INVOICE
J D E Engineering, Inc
1490 Boulder Creek Ct
Manteca, CA 95336-9109
[email protected]
+1 (209) 328-1124
www.jde-eng.com
City of Ripon:25-001 City of Ripon Inspection Services
Bill to
Attn: Carla Rodriguez
City of Ripon
259 N Wilma Avenue
Ripon, CA 95366
Invoice details
Invoice no.: 1093
Terms: Net 30
Invoice date: 04/09/2026
Due date: 05/09/2026
Product/service Description Quantity Rate ($/hour) Current amount due
City of Ripon Inspection Services
For work performed thru March 31st, 2026
Construction Inspection Provided construction inspection services for the following: installation of curb and
gutter on Fulton Avenue, reviewing of
phasing plan, paver installation, and
grading of offsite Fulton Improvements. see
attached inspection breakdown.
37.5 $150.00 $5,625.00
Please mail all payments to the above mailing address.
Note to customer
Thank you for your business
Total $5,625.00
to k e n = e b c b 5 7 9 2 e d c 2 4 9 4 b a f3 6 2 d c 9 e 7 4 3 b 9 5 8 e a 6 7 6 1 e 7 0 a 0 2 4 e 4 a b 4 1 9 5 6 7 b 4 0 8 9 9 4 3 9 3 7 4 8 2 1 7 8 1 5 f0 4 5 3 c 9 4 8 4 3 8 5 0 f6 2 1 1 e 1 1 City of Ripon Inspection Services
Meadowood Subdivision
March 2026
DATE HOURS CONTRACTOR DESCRIPTION OF WORK INSPECTED
3/10/2026 3 TEICHERT Curb and gutter grading on Fulton Avenue, review phasing plan, and meet with city staff.
3/11/2026 3.5 TEICHERT Curb and gutter grading on Fulton Ave. and roundabout at Fulton/Colony, stringline for median curb on Fulton Ave, form walkway from Fulton Ave. to courts, and form median curb at Shasta/Fulton
3/12/2026 4.5 TEICHERT Pour median curb on Fulton Ave., finish stringline for curb and gutter on Fulton Ave., and grade curb and gutter on Fulton Ave.
3/13/2026 4 TEICHERT Grade curb and gutter on Fulton Ave., remove AC at NW roundabout Fulton/Colony. Pour walkways from courts to Fulton Ave., and pour median curb on Shasta at Fulton. Review staking for curbs and stringline with city staff.
3/19/2026 4 TEICHERT Coordination with city and contractor, subgrade on Fulton, grade inspection for subgrade, compaction testing coordination and review. 3/20/2026 3.5 TEICHERT Place and compact AB on Fulton Ave., pour paver border curbs on Colony west of Fulton Ave., set forms for paver border curbs on Fulton Ave. west side north of Colony, review set up traffic control for closure on 3/23. 3/23/2026 4 TEICHERT Remove curbs and pavement on Fulton Ave., pour paver border curbs at southwest Santos/Fulton and northwest Cindy/Fulton, set up paver border curbs at southwest Santos/Fulton and Northwest Santos/Fulton, clean and grout manholes, DI's and valve boxes in subdivision.
3/24/2026 4.5 TEICHERT Pour paver curb at southbound Fulton/Cindy north and south, set up median curb at Fulton/Colony south side of roundabout, patch pave at paver curbs on Fulton/Colony, grind AC and grade AB on Fulton Ave., grade for median curb on Fulton Ave., clean valve boxes and manholes in subdivision, and NPW water tie-in.
3/30/2026 4 TEICHERT Remove AC on Fulton at turn lanes, grade AB on Fulton Ave., and review grades with city on Fulton Ave. median and edge of pavement ESD install pavers at Cindy/Fulton roundabout
3/31/2026 2.5 TEICHERT Grade AB on Fulton Ave., set up paver curbs at Colony/Fulton roundabouts.
TOTAL 37.5