F:\USERS\PLAN2\Fire Dept\General Requirements 11-16.doc 1 of 3
RIPON FIRE DISTRICT
Standard Specifications
For: General Conditions for Development
Date: 11-06-16
Supersedes: 02-01-08
Purpose: To provide standard conditions for approval of projects within the jurisdiction of the Ripon Fire District. The conditions listed in this document are not intended to be all-inclusive, and the District may impose additional conditions or requirements prior to approval. Projects are required to be constructed in accordance with any and all applicable local, state and federal laws and regulations.
FIRE DEPARTMENT ACCESS
All designated fire access routes and lanes shall be in accordance with the currently adopted codes, and as required by the District. Fire lanes will be marked in accordance with District specifications and approved by the District prior to installation. All gates located on fire access route shall be provided with means for entry as approved by the District.
One or more Knox Key Boxes shall be installed at a location approved by the District.
PREMISES IDENTIFICATION
All buildings shall be provided with approved street address/suite numbers, plainly visible and legible from the street. Where a building is set back from the street or road fronting the property, and whenever an addresses may not be clearly identifiable due to distance from the street or roadway, landscape, architectural appendages or other obstructions, address posting shall be required both at the street driveway serving the building(s) and on the building(s).
Size and Height
Determined by distance to location of address as posted, measured from curb. 25 Feet 4 inch
26-40 Feet 6 inch
41-55 Feet 9 inch
Over 55 Feet 12 inch
Numbers shall be a minimum of a ¾” stroke and shall contrast with their background.
Rear of Buildings
Any business or apartment building which affords vehicular access to the rear through a driveway, alley way or parking lot, shall also display approved identification or address numbers on the rear of the building for such business or apartment building in a location approved by the Fire Chief.
Multiple Dwelling Units
An approved diagram of the premises which clearly indicates all individual addresses of each unit in the complex shall be erected at the entrance driveways to every multiple dwelling complex having more than one building on the premises or when required by the Fire Chief. In addition, the Fire Chief may require that individual buildings on the premises be identified in an approved manner.
Exhibit A
F:\USERS\PLAN2\Fire Dept\General Requirements 11-16.doc 2 of 3
Premises identification-Multiple Buildings
An approved identification of multiple buildings within an industrial complex shall be required which clearly indicates each individual building in the complex. Identification shall be placed on each building in a size and location when required by the Fire Chief and be visible for responding emergency personal in an approved manner.
WATER SUPPLY
Water Supplies and Fire Hydrants shall be in accordance with all current codes and specifications adopted by the District.
Fire hydrant location, distribution and installation shall be in accordance with the current codes and specifications adopted by the District.
All Hydrants shall be supplied by a dedicated 8” service from the main line, unless otherwise approved by the Fire Chief.
On-site systems may be required to be supplied from two directions otherwise known as “looped” systems.
FIRE CODE PLAN CHECK
Submit 3 complete set of plans to the Ripon Fire District office located at 142 S. Stockton Ave. in Ripon, CA. Plans for fire protection systems shall be submitted and approved prior to construction, unless other arrangements have been made and approved to by the District.
FIRE PROTECTION SYSTEMS
Automatic Sprinkler Systems
Submit five (5) complete sets of sprinkler system plans and hydraulic calculations to the Ripon Fire District. All plans for fire protection systems shall be submitted and approved prior to construction, unless other arrangements have been made and approved by the District.
System Requirements
The location of all hydrants, fire department connections, indicating valves, etc. shall be approved by the District prior to installation. All hydrants, OS&Y’s and FDC’s shall be painted for identification purposes as required by the Fire District.
All fire department connections (FDC) shall be provided with locking cap(s) to prevent tampering. The approved make and model is as follows:
KNOX Company
Locking FDC Cap
Model #3011
Ordering information for Knox Company products is available from the District office.
All backflow and detector check assemblies shall be installed per City of Ripon specifications, and monitored with tamper switch(s). Indicating valves shall be provided with locking devices in order to lock valve(s) in open position.
All piping that is any part of an automatic sprinkler system shall meet the C 900 specification, rated at 200 psi.
Unless otherwise approved, all automatic sprinkler systems shall be supplied by a dedicated 8” connection from the main line.
Fire Department Connections (FDC) shall be located within 30 feet of an approved fire hydrant.
Exhibit A
F:\USERS\PLAN2\Fire Dept\General Requirements 11-16.doc 3 of 3
ALARM SYSTEMS
Automatic Fire Suppression Systems controls shall be monitored by an approved alarm monitoring Service. Three (3) sets of plans and equipment specifications shall be submitted to the District for approval prior to installation.
The following devices shall be monitored by the alarm system:
System valves - Tamper Switches
Sprinkler Risers - Flow switches
Post Indicator Valves - Tamper Switches
Manual Pull Stations
Commercial Hood & Duct Systems
COMMERCIAL COOKING OPERATIONS
Automatic Fire Suppression Systems shall be installed for protection of commercial cooking equipment. Submit three (3) complete sets of plans for hood & duct systems to the Ripon Fire District Office for review and approval prior to installation.
INSPECTIONS
Builder/Contractor is required to contact the Fire District 24 hours in advance to arrange the following on-site inspections when required:
Fire Access Roads and Lanes
Sprinkler Systems
Fire Alarm Systems
Fire Hydrant Installation
Fire Extinguisher Placement
Special Systems
Final Occupancy Inspections
FIRE EXTINGUISHERS
Provide extinguishers with a minimum rating of 2A 10B:C within 75 feet of exits and for every 3000 square feet in general use areas. Placement of extinguishers shall be in compliance with currently adopted codes. In any event, placement of fire extinguishers shall meet or exceed Section 906 of the California Fire Code.
The Fire District shall be notified prior to occupancy of the facility for the approval of the locations, type and size of each fire extinguisher. Extinguishers are required during construction, alteration or demolition of any building. Fire Extinguishers shall be tagged by a licensed extinguisher service company prior to installation.
