8/22/2022
1 RiversideCA.gov
1 RiversideCA.gov
FY 2022/23 PROJECTS FUNDED BY THE
ROAD MAINTENANCE AND REHABILITATION
ACCOUNT CREATED BY SENATE BILL 1
City Council
September 6, 2022
Public Works Department
RiversideCA.gov
2 BACKGROUND
• On April 28, 2017 the California Governor signed Senate Bill 1 (SB-1) to address basic road rehabilitation and
traffic safety needs, including on local streets.
• SB-1 is funded by gasoline excise taxes, diesel fuel sales taxes, and vehicle registration fees.
• These revenues are deposited into the State’s Road
Maintenance and Rehabilitation Account (RMRA). A
percentage of the RMRA funds are apportioned to cities
as part of the Local Street and Roads Program (LSRP).
1 2
8/22/2022
2 RiversideCA.gov
3 BACKGROUND
• SB-1 guidelines include accountability and transparency provisions that ensure the public is aware of the projects being completed utilizing these RMRA funds.
• Any jurisdiction receiving RMRA funds must adopt, by
resolution, a list of projects anticipated to be completed. • The project list does not limit the flexibility of the City to fund projects in accordance with the City’s priorities so long as the projects are consistent with the SB-1 program priorities.
RiversideCA.gov
4 FY 2022/23 SB-1 PROJECTS
The State estimates the City of Riverside will receive
$7,181,384 in FY 2022/23 RMRA funds. RMRA funds are
included in the City’s budget for FY 2022/23. The proposed projects included in the City’s SB-1 Resolution include the following:
3 4
8/22/2022
3 RiversideCA.gov
5 FY 2022/23 SB-1 PROJECTS
Maintenance and Rehabilitation
• 3 Arterials (8.0 miles) and 1 Collector (0.73 miles)
– Victoria Ave. from Washington St. to Horace St.
– Madison St. from Indiana Ave. to Victoria Ave.
– Magnolia Ave. from Hole Ave. to Jackson St.
– Jefferson St. from Magnolia Ave. to Arlington Ave.
• 23 Local Streets in 6 Neighborhoods (4.2 miles).
Asphalt resurfacing; reconstruction of damaged concrete; replacement of non-compliant pedestrian ramps; and
replacement of signing and striping.
RiversideCA.gov
6 FY 2022/23 SB-1 PROJECTS
Preservation
• 15 Local Streets in 2 Neighborhoods (5.0 miles)
Improvements generally include filling cracks and
applying a slurry seal treatment to the entire roadway
surface.
5 6
8/22/2022
4 RiversideCA.gov
7 FY 2022/23 SB-1 PROJECTS
Alley Reconstruction
• 7 Alleys within 3 neighborhoods (0.79 miles).
Improvements include grading to improve
drainage, constructing a new asphalt pavement
over a crushed aggregate rock base material,
and potentially constructing a concrete center
ribbon gutter.
RiversideCA.gov
8 FY 2022/23 SB-1 PROJECTS
Traffic Safety
• 2 pedestrian scrambles on Market St. at Mission Blvd. and University Ave.
• 4 residential traffic circles on Howard St. at Cottage St., Pleasant St., Prospect Av., and Denton St.
• Construct left-turn pockets at the intersection of Orange Terrace Pkwy. and Hillsdale Rd.
Traffic improvements improve circulation for pedestrians, bicyclists, and motorists. These improvements should also reduce vehicular and pedestrian collisions.
7 8
8/22/2022
5 RiversideCA.gov
9 EXISTING CONDITIONS
MADISON STREET ALLEY - PINE/CEDAR @ TWELFTH
RiversideCA.gov
10 EXAMPLES OF TRAFFIC ENHANCEMENTS
PEDESTRIAN SCRAMBLE RESIDENTIAL TRAFFIC CIRCLE
9 10
8/22/2022
6 RiversideCA.gov
11 Strategic Priority 6 – Infrastructure, Mobility and Connectivity Goal 6.2 – Maintain, protect, and improve assets and
infrastructure within the City’s built environment to ensure and enhance reliability, resiliency, sustainability, and facilitate connectivity.
Cross-Cutting Threads
STRATEGIC PLAN ALIGNMENT
RiversideCA.gov
12 That the City Council adopt a resolution approving the FY 2022/23 Project List to be completed utilizing the
projected revenues from the FY 2022/23 Road
Maintenance and Rehabilitation Account created by
Senate Bill 1: The Road Repair and Accountability Act of 2017.
RECOMMENDATION
11 12