RIPON FIRE DISTRICT
General Conditions
1 of 4
For: General Conditions for Development
Date: 01-01-22
Supersedes: 10-01-21
Purpose: To provide general conditions for approval of projects within the jurisdiction of the Ripon Fire District. The conditions listed in this document are not intended to be all-inclusive, and the District may impose additional conditions or requirements prior to approval. Projects are required to be constructed in accordance with any and all applicable local, state and federal laws and regulations.
FIRE DEPARTMENT ACCESS
󠄀 All designated fire access routes and lanes shall be in accordance with the currently adopted codes, and as required by the District. Fire lanes will be marked in accordance with District specifications and approved by the District prior to installation. All gates located on fire access route shall be provided with means for entry as approved by the District.
󠄀 One or more Knox Key Boxes shall be installed at a location approved by the District. Ordering information for Knox Company products is available online at www.knoxbox.com
PREMISES IDENTIFICATION
󠄀 All buildings shall be provided with approved street address/suite numbers, plainly visible and legible from the street. Where a building is set back from the street or road fronting the property, and whenever an addresses may not be clearly identifiable due to distance from the street or roadway, landscape, architectural appendages or other obstructions, address posting shall be required both at the street driveway serving the building(s) and on the building(s).
Size and Height
Determined by distance to location of address as posted, measured from curb. 25 Feet 4 inch
26-40 Feet 6 inch
41-55 Feet 9 inch
Over 55 Feet 12 inch
Numbers shall be a minimum of a ¾” stroke and shall contrast with their background.
Rear of Buildings
Any business or apartment building which affords vehicular access to the rear through a driveway, alley way or parking lot, shall also display approved identification or address numbers on the rear of the building for such business or apartment building in a location approved by the Fire Chief.
Multiple Dwelling Units
An approved diagram of the premises which clearly indicates all individual addresses of each unit in the complex shall be erected at the entrance driveways to every multiple dwelling complex having more than one building on The Terraces - Project Condition Letter Packet
RIPON FIRE DISTRICT
General Conditions
2 of 4
the premises or when required by the Fire Chief. In addition, the Fire Chief may require that individual buildings on the premises be identified in an approved manner.
Premises identification-Multiple Buildings
An approved identification of multiple buildings within an industrial complex shall be required which clearly indicates each individual building in the complex. Identification shall be placed on each building in a size and location when required by the Fire Chief and be visible for responding emergency personal in an approved manner.
WATER SUPPLY
󠄀 Water Supplies and Fire Hydrants shall be in accordance with all current codes and specifications adopted by the District.
󠄀 Fire hydrant location, distribution and installation shall be in accordance with the current codes and specifications adopted by the District. Onsite hydrants may be required depending on access and hazards present. 󠄀 All Hydrants shall be supplied by a dedicated 8” service from the main line, unless otherwise approved by the Fire Chief. On-site systems may be required to be supplied from two directions otherwise known as “looped” systems.
FIRE CODE PLAN CHECK
󠄀 Submit 1 complete set of plans to the Ripon Fire District office located at 142 S. Stockton Ave. in Ripon, CA.
Plans for fire protection systems shall be submitted and approved prior to construction, unless other arrangements have been made and approved to by the District.
󠄀 Submit to the District a one page facility plan in PDF format for inclusion in Fire Department Pre-Fire Plan Program. Contact Fire Chief for additional information. 󠄀 Payment for all Plan Checks are due at the time of completion of the plan check process in order to receive approved plans and proceed. . Work shall not commence until approved plans are received from the District.
FIRE PROTECTION SYSTEMS
󠄀 Automatic Sprinkler Systems
Electronic plan submittal is preferred. If electronic submittal is not possible, contact via email for instructions. All plans for fire protection systems shall be submitted and approved prior to construction, unless other arrangements have been made and approved by the District in advance. All correspondence should be routed to [email protected]
System Requirements
The location of all hydrants, fire department connections, indicating valves, etc. shall be approved by the District prior to installation. All hydrants, OS&Y’s and FDC’s shall be painted for identification purposes as required by the Fire District.
All fire department connections (FDC) shall be provided with locking cap(s) to prevent tampering. The approved make and model is as follows:
The Terraces - Project Condition Letter Packet
RIPON FIRE DISTRICT
General Conditions
3 of 4
KNOX Company
Locking FDC Cap
Model #3011
Ordering information for Knox Company products is available online at www.knoxbox.com All backflow and detector check assemblies shall be installed per City of Ripon specifications, and monitored with tamper switch(s). Indicating valves shall be provided with locking devices in order to lock valve(s) in open position.