FEES
Plan Check/Inspection Fees
Plan check/inspection fees will be charged for the following in accordance with the fee schedule adopted by the Board of Directors of the Ripon Fire District:
Fire Code Plan Check
Fire Protection Systems
Commercial Cooking Operations (Hood and Duct) Fire Protection Systems Fire Alarm Systems
A list of permit fees can be found on the Ripon Fire District website @ www.riponfire.com Fire Impact Fees
Fire Impact Fees will be charged in accordance with the fee schedule on record at the City of Ripon and/or as described in the Development Agreement between the City of Ripon and the Developer.
Exhibit A
1231 Eleventh St.
P.O. Box 4060
Modesto, CA 95352
(209) 526-7373
October 7, 2020
City of Ripon – Department of Planning and Economic Development 259 N. Wilma Ave.
Ripon, CA 95366
RE: Tentative Parcel Map - PM20-32
APN: 228-110-10 (1302 W. Santos Ave., Ripon, CA)
Thank you for allowing the District to comment on this referral. Following are the recommendations from our Electrical, Irrigation and Domestic Water Divisions:
Irrigation
• No Comments at this time.
Domestic Water
• No Comments at this time.
Electrical
• The electric division does not have any electric facilities within or adjacent to the project area. This area falls within the PG&E and MID competitive zone. If electric service is desired contact the District’s Electric Engineering department to determine the availability of electric service and coordinate service requirements to the propose project. Please contact Modesto Irrigation District at (209) 526-7337 or (888) 335-1643 and ask for the Electrical Engineering Design Group if you have any questions or concerns.
The Modesto Irrigation District reserves its future rights to utilize its property, including its canal and electrical easements and rights-of-way, in a manner it deems necessary for the installation and maintenance of electric, irrigation, agricultural and urban drainage, domestic water and telecommunication facilities.
These needs, which have not yet been determined, may consist of poles, crossarms, wires, cables, braces, insulators, transformers, service lines, open channels, pipelines, control structures and any necessary appurtenances, as may, in District’s opinion, be necessary or desirable.
If you have any questions, please contact me at (209) 526-7447.
Sincerely,
Lien Campbell
Risk & Property Analyst
Copy: File
Lien Campbell
Exhibit A
Plan Review Team
Land Management
[email protected]
6111 Bollinger Canyon Road 3370A
San Ramon, CA 94583
PG&E Gas and Electric Facilities Page 1
October 8, 2020
Mitzi Johnson
City of Ripon
259 N Wilma Ave
Ripon, CA 95366
Ref: Gas and Electric Transmission and Distribution
Dear Mitzi Johnson,
Thank you for submitting the 1302 W Santos Ave plans for our review. PG&E will review the submitted plans in relationship to any existing Gas and Electric facilities within the project area.
If the proposed project is adjacent/or within PG&E owned property and/or easements, we will be working with you to ensure compatible uses and activities near our facilities.
Attached you will find information and requirements as it relates to Gas facilities (Attachment 1) and Electric facilities (Attachment 2). Please review these in detail, as it is critical to ensure your safety and to protect PG&E’s facilities and its existing rights.
Below is additional information for your review:
1. This plan review process does not replace the application process for PG&E gas or electric service your project may require. For these requests, please continue to work with PG&E Service Planning: https://www.pge.com/en_US/business/services/buildingand-renovation/overview/overview.page.
2. If the project being submitted is part of a larger project, please include the entire scope of your project, and not just a portion of it. PG&E’s facilities are to be incorporated within any CEQA document. PG&E needs to verify that the CEQA document will identify any required future PG&E services.
3. An engineering deposit may be required to review plans for a project depending on the size, scope, and location of the project and as it relates to any rearrangement or new installation of PG&E facilities.
Any proposed uses within the PG&E fee strip and/or easement, may include a California Public Utility Commission (CPUC) Section 851 filing. This requires the CPUC to render approval for a conveyance of rights for specific uses on PG&E’s fee strip or easement. PG&E will advise if the necessity to incorporate a CPUC Section 851filing is required.
This letter does not constitute PG&E’s consent to use any portion of its easement for any purpose not previously conveyed. PG&E will provide a project specific response as required.
Sincerely,
Plan Review Team
Land Management
Exhibit A
PG&E Gas and Electric Facilities Page 2
Attachment 1 – Gas Facilities
There could be gas transmission pipelines in this area which would be considered critical facilities for PG&E and a high priority subsurface installation under California law. Care must be taken to ensure safety and accessibility. So, please ensure that if PG&E approves work near gas transmission pipelines it is done in adherence with the below stipulations. Additionally, the following link provides additional information regarding legal requirements under California excavation laws: https://www.usanorth811.org/images/pdfs/CA-LAW-2018.pdf
1. Standby Inspection: A PG&E Gas Transmission Standby Inspector must be present during any demolition or construction activity that comes within 10 feet of the gas pipeline. This includes all grading, trenching, substructure depth verifications (potholes), asphalt or concrete demolition/removal, removal of trees, signs, light poles, etc. This inspection can be coordinated through the Underground Service Alert (USA) service at 811. A minimum notice of 48 hours is required. Ensure the USA markings and notifications are maintained throughout the duration of your work.
2. Access: At any time, PG&E may need to access, excavate, and perform work on the gas pipeline. Any construction equipment, materials, or spoils may need to be removed upon notice.
Any temporary construction fencing installed within PG&E’s easement would also need to be capable of being removed at any time upon notice. Any plans to cut temporary slopes exceeding a 1:4 grade within 10 feet of a gas transmission pipeline need to be approved by PG&E Pipeline Services in writing PRIOR to performing the work.
3. Wheel Loads: To prevent damage to the buried gas pipeline, there are weight limits that must be enforced whenever any equipment gets within 10 feet of traversing the pipe.
Ensure a list of the axle weights of all equipment being used is available for PG&E’s Standby Inspector. To confirm the depth of cover, the pipeline may need to be potholed by hand in a few areas.
Due to the complex variability of tracked equipment, vibratory compaction equipment, and cranes, PG&E must evaluate those items on a case-by-case basis prior to use over the gas pipeline (provide a list of any proposed equipment of this type noting model numbers and specific attachments).
No equipment may be set up over the gas pipeline while operating. Ensure crane outriggers are at least 10 feet from the centerline of the gas pipeline. Transport trucks must not be parked over the gas pipeline while being loaded or unloaded.
