CONTRACTOR: Knife River Construction
PROJECT: Ripona Resurface Project
PROJECT DESCRIPTION:
INVOICE NO: 4
DATE: 2/28/2026
ORIGINAL CONTRACT AMOUNT: $1,521,980.00 PREVIOUSLY BILLED AMOUNT: $1,499,241.80 LESS RETENTION: $74,962.10
APPROVED CONTRACT CHANGES: $138,606.80 PREVIOUSLY PAID AMOUNT: $1,424,279.70 CURRENT INVOICED AMOUNT: $27,610.00
LESS RETENTION: $1,380.50
TOTAL CONTRACT AMOUNT: $1,660,586.80 CURRENT AMOUNT DUE: $26,229.50 TOTAL BILLED TO DATE (INCL CURRENT INVOICE) $1,526,851.80 LESS RETENTION: $76,342.60
TOTAL PAID TO DATE: $1,450,509.20
INVOICE SUMMARY
TOTAL PROGRESS
Remaining Contract Amount: $133,735.00
Approx. % Complete: 92%
Final installation of Rectangular Rapid Flashing Beacons on Frontage Road in the Ripona area completed.
INVOICE SUMMARY
The project includes 8 miles of roads that are planned to receive a chip/slurry seal resurfacing and 400 feet of roads that require reconstruction. Roads include Ripona Ave., Milgeo Ave., Shasta Ave., N. Ripon Rd., and other streets north of Hwy 99 and south of Colony Rd.