All piping that is any part of an automatic sprinkler system shall meet the C 900 specification, rated at 200 psi.
Unless otherwise approved, all automatic sprinkler systems shall be supplied by a dedicated 8” connection from the main line.
Fire Department Connections (FDC) shall be located within 30 feet of an approved fire hydrant
ALARM SYSTEMS
󠄀 Automatic Fire Suppression Systems controls shall be monitored by an approved alarm monitoring Service.
Electronic plan submittal is preferred. If electronic submittal is not possible, contact via email for instructions. All plans for fire protection systems shall be submitted and approved prior to construction, unless other arrangements have been made and approved by the District in advance. All correspondence should be routed to [email protected]
In the event that electronic submittal is not possible, three (3) sets of plans and equipment specifications shall be submitted to the District for approval prior to commencement of installation.
The following devices shall be monitored by the alarm system:
System valves - Tamper Switches
Sprinkler Risers - Flow switches
Post Indicator Valves - Tamper Switches
Manual Pull Stations
Commercial Hood & Duct Systems
COMMERCIAL COOKING OPERATIONS
󠄀 Automatic Fire Suppression Systems shall be installed for protection of commercial cooking equipment.
Electronic plans submittal is preferred, otherwise submit three (3) complete sets of plans for hood & duct systems to the Ripon Fire District Office for review and approval prior to installation.
INSPECTIONS
󠄀 Builder/Contractor is required to contact the Fire District 48 hours in advance to arrange the following on-site I inspections when required:
Fire Access Roads and Lanes
Sprinkler Systems
Fire Alarm Systems
Fire Hydrant Installation
Fire Extinguisher Placement
Special Systems
Final Occupancy Inspections
The Terraces - Project Condition Letter Packet
RIPON FIRE DISTRICT
General Conditions
4 of 4
A set of stamped and approved plans shall be on-site at all times during construction.
FIRE EXTINGUISHERS
󠄀 Provide extinguishers with a minimum rating of 2A 10B:C within 75 feet of exits and for every 3000 square feet in general use areas. Placement of extinguishers shall be in compliance with currently adopted codes. In any event, placement of fire extinguishers shall meet or exceed Section 906 of the California Fire Code. 󠄀 The Fire District shall be notified prior to occupancy of the facility for the approval of the locations, type and size of each fire extinguisher. Extinguishers are required during construction, alteration or demolition of any building.
Fire Extinguishers shall be tagged by a licensed extinguisher service company prior to installation.
FEES/PERMITS
󠄀 Plan Check/Inspection Fees
Plan check/inspection fees will be charged for the following in accordance with the fee schedule adopted by the Board of Directors of the Ripon Fire District:
Fire Code Plan Check
Fire Protection Systems
Commercial Cooking Operations (Hood and Duct) Fire Protection Systems Fire Alarm Systems
A list of construction permit fees can be found on the Ripon Fire District website @ www.riponfire.com Construction permits include the cost for all inspections and certifications. 󠄀 Fire Impact Fees
Fire Impact Fees will be charged in accordance with the fee schedule on record at the City of Ripon and/or as described in the Development Agreement between the City of Ripon and the Developer.
ANNUAL OPERATING PERMIT(S)
󠄀 The California Fire Code (CFC) lists specific uses or operations that require annual operating permits. This list can be found on the District’s website located at www.riponfire.com under Fire Code Permit Fee Schedule.
PARTICIPATION IN RCFD COMMUNITY CONNECT PROGRAM
󠄀 Occupant may be required to register an account in RCFD Community Connect Program for specific pre-arrival and pre-planning information.
The Terraces - Project Condition Letter Packet
Plan Review Team
Land Management
[email protected]
PG&E Gas and Electric Facilities Page 1
December 16, 2021
Mitzi Johnston
City of Ripon
259 N Wilma Ave
Ripon, CA 95366
Re: UP21-70/PUD21-79 Bethany Home Residential Care Facility 816 W Main Street, Ripon, CA 95366
Dear Mitzi:
Thank you for giving us the opportunity to review the subject plans. The proposed UP21- 70/PUD21-79 Bethany Home Residential Care Facility is within the same vicinity of PG&E’s existing facilities that impact this property.