4. Grading: PG&E requires a minimum of 36 inches of cover over gas pipelines (or existing grade if less) and a maximum of 7 feet of cover at all locations. The graded surface cannot exceed a cross slope of 1:4.
5. Excavating: Any digging within 2 feet of a gas pipeline must be dug by hand. Note that while the minimum clearance is only 12 inches, any excavation work within 24 inches of the edge of a pipeline must be done with hand tools. So to avoid having to dig a trench entirely with hand tools, the edge of the trench must be over 24 inches away. (Doing the math for a 24 inch Exhibit A
PG&E Gas and Electric Facilities Page 3
wide trench being dug along a 36 inch pipeline, the centerline of the trench would need to be at least 54 inches [24/2 + 24 + 36/2 = 54] away, or be entirely dug by hand.) Water jetting to assist vacuum excavating must be limited to 1000 psig and directed at a 40° angle to the pipe. All pile driving must be kept a minimum of 3 feet away.
Any plans to expose and support a PG&E gas transmission pipeline across an open excavation need to be approved by PG&E Pipeline Services in writing PRIOR to performing the work.
6. Boring/Trenchless Installations: PG&E Pipeline Services must review and approve all plans to bore across or parallel to (within 10 feet) a gas transmission pipeline. There are stringent criteria to pothole the gas transmission facility at regular intervals for all parallel bore installations.
For bore paths that cross gas transmission pipelines perpendicularly, the pipeline must be potholed a minimum of 2 feet in the horizontal direction of the bore path and a minimum of 12 inches in the vertical direction from the bottom of the pipe with minimum clearances measured from the edge of the pipe in both directions. Standby personnel must watch the locator trace (and every ream pass) the path of the bore as it approaches the pipeline and visually monitor the pothole (with the exposed transmission pipe) as the bore traverses the pipeline to ensure adequate clearance with the pipeline. The pothole width must account for the inaccuracy of the locating equipment.
7. Substructures: All utility crossings of a gas pipeline should be made as close to perpendicular as feasible (90° +/- 15°). All utility lines crossing the gas pipeline must have a minimum of 12 inches of separation from the gas pipeline. Parallel utilities, pole bases, water line ‘kicker blocks’, storm drain inlets, water meters, valves, back pressure devices or other utility substructures are not allowed in the PG&E gas pipeline easement.
If previously retired PG&E facilities are in conflict with proposed substructures, PG&E must verify they are safe prior to removal. This includes verification testing of the contents of the facilities, as well as environmental testing of the coating and internal surfaces. Timelines for PG&E completion of this verification will vary depending on the type and location of facilities in conflict.
8. Structures: No structures are to be built within the PG&E gas pipeline easement. This includes buildings, retaining walls, fences, decks, patios, carports, septic tanks, storage sheds, tanks, loading ramps, or any structure that could limit PG&E’s ability to access its facilities.
9. Fencing: Permanent fencing is not allowed within PG&E easements except for perpendicular crossings which must include a 16 foot wide gate for vehicular access. Gates will be secured with PG&E corporation locks.
10. Landscaping: Landscaping must be designed to allow PG&E to access the pipeline for maintenance and not interfere with pipeline coatings or other cathodic protection systems. No trees, shrubs, brush, vines, and other vegetation may be planted within the easement area.
Only those plants, ground covers, grasses, flowers, and low-growing plants that grow unsupported to a maximum of four feet (4’) in height at maturity may be planted within the easement area.
Exhibit A
PG&E Gas and Electric Facilities Page 4
11. Cathodic Protection: PG&E pipelines are protected from corrosion with an “Impressed Current” cathodic protection system. Any proposed facilities, such as metal conduit, pipes, service lines, ground rods, anodes, wires, etc. that might affect the pipeline cathodic protection system must be reviewed and approved by PG&E Corrosion Engineering.
12. Pipeline Marker Signs: PG&E needs to maintain pipeline marker signs for gas transmission pipelines in order to ensure public awareness of the presence of the pipelines.
With prior written approval from PG&E Pipeline Services, an existing PG&E pipeline marker sign that is in direct conflict with proposed developments may be temporarily relocated to accommodate construction work. The pipeline marker must be moved back once construction is complete.
13. PG&E is also the provider of distribution facilities throughout many of the areas within the state of California. Therefore, any plans that impact PG&E’s facilities must be reviewed and approved by PG&E to ensure that no impact occurs which may endanger the safe operation of its facilities.
Exhibit A
PG&E Gas and Electric Facilities Page 5
Attachment 2 – Electric Facilities
It is PG&E’s policy to permit certain uses on a case by case basis within its electric transmission fee strip(s) and/or easement(s) provided such uses and manner in which they are exercised, will not interfere with PG&E’s rights or endanger its facilities. Some examples/restrictions are as follows:
1. Buildings and Other Structures: No buildings or other structures including the foot print and eave of any buildings, swimming pools, wells or similar structures will be permitted within fee strip(s) and/or easement(s) areas. PG&E’s transmission easement shall be designated on subdivision/parcel maps as “RESTRICTED USE AREA – NO BUILDING.”
2. Grading: Cuts, trenches or excavations may not be made within 25 feet of our towers.
Developers must submit grading plans and site development plans (including geotechnical reports if applicable), signed and dated, for PG&E’s review. PG&E engineers must review grade changes in the vicinity of our towers. No fills will be allowed which would impair ground-toconductor clearances. Towers shall not be left on mounds without adequate road access to base of tower or structure.
3. Fences: Walls, fences, and other structures must be installed at locations that do not affect the safe operation of PG&’s facilities. Heavy equipment access to our facilities must be maintained at all times. Metal fences are to be grounded to PG&E specifications. No wall, fence or other like structure is to be installed within 10 feet of tower footings and unrestricted access must be maintained from a tower structure to the nearest street. Walls, fences and other structures proposed along or within the fee strip(s) and/or easement(s) will require PG&E review; submit plans to PG&E Centralized Review Team for review and comment.
4. Landscaping: Vegetation may be allowed; subject to review of plans. On overhead electric transmission fee strip(s) and/or easement(s), trees and shrubs are limited to those varieties that do not exceed 15 feet in height at maturity. PG&E must have access to its facilities at all times, including access by heavy equipment. No planting is to occur within the footprint of the tower legs. Greenbelts are encouraged.
