MEMO
To: Honorable City Council
From: Christiana Giedd, Associate Civil Engineer
Date: 11/14/2023
Subject: Fleet Maintenance Facility Change Order 6
RECOMMENDED ACTION:
Approve Change Order No. 6 for additional structural column, addition of power to electric trap primers, modifying existing storm drain manhole elevation, and piping credit in the not to exceed amount of $10,424 (funding sources: Corp Yard AB1600 Fund, Enterprise Capital Funds, and General Capital Fund).
BACKGROUND:
The Fleet Maintenance Facility Project was awarded to Diede Construction, Inc. at the December 13, 2022 City Council meeting for an amount of $11,156,000. The Fleet Maintenance Facility Project will involve the construction of a 12,500 square foot maintenance building and parking lot.
At the March 14, 2023 City Council meeting, Council approved Change Order No. 1 in the not to exceed amount of $288,622 for raising the elevation of the existing berm at the Wastewater Treatment Plant disposal ponds in order to provide additional storage capacity.
At the June 13, 2023 City Council meeting, Council approved Change Order No. 2 in the not to exceed amount of $1,466 for additional survey staking.
At the July 26, 2023 City Council meeting, Council approved Change Order No. 3 in the not to exceed amount of $132,150 for electrical revisions and revisions to accommodate SSJID, MID, and Fire Department requirements.
At the August 8, 2023 City Council meeting, Council approved Change Order No. 4 in the not to exceed amount of $4,889 for countertop leg panels, additional concrete for sidewalk, and filling an underground concrete pipe.
At the September 12, 2023 City Council meeting, Council approved Change Order No. 5 in the not to exceed amount of $62,905 for various contract changes related to unforeseen field conditions, electrical design changes, and new Modesto Irrigation District (MID) requirements.
DISCUSSION:
The Fleet Maintenance Facility Project required design changes due to field conditions, electrical revisions, and requirements from Modesto Irrigation District (MID), as summarized below:
Additional structural column: The structural design requires one more column than was included in the bid package. The additional cost related to this change is $651.
Electrical trap primer: The bid drawings for the building interior had a discrepancy between the plumbing and electrical drawings. The electrical trap primers shown on the plumbing plans need electrical connections. The additional cost related to this change is $3,281.
Modify existing SDMH elevation: An existing storm drain manhole (SDMH) requires an elevation adjustment that was not included in the bid package. The additional cost related to this change is $6,952.
Piping credit: The contractor issued a credit for piping that was not required for the project. The amount of credit issued for this change is $460.
The additional work is to be billed at a cost not to exceed $10,424.
FISCAL IMPACT:
The attached Change Order No. 6 is in the amount of $10,424 and will be allocated to the Corp Yard AB1600 Fund (47.0%), Water, Sewer and Storm Enterprise Capital Funds (15.8%) and General Capital Fund (37.2%). The amended construction contract price is shown in Table 1.
Table 1 – Current Contract Price
Amount
Original Contract Price $ 11,156,000
Change Orders (1-6) $ 500,456
Current Contract Price $ 11,656,456
On December 13, 2022, City Council approved the total cost of the Fleet Maintenance Facility Project which included $1,115,600 for construction contingency. Change Order No. 1 did not utilize the project contingency because the work was performed at the Wastewater Treatment Plant disposal ponds. The total remaining contingency after subtracting Change Orders No. 2 through 6 is $903,766.