The proposed plans indicate that there will be significant development over existing underground electric distribution conduits and that PG&E poles will need to be relocated. The plan submitted show the PG&E poles to be relocated but does not show the existing underground electric distribution conduits. Due to the proposed development, these existing facilities will need to be relocated to provide adequate service to the proposed development. These relocations will be done at one hundred percent developer expense. The applicant needs to contact [email protected] to receive facility mapping that will denote the current location of the existing underground electric distribution conduits and to incorporate said facilities into their plans. Once receiving facility mapping, the applicant may submit an application to relocate facilities with PG&E’s Service Planning department at www.pge.com/cco. Once these two steps are complete the applicant may reach out to Land Agent Lauren Ruby ([email protected]) to discuss the relocations and any cost estimates.
Please contact the Building and Renovation Center (BRSC) for facility map requests by calling 1-877-743-7782 and PG&E’s Service Planning department at www.pge.com/cco for any modification or relocation requests, or for any additional services you may require. As a reminder, before any digging or excavation occurs, please contact Underground Service Alert (USA) by dialing 811 a minimum of 2 working days prior to commencing any work. This free and independent service will ensure that all existing underground utilities are identified and marked on-site.
If you have any questions regarding our response, please contact me at [email protected].
Sincerely,
Justin Newell
Land Management
916-594-4068
The Terraces - Project Condition Letter Packet
December 9, 2021
Mitzi Johnston
City of Ripon
Department of Planning and Economic Development
259 N Wilma Avenue
Ripon, CA 95366
Project: Conditional Use Permit (CUP21-70) for Residential Care Facility District CEQA Reference No: 20211158
Dear Mr. Johnston:
The San Joaquin Valley Unified Air Pollution Control District (District) has reviewed the project referenced above from the City of Ripon (City). The project consists of the construction of a 106,894 square foot, 82-unit residential care facility with indoor amenities including dining, multipurpose room, fitness center, salon, studio, and support spaces (Project). The Project is located at 816 W Main Street and 200 Vera Avenue, in Ripon, CA (APN 259-180-16, and -17).
The District offers the following comments:
1) Project Related Emissions
At the federal level under the National Ambient Air Quality Standards (NAAQS), the District is designated as extreme nonattainment for the 8-hour ozone standards and serious nonattainment for the particulate matter less than 2.5 microns in size (PM2.5) standards. At the state level under California Ambient Air Quality Standards (CAAQS), the District is designated as nonattainment for the 8-hour ozone, PM10, and PM2.5 standards.
Based on information provided to the District, Project specific annual emissions from construction and operation emissions of criteria pollutants are not expected to exceed any of the following District significance thresholds: 100 tons per year of carbon monoxide (CO), 10 tons per year of oxides of nitrogen (NOx), 10 tons per year of reactive organic gases (ROG), 27 tons per year of oxides of sulfur (SOx), 15 tons per year of particulate matter of 10 microns or less in size (PM10), or 15 tons per year of particulate matter of 2.5 microns or less in size (PM2.5).
The Terraces - Project Condition Letter Packet
San Joaquin Valley Air Pollution Control District Page 2 District Reference No. 20211158
December 9, 2021
1a) Construction Emissions
Project construction air emissions are short-term emissions generated from construction activities and are not expected to exceed the District’s significance thresholds. However, the District recommends, to further lessen air quality impacts from construction-related diesel exhaust emissions, the City consider incorporating the below measure into the Project.
Recommended Measure: To reduce impacts from construction-related diesel exhaust emissions, the Project should utilize clean off-road construction equipment, including the latest tier equipment as feasible. 2) Health Risk Screening/Assessment
The City should evaluate the risk associated with the Project for sensitive receptors (residences, businesses, hospitals, day-care facilities, health care facilities, etc.) in the area and mitigate any potentially significant risk to help limit exposure of sensitive receptors to emissions.
To determine potential health impacts on surrounding receptors (residences, businesses, hospitals, day-care facilities, health care facilities, etc.) a Prioritization and/or a Health Risk Assessment (HRA) should be performed for the Project. These health risk determinations should quantify and characterize potential Toxic Air Contaminant (TAC) air pollutants identified by the Office of Environmental Health Hazard Assessment/California Air Resources Board (OEHHA/CARB) that pose a present or potential hazard to human health.