5. Reservoirs, Sumps, Drainage Basins, and Ponds: Prohibited within PG&E’s fee strip(s) and/or easement(s) for electric transmission lines.
6. Automobile Parking: Short term parking of movable passenger vehicles and light trucks (pickups, vans, etc.) is allowed. The lighting within these parking areas will need to be reviewed by PG&E; approval will be on a case by case basis. Heavy equipment access to PG&E facilities is to be maintained at all times. Parking is to clear PG&E structures by at least 10 feet.
Protection of PG&E facilities from vehicular traffic is to be provided at developer’s expense AND to PG&E specifications. Blocked-up vehicles are not allowed. Carports, canopies, or awnings are not allowed.
7. Storage of Flammable, Explosive or Corrosive Materials: There shall be no storage of fuel or combustibles and no fueling of vehicles within PG&E’s easement. No trash bins or incinerators are allowed.
Exhibit A
PG&E Gas and Electric Facilities Page 6
8. Streets and Roads: Access to facilities must be maintained at all times. Street lights may be allowed in the fee strip(s) and/or easement(s) but in all cases must be reviewed by PG&E for proper clearance. Roads and utilities should cross the transmission easement as nearly at right angles as possible. Road intersections will not be allowed within the transmission easement.
9. Pipelines: Pipelines may be allowed provided crossings are held to a minimum and to be as nearly perpendicular as possible. Pipelines within 25 feet of PG&E structures require review by PG&E. Sprinklers systems may be allowed; subject to review. Leach fields and septic tanks are not allowed. Construction plans must be submitted to PG&E for review and approval prior to the commencement of any construction.
10. Signs: Signs are not allowed except in rare cases subject to individual review by PG&E.
11. Recreation Areas: Playgrounds, parks, tennis courts, basketball courts, barbecue and light trucks (pickups, vans, etc.) may be allowed; subject to review of plans. Heavy equipment access to PG&E facilities is to be maintained at all times. Parking is to clear PG&E structures by at least 10 feet. Protection of PG&E facilities from vehicular traffic is to be provided at developer’s expense AND to PG&E specifications.
12. Construction Activity: Since construction activity will take place near PG&E’s overhead electric lines, please be advised it is the contractor’s responsibility to be aware of, and observe the minimum clearances for both workers and equipment operating near high voltage electric lines set out in the High-Voltage Electrical Safety Orders of the California Division of Industrial Safety (https://www.dir.ca.gov/Title8/sb5g2.html), as well as any other safety regulations.
Contractors shall comply with California Public Utilities Commission General Order 95 (http://www.cpuc.ca.gov/gos/GO95/go_95_startup_page.html) and all other safety rules. No construction may occur within 25 feet of PG&E’s towers. All excavation activities may only commence after 811 protocols has been followed.
Contractor shall ensure the protection of PG&E’s towers and poles from vehicular damage by (installing protective barriers) Plans for protection barriers must be approved by PG&E prior to construction.
13. PG&E is also the owner of distribution facilities throughout many of the areas within the state of California. Therefore, any plans that impact PG&E’s facilities must be reviewed and approved by PG&E to ensure that no impact occurs that may endanger the safe and reliable operation of its facilities.
Exhibit A
P.O. Box 747, Ripon, CA 95366-0747 (Mailing)
11011 E. Highway 120, Manteca, CA 95336-9750
(209) 249-4600
September 30, 2020
Ken Zuidervaart
City of Ripon
259 N. Wilma Ave.
Ripon, CA 95366
Subject: PM20-32, UP20-33
Owner: Thompson Family Living Trust
Dear Mr. Zuidervaart:
The South San Joaquin Irrigation District owns, operates and maintains irrigation and/or drainage facilities which may provide service to the property described in the subject application.
When property boundaries are changed, it is likely to affect the current method of water billing and water delivery. In some cases, the District will no longer be able to provide irrigation service unless certain provisions are made to extend or relocate facilities to accommodate the newly established parcels. Further conflicts could occur if these parcels are sold or transferred to others without provisions for irrigation service.
Based upon the information provided in the referral, there may be a concern relative to the District’s ability to continue to service the newly configured parcels. If changes in the method of irrigation are desired by owner, it is recommended that the owner contact the District, prior to the completion of the process, to determine the necessity for changes to the existing infrastructure, or easements in order to accommodate the proposed boundary changes. The owner will need to Exhibit A
P.O. Box 747, Ripon, CA 95366-0747 (Mailing)
11011 E. Highway 120, Manteca, CA 95336-9750
(209) 249-4600
provide information concerning any changes in the method in which the adjusted parcels will be irrigated and may need to obtain a structure permit if new connections are necessary.
Owners may contact Dawn Driesen, in the Engineering Dept. at 249-4619 for further information and assistance in this matter.
Sincerely,
Forrest Killingsworth
Engineering Dept. Manager
Exhibit A
S J C O G, Inc.
555 East Weber Avenue ● Stockton, CA 95202 ● (209) 235-0600 ● FAX (209) 235-0438 San Joaquin County Multi-Species Habitat Conservation & Open Space Plan (SJMSCP)
SJMSCP RESPONSE TO LOCAL JURISDICTION (RTLJ)
ADVISORY AGENCY NOTICE TO SJCOG, Inc.
To: Ken Zuidervaart, City of Ripon, Community Development Department From: Laurel Boyd, SJCOG, Inc.
Date: September 29, 2020
Local Jurisdiction Project Title: Tentative Parcel Map (PM20-32), Conditional Use Permit (UP20-33) Assessor Parcel Number(s): 228-110-10
Local Jurisdiction Project Number: PM20-32, UP20-33
Total Acres to be converted from Open Space Use: Unknown Habitat Types to be Disturbed: Multi-Purpose Open Space Habitat Land Species Impact Findings: Findings to be determined by SJMSCP biologist.
