RiversideCA.gov
2 1. On April 28, 2017, the California Governor
signed Senate Bill-1 (SB-1), known as the
Road Repair and Accountability Act of
2017, to address basic road maintenance,
rehabilitation and critical safety needs.
2. SB-1 increases gas taxes and vehicle
registration fees and provides for inflation
adjustments to fund these needs.
BACKGROUND
1 2
11/30/2023
2 RiversideCA.gov
3 3. The California State Controller’s Office deposits
various portions of these revenues into the
State’s Road Maintenan ce and Rehabilitation
Account (RMRA). A percentage of the RMRA
funds are apportioned to eligible cities and
counties as part the SB-1 Local Street and Roads
Program (LSRP).
4. On September 6, 2022, the City Council adopted
Resolution No. 23899 to approve the FY2022-23
Project List to be completed utilizing the
projected FY2022-23 SB-1 revenue.
BACKGROUND
RiversideCA.gov
4 5. The Public Works Department utilizes a Pavement
Management Program and receives service
requests from residents to plan various
maintenance improvements throughout the City.
6. Every fiscal year, the Public Works Department
budgets a portion of State Gas Tax, County
Measure A, and Measure Z revenues for street
rehabilitation of City arterial and minor streets. This project will rehabilitate marginal, poor, and very
poor roads.
BACKGROUND
3 4
11/30/2023
3 RiversideCA.gov
5 7. Utilization of funds from two completed project
accounts: the Monroe Street Resurfacing Project
account has a surplus, and Berry Street Widening was
constructed using a different funding source.
BACKGROUND
RiversideCA.gov
6 1. Resurface 3.1 miles of Arterial street maintenance on • Magnolia Ave from Hole Ave to Jackson St
• Madison St from Indiana Ave to Victoria Ave
• Victoria Ave from Washington St to Horace St.
2. Resurface 4.7 miles of minor streets maintenance in 7 neighborhoods.
3. Reconstruct 0.9 miles of alley ways.
4. Provide 5.0 miles of slurry preservation.
CURRENT PROJECT
5 6
11/30/2023
4 RiversideCA.gov
7 5 . C o n s t r u c tm e d i a nt u r np o c k e to nO r a n g eT e r r a c e Pkwy at Hillsdale Rd.
6. Reconstruct damaged concrete curbs, gutters,
sidewalks, driveways, and pedestrian ramps
throughout maintenance locations.
7. And Install signing and striping throughout as
required.
8. Install 2 new traffic circles on Howard Ave at Pleasant St and on Howard Ave at Cottage St
CURRENT PROJECT
RiversideCA.gov
8 LOCATION MAP
7 8
11/30/2023
5 RiversideCA.gov
9 EXISTING CONDITIONS
MAGNOLIA AVENUE MADISON AVENUE
RiversideCA.gov
10 EXISTING CONDITIONS
VICTORIA AVENUE ALLEY W/O BROCKTON AVE
9 10
11/30/2023
6 RiversideCA.gov
11 • Strategic Priority No. 6 Infrastructure, Mobility and Connectivity and Goal No. 6.2 – Maintain, protect, and improve assets and infrastructure within the City’s built environment to ensure a nd enhance reliability, resiliency, sustainability, and facilitate connectivity.
• This item aligns with each thread for Community Trust, Equity, Fiscal Responsibility, Innovation, and Sustainability & Resiliency.
Cross-Cutting Threads
STRATEGIC PLAN ALIGNMENT
RiversideCA.gov
12 1. Award a construction contract for Bid No. 7996 for FY 2022/2023 Road Repair and Accountability Act of 2017
Street Maintenance Improvements to All American Asphalt of Corona, California, in the amount of $13,449,317.00;
2. Authorize the City Manager, or designee, to execute the construction contract with All American Asphalt, including making minor and non-substantive changes, subject to the availability of budgeted funds;
RECOMMENDATIONS
11 12
11/30/2023
7 RiversideCA.gov
13 3. Authorize a project funds transfer in the amount of $1,505,631.17 in surplus Measure A funds from the
Monroe Street Resurfacing project account to the
Major Streets Rehabilitation project account; and
4. Authorize a project funds transfer in the amount of
$800,000.00 in surplus Gas Tax funds from the Berry
Street Widening project account to the Minor Street
Rehabilitation project account.
RECOMMENDATIONS
13