1 RESOLUTION NO. 2024-2
2 A RESOLUTION OF THE BOARD OF PUBLIC UTILITIES OF THE CITY OF RIVERSIDE, CALIFORNIA (1) ADOPTING REVISED ELECTRIC FEES 3 AND CHARGES SCHEDULE (APPENDIX A), ELECTRIC RULE 4,
ELECTRIC RULE 7, ELECTRIC RULE 11, ELECTRIC RULE 22, WATER 4 FEES AND CHARGES SCHEDULE (APPENDIX A), WATER • RULE 4, WATER RULE 7, WATER RULE 8, WATER RULE 10, WATER RULE 11, 5 WATER RULE • 14, WATER RULE 16, WATER SCHEDULE WA-5;
(2) MAKING FINDINGS OF FACT; AND (3) RECOMMENDING CITY
6 COUNCIL APPROVAL THEREOF
7 WHEREAS, the City of Riverside's ("City") Department of Public Utilities ("RPU") has 8 submitted for action by the Board of Public Utilities ("Board") and the City Council, the 9 proposed adoption and approval of revised Electric Fees and Charges Schedule (Appendix A), 10 Electric Rule 4, Electric Rule 7, Electric Rule 11, Electric Rule 22, Water Fees and Charges 11 Schedule (Appendix A), Water Rule 4, Water Rule 7, Water Rule 8, Water Rule 10, Water Rule 12 11, Water Rule 14, Water Rule 16 and Water Schedule WA-5; and 13 WHEREAS, on March 3, 2022, RPU contracted with MGT of America Consulting, LLC, 14 for a fee study ("Study") for Electric and Water Fees and Charges for time and materials-base 15 user fees for RPU; and
16 WHEREAS, on May 8, 2023, the Board approved Resolution 2023-1, and on June 20, 17 2023, the City Council adopted Resolution R-24003 for the FY 2023/24 Master Fees and 18 Charges schedule, which included a 7.5% CPI increase to account for inflation that was in line 19 with the Consumer Price Index (CPI) of Riverside-San Bernardino-Ontario region in November 20 2022 (12 month, with the goal of implementing a CPI adjustment to mitigate potentially 21 significant increases to fees and charges until the formal study was updated; and 22 WHEREAS, the Electric and Water Fees and Charges Schedules have not otherwise been 23 substantially updated since 2011; and
24 WHEREAS, in recent years, the Riverside area has experienced unprecedented inflation 25 resulting in many charges becoming insufficient to recover the City's costs for providing the 26 service; and
27 28
1 (5) 82659232-
1 WHEREAS, in addition to inflation, the cost of providing services has increased, since 2 the last Electric and Water Fees and Charges update in 2011; and 3 WHEREAS, the Study reviewed the electric services, as requested by or benefiting 4 specific individuals or businesses, are recovering 59% of the costs to complete those services; and
6 WHEREAS, the Study recommended three (3) Electric fees for deletion since those 7 services are no longer provided; and
8 WHEREAS, the Study proposes seven (7) new Electric fees, including: Service Turn-on 9 Charge for Customers with AMI; Service Reconnection for Customers with AMI; Meter Spot 10 Initial Inspection; Plan Check for Building and Public Works; Cancellation Fee; Temporary 11 Meter Removal for Main Breaker Repair; CEQA Review; and 12 WHEREAS, the study reviewed the water services, as requested by or benefiting specific 13 individuals or businesses, and found that they are recovering 37% of the costs to complete those 14 services; and
15 WHEREAS, the Study recommends seven (7) Water fees for deletion since those 16 services are no longer provided; and
17 WHEREAS, the Study proposes five (5) new Water fees, including Water Service 18 Connection Charges - ¾ inch meter (non-residential/4-lane street); Water Service Connection 19 Charges - 1-inch meter (non-residential/4-lane street); Water Supply Assessment; Fire Flow 20 Test; Plan Check for Building and Public Works; and
21 WHEREAS, the Board is charged by Section 1202(e) of the City Charter to establish and 22 adopt the rates, rules, fees and charges for the Electric and Water Utility, subject to the approval 23 of the City Council; and
24 WHEREAS, the Board intends to establish and adopt the revised Electric Fees and 25 Charges Schedule (Appendix A), Electric Rule 4, Electric Rule 7, Electric Rule 11, Electric Rule 26 22, Water Fees and Charges Schedule (Appendix A), Water Rule 4, Water Rule 7, Water Rule 8, 27 Water Rule 10, Water Rule 11, Water Rule 14, Water Rule 16 and Water Schedule WA-5 in 28 2
Y ATTORNEY'S OFF
O MAIN STRI
RIVERSIDE, CA 92522
(951) 826-5567
1 accordance with RPU staff recommendations, subject to City Council approval after a duly 2 noticed public hearing; and