Dear Mr. Zuidervaart:
SJCOG, Inc. has reviewed the application referral the Tentative Parcel Map (PM20-32) and Conditional Use Permit (UP20- 33) This project consists of a request to subdivide a 13.26 acre site into two parcels in order to develop 4.09 acres of the parcel as a battery energy storage and substation facility. The site is located in the C4 (Highway Service) district. The proposal is to construct and operate the Battery Energy Storage System (BESS) to enhance transmission grid reliability and further California’s goal of decarbonizing the energy sector. The project would consist of battery storage cabinets, transformers, inverters, a main step-up transformer, and an interconnection line to the Ripon Substation. The project would also include on-site and off-site improvements, including landscaping, a security barrier and streetscape improvements.
The project site is located at 1302 W. Santos Ave, Ripon, (APN: 228-110-10).
The City of Ripon is a signatory to San Joaquin County Multi-Species Habitat Conservation and Open Space Plan (SJMSCP). Participation in the SJMSCP satisfies requirements of both the state and federal endangered species acts and ensures that the impacts are mitigated below a level of significance in compliance with the California Environmental Quality Act (CEQA). The LOCAL JURISDICTION retains responsibility for ensuring that the appropriate Incidental Take Minimization Measure are properly implemented and monitored and that appropriate fees are paid in compliance with the SJMSCP. Although participation in the SJMSCP is voluntary, Local Jurisdiction/Lead Agencies should be aware that if project applicants choose against participating in the SJMSCP, they will be required to provide alternative mitigation in an amount and kind equal to that provided in the SJMSCP.
At this time, the applicant is requesting a Subdivision with no ground disturbance. Any future ground disturbing activities (e.g. roads, curb, gutter, electrical, water, etc.) or any physical structures that require ground disturbance on this or subsequent divided parcels will be subject to participate in the SJMSCP before ANY ground disturbance occurs and should be resubmitted to this agency. Current or future owners of this-or subdivided properties should be made aware of the conditions that are placed by the SJMSCP on future development on the created parcels.
This Project is subject to the SJMSCP. This can be up to a 30-day process and it is recommended that the project applicant contact SJMSCP staff as early as possible. It is also recommended that the project applicant obtain an information package. http://www.sjcog.org
Please contact SJMSCP staff regarding completing the following steps to satisfy SJMSCP requirements:
▪ Schedule a SJMSCP Biologist to perform a pre-construction survey prior to any ground disturbance ▪ SJMSCP Incidental Take Minimization Measures and mitigation requirement:
1. Incidental Take Minimization Measures (ITMMs) will be issued to the project and must be signed by the project applicant prior to any ground disturbance but no later than six (6) months from receipt of the ITMMs. If ITMMs are not signed within six months, the applicant Exhibit A
2 | S J C O G , I n c .
must reapply for SJMSCP Coverage. Upon receipt of signed ITMMs from project applicant, SJCOG, Inc. staff will sign the ITMMs. This is the effective date of the ITMMs.
2. Under no circumstance shall ground disturbance occur without compliance and satisfaction of the ITMMs.
3. Upon issuance of fully executed ITMMs and prior to any ground disturbance, the project applicant must:
a. Post a bond for payment of the applicable SJMSCP fee covering the entirety of the project acreage being covered (the bond should be valid for no longer than a 6 month period); or b. Pay the appropriate SJMSCP fee for the entirety of the project acreage being covered; or c. Dedicate land in-lieu of fees, either as conservation easements or fee title; or d. Purchase approved mitigation bank credits.
4. Within 6 months from the effective date of the ITMMs or issuance of a building permit, whichever occurs first, the project applicant must:
a. Pay the appropriate SJMSCP for the entirety of the project acreage being covered; or b. Dedicate land in-lieu of fees, either as conservation easements or fee title; or c. Purchase approved mitigation bank credits.
Failure to satisfy the obligations of the mitigation fee shall subject the bond to be called. ▪ Receive your Certificate of Payment and release the required permit It should be noted that if this project has any potential impacts to waters of the United States [pursuant to Section 404 Clean Water Act], it would require the project to seek voluntary coverage through the unmapped process under the SJMSCP which could take up to 90 days. It may be prudent to obtain a preliminary wetlands map from a qualified consultant. If waters of the United States are confirmed on the project site, the Corps and the Regional Water Quality Control Board (RWQCB) would have regulatory authority over those mapped areas [pursuant to Section 404 and 401 of the Clean Water Act respectively] and permits would be required from each of these resource agencies prior to grading the project site.
If you have any questions, please call (209) 235-0600.
Exhibit A
3 | S J C O G , I n c .
S J C O G, Inc.
San Joaquin County Multi-Species Habitat Conservation & Open Space Plan 555 East Weber Avenue ● Stockton, CA 95202 ● (209) 235-0600 ● FAX (209) 235-0438
SJMSCP HOLD
TO: Local Jurisdiction: Community Development Department, Planning Department, Building Department, Engineering Department, Survey Department, Transportation Department, Public Works Department,
Other: ___________
FROM: Laurel Boyd, SJCOG, Inc.
DO NOT AUTHORIZE SITE DISTURBANCE
DO NOT ISSUE A BUILDING PERMIT
DO NOT ISSUE __________ FOR THIS PROJECT
The landowner/developer for this site has requested coverage pursuant to the San Joaquin County MultiSpecies Habitat Conservation and Open Space Plan (SJMSCP). In accordance with that agreement, the Applicant has agreed to:
1) SJMSCP Incidental Take Minimization Measures and mitigation requirement:
1. Incidental Take Minimization Measures (ITMMs) will be issued to the project and must be signed by the project applicant prior to any ground disturbance but no later than six (6) months from receipt of the ITMMs.
If ITMMs are not signed within six months, the applicant must reapply for SJMSCP Coverage. Upon receipt of signed ITMMs from project applicant, SJCOG, Inc. staff will sign the ITMMs. This is the effective date of the ITMMs.
2. Under no circumstance shall ground disturbance occur without compliance and satisfaction of the ITMMs.
3. Upon issuance of fully executed ITMMs and prior to any ground disturbance, the project applicant must:
a. Post a bond for payment of the applicable SJMSCP fee covering the entirety of the project acreage being covered (the bond should be valid for no longer than a 6 month period); or b. Pay the appropriate SJMSCP fee for the entirety of the project acreage being covered; or c. Dedicate land in-lieu of fees, either as conservation easements or fee title; or d. Purchase approved mitigation bank credits.
