 12, 2022
Body
Ripon City Council
Original file
32 KB
Text extracted from the city's file for reading and search. Open the original on riponcityca.iqm2.com. That file is the official record.

INVOICE SUMMARY
CONTRACTOR: D.A. Wood Construction, Inc.

PROJECT: Stockton Avenue Rehabilitation
PROJECT DESCRIPTION: Reconstruction of Stockton Avenue, replacement of underground utilities, sidewalk, curb and gutter.

INVOICE NO: 16
DATE: 6/30/2022

CONTRACT INFORMATION BILLING INFORMATION
ORIGINAL CONTRACT AMOUNT: $4,747,866.50 PREVIOUSLY BILLED AMOUNT: $4,949,842.81 LESS RETENTION: $247,492.15
APPROVED CONTRACT CHANGES: $674,823.40 PREVIOUSLY PAID AMOUNT: $4,702,350.66 CURRENT INVOICED AMOUNT: $264,737.14
LESS RETENTION: $13,236.85
TOTAL CONTRACT AMOUNT: $5,422,689.90 CURRENT AMOUNT DUE: $251,500.29 TOTAL BILLED TO DATE (INCL CURRENT INVOICE) $5,214,579.95 LESS RETENTION: $260,729.00
TOTAL PAID TO DATE: $4,953,850.95

INVOICE SUMMARY
Paving and restoration 80% completed. Storm and Industrial Manholes beginning to be raised to grade. Potable water and Hydrant valve risers installed and raised to grade. Pavers 100% complete, awaiting all utilities to be raised to grade to complete final sealing.

TOTAL PROGRESS
Remaining Contract Amount: $208,109.95
Approx. % Complete: 96.16%
Accounts Payable
Total Due [Retention
WA $16,800.00 $15,960.00 $840.00
sw $15,175.00 $14,416.25 $758.75
ST $197,450.49 $187,577.97 $9,872.52
ST - MK $10,750.65 $10,213.12 $537.53
Storm $24,561.00 $23,332.96 $1,228.04
TOTALS $264,737.14 $251,500.29 $13,236.85

← All documents from this meeting