Health risk analyses should include all potential air emissions from the project, which include emissions from construction of the facility, including multi-year construction, as well as ongoing operational activities of the facility. Note, two common sources of TACs can be attributed to diesel exhaust emitted from heavy-duty off-road earth moving equipment during construction, and from ongoing operation of heavy-duty on-road trucks. A list of TACs identified by OEHHA/CARB can be found at:
https://ww2.arb.ca.gov/resources/documents/carb-identified-toxic-air-contaminants Prioritization (Screening Health Risk Assessment):
A “Prioritization” is the recommended method for a conservative screening-level health risk assessment. The Prioritization should be performed using the California Air Pollution Control Officers Association’s (CAPCOA) methodology. The District recommends that a more refined analysis, in the form of an HRA, be performed for any project resulting in a Prioritization score of 10 or greater. This is because the prioritization results are a conservative health risk representation, while the detailed HRA provides a more accurate health risk evaluation.
The Terraces - Project Condition Letter Packet
San Joaquin Valley Air Pollution Control District Page 3 District Reference No. 20211158
December 9, 2021
To assist land use agencies and project proponents with Prioritization analyses, the District has created a prioritization calculator based on the aforementioned CAPCOA guidelines, which can be found here:
http:www.valleyair.org/busind/pto/emission_factors/Criteria/Toxics/Utilities/PRIORITI ZATION%20RMR%202016.XLS
Health Risk Assessment:
Prior to performing an HRA, it is strongly recommended that land use agencies/development project proponents contact the District to review the proposed health risk modeling protocol. A development project would be considered to have a potentially significant health risk if the HRA demonstrates that the project-related health impacts would exceed the Districts significance threshold of 20 in a million for carcinogenic risk, or 1.0 for either the Acute or Chronic Hazard Indices. A project with a significant health risk would trigger all feasible mitigation measures. The District strongly recommends that development projects that result in a significant health risk not be approved by the land use agency.
The District is available to review HRA protocols and analyses. For HRA submittals please provide the following information electronically to the District for review:
HRA (AERMOD) model files
HARP2 files
Summary of emissions source locations, emissions rates, and emission factor calculations and methodology.
For assistance, please contact the District’s Technical Services Department by:
E-Mailing inquiries to: [email protected]
Calling (559) 230-5900
Visiting the Districts modeling guidance website at:
http://www.valleyair.org/busind/pto/Tox_Resources/AirQualityMonitoring.htm.
Recommended Measure: Development projects resulting in TAC emissions should be located an adequate distance from residential areas and other sensitive receptors in accordance to CARB's Air Quality and Land Use Handbook: A Community Health Perspective.
Recommended Measure: A health risk screening and/or assessment should be performed to assess potential risks to sensitive receptors for all of the following projects:
Projects whose proposed locations are within the established buffer distances identified in CARB's handbook located at
https://ww3.arb.ca.gov/ch/handbook.pdf
The Terraces - Project Condition Letter Packet
San Joaquin Valley Air Pollution Control District Page 4 District Reference No. 20211158
December 9, 2021
Projects whose land uses are not specifically identified in CARB's handbook (such as shopping centers), but there is sufficient information to reasonably conclude that sensitive receptors would be exposed to significant sources of TACs; and
Projects that would otherwise appear to be exempt from CEQA requirements, but there is sufficient information to reasonably conclude that sensitive receptors would be exposed to significant sources of TACs, such as industrial use projects allowed by right.
3) Ambient Air Quality Analysis
An Ambient Air Quality Analysis (AAQA) uses air dispersion modeling to determine if emissions increases from a project will cause or contribute to a violation of State or National Ambient Air Quality Standards. The District recommends an AAQA be performed for the Project if emissions exceed 100 pounds per day of any pollutant.
An acceptable analysis would include emissions from both project-specific permitted and non-permitted equipment and activities. The District recommends consultation with District staff to determine the appropriate model and input data to use in the analysis.
Specific information for assessing significance, including screening tools and modeling guidance, is available online at the District’s website:
www.valleyair.org/ceqa.
4) On-site Solar Deployment
It is the policy of the State of California that renewable energy resources and zerocarbon resources supply 100% of retail sales of electricity to California end-use customers by December 31, 2045. While various emission control techniques and programs exist to reduce air quality emissions from mobile and stationary sources, the production of solar energy is contributing to improving air quality and public health. The District suggests that the City consider the feasibility of incorporating solar power systems, as an emission reduction strategy for this Project. 5) Clean Lawn and Garden Equipment in the Community
Since the Project consists of residential development, gas-powered residential lawn and garden equipment have the potential to result in an increase of NOx and PM2.5 emissions. Utilizing electric lawn care equipment can provide residents with immediate economic, environmental, and health benefits. The District recommends the Project proponent consider the District’s Clean Green Yard Machines (CGYM) program which provides incentive funding for replacement of existing gas powered The Terraces - Project Condition Letter Packet
San Joaquin Valley Air Pollution Control District Page 5 District Reference No. 20211158
December 9, 2021
lawn and garden equipment. More information on the District CGYM program and funding can be found at: http://www.valleyair.org/grants/cgym.htm and http://valleyair.org/grants/cgym-commercial.htm.