4. Within 6 months from the effective date of the ITMMs or issuance of a building permit, whichever occurs first, the project applicant must:
a. Pay the appropriate SJMSCP for the entirety of the project acreage being covered; or b. Dedicate land in-lieu of fees, either as conservation easements or fee title; or c. Purchase approved mitigation bank credits.
Failure to satisfy the obligations of the mitigation fee shall subject the bond to be called.
Project Title: Tentative Parcel Map (PM20-32), Conditional Use Permit (UP20-33) Landowner: Thompson Family Living Trust Applicant: Noosa Energy Storage, LLC Assessor Parcel #s: 228-110-10
T _______, R______, Section(s): _____
Local Jurisdiction Contact: Ken Zuidervaart
The LOCAL JURISDICTION retains responsibility for ensuring that the appropriate Incidental Take Minimization Measures are properly implemented and monitored and that appropriate fees are paid in compliance with the SJMSCP.
Exhibit A
c SAN joAouiN
. --COUNTY
Greatness grows here.
Environmental Health Department
Jasjit Kang, REHS, Interim Director
Muniappa Naidu, REHS, Assistant Director
PROGRAM COORDINATORS
Robert McCiellon, REHS
Jeff Carruesco, REHS, RDI
Willy Ng, REHS
Michael Kith, REHS
Melissa Nissim, REHS
October 15, 2020
To: City of Ripon Department of Planning and Economic Development Attention: Ken Zuidervaart
From: Naseem Ahmed; 209-616-3018
Senior Registered Environmental Health Specialist
RE: Tentative Parcel Map (PM-20-32), SU0013671
1302 W. Santos Ave, Ripon
The following requirements have been identified as pertinent to this project. Other requirements may also apply. These requirements cannot be modified.
The San Joaquin County Environmental Health Department (EHD) is supportive of this project in regards to the provision of full public services.
Any existing wells or septic systems to be abandoned shall be destroyed under permit and inspection by the EHD (San Joaquin County Development Title, Section 9-1110.3 & 9-1110.4) Note: During site visit one domestic well was discovered in the shop building and one agricultural well was discovered in the almond orchard.
Any geotechnical drilling shall be conducted under permit and inspection by The Environmental Health Department (San Joaquin County Development Title, Section 9-1115.3 and 9-1115.6).
Before any hazardous materials/waste can be stored or used onsite, the owner/operator must report the use or storage of these hazardous materials to the California Environmental Reporting System (CERS) at cers.calepa.ca.qov/ and comply with the laws and regulations for the programs listed below (based on quantity of hazardous material in some cases). The applicant may contact the Program Coordinator of the CUPA program, Melissa Nissim (209) 468-3168, with any questions.
Any amount but not limited to the following hazardous waste; hazardous material spills, used oil, used oil filters, used oil-contaminated absorbent/debris, waste antifreeze, used batteries or other universal waste, etc. — Hazardous Waste Program (Health &Safety Code (HSC) Sections 25404 & 25180 et sec.)
Onsite treatment of hazardous waste — Hazardous Waste Treatment Tiered Permitting Program (HSC Sections 25404 & 25200 et sec. & California Code of Regulations (CCR), Title 22, Section 67450.1 et sec.)
Reportable quantities of hazardous materials-reportable quantities are 55 gallons or more of liquids, 500 pounds for solids, or 200 cubic feet for compressed gases, with some exceptions.
Carbon dioxide is a regulated substance and is required to be reported as a hazardous 1868 E. HazeIton Avenue I Stockton, California 95205 I T 209 468-3420 I F 209 464-0138 I www.sjgov.org/ehd Exhibit A
Tentative Parcel Map (PM-20-32), SU0013671 Page 2 of 2
1302 W. Santos Ave, Ripon
material if storing 1,200 cubic feet (137 pounds) or more onsite in San Joaquin County — Hazardous Materials Business Plan Program (HSC Sections 25508 & 25500 et sec.) d. Any amount of hazardous material stored in an Underground Storage Tank — Underground Storage Tank Program (HSC Sections 25286 & 25280 et sec.) If an underground storage tank (UST) system will be installed, a permit is required to be submitted to, and approved by, the San Joaquin County Environmental Health Department (EHD) before any UST installation work can begin.
Additionally, an EHD UST permit to operate is required once the approved UST system is installed.
e. Storage of at least 1,320 gallons of petroleum aboveground or any amount of petroleum stored below grade in a vault — Aboveground Petroleum Storage Program (HSC Sections 25270.6 & 25270 et sec.)
i. Spill Prevention, Countermeasures and Control (SPCC) Plan requirement f. Threshold quantities of regulated substances stored onsite - California Accidental Release Prevention (CalARP) Program (Title 19, Section 2735.4 & HSC Section 25531 et sec.) i. Risk Management Plan requirement for covered processes Exhibit A
Plan Review Team
Land Management
[email protected]
6111 Bollinger Canyon Road 3370A
San Ramon, CA 94583
PG&E Gas and Electric Facilities Page 1
October 8, 2020
Mitzi Johnson
City of Ripon
259 N Wilma Ave
Ripon, CA 95366
Ref: Gas and Electric Transmission and Distribution
Dear Mitzi Johnson,
Thank you for submitting the 1302 W Santos Ave plans for our review. PG&E will review the submitted plans in relationship to any existing Gas and Electric facilities within the project area.
If the proposed project is adjacent/or within PG&E owned property and/or easements, we will be working with you to ensure compatible uses and activities near our facilities.
Attached you will find information and requirements as it relates to Gas facilities (Attachment 1) and Electric facilities (Attachment 2). Please review these in detail, as it is critical to ensure your safety and to protect PG&E’s facilities and its existing rights.
Below is additional information for your review:
1. This plan review process does not replace the application process for PG&E gas or electric service your project may require. For these requests, please continue to work with PG&E Service Planning: https://www.pge.com/en_US/business/services/buildingand-renovation/overview/overview.page.
2. If the project being submitted is part of a larger project, please include the entire scope of your project, and not just a portion of it. PG&E’s facilities are to be incorporated within any CEQA document. PG&E needs to verify that the CEQA document will identify any required future PG&E services.
