WATER SUPERVISORY CONTROL AND DATA

ACQUISITION (SCADA) PHASE II -

DESIGN-BUILD AGREEMENT AND PROFESSIONAL

SERVICES AGREEMENT
City Council
December 6, 2022
Public Utilities Department
RiversideCA.gov
2 RPU Water has many remote assets including:
• 52 Wells
• 32 Booster Stations
• 16 Reservoirs
• 6 Treatment Plants
• Inter-Agency Connections
• Future sites

BACKGROUND
1 2
11/17/2022
2 RiversideCA.gov
3 Supervisory Control and Data Acquisition (SCADA)
• Controls and Monitors
• Allows Remote Operation
• Provides Critical Data
• Alerts System Operators

BACKGROUND
RiversideCA.gov
4 RPU Water SCADA System was developed in the 1990s
• Obsolete Technology
• Unsupported
• Failed components
• Lack of replacement
components
• Increased O&M Costs

BACKGROUND
3 4
11/17/2022
3 RiversideCA.gov
5 1. RPU Water’s SCADA system had 29 findings in the 2016 SCADA Vulnerability Assessment.

2. RPU Water launched a multi-ph ased project to address the aging infrastructure and the critical
findings.

3. SCADA Phase I – Communications upgrade
was completed in 2022.

4. SCADA Phase II – Technology upgrade will be
a 5-year project, discussed herein.

5. SCADA Phase III – Site specific instrumentation
upgrades, will be brought back, at a later date.

DISCUSSION
RiversideCA.gov
6 Multiple RFPs for SCADA Phase II:

1. RFP 2031 SCADA Software Application (pricing included as a subcontractor of Design Build RFP) - Inductive
Automation

2. RFP 2056 Design-Build Construction Services – Tesco
Controls

3. RFP 2109 Owners Representative – Eramosa International, Inc.

4. Ongoing Maintenance & Service Agreement – Inductive
Automation

5. RPU Staff Support

DISCUSSION
5 6
11/17/2022
4 RiversideCA.gov
7 DISCUSSION
RiversideCA.gov
8 Strategic Priority 6 - Infrastructure, Mobility & Connectivity Goal 6.2 - Maintain, protect, and improve assets and infrastructure within the City’s built environment to ensure and enhance reliability, resiliency, sustainability, and facilitate connectivity.

Cross-Cutting Threads

STRATEGIC PLAN ALIGNMENT
7 8
11/17/2022
5 RiversideCA.gov
9 That the City Council:

1. Approve the Design-Build Agreement for Water SCADA
Technology Upgrade from RFP No. 2056 with Tesco Controls of Sacramento, California in the amount of $9,318,000 plus 10% change order authority in the amount of $931,800;

2. Authorize the City Manager, or designee, to execute the Design-Build Services Agreem ent including making minor and non-substantive changes and to sign all documents and instruments necessary to complete the transactions;

RECOMMENDATIONS
RiversideCA.gov
10 3. Approve the Professional Services Agreement for
Owner’s Representative Services for the Water
SCADA Technology Upgrade Project from RFP No. 2109 with Eramosa International, Inc. of Overland Park, Kansas, for a term through December 31, 2028, in the amount of
$1,303,286, plus 10% change order authority in the amount of $130,329; and

4. Authorize the City Manager, or designee, to execute
the Professional Services Agreement including making minor and non-substantive changes and to sign all documents and instruments necessary to complete the transactions.

RECOMMENDATIONS (CONT.)
9 10