Exhibit E_2025.10.07-NC13140-Meadowood - Offsite Fulton Avenue Preliminary Engineer's Estimate_Redline

Ripon City Council
October 14, 2025

Document
Exhibit E_2025.10.07-NC13140-Meadowood - Offsite Fulton Avenue Preliminary Engineer's Estimate_Redline
Meeting
October 14, 2025
Body
Ripon City Council
Original file
334 KB
Text extracted from the city's file for reading and search. Open the original on riponcityca.iqm2.com. That file is the official record.

UNIT
ITEM DESCRIPTION QUAN. UNIT COST AMOUNT
I. OVERALL OFFSITE & SAFE ROUTES TO SCHOOL SITE PREPARATION / GRADING A. SITE PREPARATION/GRADING

1. MOBILIZATION 1 LS $50,000.00 $50,000

2. CONSTRUCTION WATER 1 LS $30,000.00 $30,000

3. SITE CLEARING & GRUBBING 1 LS $10,000.00 $10,000

4. SITE GRADING 1 LS $150,000.00 $150,000

5. TEMPORARY EROSION CONTROL / SWPPP PROTECTION 1 LS $100,000.00 $100,000

6. TRAFFIC CONTROL 1 LS $136,250.00 $136,250
----------------------------------
SUB-TOTAL $476,250
II. FULTON AVENUE SUBDIVISION FRONTAGE IMPROVEMENTS
A. DEMOLITION

1. EXISTING PAVEMENT REMOVAL (5" A.C. OVER 10" A.B.) 6,392 SF $4.88 $31,193

2. 6" VERTICAL CURB REMOVAL 974 LF $6.10 $5,941

3. GRIND & REMOVE EXISTING STRIPING 1 LS $2,500.00 $2,500 ----------------------------------
SUBTOTAL $39,634
B. STREET WORK

1. A.C. PAVEMENT (5" A.C. OVER 10" A.B.) 24,138 SF $8.00 $193,104

2. 6" VERTICAL CURB & GUTTER 844 LF $33.25 $28,063

3. MEDIAN CURB TYPE "C" 1,416 LF $40.25 $56,994

4. CONCRETE SIDEWALK (4" P.C.C. OVER 4" A.B.) 4,558 SF $8.65 $39,427 ----------------------------------
SUBTOTAL $317,588
C. STORM DRAINAGE

1. 18" R.C.P. 140 LF $175.00 $24,500

2. CATCH BASIN 1 EA $5,250.00 $5,250

3. MANHOLE 1 EA $6,120.00 $6,120
----------------------------------
SUBTOTAL $35,870
D. WATER SYSTEM

1. 8" PVC 95 LF $80.00 $7,600

2. 12" GATE VALVE 1 EA $4,075.00 $4,075

3. 8" GATE VALVE 1 EA $3,295.00 $3,295

4. TIE IN / TESTING AND DISINFECTION 1 EA $15,000.00 $15,000 ----------------------------------
SUBTOTAL $29,970
E. NON-POTABLE WATER SYSTEM

1. 12" PVC 737 LF $116.00 $85,492

2. 8" PVC 70 LF $80.00 $5,600

3. BLOWOFF VALVE 1 EA $2,000.00 $2,000

4. 12" GATE VALVE 3 EA $5,195.00 $15,585

5. 8" GATE VALVE 1 EA $2,700.00 $2,700

6. TIE IN TO EXISTING NON POTABLE WATER 1 EA $15,000.00 $15,000 ----------------------------------
SUBTOTAL $126,377
F. MISCELLANEOUS ITEMS & LANDSCAPE IMPROVEMENTS

1. STRIPING & SIGNAGE 1 LS $15,000.00 $15,000

2. RETROFIT EXISTING STREETLIGHT WITH DOUBLE ARM 1 EA $13,500.00 $13,500

3. CITY STANDARD STREETLIGHT W/DOUBLE MAST ARM 2 EA $15,000.00 $30,000

4. LANDSCAPE 12,484 SF $6.00 $74,904

5. LANDSCAPE FINISHING GRADING 12,484 LF $0.45 $5,618

6. SOIL AMENDMENTS 12,484 SF $0.40 $4,994

7. MULCH 12,484 SF $0.45 $5,618

8. IRRIGATION SYSTEM 12,484 SF $6.00 $74,904
----------------------------------

RIPON, CALIFORNIA
9/5/2025

PRELIMINARY OPINION OF PROBABLE COST
FOR
MEADOWOOD SUBDIVISION - TRACT NO. 4019

OFFSITE FULTON AVENUE & SAFE ROUTES TO SCHOOL IMPROVEMENTS 1 $209,550 Church Frontage (773 LF)
$266,700 Meadowood Frontage (985 LF)

