Cities Index.
Invoice 17_D.A. Wood Construction, Inc

Ripon City Council
August 9, 2022

Document
Invoice 17_D.A. Wood Construction, Inc
Meeting
August 9, 2022
Body
Ripon City Council
Original file
22 KB
Text extracted from the city's file for reading and search. Open the original on riponcityca.iqm2.com. That file is the official record.

INVOICE SUMMARY
CONTRACTOR: D.A. Wood Construction, Inc.

PROJECT: Stockton Avenue Rehabilitation
PROJECT DESCRIPTION: Reconstruction of Stockton Avenue, replacement of underground utilities, sidewalk, curb and gutter.

INVOICE NO: 17
DATE: 7/31/2022

CONTRACT INFORMATION BILLING INFORMATION
ORIGINAL CONTRACT AMOUNT: $4,747,866.50 PREVIOUSLY BILLED AMOUNT: $5,214,579.95 LESS RETENTION: $260,729.00
APPROVED CONTRACT CHANGES: $813,622.65 PREVIOUSLY PAID AMOUNT: $4,953,850.95 CURRENT INVOICED AMOUNT: $244,721.25
LESS RETENTION: $12,236.06
TOTAL CONTRACT AMOUNT: $5,561,489.15 CURRENT AMOUNT DUE: $232,485.19 TOTAL BILLED TO DATE (INCL CURRENT INVOICE) $5,459,301.20 LESS RETENTION: $272,965.06
TOTAL PAID TO DATE: $5,186,336.14

INVOICE SUMMARY
All asphalt paving on Stockton Avenue completed. All manhole and water valve concrete collars poured. Final site clean up and punchlist item work proceeding.

TOTAL PROGRESS
Remaining Contract Amount: $102,187.95
Approx. % Complete: 98.16%
Accounts Payable
Total Retention
$0.00 $0.00
$0.00 $0.00
ST $163,731.86 $155,545.27 $8, 186.59
ST - MK $80,989.39$76,939.92 $4,049.47
Stor $0.00 $0.00
TOTALS $244,721.25 $232,485. 19| $12,236.06

← All documents from this meeting