HOUSING AUTHORITY’S PROJECTS
UPDATE
HOUSING AUTHORITY
RiversideCA.gov
2 DEVELOPMENT PIPELINE
• 611 affordable housing units
o PSH: 219
• 41 transitional housing beds
1 2
5/10/2023
2 RiversideCA.gov
3 Estimated Unit Completion
155 117 339 80
Number of Units Estimated to be Completed by:
End of Fiscal Year End of Year 2024 + Proposed
RiversideCA.gov
4 WARD 1 – RIVERSIDE ACCESS CENTER
• 2880 Hulen Place
• Homeless Drop-in Day
Center
• Submitted $661,000 CDBG
funding application.
• Funding request is part of
the FY 2023/24 HUD
Annual Action Plan being
considered by City
Council on May 9, 2023
3 4
5/10/2023
3 RiversideCA.gov
5 WARD 1 – 4292 CEDAR STREET
• Developer: Riverside
Housing Development
Corporation
• 4292 Cedar Street
• 3 affordable housing
units – Duplex and
ADU
• Building permits have
been issued
• Project to be
completed by
December 2023
RiversideCA.gov
6 WARD 2 – ENTRADA
• Developer: Wakeland
Housing & Development
Corporation
• 1705 – 1761 Seventh Street
• CAO drafting $1 million ARPA
funding agreement
• CAO drafting a subrecipient
agreement between the
City and Wakeland and a
MOU with HA and Public
Works for the ASHC grant
transit related activities
5 6
5/10/2023
4 RiversideCA.gov
7 WARD 2 – TRANFORMATIVE CLIMATE COMMUNITIES GRANT
UPDATE
• Close to 700 shade trees planted and 268 trees
have been provided to residents to plant at
homes
• Construction workforce cohort: New trainer has
been procured and recruitment is in progress
Combined event with Workforce
Development Department is being planned
• Xeriscaping program: Received 14 applications,
which six have been approved
• Solar Installations: Received 13 applications, 2
solar installations have been completed
• Gen Farmer Training held on April 17th
• Town Hall with County Workforce Development
job fair held April 26th
RiversideCA.gov
8 WARD 5 – ST. MICHAELS
• Developer: Mercy
House in partnership
with St. Michaels
Episcopal Church
• 4070 Jackson St.
• 50 Units
including 24 PSH Units
• Construction
Completed
• Grand opening July 24
7 8
5/10/2023
5 RiversideCA.gov
9 WARD 7 – SUNRISE AT BOGART
• Developer: Neighborhood
Partnership Housing
Services (NPHS)
• 11049 Bogart Avenue
• 22 PSH units
• HCD approved draft
resolution declaring the
subject property as
Exempt Surplus Property,
which will be presented to
City Council in May 2023
for their consideration
RiversideCA.gov
10 STRATEGIC PLAN ALIGNMENT
Envision Riverside 2025 Strategic Plan Priorities
Cross-Cutting Threads
#2 Community Well-Being
Community Trust
Equity
Fiscal Responsibility
Innovation
Sustainability &
Resiliency
9 10
5/10/2023
6 RiversideCA.gov
11 RECOMMENDATION
That the Housing and Homelessness Committee
receive the update on the Housing Authority’s
housing projects.
11