CONTRACTOR: Diede Construction, Inc.
PROJECT: Fleet Maintenance Facility
PROJECT DESCRIPTION:
INVOICE NO: 1
DATE: 3/1/2023
ORIGINAL CONTRACT AMOUNT: $11,156,000.00 PREVIOUSLY BILLED AMOUNT: $0.00 LESS RETENTION: $0.00
APPROVED CONTRACT CHANGES: $288,622.00 PREVIOUSLY PAID AMOUNT: $0.00 CURRENT INVOICED AMOUNT: $502,526.60
LESS RETENTION: $25,126.33
TOTAL CONTRACT AMOUNT: $11,444,622.00 CURRENT AMOUNT DUE: $477,400.27 TOTAL BILLED TO DATE (INCL CURRENT INVOICE) $502,526.60 LESS RETENTION: $25,126.33
TOTAL PAID TO DATE: $477,400.27
INVOICE SUMMARY
TOTAL PROGRESS
Remaining Contract Amount: $10,942,095.40
Approx. % Complete: 4%
INVOICE SUMMARY
Project consists of a new maintenance and operations building and vehicle wash for the City of Ripon Public Works Dept., including a repair and machine shop, office spaces, restrooms and locker rooms.
CONTRACT INFORMATION BILLING INFORMATION
Work performed includes purchasing of bonds and insurance, submittals, construction staking, erosion control measures, mobilization, site clearing, scarifying and pre-compacting fill areas, rough grading, dirt offhaul, and pond berm restoration.