3. An engineering deposit may be required to review plans for a project depending on the size, scope, and location of the project and as it relates to any rearrangement or new installation of PG&E facilities.
Any proposed uses within the PG&E fee strip and/or easement, may include a California Public Utility Commission (CPUC) Section 851 filing. This requires the CPUC to render approval for a conveyance of rights for specific uses on PG&E’s fee strip or easement. PG&E will advise if the necessity to incorporate a CPUC Section 851filing is required.
This letter does not constitute PG&E’s consent to use any portion of its easement for any purpose not previously conveyed. PG&E will provide a project specific response as required.
Sincerely,
Plan Review Team
Land Management
Exhibit A
PG&E Gas and Electric Facilities Page 2
Attachment 1 – Gas Facilities
There could be gas transmission pipelines in this area which would be considered critical facilities for PG&E and a high priority subsurface installation under California law. Care must be taken to ensure safety and accessibility. So, please ensure that if PG&E approves work near gas transmission pipelines it is done in adherence with the below stipulations. Additionally, the following link provides additional information regarding legal requirements under California excavation laws: https://www.usanorth811.org/images/pdfs/CA-LAW-2018.pdf
1. Standby Inspection: A PG&E Gas Transmission Standby Inspector must be present during any demolition or construction activity that comes within 10 feet of the gas pipeline. This includes all grading, trenching, substructure depth verifications (potholes), asphalt or concrete demolition/removal, removal of trees, signs, light poles, etc. This inspection can be coordinated through the Underground Service Alert (USA) service at 811. A minimum notice of 48 hours is required. Ensure the USA markings and notifications are maintained throughout the duration of your work.
2. Access: At any time, PG&E may need to access, excavate, and perform work on the gas pipeline. Any construction equipment, materials, or spoils may need to be removed upon notice.
Any temporary construction fencing installed within PG&E’s easement would also need to be capable of being removed at any time upon notice. Any plans to cut temporary slopes exceeding a 1:4 grade within 10 feet of a gas transmission pipeline need to be approved by PG&E Pipeline Services in writing PRIOR to performing the work.
3. Wheel Loads: To prevent damage to the buried gas pipeline, there are weight limits that must be enforced whenever any equipment gets within 10 feet of traversing the pipe.
Ensure a list of the axle weights of all equipment being used is available for PG&E’s Standby Inspector. To confirm the depth of cover, the pipeline may need to be potholed by hand in a few areas.
Due to the complex variability of tracked equipment, vibratory compaction equipment, and cranes, PG&E must evaluate those items on a case-by-case basis prior to use over the gas pipeline (provide a list of any proposed equipment of this type noting model numbers and specific attachments).
No equipment may be set up over the gas pipeline while operating. Ensure crane outriggers are at least 10 feet from the centerline of the gas pipeline. Transport trucks must not be parked over the gas pipeline while being loaded or unloaded.
4. Grading: PG&E requires a minimum of 36 inches of cover over gas pipelines (or existing grade if less) and a maximum of 7 feet of cover at all locations. The graded surface cannot exceed a cross slope of 1:4.
5. Excavating: Any digging within 2 feet of a gas pipeline must be dug by hand. Note that while the minimum clearance is only 12 inches, any excavation work within 24 inches of the edge of a pipeline must be done with hand tools. So to avoid having to dig a trench entirely with hand tools, the edge of the trench must be over 24 inches away. (Doing the math for a 24 inch Exhibit A
PG&E Gas and Electric Facilities Page 3
wide trench being dug along a 36 inch pipeline, the centerline of the trench would need to be at least 54 inches [24/2 + 24 + 36/2 = 54] away, or be entirely dug by hand.) Water jetting to assist vacuum excavating must be limited to 1000 psig and directed at a 40° angle to the pipe. All pile driving must be kept a minimum of 3 feet away.
Any plans to expose and support a PG&E gas transmission pipeline across an open excavation need to be approved by PG&E Pipeline Services in writing PRIOR to performing the work.
6. Boring/Trenchless Installations: PG&E Pipeline Services must review and approve all plans to bore across or parallel to (within 10 feet) a gas transmission pipeline. There are stringent criteria to pothole the gas transmission facility at regular intervals for all parallel bore installations.
For bore paths that cross gas transmission pipelines perpendicularly, the pipeline must be potholed a minimum of 2 feet in the horizontal direction of the bore path and a minimum of 12 inches in the vertical direction from the bottom of the pipe with minimum clearances measured from the edge of the pipe in both directions. Standby personnel must watch the locator trace (and every ream pass) the path of the bore as it approaches the pipeline and visually monitor the pothole (with the exposed transmission pipe) as the bore traverses the pipeline to ensure adequate clearance with the pipeline. The pothole width must account for the inaccuracy of the locating equipment.
7. Substructures: All utility crossings of a gas pipeline should be made as close to perpendicular as feasible (90° +/- 15°). All utility lines crossing the gas pipeline must have a minimum of 12 inches of separation from the gas pipeline. Parallel utilities, pole bases, water line ‘kicker blocks’, storm drain inlets, water meters, valves, back pressure devices or other utility substructures are not allowed in the PG&E gas pipeline easement.
If previously retired PG&E facilities are in conflict with proposed substructures, PG&E must verify they are safe prior to removal. This includes verification testing of the contents of the facilities, as well as environmental testing of the coating and internal surfaces. Timelines for PG&E completion of this verification will vary depending on the type and location of facilities in conflict.
8. Structures: No structures are to be built within the PG&E gas pipeline easement. This includes buildings, retaining walls, fences, decks, patios, carports, septic tanks, storage sheds, tanks, loading ramps, or any structure that could limit PG&E’s ability to access its facilities.
9. Fencing: Permanent fencing is not allowed within PG&E easements except for perpendicular crossings which must include a 16 foot wide gate for vehicular access. Gates will be secured with PG&E corporation locks.
10. Landscaping: Landscaping must be designed to allow PG&E to access the pipeline for maintenance and not interfere with pipeline coatings or other cathodic protection systems. No trees, shrubs, brush, vines, and other vegetation may be planted within the easement area.