6) Charge Up! Electric Vehicle Charger
To support further installation of electric vehicle charging equipment and development of such infrastructure, the District offers incentives to public agencies, businesses, and property owners of multi-unit dwellings to install electric charging infrastructure (Level 2 and 3 chargers). The purpose of this incentive program is to promote clean air alternative-fuel technologies and the use of low or zero-emission vehicles. The District suggests that the City and Project proponent consider the feasibility of installing electric vehicle chargers for this Project.
Please visit www.valleyair.org/grants/chargeup.htm for more information. 7) District Rules and Regulation
The District issues permits for many types of air pollution sources and regulates some activities not requiring permits. A project subject to District rules and regulation would reduce its impacts on air quality through compliance with regulatory requirements. In general, a regulation is a collection of rules, each of which deals with a specific topic. For example, Regulation II - Permits encompasses multiple rules associated with the permitting of emission sources such as Rule 2010 (Permits Required), Rule 2201 (New and Modified Stationary Source Review), and others. 7a) District Rules 2010 and 2201 - Air Quality Permitting for Stationary Sources Stationary Source emissions include any building, structure, facility, or installation which emits or may emit any affected pollutant directly or as a fugitive emission.
District Rule 2010 requires operators of emission sources to obtain an Authority to Construct (ATC) and Permit to Operate (PTO) from the District. District Rule 2201 requires that new and modified stationary sources of emissions mitigate their emissions using best available control technology (BACT).
This Project may be subject to District Rule 2010 (Permits Required) and Rule 2201 (New and Modified Stationary Source Review) and may require District permits.
Prior to commencing construction on any permit-required equipment or process, a finalized ATC must be issued to the Project proponent by the District. For further information or assistance, the project proponent may contact the District’s Small Business Assistance (SBA) Office at (209) 557-6446.
The Terraces - Project Condition Letter Packet
San Joaquin Valley Air Pollution Control District Page 6 District Reference No. 20211158
December 9, 2021
7b) District Rule 9510 (Indirect Source Review)
The purpose of District Rule 9510 (Indirect Source Review) is to reduce the growth in both NOx and PM10 emissions associated with development and transportation projects from mobile and area sources associated with construction and operation of development projects. The rule encourages clean air design elements to be incorporated into the development project. In case the proposed project clean air design elements are insufficient to meet the targeted emission reductions, the rule requires developers to pay a fee used to fund projects to achieve off-site emissions reductions.
The proposed Project is subject to District Rule 9510 because it will receive a project-level discretionary approval from a public agency and will equal or exceed 50 residential units. When subject to the rule, an Air Impact Assessment (AIA) application is required no later than applying for project-level approval from a public agency. In this case, if not already done, please inform the project proponent to immediately submit an AIA application to the District to comply with District Rule 9510.
An AIA application is required and the District recommends that demonstration of compliance with District Rule 9510, before issuance of the first building permit, be made a condition of Project approval.
Information about how to comply with District Rule 9510 can be found online at:
http://www.valleyair.org/ISR/ISRHome.htm.
The AIA application form can be found online at:
http://www.valleyair.org/ISR/ISRFormsAndApplications.htm 7c) District Rule 4002 (National Emissions Standards for Hazardous Air Pollutants)
In the event an existing building will be renovated, partially demolished or removed, the Project may be subject to District Rule 4002. This rule requires a thorough inspection for asbestos to be conducted before any regulated facility is demolished or renovated. Information on how to comply with District Rule 4002 can be found online at:
http://www.valleyair.org/busind/comply/asbestosbultn.htm. 7d) District Regulation VIII (Fugitive PM10 Prohibitions) The project proponent may be required to submit a Construction Notification Form or submit and receive approval of a Dust Control Plan prior to commencing any earthmoving activities as described in Regulation VIII, specifically Rule 8021 The Terraces - Project Condition Letter Packet
San Joaquin Valley Air Pollution Control District Page 7 District Reference No. 20211158
December 9, 2021
– Construction, Demolition, Excavation, Extraction, and Other Earthmoving Activities.
