Projects - New/Under
Construction Partner Total Units PSH
Units Status City Funds Allocation/ Set Aside Development Cost Other Funding Sources 3943 10th Street Riverside Housing Development
Corporation 66
Pre-Entitlement. CARES Act. Contract is
being routed for signature. Architect working
on floor plans and elevations. Jeff will create
a mock DRC to speed up the review
process for permits.
Housing Authority/ CDBG FY
2020/21 750,000$ 750,000 $ HA: land write down
Mulberry Habitat for Humanity 10 10 Permits to be issued in June 2020; waiting for PW comments on submittal. Housing Authority/HOME 884,250$ 1,129,752 $ HA: land write down Aspire (Third and Fairmount) Innovative Housing
Opportunities/RCC/County 32 32
Received Certificate of Appropriateness.
NEPA has been completed. Applying for
MHP funding in September 2020. DDA,
HOME, and PLHA loan agreement
comments were to CAO comments for
review. Tenatively scheduled for CC-HA
November 2020.
Housing Authority/PLHA/
HOME 1,000,000$ 16,500,000 $
Permanent Local
Housing Allocaiton
(PLHA): $541,019,
HOME: $458,981, HA:
Land only
Mission Heritage Wakeland Housing & Development Corp. 72 11 Entitled; awaiting construction to begin.
Resolution and Parntership Agreement are
done need to be submitted to CC.
Subordination Agreement - they are
requesting to increase incomes if Vouchers
go away. Tentative: October 6, 2020. Parcel
Map is going as well.
Housing Authority 3,000,000$
$47,023,695
(residential only
$44,875,590
Affordable Housing
Sustainable Communities
(AHSC) - $17M; State
Budget Allocation - $3M
Entrada (Chicago/Linden) Wakeland Housing & Development Corp. 65 8 Entitled; awaiting AHSC awards. AHSC
contract executed Wakeland and City in
next 90 da
ys.
Housing Authority 4,000,000$ 22,731,969 $
Crest City / Crest Community Church 10 10 Drafting site design Housing Authority - $ -$ 2550 14th Street Path of Life Ministries 2 2
Kenny is working on the project budget and
timeline for the DDA. HA on 10/28/2020.
Received Budget. Kenny is working on the
timeline.
Housing Authority 60,000$ 350,000 $
Oasis Senior Villas Community of Friends 95 46
Submitted application for HOME Program
funds, which is under review. Gap $3.2
million. Request $1 million. Needs
Resolution to fill $2 million gap.
HOME 1,000,000 $ 44,733,756 $ No Place Like Home - $4.3M
St. Michaels St. Michaels Church / Mercy House 50 24
Entitled; awaiting construction. Submitting
TCAC a pplication in June 2020. awaiting
awards on September 18, 2020. PO is
being set-up. TCAC awards on September
11, 2020.
Housing Authority/PLHA 2,000,000$ 17,939,043 $ No Place Like Home - $4.6M
3753 Myers Habitat for Humanity 4 (affordable
homeownership) 0
Under Construction. Fourth Amendment to
DDA and Third Amendment to HOME
Agreement to City Council/HA on October
6th.
HOME 950,000 $
1,178,121$
Cedar Glen II Palm Communities 50 24 Under Construction. Project to be completed by Fall 2021. Housing Authority 650,000$ 24,146,405 $ NPLH: $3,311,952 4350 La Sierra Avenue National Community Renaissance 34 (7 affordable housing) 0
Closed escrow. Property has been removed
from HA land held for resale. Jeff to obtain
updated project schedule.
Housing Authority - Land 1,400,000$ 13,816,845 $
11502 Anacapa Place Northtown Housing, Inc. 2 0 In escrow to transfer property. Northtown is working on vendor form and W2. HOME 354,726 $ 532,201$ Affordable Housing Projects
ATTACHMENT 1
Pierce/Golden La Sierra University Church / National
Core 80 34 Under Entitlement Review. Going to City
Council October 6th. Loan Agreement Housing Authority/PLHA 2,000,000$ 35,858,408$ HA: $1 million, PLHA $2,000,000
Bushnell and Bogart Neighborhood Partnership Housing
Services 22 22
Pre-Entitlement; Applied for MHP Funds and
awaiting award announcements in June
2020. NEPA revisions need to be sent back
to. Public Notice com
pleted.
Housing Authority/HOME 1,090,000$ 7,123,429 $ HA: land write down 534 229 19,138,976$ 186,789,928.68$
STAGE OF DEVELOPMENT DESCRIPTION
Conceptual Conceptual plans developed; still need a
development team
Pre-Entitlement Developer team in place; working to prepare submittal for entitlement review
Under Entitlement Review Plans/documents have been submitted; project now officially under City review
Entitled; Awaiting Construction City approvals secured; awaiting for construction to begin
Under Construction The project is under construction
$446,654
TOTAL