3 WHEREAS, the proposed fee revisions fall within the stated exceptions to the definition 4 of "tax" established by Proposition 26, because the fees and charges are imposed for a specific 5 government service provided directly to the payor that is not provided to those not charged and which does not exceed the reasonable costs to the local government of providing the service and 7 are therefore not subject to the requirements of Article XIIIC of the California Constitution; and 8 NOW, THEREFORE, BE IT RESOLVED, based upon the foregoing facts, the staff 9 report, and other evidence submitted by RPU to the Board, by the Board of Public Utilities of the 10 City of Riverside, California, as follows:
11 Section 1. The foregoing recitals are true and correct and are adopted and incorporated 12 herein by reference as findings of fact of this Board. 13 Section 2. On the basis of the Study, RPU staff analyses, data and reports, the foregoing 14 recitals and the other evidence submitted by RPU to the Board, the Board hereby finds and 15 determines that the revised Electric Fees and Charges Schedule (Appendix A), Electric Rule 4, 16 Electric Rule 7, Electric Rule 11, Electric Rule 22, Water Fees and Charges Schedule (Appendix 17 A), Water Rule 4, Water Rule 7, Water Rule 8, Water Rule 10, Water Rule 11, Water Rule 14, 18 Water Rule 16 and Water Schedule WA-5 are exempt from the provisions of the California 19 Environmental Quality Act (Pub. Res. Code Section 21000 et seq.) under Public Resources Code 20 section 21080(b) (8).
21 Section 3: The proposed revised Electric Fees and Charges Schedule (Appendix A), 22 Electric Rule 4, Electric Rule 7, Electric Rule 11, Electric Rule 22, Water Fees and Charges 23 Schedule (Appendix A), Water Rule 4, Water Rule 7, Water Rule 8, Water Rule 10, Water Rule 24 11, Water Rule 14, Water Rule 16 and Water Schedule WA-5, attached hereto as Exhibit A and 25 incorporated herein by reference, are hereby adopted and established under and pursuant to 26 Section 1202(e) of the Charter of the City of Riverside, California, are recommended for 27 28
3 1 approval by the City Council of the City of Riverside, California, and shall become effective 2 sixty days from date of approval by the City Council of the City of Riverside, California. 3 ADOPTED by the Board of Public Utilities of the City of Riverside this 13th day of June 4 2024.
5 6
That the regendic Vities Camera
7 City of Riverside, California
8 Attest:
10 set
11 Secretary of the Board of Public Utilities
City of Riverside, California
12 13 I, Donesia Gause, Secretary of the Board of Public Utilities of the City of Riverside, 14 California, hereby certify that the foregoing Resolution was adopted by the Board of Public 15 Utilities of said City at its meeting held on the 10th day of June 2024, to wit:
16 Ayes: Chair Oceguera, Vice Chair Goldware, , Board Members 17 Wohlgemuth, Melendez, and Heru
18 Noes: Board Member Siana
19 Absent: Board Members Polichetti, Avery and Montgomery 20 Abstain:
21 IN WITNESS WHEREOF, I have hereunto set my hand this 13th day of June 2024. 22 23
24 Secretary to the Board of Public Utilities
City of Riverside, California
25 26
27 28
4 CITY ATTORNEY'S OFFICE
3900 MAIN STREET
RIVERSIDE, CA 92522
(951) 826-5567
1 EXHIBIT A
2 ELECTRIC FEES AND CHARGES SCHEDULE (APPENDIX A), ELECTRIC RULE 4, ELECTRIC RULE 7, ELECTRIC RULE 11, ELECTRIC RULE 22, WATER FEES AND 3 CHARGES SCHEDULE (APPENDIX A), WATER RULE 4, WATER RULE 7, WATER RULE 8, WATER RULE 10, WATER RULE 11, WATER RULE 14, WATER RULE 16, 4 WATER SCHEDULE WA-5
5 6
7 8
9 10
11 12
13 14
15 16
17 18
19 20
21 22
23 24
25 26
27 28
CITY ATTORNEY'S OFFICE
3900 MAIN STREET
RIVERSIDE, CA 92522
(951) 826-5567
RECOMMENDED ELECTRIC AND WATER FEE SCHEDULE CHANGES
Schedule No. Schedule Name Proposed Eff Date
ELECTRIC:
APPENDIX A Appendix A: Electric Fees and Charges Schedule July 1, 2024 RULE 4 Deposits and Service Turn-On Charge July 1, 2024 RULE 7 Discontinuance and Restoration of Electric Service July 1, 2024 RULE 11 Electric Service Facilities July 1, 2024
RULE 22 Distributed Generation Facilities Interconnection July 1, 2024 WATER:
APPENDIX A Appendix A: Water Fees and Charges Schedule July 1, 2024 RULE 4 Deposits and Service Turn-On Charge July 1, 2024 RULE 7 Discontinuance and Restoration of Water Service July 1, 2024 RULE 8 Temporary Water Service July 1, 2024
RULE 10 Water System and Fee Requirements July 1, 2024
RULE 11 Water Service Connections, Water Meters and Related Apparatus July 1, 2024 RULE 14 Turn-On & Turn-Off of Water Service for Repair by Customer July 1, 2024 RULE 16 Conveyance of Water Rights and Water Stock July 1, 2024 WA-5 Fire Protection Services and Fire Hydrants July 1, 2024 Note: The above rate schedules are being updated in the proposed fee study. All other rules and rate schedules remain unchanged.
