4/19/2023
1 RiversideCA.gov
1 RiversideCA.gov
Public Works Department
Federal Highway Administration
Highway Safety Improvement Program
(H.S.I.P.) Cycle XI – Award Acceptance
of $7.8 Million
City Council
May 2, 2023
RiversideCA.gov
2 • On September 6, 2022 the City Council approved
submittal of an application to the Highway Safety
Improvement Program
• On September 11, 2022 the Public Works Department
submitted the grant application with a total grant
request of $9M
• On March 14, the California Department of
Transportation (Caltrans) informed the City that it’s grant application was successful

BACKGROUND
1 2
4/19/2023
2 RiversideCA.gov
3 City of Riverside HSIP Cycle XI Grant Award:
- Total Project Cost $9+ Million
- Grant Amount Awarded $7.8+ Million
- Local Match $1.2+ Million
HSIP Cycle XI Program Objectives:
- Reduce or eliminate fatal or severe
injury traffic collisions at signalized
intersections & along Mission Inn Ave

HSIP CYCLE XI PROJECT AWARD & OBJECTIVES
RiversideCA.gov
4 • Retro-reflective Signal
Backplates (citywide)
• Leading Pedestrian
Interval (LPI) (citywide)
• Median & High Friction Surface Treatment
along Mission Inn between Redwood Dr & Scout Lane

HSIP CYCLE XI PROJECT COMPONENTS
3 4
4/19/2023
3 RiversideCA.gov
5 STRATEGIC PLAN ALIGNMENT
• Strategic Priority No. 2 – Community Well Being Goals 2.4 and 2.5, Strategic Priority No. 6 – Infrastructure, Mobility & Connectivity Goals 6.2, 6.3 and 6.4,
• This item aligns with each cross-cutting thread:

Community Trust, Equity, Fiscal Responsibility, Innovation, and Sustainability & Resiliency
RiversideCA.gov
6 RECOMMENDATIONS
That the City Council:

1.Accept the Federal Highway Safety Improvement Program (HSIP) Cycle XI grant award, contingent upon receipt of funds, in the amount of $7,815,420 awarded to the Public Works Department for the purchase of equipment, implementation of new leading pedestrian interval signal timing, and installation of a median barrier & high friction surface treatment along Mission Inn Avenue between Redwood Avenue and Scout Lane;
5 6
4/19/2023
4 RiversideCA.gov
7 RECOMMENDATIONS

2. Authorize the City Manager, or designee, to execute all the Federal Highway Safety Improvement Program (HSIP) (Cycle XI) Grant Agreements and any related grant documents; and

3. Authorize an increase in estimated revenues in the amount of $7,815,420 and appropriate expenditures in the same amount to the Capital Outlay – Grants (430) Fund - Signal Backplate LPI M i s s i o nI n nM e d i a np r o j e c t .