2/15/2022
1 RiversideCA.gov1
RiversideCA.gov
Housing and Homelessness CommitteeFebruary 28, 2022HOUSING AUTHORITY’S HOUSING PROJECTS UPDATEOFFICE OF HOMELESS SOLUTIONS RiversideCA.gov2
PROJECTS IN THE PIPELINE689 affordable housing unitsPermanent Supportive Housing: 207 units 1 2
2/15/2022
2 RiversideCA.gov3
WARD 1 PROJECTSPROJECT ADDRESS PARTNERS UNITS STATUS UPDATEMulberry Village 2825 Mulberry StreetHabitat for Humanity10 Project is under development and to be completed by completed by April 2022. Habitat will be submitting a request for additional funding to cover increased construction costs. The Aspire 3861 - 3893 Third Street Innovative Housing Opportunities32 Permanent Supportive Housing (PSH) project for termed out foster, and homeless, youth. Developer submitted a State Multifamily Housing Program (MHP) funding application. Awards have not yet been announced.

RiversideCA.gov4
WARD 1 PROJECTSPROJECT ADDRESS PARTNERS UNITS STATUS UPDATEMission Heritage3993 Mission Inn Blvd.Wakeland Housing Dev. Corporation72 Affordable and permanent supportive housing with integrated Civil Rights Institute. Project began construction in spring of 2021 and is to be completed by 8/14/2022.The Place 2800 Hulen PlaceRiverside University Health System - Behavioral Health 30Riverside County Behavioral Health has been a lessee in the building since 2006. The County and City have executed a new $1 per year lease. The County will be providing $2.1 million in funding to rehabilitate the building and expand capacity 20%. RFP for architect services will be released by mid-February 2022. 3 4
2/15/2022
3 RiversideCA.gov5
WARD 1 PROJECTSPROJECT ADDRESS PARTNERS UNITS STATUS UPDATEHelping Hearts Hulen2801 Hulen PlaceHelping Hearts Hulen28The Helping Hearts Hulen Facility opened on November 15, 2021, which provides 28 interim housing beds for homeless individuals with mental health conditions. The organization is requesting additional funding to cover the increased project costs totaling $226,454.Bridge Housing2881 Hulen PlaceMercy House 2323-bed Bridge Housing project. Project is under construction and is to be completed by March 2022.

RiversideCA.gov6
WARD 1 PROJECTSPROJECT ADDRESS PARTNERS UNITS STATUS UPDATECedar Rental Housing4292 Cedar StreetRHDC 3A CDBG Agreement has been executed between the Community & Economic Development Department and Office of Homeless Solutions for the rehabilitation of the property. The CDBG and HOME Agreements between OHS and RHDC are being drafted. Procuring Birdseye Planning to complete the NEPA (environmental process) for the HOME grant funds. UCR Medical Clinic2880 Hulen PlaceAccess Center/Medical Clinic23CDBG Grant Agreement with UCR has been executed for $567,228.15 of grant funds for the rehabilitation of Access Center space being converted into a medical clinic. 5 6
2/15/2022
4 RiversideCA.gov7
WARD 1 PROJECTSPROJECT ADDRESS PARTNERS UNITS STATUS UPDATECalFire Site2524 Mulberry StreetEden Housing 209State owned property. The State released a Request for Qualifications and a Request for Proposals which results in Eden Housing being selected to develop 209 housing units. The project is in the pre-development phase. First community meeting took place January 19, 2022. City staff is scheduled to meet with developer on 2/11/22 to discuss the application process of the HCD NOFA -Excess Sites Local Government Matching Grants Program (April 2022).

RiversideCA.gov8
WARD 2 PROJECTSPROJECT ADDRESS PARTNERS UNITS STATUS UPDATEEntrada 1705, 1719, 1725, 1733, 1747, 1753 and 1761 Seventh StreetWakeland Housing & Development Corporation65 Financing to close in March 2022. Subordination Agreement and AHSC Co-Applicant agreement under review. Waiting on State to email the AHSC Standard Agreement to the City/Wakeland, which needs to be presented to City Council for their consideration. Crest PSH Project 3431 Mt. Vernon AvenueCrest Community Church10 Manufactured housing project. Located in a high fire zone. The church has procured a firm to prepare a fire mitigation plans that can develop alternatives for compliance. 7 8
2/15/2022
5 RiversideCA.gov9
WARD 2 PROJECTSPROJECT ADDRESS PARTNERS UNITS STATUS UPDATE14th Street Rental 2550 14thStreet Path of Life 65 Escrow closed 10/2021. In December 2021, POL informed staff their board would be appointing a new contractor and would have an update in January. City staff has reached out to POL for project update meeting. Oasis Senior Villas 2340 14th Street A Community of Friends95 Financing closed on October 20, 2021. The site is currently being graded.

