3/3/2022
1 RiversideCA.gov
1 RiversideCA.gov
City Council
March 15, 2022
Bid 7872 – FY 2020/21 Arterial and Minor
Street Maintenance, Phase 1 & Phase 2
Public Works Department
RiversideCA.gov
2 BACKGROUND

1. The Public Works Department utilizes a Pavement
Management Program and receives service requests from
residents to plan various maintenance improvements
throughout the City.

2. Every fiscal year, the Public Works Department budgets a portion of State Gas Tax, County Measure A, and City
Measure Z revenues for street rehabilitation of City arterial and minor streets. This project will focus on rehabilitation of streets in very poor condition.
1 2
3/3/2022
2 RiversideCA.gov
3 CURRENT PROJECT

1. Repave 8.68 miles of residential streets within 11 different neighborhoods including 8 residential collectors:
• Columbia Ave. from Main St. to Salmon River Rd.
• Twelfth St. from Victoria Ave. to Douglas Ave.
• Eucalyptus Ave. from University Ave. to Third St.
• Franklin Ave. from University Ave. to Fourth St.
• Palm Ave. from Magnolia Ave. to Central Ave.
• Challen Ave. from Van Buren Blvd. to Wells Ave.
• Primrose Dr. from Myers St. to Van Buren Blvd.
• Grove Community Dr. from Deercreek Dr. to Bakal Dr.

RiversideCA.gov
4 CURRENT PROJECT

2. Provide maintenance improvements on the alley
west of Orange Street between Tenth Street and
Mission Inn Avenue;

3. Reconstruct damaged concrete curbs, gutters,
sidewalks, driveways, and non-compliant pedestrian
ramps at all locations; and

4. Install new signing and striping throughout.
3 4
3/3/2022
3 RiversideCA.gov
5 CITY’S STRATEGIC PRIORITIES
• Strategic Priority 6 – Infrastructure, Mobility and Connectivity and Goal 6.2 – Maintain, protect, and improve assets and infrastructure within the City’s built environment to ensure and enhance reliability, resiliency, sustainability, and facilitate connectivity.
• This item aligns with each thread for Community Trust, Equity, Fiscal Responsibility, Innovation, and Sustainability & Resiliency.

RiversideCA.gov
6 LOCATION MAP
5 6
3/3/2022
4 RiversideCA.gov
7 PROJECT LOCATION LIST
RiversideCA.gov
8 EXISTING CONDITIONS

DOWNTOWN ALLEY FRANKLIN AVENUE
7 8
3/3/2022
5 RiversideCA.gov
9 EXISTING CONDITIONS

EDISON COURT CHALLEN AVENUE
RiversideCA.gov
10 RECOMMENDATION

1. Award a construction contract for Bid. No. 7872 for
Fiscal Year 2020/21 Arterial and Minor Streets
Maintenance, Phase 1 & Phase 2 to Onyx Paving
Company, Inc. of Anaheim, California, in the
amount of $4,384,000; and

2. Authorize the City Manager, or his designee, to
execute the construction contract with Onyx
Paving Company, Inc., including making minor
and non-substantive changes.
9 10