BID AWARD RECOMMENDATION
CITY OF RIVERSIDE
Finance Department
DATE SUBMITTED: 05/02/2023
BID NO.
7974
BID TITLE
Installation of Gravity Sewer and Force Main Pipelines on Van Buren Boulevard
DEPARTMENT/DIVISION
Public Works
DATE BID OPENED
02/10/23
BIDS RECEIVED (13) INVITATIONS ISSUED (Online) ESTIMATED COST:$9,460,810.00
BID PRICE GOOD THROUGH: MAY 11, 2023
BIDDERS: CITY AMOUNT BID
E.J. Meyer Company Yucaip a $7,848,888.00
TE Roberts Inc. Irvine $8,206,777.00
Mamco, Inc. dba Alabassi Perris $8,277,777.00
Christensen Brothers General Engineering Inc Apple Valle y $8,809,830.00 C.P. Construction Co., Inc.* Ontario $9,253,015.00
James W. Fowler Co.
Kirtley Construction, Inc.
MNR Construction Inc.
Weka Inc
Vasilj Inc*
Vido Artukovich & Son Inc./Vidmar Inc. A JV
Boudreau Pipeline Corporation
Mike Bubalo Construction Co., Inc.*
Dallas, OR
San Bernardino
La Verne
Highland
Irwindale
South El Monte
Corona
Baldwin Par
k
$9,348,064.00
$9,855,487.00
$9,983,300.00
$11,318,523.00
$11,482,848.99
$11,498,295.00
$11,997,187.00
$14,685,577.00
*Vendors were deemed non-responsive due to not meeting the experience requirement
BID DESCRIPTION: This project proposes to install a new gravity sewer main and two parallel sewer force mains on Van Buren Blvd from King Ave to Wood Rd and on Washington St from Van Buren Blvd to Krameria Ave together with two new parallel sewer force mains running north alo ng Washington St, then east along Van Buren Blvd to Wood Rd.
BID Recommended For Award (Includes Sales Tax) 10% Surety Included Contract 10% Surety not required Purchase Order
Lowest Responsive and Responsible Bidder Amount of Award
E.J. Me
yer Company $7,848,888.00
COMMENTS:
The Purchasing Division has evaluated all bids received and recommends award be made to the lowest responsive and responsible bidder
in compliance with Purchasing Resolution 23914 . The Public Works Department concurs with this recommendation and will be submitting a report.
Submitted by: Purchasing Manager Date:
03/15/2023