4/10/2024
1 RiversideCA.gov
1 RiversideCA.gov

SOUTHERN CALIFORNIA PUBLIC POWER

AUTHORITY EXPENDITURE REPORT
FISCAL YEAR 2023-24
City Council
April 23, 2024
Public Utilities Department
RiversideCA.gov
2 A joint powers authority comprising of 12 local publicly owned utilities.

SOUTHERN CALIFORNIA PUBLIC POWER AUTHORITY
1 2
4/10/2024
2 RiversideCA.gov
3 Generation and Transmission Projects:

1. Palo Verde Nuclear Generation Station - Generation

2. Southern Transmission System - Transmission

3. Mead-Adelanto Transmission Project - Transmission

4. Mead-Phoenix Transmission Project - Transmission

SCPPA PROJECT APPROVALS
RiversideCA.gov
4 Executed renewable energy, power sales agreements and Buyers Joint Project Agreements since 2012:

1. Columbia II Solar

2. Kingbird B (Solar)

3. Summer Solar

4. Antelope Big Sky Ranch (Solar)

5. Antelope DSR 1 (Solar)

6. Coso Geothermal

7. Roseburg Biomass

8. Loyalton Biomass - Expired April 20,2023

SCPPA PROJECT APPROVALS
3 4
4/10/2024
3 RiversideCA.gov
5 Existing joint generation, transmission, and renewable projects – Approx. 100% Other member services – Approx. less than 1%
FY 2023-24 ACTUAL EXPENDITURES
FOR JULY 2023 – DECEMBER 2023
Jul‐Dec
2023
Joint Power Supply & Transmission Generation  Projects  1,730,767$ Joint Power Supply & Transmission Transmission  Projects  3,088,712 Joint Power Supply & Transmission Renewable  Projects  4,438,898 Other Member Services Energy  Efficiency  Programs ‐
Other Member Services Training 5,201
Other Member Services Legislation  & Regulatory ‐
Total Actual Expenditures 9,263,578 $
SCPPA Category
RiversideCA.gov
6 1. Energy Efficiency Programs and Support (Riverside
does not participate)

2. Training

3. Legislation & Regulatory

OTHER MEMBER SERVICES
5 6
4/10/2024
4 RiversideCA.gov
7 Priority 4 – Environmental Stewardship
Goal 4.1 - Rapidly decrease Riverside’s carbon footprint by acting urgently to reach a zero-carbon electric grid with the goal of reaching 100% zero-carbon electricity production by 2040 while continuing to ensure safe, reliable, and affordable energy for all residents.

Priority 5 - High Performing Government
Goal 5.4 - Achieve and maintain financial health by addressing gaps between revenues and expenditures and aligning resources with strategic priorities to yield the greatest impact.

Cross-Cutting Threads

STRATEGIC PLAN ALIGNMENT
RiversideCA.gov
8 That the City Council receive the Southern California Public Power Authority semi-annual expenditure report for the period of July 2023 through December 2023.

RECOMMENDATION
7 8