The application for both the Construction Notification and Dust Control Plan can be found online at:
https://www.valleyair.org/busind/comply/PM10/forms/DCP-Form.docx Information about District Regulation VIII can be found online at:
http://www.valleyair.org/busind/comply/pm10/compliance_pm10.htm 7e) Other District Rules and Regulations
The Project may also be subject to the following District rules: Rule 4102 (Nuisance), Rule 4601 (Architectural Coatings), and Rule 4641 (Cutback, Slow Cure, and Emulsified Asphalt, Paving and Maintenance Operations).
The list of rules above is neither exhaustive nor exclusive. Current District rules can be found online at: www.valleyair.org/rules/1ruleslist.htm. To identify other District rules or regulations that apply to this Project or to obtain information about District permit requirements, the applicant is strongly encouraged to contact the District’s SBA Office at 209) 557-6446.
8) Potential Air Quality Improvement Measures
The District encourages the following air quality improvement measures to further reduce Project related emissions from construction and operation. A complete list of potential air quality improvement measures can be found online at:
http://www.valleyair.org/ceqaconnected/aqimeasures.aspx. a. Improve Walkability Design – This measure is to improve design elements to enhance walkability and connectivity. Improved street network characteristics within a neighborhood include street accessibility, usually measured in terms of average block size, proportion of four-way intersections, or number of intersections per square mile. Design is also measured in terms of sidewalk coverage, building setbacks, street widths, pedestrian crossings, presence of street trees, and a host of other physical variables that differentiate pedestrian-oriented environments from auto-oriented environments. b. Improve Destination Accessibility – This measure is to locate the project in an area with high accessibility to destinations. Destination accessibility is measured in terms of the number of jobs or other attractions reachable within a given travel time, which tends to be highest at central locations and lowest at peripheral ones. The location of the project also increases the potential for pedestrians to walk and bike to these destinations and therefore reduces the (vehicle miles traveled) VMT.
The Terraces - Project Condition Letter Packet
San Joaquin Valley Air Pollution Control District Page 8 District Reference No. 20211158
December 9, 2021
c. Increase Transit Accessibility – This measure is to locate the project with high density near transit which will facilitate the use of transit by people traveling to or from the Project site. The use of transit results in a mode shift and therefore reduced VMT. A project with a residential/commercial center designed around a rail or bus station, is called a transit-oriented development (TOD). The project description should include, at a minimum, the following design features:
A transit station/stop with high-quality, high-frequency bus service located within a 5-10 minute walk (or roughly ¼ mile from stop to edge of development), and/or
A rail station located within a 20 minute walk (or roughly ½ mile from station to edge of development)
Fast, frequent, and reliable transit service connecting to a high percentage of regional destinations
Neighborhood designed for walking and cycling
9) District Comment Letter
The District recommends that a copy of the District’s comments be provided to the Project proponent.
If you have any questions or require further information, please contact Diana Walker by e-mail at [email protected] or by phone at (559) 230-5820.
Sincerely,
Brian Clements
Director of Permit Services
For: Mark Montelongo
Program Manager
The Terraces - Project Condition Letter Packet
S J C O G, Inc.
555 East Weber Avenue ● Stockton, CA 95202 ● (209) 235-0600 ● FAX (209) 235-0438 San Joaquin County Multi-Species Habitat Conservation & Open Space Plan (SJMSCP)
SJMSCP RESPONSE TO LOCAL JURISDICTION (RTLJ)
ADVISORY AGENCY NOTICE TO SJCOG, Inc.
To: Ken Zuidervaart, City of Ripon, Department of Planning and Economic Development From: Laurel Boyd, SJCOG, Inc.
Date: October 18, 2021
-Local Jurisdiction Project Title: Conditional Use Permit (UP21-70), Planned Unit Development (PUD21-79) Assessor Parcel Number(s): 259-180-16, -17
Local Jurisdiction Project Number: UP21-70, PUD21-79
Total Acres to be converted from Open Space Use: Unknown Habitat Types to be Disturbed: Urban Habitat Land
Species Impact Findings: Findings to be determined by SJMSCP biologist.
Dear Mr. Zuidervaart:
SJCOG, Inc. has reviewed the project referral for the Conditional Use Permit (UP21-70), Planned Unit Development (PUD21-79).