EXHIBIT E
SUB-TOTAL $224,537
FULTON AVENUE SUBDIVISION FRONTAGE IMPROVEMENTS TOTAL =====> $1,250,226 UNIT
ITEM DESCRIPTION QUAN. UNIT COST AMOUNT
II. FULTON AVENUE CALVARY REFORMED CHURCH FRONTAGE IMPROVEMENTS A. STREET WORK

1. A.C. PAVEMENT (5" A.C. OVER 10" A.B.) 14,289 SF $8.00 $114,312

2. 6" VERTICAL CURB & GUTTER 706 LF $33.25 $23,475

3. MEDIAN CURB TYPE "C" 690 LF $40.25 $27,773

4. CONCRETE SIDEWALK (4" P.C.C. OVER 4" A.B.) 4,857 SF $8.65 $42,013 5 TRAFFIC CONTROL 1 LS $25,000.00 $25,000
6 GRADING 1 LS $60,000.00 $60,000
7 S.S.J.I.D. DRIVEWAY APPROACH 248 SF $14.50 $3,596
8 S.S.J.I.D. PARKING TURNOUT 2 EA $5,000.00 $10,000
9 VENEER S.S.J.I.D. STRUCTURE 1 LS $10,000.00 $10,000
10 REPLACE SSJID STRUCTURE WITH FLUSH MANHOLE 1 LS $150,000.00 $150,000 11 CONCRETE COBBLESTONE 2,222 SF $18.50 $41,107
12 4.5" DRIVE OVER CURB & GUTTER 423 LF $45.75 $19,352
----------------------------------
SUBTOTAL $526,627
B. STORM DRAINAGE

1. 18" R.C.P. 70 LF $175.00 $12,250

2. CATCH BASIN 2 EA $5,250.00 $10,500
----------------------------------
SUBTOTAL $22,750
C. MISCELLANEOUS ITEMS & LANDSCAPE IMPROVEMENTS

1. STRIPING & SIGNAGE 706 LF $25.00 $17,650

2. RETROFIT EXISTING STREETLIGHT WITH DOUBLE ARM 1 EA $13,500.00 $13,500

3. LANDSCAPE 15,628 SF $9.00 $140,652

4. LANDSCAPE FINISHING GRADING 15,628 LF $0.68 $10,549

5. SOIL AMENDMENTS 15,628 SF $0.60 $9,377

6. MULCH 15,628 SF $0.68 $10,549

7. IRRIGATION SYSTEM 15,628 SF $9.00 $140,652
----------------------------------
SUB-TOTAL $342,929
FULTON AVENUE CALVARY REFORMED CHURCH FRONTAGE IMPROVEMENTS TOTAL =====> $892,306 III. SAFE ROUTES TO SCHOOL FULTON AVENUE & COLONY ROAD CROSSING IMPROVEMENTS A. DEMOLITION

1. EXISTING PAVEMENT REMOVAL (5" A.C. OVER 10" A.B.) 9,090 SF $4.88 $44,359

2. GRIND & REMOVE EXISTING STRIPING 1 LS $2,500.00 $2,500 ----------------------------------
SUBTOTAL $46,859
B. STREET WORK

1. A.C. PAVEMENT (5" A.C. OVER 10" A.B.) 3,506 SF $8.00 $28,048

2. CONCRETE COBBLESTONE 2,222 SF $18.50 $41,107

3. 6" VERTICAL CURB & GUTTER 124 LF $33.25 $4,123

4. 6" VERTICAL CURB 925 LF $36.00 $33,300

5. 4.5" DRIVE OVER CURB & GUTTER 423 LF $45.75 $19,352

6. MEDIAN CURB TYPE "C" 128 LF $40.25 $5,152

7. CONCRETE SIDEWALK (4" P.C.C. OVER 4" A.B.) 1,094 SF $8.65 $9,463

8. ACCESSIBLE RAMP (MATERIALS + LABOR) 1 EA $2,500.00 $2,500

9. TRUNCATED DOMES 8 EA $750.00 $6,000

10. RECTANGULAR RAPID FLASHING BEACON 8 EA $10,000.00 $80,000 ----------------------------------
SUB-TOTAL $229,045
C. MISCELLANIOUS ITEMS

