Housing and Homelessness Committee
September 25, 2023
HOUSING AUTHORITY’S PROJECTS
UPDATE
HOUSING AUTHORITY
RiversideCA.gov
2 DEVELOPMENT PIPELINE
571 affordable housing units
• Permanent Supportive
Housing units: 197
1 2
9/13/2023
2 RiversideCA.gov
3 Estimated Unit Completion
210 128 14 219
Number of Units Estimated to be Completed by:
2023 2024 2025+
Proposed
RiversideCA.gov
4 WARD 1 – MULBERRY VILLAGE
• Developer: Habitat for
Humanity Riverside
• 2825 Mulberry Street
• 10 permanent
supportive housing
units
• Dedication Ceremony
held on June 23, 2023
• Estimated completion
August 2023
(9 of 10 Units)
3 4
9/13/2023
3 RiversideCA.gov
5 WARD 1 – THE PLACE
• 2800 Hulen Place
• Operated by: Riverside University
Health Systems – Behavioral
Health
• Rehabilitate City-owned facility
for 31 transitional housing units
• Building plans were submitted to
Building and Safety for review
• Anticipate permits to be issued
at the end of September
RiversideCA.gov
6 WARD 1 – UCR MEDICAL CLINIC
• 2880 Hulen Place
• Medical Clinic for low
income community
• Will begin accepting
patients on September
12, 2023
• Psychiatrist will be on
staff in October 2023
5 6
9/13/2023
4 RiversideCA.gov
7 WARD 1 – RIVERSIDE ACCESS CENTER
• 2880 Hulen Place
• Homeless Drop-in Day
Center
• Rehabilitation of interior
space and replace HVAC
system and roof
• Awarded $661,000 in CDBG
FY 2023/2024 funding
• August 1, 2023, City Council
approved $178,155 in
Measure Z funds
RiversideCA.gov
8 WARD 1 – MULBERRY GARDENS
• 2524 Mulberry Street
• Eden Housing
• 150 affordable family
housing units
• 59 affordable senior
housing units
• Awarded $27 million in
Affordable Housing &
Sustainable
Communities
7 8
9/13/2023
5 RiversideCA.gov
9 WARD 2 – GRAPEVINE
• 2882 Mission Inn (Housing
Authority site) and 2731-
2871 University Avenue
(Successor Agency)
• MJW Investments, Inc.
• Development of 64 units,
including 10 affordable
housing units
• October 17, Successor
Agency/City Council
consider disposition of
properties
RiversideCA.gov
10 WARD 2 – OASIS SENIOR APARTMENS
• 2335 14th Street
• A Community of
Friends
• 95 affordable senior
housing units
• Application window
closes on September
14 th
9 10
9/13/2023
6 RiversideCA.gov
11 WARD 2 – TRANFORMATIVE CLIMATE COMMUNITIES GRANT
UPDATE
• 712 shade trees planted and
453 trees have been
provided to residents to
plant at homes
• Solar Installations: 6 solar
installations have been
completed
• Shade Tree Giveaway in
September
RiversideCA.gov
12 WARD 7 – VISTA DE LA SIERRA
• Developer: National
Community Renaissance/La
Sierra University Church
• 11253 Pierce Street
• 80 Units, including 34 PSH
• Project is under construction
with an expected October
2023 Completion
• Preapplications process
started on September 1
st
11 12
9/13/2023
7 RiversideCA.gov
13 WARD 7 – SUNRISE AT BOGART
• Developer: Neighborhood
Partnership Housing Services
(NPHS)
• 11049 Bogart Avenue
• 22 PSH units
• Resolution to declare the
property as exempt surplus
approved June 6, 2023.
• RFP for affordable housing
development has been
released and is due on
September 18
th
RiversideCA.gov
14 STRATEGIC PLAN ALIGNMENT
Envision Riverside 2025 Strategic Plan Priorities
Cross-Cutting Threads
#2 Community Well-Being
Community Trust
Equity
Fiscal Responsibility
Innovation
Sustainability &
Resiliency
13 14
9/13/2023
8 RiversideCA.gov
15 RECOMMENDATION
That the Housing and Homelessness Committee
receive the update on the Housing Authority’s
housing projects.