11/16/2022
1 RiversideCA.gov
1 RiversideCA.gov
Housing and Homelessness Committee
November 28, 2022
HOUSING AUTHORITY’S PROJECTS
UPDATE
OFFICE OF HOMELESS SOLUTIONS
RiversideCA.gov
2 PROJECTS IN THE PIPELINE
689 affordable housing units
PSH: 199 units
1 2
11/16/2022
2 RiversideCA.gov
3 WARD 1 PROJECTS
PROJECT ADDRESS PARTNERS UNITS STATUS UPDATE
Mulberry Village 2825 Mulberry
Street
Habitat for
Humanity
10 Habitat for Humanity submitted a
funding request of $1,271,149 to cover
increased material and labor costs that
resulted from the COVID‐19 pandemic.
The First Amendment to the HOME
Development Agreement for the
increase of funding is scheduled for
City Council on November 15th and the
Neighborhood Stabilization Program
Development Agreement will be
presented to City Council in December
2022.The project is expected to be
completed by the end of March 2023.
RiversideCA.gov
4 WARD 1 PROJECTS
PROJECT ADDRESS PARTNERS UNITS STATUS UPDATE
The Aspire 3861 ‐ 3893
Third Street
Innovative
Housing
Opportunities
32 HOME Loan Agreement will be presented to
the City Council for consideration on
December 6th. Anticipate closing escrow in
early December. The project is expected to
begin construction after the close of
escrow.
Mission
Heritage
3993 Mission
Inn Blvd.
Wakeland
Housing Dev.
Corporation
72 The project is 90% complete and is expected
to be completed in September 2022. A
Grand Opening was held on October 22nd.
3 4
11/16/2022
3 RiversideCA.gov
5 WARD 1 PROJECT
PROJECT ADDRESS PARTNERS UNITS STATUS UPDATE
Helping
Hearts
Hulen
2801 Hulen
Place
Helping Hearts
Hulen
28 Helping Hearts requested $185,094.15 to
cover their project funding gap. On October
4, 2022, City Council approved Helping
Hearts request for additional funding
totaling $185,094.15 from Measure Z. The
Purchase Order has been issued and staff is
reviewing the invoice and supporting
documentation in order to process the
invoice for payment.
Bridge
Housing
2881 Hulen
Place
Mercy House 23 The facility will be up and running at full capacity by Thanksgiving.
RiversideCA.gov
6 WARD 1 PROJECTS
PROJECT ADDRESS PARTNERS UNITS STATUS UPDATE
Cedar
Rental
Housing
4292 Cedar
Street
RHDC 3 HOME and CDBG Agreements are
anticipated to go before City Council on
December 6th.
UCR
Medical
Clinic
2880 Hulen
Place
Access
Center/Medical
Clinic
23 A First Amendment to the Lease has been
executed to extend the lease term. The
Second Amendment to Lease was
approved by Council on November 1st and
the project is underway.
5 6
11/16/2022
4 RiversideCA.gov
7 WARD 5 PROJECT
PROJECT ADDRESS PARTNERS UNITS STATUS UPDATE
St.
Michael’s
4070 Jackson
Street
Community
Development
Partners/Mercy
House
50 The project is under construction and is
expected to be completed by December
2022. Developer is working with the St.
Michael's Church to address the landscape
in the right‐of‐way.
RiversideCA.gov
8 WARD 2 PROJECTS
PROJECT STATUS UPDATE
TCC Grant 295 trees have been planted and an additional 60 trees to be planted by the end of the year. 100 fruit trees were distributed at a Trick‐or‐Tree Event. There are four (4) more planting events scheduled for this year. The xeriscaping project is underway with four (4) approved applications and five (5) more are under review. Sixteen (16) applications have been received for solar installation and five (5) applications have been approved. A showcase event for the first installation will take place in December. The next construction workforce cohort will take place on December 6th. Housing workshops are scheduled for November 8th and 17th. The eight invoice and progress report have been submitted and the ninth is in progress. There are two ongoing Resident Leadership Academy cohorts focusing on the TCC projects with seven (7) participants in the English cohort and 17 participants in the Spanish cohort. TCC partners will present to each cohort in November and a symposium for their graduation and presentation on the projects will occur in January. Project was runner up for an Inland Empire Economic Partnership Sustainable Development Award.
7 8
11/16/2022
5 RiversideCA.gov
9 WARD 7 PROJECTS
PROJECT ADDRESS PARTNERS TOTAL
UNITS
STATUS UPDATE
Anacapa Rental
Housing
11502 Anacapa
Place
Northtown
Housing, Inc.
2T h e developer has requested
an additional $156,062 in HOME
funds to cover increased
material costs. A First
Amendment to the HOME Loan
Agreement, Promissory Note,
and Deed of Trust to reflect the
increase of HOME funds from
$354,726 to $510,788 will be
presented to City Council for
consideration on November
15th.
RiversideCA.gov
10 WARD 7 PROJECTS
PROJECT ADDRESS PARTNERS TOTAL
UNITS
STATUS UPDATE
Sunrise at
Bogart
111049 Bogart
Avenue
Neighborhood
Partnership
Housing Services
22 Staff will be submitting an application
for Round 3 Homekey grant that will
be released in Spring 2023. NPHS is
considering applying for the State's
competitive PLHA funds. A First
Amendment to the Disposition and
Development Agreement to extend
the outside closing date and update
the project schedule has been
executed. The property is in escrow.
9 10
11/16/2022
6 RiversideCA.gov
11 STRATEGIC PLAN ALIGNMENT
Envision Riverside 2025 Strategic Plan Priorities
Cross-Cutting Threads
#2 Community Well-Being
Community Trust
Equity
Fiscal Responsibility
Innovation
Sustainability &
Resiliency
RiversideCA.gov
12 RECOMMENDATION
That the Housing and Homelessness Committee
receive the update on the Housing Authority’s
housing projects.
11 12