1. STRIPING & SIGNAGE 1 LS $10,000.00 $10,000
----------------------------------
SUB-TOTAL $10,000
SAFE ROUTES TO SCHOOL FULTON AVENUE & COLONY ROAD CROSSING IMPROVEMENTS TOTAL =====> $285,905 IV. SAFE ROUTES TO SCHOOL FULTON AVENUE & SANTOS AVE CROSSING IMPROVEMENTS A. DEMOLITION
2 $31,150
$376,627
$430,527

1. EXISTING PAVEMENT REMOVAL (5" A.C. OVER 10" A.B.) 9,147 SF $5.00 $45,735 ----------------------------------
SUB-TOTAL $45,735
B. STREET WORK

1. A.C. PAVEMENT (5" A.C. OVER 10" A.B.) 1,740 SF $8.00 $13,920

2. CONCRETE COBBLESTONE 5,050 SF $18.50 $93,425

3. 6" VERTICAL CURB 732 LF $28.00 $20,496

4. 4.5" DRIVE OVER CURB & GUTTER 299 LF $46.00 $13,754

5. TRUNCATED DOMES 6 EA $750.00 $4,500

6. RECTANGULAR RAPID FLASHING BEACON 6 EA $10,000.00 $60,000 ----------------------------------
SUB-TOTAL $206,095
UNIT
ITEM DESCRIPTION QUAN. UNIT COST AMOUNT
C. MISCELLANEOUS ITEMS

1. STRIPING & SIGNAGE 1 LS $10,000.00 $10,000
----------------------------------
SUB-TOTAL $10,000
SAFE ROUTES TO SCHOOL FULTON AVENUE & SANTOS AVE CROSSING IMPROVEMENTS TOTAL =====> $261,830 V. SAFE ROUTES TO SCHOOL FULTON AVENUE & CINDY DRIVE CROSSING IMPROVEMENTS A. DEMOLITION

1. EXISTING PAVEMENT REMOVAL (5" A.C. OVER 10" A.B.) 915 SF $5.00 $4,575

2. GRIND & REMOVE EXISTING STRIPING 1 LS $2,500.00 $2,500

3. DEMOLISH EXISTING CURB AND GUTTER 125 LF $6.10 $763

4. DEMOLISH EXISTING CONCRETE RAMPS 348 SF $6.10 $2,123 ----------------------------------
SUB-TOTAL $9,960
B. STREET WORK

1. A.C. PAVEMENT (5" A.C. OVER 10" A.B.) 445 SF $8.00 $3,560

2. 6" VERTICAL CURB & GUTTER 138 LF $35.00 $4,830

3. ACCESSIBLE RAMPS (MATERIALS + LABOR) 2 EA $1,350.00 $2,700 ----------------------------------
SUB-TOTAL $11,090
C. MISCELLANEOUS ITEMS

1. STRIPE CROSSWALK AND STOP BAR 1 LS $10,000.00 $10,000 ----------------------------------
SUB-TOTAL $10,000
SAFES ROUTE TO SCHOOL FULTON AVENUE & CINDY DRIVE CROSSING IMPROVEMENTS =====> $31,050 FULTON AVENUE SUBDIVISION FRONTAGE IMPROVEMENTS TOTAL =====> $1,250,226 FULTON AVENUE CALVARY REFORMED CHURCH FRONTAGE IMPROVEMENTS TOTAL =====> $892,306 SAFE ROUTES TO SCHOOL CROSSING IMPROVEMENTS TOTAL =====> $578,785 20% CONSTRUCTION CONTINGENCY =====> $544,263
GRAND TOTAL CONSTRUCTION COST INCLUDING CONTINGENCY =====> $3,265,580 3 $430,527
$2,711,446