RiversideCA.gov10
WARD 2 PROJECTSPROJECT PARTNERS STATUS UPDATETCC Grantaward: $9,080,894, AHSC, $22,121,206 for Entrada1. GRID Alternatives IE (Energy for All)2. TreePeople (Eastside Greening)3. Santa Ana Watershed Project Authority (SAWPA) (Water Energy Community Action Network)4. Riverside Community Health Foundation (RCHF) (Community Engagement Plan)5. Community Settlement Association (CSA) (Displacement Avoidance Plan)6. County of Riverside EDA (Workforce Development and Economic Opportunities Plan)7. UC Riverside CE-CERT (Indicator Tracking Plan)First cohort of a 7-week workforce development course. Solar program is recruiting for interns. Zero Scape program: Working with the partners to lower the program implementation cost. Tree planting has begun with two large volunteer events planned for February.9 10 2/15/2022
6 RiversideCA.gov11
WARD 2 PROJECTSPROJECT ADDRESS PARTNERS UNITS STATUS UPDATEUniversity Duplex 2348 University AvenueProperty Manager: RHDC2 Substantial rehabilitation of a duplex. CDBG funding for the rehabilitation of this duplex has been approved by City Council. CAO is drafting an Agreement between the Community & Economic Development and Office of Homeless Solutions. Working on tenant relocation.

RiversideCA.gov12
WARD 5 PROJECTPROJECT ADDRESS PARTNERS UNITS STATUS UPDATESt. Michaels4070 Jackson StreetCommunity Development Partners / Mercy House50 Partnership with St. Michaels Episcopal Church. The project is under construction and the framing is almost complete. 11 12 2/15/2022
7 RiversideCA.gov13
WARD 6 PROJECTPROJECT ADDRESS PARTNERS UNITS STATUS UPDATECollett Crossings4350 La Sierra AvenueNational Community Renaissance34 Single Family (7 affordable housing units)A lottery was conducted to select the 7 homebuyers and 8 applicants will remain on standby in the event one of the selected applications do not proceed. Of the 27 market-rate homes, 11 have sold and 11 are in escrow. Homes in Phase I have been completed. Homes in Phase II have all slabs poured over the week of January 31, 2022. Phase II houses to be completed and sold by August 2022.

RiversideCA.gov14
WARD 7 PROJECTSPROJECT ADDRESS PARTNERS TOTAL UNITSSTATUS UPDATEAnacapa Rental Housing11502 Anacapa PlaceNorthtown Housing, Inc.2 Permits issued. Project is 30% completed. A meeting is being scheduled with city staff and the developer for 2/11/22 to discuss options for increased construction costs. Sunrise at Bogart111049 Bogart AvenueNeighborhood Partnership Housing Services22 City Council approved Homekey Resolution on 1/11/2022. Staff and NPHS submitted HomekeyApplication to the State on 1/31/22. 45-day response period. 13 14
2/15/2022
8 RiversideCA.gov15
WARD 7 PROJECTSPROJECT ADDRESS PARTNERS UNITS STATUS UPDATEVista de la Sierra 11253 Pierce Street La Sierra University Church / National Community Renaissance80 The developer received $23.5 million in tax credits tax credits. Financing to close January 12th. Construction to begin spring 2022. Financing closed 2/4/2022. Grading to begin shortly.

RiversideCA.gov16
STRATEGIC PLAN ALIGNMENTEnvision Riverside 2025 Strategic Plan PrioritiesCross-Cutting Threads#2 Community Well-BeingCommunity TrustEquityFiscal ResponsibilityInnovationSustainability & Resiliency 15 16
2/15/2022
9 RiversideCA.gov17
RECOMMENDATIONThat the Housing and Homelessness Committeereceive and file an update regarding HousingAuthority housing projects.17