MEASURE Z – BID 7995
FY 2022/23 ARTERIAL AND MINOR STREET
MAINTENANCE, PHASE 3
City Council
MAY 21, 2024
Public Works Department
RiversideCA.gov
2 1. The Public Works Department utilizes a Pavement
Management Program and receives service requests
from residents to plan various maintenance
improvements throughout the City.

2. Every fiscal year, the Public Works Department budgets a portion of State Gas Tax, County Measure A, and City
Measure Z revenues for street rehabilitation of City
arterial and minor streets. This project will primarily focus on rehabilitation of streets in poor condition.

BACKGROUND
1 2
4/24/2024
2 RiversideCA.gov
3 3. On December 6, 2022, the Ci ty Council received a list of proposed maintenance locations to be
completed with the various Fiscal Year 2022/23
funding sources.

4. The maintenance improvements included in Bid 7995
were locations included in the complete list provided
in the report from December 2022.

5. The Book of Work sets a target of over 50 miles of
paving treatments in Calendar Year 2024.

BACKGROUND
RiversideCA.gov
4 1. Resurface 0.4 miles on one collector street:
• Tyler Street from Arlington Avenue to Verona Street.

2. Resurface 5.8 miles of local streets within five different neighborhoods.

3. Remove the existing splash pad in the Main Street
Mall between University Avenue and Mission Inn
Boulevard.

CURRENT PROJECT
3 4
4/24/2024
3 RiversideCA.gov
5 4. Reconstruct damaged c oncrete curbs, gutters,
sidewalks, driveways, and non-compliant pedestrian
ramps within all rehabilitation locations.

5. Install new signing and striping throughout as
necessary.

6. Install new traffic signals at the following intersections:
• Wells Avenue and Challen Avenue
• Main Street and Placentia Lane
• Lincoln Avenue and Monroe Street

CURRENT PROJECT
RiversideCA.gov
6 LOCATION MAP
5 6
4/24/2024
4 RiversideCA.gov
7 EXISTING CONDITIONS

ARROWWOOD DRIVE MOHAWK TRAIL
RiversideCA.gov
8 EXISTING CONDITIONS

AMERICAN DRIVE STEPHANIE STREET
7 8
4/24/2024
5 RiversideCA.gov
9 Strategic Priority No. 6 Infrastructure, Mobility and Connectivity Goal No. 6.2 – Maintain, protect, and improve assets and infrastructure within the City’s built environment to ensure and enhance reliability, resiliency, sustainability, and facilitate connectivity.

Cross-Cutting Threads

STRATEGIC PLAN ALIGNMENT
RiversideCA.gov
10 1. Award Bid No. 7995 for Fisca l Year 2022/23 Arterial and Minor Streets Maintenance, Phase 3 to All American
Asphalt, of Corona, California, in the amount of
$6,809,118; and

2. Authorize the City Manager, or designee, to execute the construction contract with All American Asphalt,
including making minor non-substantial changes,
subject to the availability of budgeted funds.

RECOMMENDATIONS
9 10