MEMO
To: Honorable City Council
From: Christiana Giedd, Associate Civil Engineer
Date: 02/13/2024
Subject: Fleet Maintenance Facility Change Order 8
RECOMMENDED ACTION:

Approve Change Order No. 8 for flagpole modifications, electric vehicle charging station conduit, and a credit for the removal of skylights from the contract in the not to exceed amount of $11,920 (funding sources: Corp Yard AB1600 Fund, Enterprise Capital Funds, and General Capital Fund).

BACKGROUND:

The Fleet Maintenance Facility Project was awarded to Diede Construction, Inc. at the December 13, 2022 City Council meeting for an amount of $11,156,000. The Fleet Maintenance Facility Project will involve the construction of a 12,500 square foot maintenance building and parking lot.

At the March 14, 2023 City Council meeting, Council approved Change Order No. 1 in the not to exceed amount of $288,622 for raising the elevation of the existing berm at the Wastewater Treatment Plant disposal ponds in order to provide additional storage capacity.

At the June 13, 2023 City Council meeting, Council approved Change Order No. 2 in the not to exceed amount of $1,466 for additional survey staking.

At the July 26, 2023 City Council meeting, Council approved Change Order No. 3 in the not to exceed amount of $132,150 for electrical revisions and revisions to accommodate SSJID, MID, and Fire Department requirements.

At the August 8, 2023 City Council meeting, Council approved Change Order No. 4 in the not to exceed amount of $4,889 for countertop leg panels, additional concrete for sidewalk, and filling an underground concrete pipe.

At the September 12, 2023 City Council meeting, Council approved Change Order No. 5 in the not to exceed amount of $62,905 for various contract changes related to unforeseen field conditions, electrical design changes, and new Modesto Irrigation District (MID) requirements.

At the November 14, 2023 City Council meeting, Council approved Change Order No. 6 in the not to exceed amount of $10,424 for an additional structural column, addition of power to electric trap primers, modifying existing storm drain manhole elevation, and piping credit.

At the December 12, 2023 City Council meeting, Council approved Change Order No. 7 in the not to exceed amount of $26,385 for additional grading and paving, restroom wall tile changes, fixture credit, and doorframe and hardware changes.

DISCUSSION:

The Fleet Maintenance Facility Project has the following contract changes:

Flagpole modifications: The original bid included a flagpole that could hang up to a 5’x7’ flag and did not require lighting. The City plans to install a larger flagpole in the future that will require lighting. The original flagpole will no longer be installed as part of this contract and the Contractor installed the required conduit for the future flagpole lighting. The removal of the flagpole from the project resulted in a $5,288 credit and the addition of conduit for future flagpole lighting added a cost of $3,901. The net credit issued for this change is $1,387.

Electric vehicle (EV) charging station conduit: The original bid package included conduit for future EV charging station locations, but none of the locations were in parking spaces intended for larger vehicles. Staff requested a change order from the Contractor to run four conduit lines to the larger parking stalls for future EV charging stations. The additional cost related to this change is $18,613.

Skylight credit: The original contract included translucent panels that are no longer manufactured and therefore will not be installed. The Contractor has issued a credit for the installation and materials associated with this work. The amount of credit issued for this change is $5,306.

The additional work is to be billed at a cost not to exceed $11,920.

FISCAL IMPACT:

The attached Change Order No. 8 is in the amount of $11,920 and will be allocated to the Corp Yard AB1600 Fund (47.0%), Water, Sewer and Storm Enterprise Capital Funds (15.8%) and General Capital Fund (37.2%). The amended construction contract price is shown in Table 1.

Table 1 – Current Contract Price
Amount
Original Contract Price $ 11,156,000
Change Orders (1-8) $ 538,761
Current Contract Price $ 11,694,761
On December 13, 2022, City Council approved the total cost of the Fleet Maintenance Facility Project which included $1,115,600 for construction contingency. Change Order No. 1 did not utilize the project contingency because the work was performed at the Wastewater Treatment Plant disposal ponds. The total remaining contingency after subtracting Change Orders No. 2 through 8 is $865,461.