City of Riverside Deposits and Service Turn-On Charge
Public Utilities Department
ELECTRIC RULE 4
DEPOSITS AND SERVICE TURN-ON CHARGE
DEPOSITS
Deposits will be required when a customer is otherwise unable to satisfactorily establish or re-establish credit as set forth in Rule No. 3 B. AMOUNT OF DEPOSIT TO ESTABLISH SERVICE
A minimum deposit will be required to establish residential service. The amount of deposit required to establish non-residential service will be equal to twice the estimated average monthly bill for electric service, but in no event less than a nouncum residential deposit as established by the Board of Public Utilities and City
AMOUNT OF DEPOSIT TO RE-ESTABLISH SERVICE
If service is terminated for any reason other than a Customer requested turn off, or if a notice of discontinuance has been given, the Utility may require the Customer to pay a deposit, or an additional deposit, up to an estimated average three-month bill.
In no case shall the amount of deposit be less than the minimum deposit as set forth in APPENDIX A, ELECTRIC FEES AND CHARGES SCHEDULE.
D. PAYMENT OF DEPOSIT
Deposits are due upon application for service and delinquent 14 days later.
Deposits will not be used as payment for past-due bills to avoid discontinuance of service.
E. RETURN OF DEPOSIT
Upon discontinuance of service, the Utility shall apply the Customer's deposit and accrued interest to the unpaid bills and refund any balances that exceed $10 by mail. Any refunds with a balance of less than $10 will be refunded to Customer upon request.
2. After the Customer has maintained a good payment record for twelve (12) consecutive months, the Utility shall apply the Customer's deposit, including accrued interest, to the Customer's bill.
The Utility may apply the deposit to the Customer's account at any time upon request, provided the Customer's credit may otherwise be established in accordance with Rule No. 3, ESTABLISHMENT AND RE-ESTABLISHMENT OF CREDIT.
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside Deposits and Service Turn-On Charge
Public Utilities Department 4-2
F. INTEREST ON DEPOSIT
Simple interest as established annually by the Board of Public Utilities will be accrued for the period that the deposit is held by the Utility.
2. Interest may only be applied to the Customer's active account at the discretion
SERVICE TURN-ON CHARGE
A service turn-on charge shall be made for turning on electric service during normal working hours on the following workday. There will be an additional charge for the same day and after-hours turn-on of service when specifically requested by the Customer. A service charge will be assessed for each additional field visit required to complete the service turn-on order. a. There will be no service turn-on charge when Customer has a valid Leave on for Owner contract, and a separate field visit in addition to the move-out order is not required.
After hours for fee assessment purposes are legal holidays and hours outside the following time periods: 8AM to 4PM Monday through Friday and 9AM to 1PM Saturdays.
2. The Utility shall not be liable for any loss or damage caused by the improper installation, maintenance or malfunction of any electric apparatus or appliance, or for damage caused by the turning on and off of electric service by the Utility.
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside Discontinuance and Restoration of Electric Service Public Utilities Department 7-1
ELECTRIC RULE 7
DISCONTINUANCE AND RESTORATION OF ELECTRIC SERVICE
A. CUSTOMER'S REQUEST FOR SERVICE DISCONTINUANCE
When Customers desire to terminate their responsibility for service, they shall give the Utility not less than two working days' advance notice of their intention, state the date on which they wish the termination to become effective and provide access to the electric meter. A field visit service charge will be assessed for each additional trip (after original attempt to turn service off) required to complete the turn-off request.
