2 PROJECTS IN THE PIPELINE
• 613 affordable housing units
PSH: 219
• 41 transitional housing beds
1 2
4/12/2023
2 RiversideCA.gov
3 WARD 1 – MULBERRY VILLAGE
• Developer: Habitat for
Humanity Riverside
• 2825 Mulberry Street
• 10 permanent
supportive housing
units
• Under construction
• Anticipated completion
in May 2023
• Ground breaking event
is being scheduled
RiversideCA.gov
4 WARD 1 – THE ASPIRE
• Developer:
Innovative Housing
Opportunities
• 3861 - 3893 Third
Street
• 32 units of PSH for
homeless youth
• Construction has
begun
• Groundbreaking
event: April 11, 2023
3 4
4/12/2023
3 RiversideCA.gov
5 WARD 1 – THE PLACE
• Provider: Riverside
University Health Systems
– Behavioral Health
• 2800 Hulen Place
• 31 PSH units
• Architect completed
the schematic design,
which is with the County
for review
RiversideCA.gov
6 WARD 1 – 4292 CEDAR STREET
• Developer: Riverside
Housing Development
Corporation
• 4292 Cedar Street
• 3 affordable housing
units – Duplex and
ADU
• Submitted plans to
Building and Safety
and awaiting issuance
of building permit
• Project to be
completed by
December 2023
5 6
4/12/2023
4 RiversideCA.gov
7 WARD 1 – UCR MEDICAL CLINIC
• Provider: UCR Medical
School
• 2880 Hulen Place
• UCR RFP responses
came in over budget
• UCR has located
funding to cover the
project funding gap
• Project to be
completed by
September 2023
RiversideCA.gov
8 WARD 1 – MULBERRY GARDENS
• Developer: Eden Housing
• 2524 Mulberry Street
• 150 affordable family housing
units
• 59 affordable senior housing
Units
• March 28, 2023 City Council
approved a Resolution
authorizing a joint application
for the Affordable Housing and
Sustainable Communities
Program (AHSC) grant
• AHSC Awards expected to be
announced in August 2023
7 8
4/12/2023
5 RiversideCA.gov
9 WARD 2 – ENTRADA
• Developer: Wakeland
Housing & Development
Corporation
• 1705 – 1761 Seventh
Street
• Application received for
$1 million of American
Rescue Plan Act funding
• Anticipated completion
date: December 2023
RiversideCA.gov
10 WARD 2 – 2348 UNIVERSITY AVENUE
• Housing Authority-
owned duplex
• Rehabilitate property to
be leased to very low
income households
• Application received
for $1 million of
American Rescue Plan
Act funding
• Anticipated completion
date: December 2023
9 10
4/12/2023
6 RiversideCA.gov
11 WARD 2 – TRANFORMATIVE CLIMATE COMMUNITIES GRANT
UPDATE
• Over 556 shade trees planted and 268 trees
have been provided to residents to plant
• Construction workforce cohort: New trainer
has been procured and recruitment is in
progress
Combined event with Workforce
Development Department is being
planned
• Xeriscaping program: Received 14
applications, which six have been
approved
• Solar Installations: Received 12 applications
• Next Gen Farmer Training on April 17th
• Town Hall with County Workforce
Development job fair on April 26th
RiversideCA.gov
12 WARD 7 – ANACAPA RENTAL HOUSING
• Developer: Northtown
Housing, Inc.
• 11502 Anacapa Place
• Two (2) affordable single-
family rental units
• Certificate of Occupancy
was issued
• Both units are occupied
11 12
4/12/2023
7 RiversideCA.gov
13 WARD 7 – SUNRISE AT BOGART
• Developer: Neighborhood
Partnership Housing Services
(NPHS)
• 11049 Bogart Avenue
• 22 PSH units
• Draft Resolution declaring the
property as Exempt Surplus
Property was approved by HCD.
Present to City Council for their
consideration in May 2023
• NPHS submitted Affordable
Housing Program application for
$345,000
RiversideCA.gov
14 STRATEGIC PLAN ALIGNMENT
Envision Riverside 2025 Strategic Plan Priorities
Cross-Cutting Threads
#2 Community Well-Being
Community Trust
Equity
Fiscal Responsibility
Innovation
Sustainability &
Resiliency
13 14
4/12/2023
8 RiversideCA.gov
15 RECOMMENDATION
That the Housing and Homelessness Committee
receive and file the update on Housing
Authority projects.
15