Only those plants, ground covers, grasses, flowers, and low-growing plants that grow unsupported to a maximum of four feet (4’) in height at maturity may be planted within the easement area.
Exhibit A
PG&E Gas and Electric Facilities Page 4
11. Cathodic Protection: PG&E pipelines are protected from corrosion with an “Impressed Current” cathodic protection system. Any proposed facilities, such as metal conduit, pipes, service lines, ground rods, anodes, wires, etc. that might affect the pipeline cathodic protection system must be reviewed and approved by PG&E Corrosion Engineering.
12. Pipeline Marker Signs: PG&E needs to maintain pipeline marker signs for gas transmission pipelines in order to ensure public awareness of the presence of the pipelines.
With prior written approval from PG&E Pipeline Services, an existing PG&E pipeline marker sign that is in direct conflict with proposed developments may be temporarily relocated to accommodate construction work. The pipeline marker must be moved back once construction is complete.
13. PG&E is also the provider of distribution facilities throughout many of the areas within the state of California. Therefore, any plans that impact PG&E’s facilities must be reviewed and approved by PG&E to ensure that no impact occurs which may endanger the safe operation of its facilities.
Exhibit A
PG&E Gas and Electric Facilities Page 5
Attachment 2 – Electric Facilities
It is PG&E’s policy to permit certain uses on a case by case basis within its electric transmission fee strip(s) and/or easement(s) provided such uses and manner in which they are exercised, will not interfere with PG&E’s rights or endanger its facilities. Some examples/restrictions are as follows:
1. Buildings and Other Structures: No buildings or other structures including the foot print and eave of any buildings, swimming pools, wells or similar structures will be permitted within fee strip(s) and/or easement(s) areas. PG&E’s transmission easement shall be designated on subdivision/parcel maps as “RESTRICTED USE AREA – NO BUILDING.”
2. Grading: Cuts, trenches or excavations may not be made within 25 feet of our towers.
Developers must submit grading plans and site development plans (including geotechnical reports if applicable), signed and dated, for PG&E’s review. PG&E engineers must review grade changes in the vicinity of our towers. No fills will be allowed which would impair ground-toconductor clearances. Towers shall not be left on mounds without adequate road access to base of tower or structure.
3. Fences: Walls, fences, and other structures must be installed at locations that do not affect the safe operation of PG&’s facilities. Heavy equipment access to our facilities must be maintained at all times. Metal fences are to be grounded to PG&E specifications. No wall, fence or other like structure is to be installed within 10 feet of tower footings and unrestricted access must be maintained from a tower structure to the nearest street. Walls, fences and other structures proposed along or within the fee strip(s) and/or easement(s) will require PG&E review; submit plans to PG&E Centralized Review Team for review and comment.
4. Landscaping: Vegetation may be allowed; subject to review of plans. On overhead electric transmission fee strip(s) and/or easement(s), trees and shrubs are limited to those varieties that do not exceed 15 feet in height at maturity. PG&E must have access to its facilities at all times, including access by heavy equipment. No planting is to occur within the footprint of the tower legs. Greenbelts are encouraged.
5. Reservoirs, Sumps, Drainage Basins, and Ponds: Prohibited within PG&E’s fee strip(s) and/or easement(s) for electric transmission lines.
6. Automobile Parking: Short term parking of movable passenger vehicles and light trucks (pickups, vans, etc.) is allowed. The lighting within these parking areas will need to be reviewed by PG&E; approval will be on a case by case basis. Heavy equipment access to PG&E facilities is to be maintained at all times. Parking is to clear PG&E structures by at least 10 feet.
Protection of PG&E facilities from vehicular traffic is to be provided at developer’s expense AND to PG&E specifications. Blocked-up vehicles are not allowed. Carports, canopies, or awnings are not allowed.
7. Storage of Flammable, Explosive or Corrosive Materials: There shall be no storage of fuel or combustibles and no fueling of vehicles within PG&E’s easement. No trash bins or incinerators are allowed.
Exhibit A
PG&E Gas and Electric Facilities Page 6
8. Streets and Roads: Access to facilities must be maintained at all times. Street lights may be allowed in the fee strip(s) and/or easement(s) but in all cases must be reviewed by PG&E for proper clearance. Roads and utilities should cross the transmission easement as nearly at right angles as possible. Road intersections will not be allowed within the transmission easement.
9. Pipelines: Pipelines may be allowed provided crossings are held to a minimum and to be as nearly perpendicular as possible. Pipelines within 25 feet of PG&E structures require review by PG&E. Sprinklers systems may be allowed; subject to review. Leach fields and septic tanks are not allowed. Construction plans must be submitted to PG&E for review and approval prior to the commencement of any construction.
10. Signs: Signs are not allowed except in rare cases subject to individual review by PG&E.
11. Recreation Areas: Playgrounds, parks, tennis courts, basketball courts, barbecue and light trucks (pickups, vans, etc.) may be allowed; subject to review of plans. Heavy equipment access to PG&E facilities is to be maintained at all times. Parking is to clear PG&E structures by at least 10 feet. Protection of PG&E facilities from vehicular traffic is to be provided at developer’s expense AND to PG&E specifications.
12. Construction Activity: Since construction activity will take place near PG&E’s overhead electric lines, please be advised it is the contractor’s responsibility to be aware of, and observe the minimum clearances for both workers and equipment operating near high voltage electric lines set out in the High-Voltage Electrical Safety Orders of the California Division of Industrial Safety (https://www.dir.ca.gov/Title8/sb5g2.html), as well as any other safety regulations.
Contractors shall comply with California Public Utilities Commission General Order 95 (http://www.cpuc.ca.gov/gos/GO95/go_95_startup_page.html) and all other safety rules. No construction may occur within 25 feet of PG&E’s towers. All excavation activities may only commence after 811 protocols has been followed.
Contractor shall ensure the protection of PG&E’s towers and poles from vehicular damage by (installing protective barriers) Plans for protection barriers must be approved by PG&E prior to construction.
13. PG&E is also the owner of distribution facilities throughout many of the areas within the state of California. Therefore, any plans that impact PG&E’s facilities must be reviewed and approved by PG&E to ensure that no impact occurs that may endanger the safe and reliable operation of its facilities.