This project consists of a request to construct a 106,894 square foot three story, 82-unit residential care facility with indoor amenities including dining, multipurpose room, fitness center, salon, studio and support spaces. Outdoor amenities include open courtyard, pet area, gardens and dining areas. The building will be located on two adjacent parcels totaling approximately 2.73 acres. The plan calls for 82 parking spaces for the site including 46 standard stalls and 36 compact stalls. This project is located at 816 W. Main Street and 200 Vera Avenue, Ripon (APN: 259-180-16, -17).
The City of Ripon is a signatory to San Joaquin County Multi-Species Habitat Conservation and Open Space Plan (SJMSCP). Participation in the SJMSCP satisfies requirements of both the state and federal endangered species acts, and ensures that the impacts are mitigated below a level of significance in compliance with the California Environmental Quality Act (CEQA). The LOCAL JURISDICTION retains responsibility for ensuring that the appropriate Incidental Take Minimization Measure are properly implemented and monitored and that appropriate fees are paid in compliance with the SJMSCP. Although participation in the SJMSCP is voluntary, Local Jurisdiction/Lead Agencies should be aware that if project applicants choose against participating in the SJMSCP, they will be required to provide alternative mitigation in an amount and kind equal to that provided in the SJMSCP.
This Project is subject to the SJMSCP. This can be up to a 30 day process and it is recommended that the project applicant contact SJMSCP staff as early as possible. It is also recommended that the project applicant obtain an information package. http://www.sjcog.org
Please contact SJMSCP staff regarding completing the following steps to satisfy SJMSCP requirements:
▪ Schedule a SJMSCP Biologist to perform a pre-construction survey prior to any ground disturbance ▪ SJMSCP Incidental take Minimization Measures and mitigation requirement:
1. Incidental Take Minimization Measures (ITMMs) will be issued to the project and must be signed by the project applicant prior to any ground disturbance but no later than six (6) months from receipt of the ITMMs. If ITMMs are not signed within six months, the applicant must reapply for SJMSCP Coverage. Upon receipt of signed ITMMs from project applicant, SJCOG, Inc. staff will sign the ITMMs. This is the effective date of the ITMMs.
2. Under no circumstance shall ground disturbance occur without compliance and satisfaction of the ITMMs.
3. Upon issuance of fully executed ITMMs and prior to any ground disturbance, the project applicant must:
a. Post a bond for payment of the applicable SJMSCP fee covering the entirety of the project acreage being covered (the bond should be valid for no longer than a 6 month period); or b. Pay the appropriate SJMSCP fee for the entirety of the project acreage being covered; or c. Dedicate land in-lieu of fees, either as conservation easements or fee title; or d. Purchase approved mitigation bank credits.
4. Within 6 months from the effective date of the ITMMs or issuance of a building permit, whichever occurs first, the project applicant must:
a. Pay the appropriate SJMSCP for the entirety of the project acreage being covered; or The Terraces - Project Condition Letter Packet
2 | S J C O G , I n c .
b. Dedicate land in-lieu of fees, either as conservation easements or fee title; or c. Purchase approved mitigation bank credits.
Failure to satisfy the obligations of the mitigation fee shall subject the bond to be called. ▪ Receive your Certificate of Payment and release the required permit It should be noted that if this project has any potential impacts to waters of the United States [pursuant to Section 404 Clean Water Act], it would require the project to seek voluntary coverage through the unmapped process under the SJMSCP which could take up to 90 days. It may be prudent to obtain a preliminary wetlands map from a qualified consultant. If waters of the United States are confirmed on the project site, the Corps and the Regional Water Quality Control Board (RWQCB) would have regulatory authority over those mapped areas [pursuant to Section 404 and 401 of the Clean Water Act respectively] and permits would be required from each of these resource agencies prior to grading the project site.
If you have any questions, please call (209) 235-0600.
The Terraces - Project Condition Letter Packet
3 | S J C O G , I n c .
S J C O G, Inc.
San Joaquin County Multi-Species Habitat Conservation & Open Space Plan 555 East Weber Avenue ● Stockton, CA 95202 ● (209) 235-0600 ● FAX (209) 235-0438
SJMSCP HOLD
TO: Local Jurisdiction: Community Development Department, Planning Department, Building Department, Engineering Department, Survey Department, Transportation Department, Other: ___________
FROM: Laurel Boyd, SJCOG, Inc.
