MEMO
To: Honorable City Council
From: Christiana Giedd, Associate Civil Engineer
Date: 01/14/2025
Subject: Landscape Repair Project
RECOMMENDED ACTION:
Award the contract for the Landscape Repair Project to Grover Landscape Services, Inc. in the amount of $217,755 and authorize staff to proceed (funding source: Miscellaneous Department Capital Fund).
BACKGROUND:
During the 2023 Strategic Planning meeting, the City Council identified as a priority to address a number of landscape issues around the City. A list of landscaping issues was assembled and categorized by how the issue was to be addressed – either by public works maintenance staff or hiring a contractor to address the issue.
Improvement plans and specifications were assembled and titled the Landscape Repair Project to address the landscape issues that were to be addressed by a contractor. These plans included landscape improvements on sections of Canal Boulevard, Colony Road, Milgeo Avenue, North Ripon Road, West Ripon Road, and Jack Tone Road (see Figure 1). Work to be performed for the Project includes demolition, grading, irrigation repair, planting, and other activities as shown on the Project Plans.
Figure 1 – Map of Work Areas
DISCUSSION:
On December 17, 2024, bids for the Landscape Repair Project were opened. 5 bids were received as summarized below:
Grover Landscape Services, Inc. $217,755.00
CLS / Cervantes Landscape Services, Inc. $238,500.00
Clean Cut Landscape, Inc. $282,800.00
Westside Landscape & Concrete, Inc. $356,922.00
Saenz Landscape Construction, Co. $401,074.00
City staff has reviewed the bids and found Grover Landscape Services, Inc. to be the lowest responsive bidder. The Contractor has submitted the bid bond and all required documents. Staff is recommending that the City Council award the bid for the Landscape Repair Project to Grover Landscape Services, Inc. in the amount of $217,755.00 and authorize staff to proceed.
The total budgeted expense for this project is summarized below:
Construction: $217,755
Construction Contingency: $20,000
Total: $237,755
FISCAL IMPACT:
The total cost of $237,755.00 for construction of the Landscape Repair Project will be funded with Miscellaneous Department Capital Fund. The City Council had previously allocated $500,000 of American Rescue Plan Act funds received by the City for this project.