DO NOT AUTHORIZE SITE DISTURBANCE
DO NOT ISSUE A BUILDING PERMIT
DO NOT ISSUE __________ FOR THIS PROJECT
The landowner/developer for this site has requested coverage pursuant to the San Joaquin County MultiSpecies Habitat Conservation and Open Space Plan (SJMSCP). In accordance with that agreement, the Applicant has agreed to:
1) SJMSCP Incidental Take Minimization Measures and mitigation requirement:
1. Incidental Take Minimization Measures (ITMMs) will be issued to the project and must be signed by the project applicant prior to any ground disturbance but no later than six (6) months from receipt of the ITMMs.
If ITMMs are not signed within six months, the applicant must reapply for SJMSCP Coverage. Upon receipt of signed ITMMs from project applicant, SJCOG, Inc. staff will sign the ITMMs. This is the effective date of the ITMMs.
2. Under no circumstance shall ground disturbance occur without compliance and satisfaction of the ITMMs.
3. Upon issuance of fully executed ITMMs and prior to any ground disturbance, the project applicant must:
a. Post a bond for payment of the applicable SJMSCP fee covering the entirety of the project acreage being covered (the bond should be valid for no longer than a 6 month period); or b. Pay the appropriate SJMSCP fee for the entirety of the project acreage being covered; or c. Dedicate land in-lieu of fees, either as conservation easements or fee title; or d. Purchase approved mitigation bank credits.
4. Within 6 months from the effective date of the ITMMs or issuance of a building permit, whichever occurs first, the project applicant must:
a. Pay the appropriate SJMSCP for the entirety of the project acreage being covered; or b. Dedicate land in-lieu of fees, either as conservation easements or fee title; or c. Purchase approved mitigation bank credits.
Failure to satisfy the obligations of the mitigation fee shall subject the bond to be called.
Project Title: Conditional Use Permit (UP21-70), Planned Unit Development (PUD21-79) Assessor Parcel #s: 259-180-16, -17
T _______, R______, Section(s): _____
Local Jurisdiction Contact: Ken Zuidervaart
The LOCAL JURISDICTION retains responsibility for ensuring that the appropriate Incidental Take Minimization Measures are properly implemented and monitored and that appropriate fees are paid in compliance with the SJMSCP.
The Terraces - Project Condition Letter Packet
SAN JOAQUIN
COUNTY
Greatness grows here.
Environmental Health Department
Jasjit Kang, REHS, Director
Muniappa Naidu, REHS, Assistant Director
PROGRAM COORDINATORS
Robert McClellon, REHS
Jeff Carruesco, REHS, RDI
Willy Ng, REHS
Melissa Nissim. REHS
Steven Shih, REHS
October 25, 2021
To: City of Ripon Department of Planning and Economic Development From: Aaron Gooderham (209) 616-3062
Registered Environmental Health Specialist
RE: UP21-70 & PUD21-79, Referral, SU0014474
816 W. Main Street & 200 Vera Avenue
The San Joaquin County Environmental Health Department (EHD) recommends the following conditions as a part of developing this project:
Submit two (2) hardcopy sets, or one (1) electronic version, of food facility plans to the Environmental Health Department for review and approval prior to issuance of building permit(s) (California Retail Food Code, Article 1, 114380). The fee will be based on the current schedule at the time of payment.
A valid permit from EHD is required prior to operating food facility (California Retail Food Code, Chapter 13, Article 1, Section 14381).
Any geotechnical drilling shall be conducted under permit and inspection by The Environmental Health Department (San Joaquin County Development Title, Section 9- 1115.3 and 9-1115.6).
1868 E. HazeIton Avenue I Stockton, California 95205 I 1 209 468-3420 I F 209 464-0138 I www.sjgov.org/ehd The Terraces - Project Condition Letter Packet
P.O. Box 747, Ripon, CA 95366-0747 (Mailing)
11011 E. Highway 120, Manteca, CA 95336-9750
(209) 249-4600
October 21, 2021
Ken Zuidervaart
City of Ripon
259 N. Wilma Ave.
Ripon, Ca 95366
Re: Bethany Home
816 W. Main and 200 Vera Avenue
APN: 259-180-16 & 17
Dear Mr. Zuidervaart:
Based upon review of the above referenced site plan, there does not appear to be any active District facilities located within the proposed site. However, there is an abandoned pipeline that has been filled with slurry along the west side of the properties. We’ve attached a plan for reference.
Thank you for the opportunity to review and comment on this matter. If you have any questions, please feel free to contact me at 249-4620.
Sincerely,
Forrest Killingsworth
Engineering Dept. Manager
The Terraces - Project Condition Letter Packet