If a new application is not made for service, and the electric meter serves more than one Premises, and the Premises are occupied, the Utility will read the meter on the date requested and notify the occupants of their rights by posting of a 15-day notice, except as otherwise stated in this Rule. Any resident has the right to prevent discontinuance by applying for service to the master meter in their own name.
Responsibility for service, for any Customer making an application, will begin with that date and reading. There will be a charge for posting of the notice which will be the liability of the Customer making application.
Customers may be held responsible for all services furnished at the Premises until two working days after receiving a request for discontinuance of the service by the Utility or until such time as the Utility has received an application for new service, provided access is available.
In the event access is not provided, the Customer discontinuing service shall be held liable for all consumption until access is provided.
B. DISCONTINUANCE FOR UNSAFE EQUIPMENT
1. Service Detrimental to Other Customers
The Utility shall not provide electric service to any Premises where the use or connections made may be detrimental to the electric service rendered by the Utility to other Customers or to the Utility's facilities.
Unsafe Equipment
The Utility may refuse or discontinue service to a Customer if any part of the Customer's wiring or other equipment, or the use thereof is determined by the Utility to be unsafe or in violation of applicable laws, rules, or regulations, or if any condition existing upon the Customer's Premises is determined to endanger the Utility's facilities until it shall have been put in a safe condition or the violation remedied. The Utility does not assume any responsibility of Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside Discontinuance and Restoration of Electric Service Public Utilities Department 7-2
inspecting or repairing the Customer's wiring or other equipment and assumes no liability.
C. DISCONTINUANCE FOR USE OF ELECTRICITY WITHOUT APPICATION When a new occupant who has not applied for electrical service takes possession of Premises and finds the electric service turned on, the occupant shall notify the Utility of such findings within 1 working day.
In the event the occupant turns on the electric service, or fails to notify the Utility of finding the electric service turned on within 1 working day of occupancy, the occupant will be billed for consumption back to their move in date and owner shall be billed for any unresolved usage. If the Premises are unoccupied, or the Utility has not been notified of a new tenant by the owner, property manager, occupant or other representative of the owner, and electric service is in use, the owner of the property shall be held responsible for payment of the bill. It is the responsibility of the owner to verify that the utility service has been transferred into the name of the new occupant and to settle disputes of responsibility between the occupant and the owner.
In the event that the occupant is charged for usage where the amount charged will be determined by the Utility, the amount billed will be based upon either the meter reading or on the basis of the estimated consumption for the length of time service was received by the occupant without proper application.
When the Utility finds the electricity is being used without proper application, the Utility may terminate the service without further notice. Any amount due in excess of the amount billed to the occupant shall be billed to the owner.
Only authorized Utility personnel are permitted to turn the service on at the meter. If the occupant restores electric service, a self-restoral service fee may be imposed.
D. DISCONTINUANCE FOR NONPAYMENT OF BILLS
1. Past Due (Delinquent) Bills:
Bills will be considered past due (delinquent) if not paid within 19 days after the date of mailing. Reference PUC 10010.1(a)
2. Discontinuance of Service Notice:
When a bill for electric service has become past due and a discontinuance of service notice has been issued, service may be discontinued if the bill is not paid within the time required by such notice. A Customer deposit to establish Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside Discontinuance and Restoration of Electric Service Public Utilities Department 7-3
credit will not be used as payment to avoid discontinuance of service.
Reference PUC 10010.1(a)
If a bill is past due as set forth in Section 1 above, a Customer's service may be discontinued for nonpayment of a bill provided the Utility first gives a discontinuance of service notice to the Customer at least ten (10) working days prior to the proposed discontinuance. Such ten-day period shall not commence until five (5) working days after the mailing of the notice.
However, in no case shall residential service be discontinued for nonpayment until payment has been delinquent for at least sixty (60) calendar days. No less than seven (7) working days before discontinuation of residential service for nonpayment, the Utility shall contact the Customer named on the account by telephone or provide written notice. If the Utility is unable to contact the Customer by mail or telephone, the Utility will provide a notice of imminent discontinuation of service for nonpayment. There shall be a charge for posting this notice of termination at the Premise.
Notwithstanding the foregoing, residential Customers who are delinquent under the terms of an amortization agreement shall be subject to disconnection procedures required by State law.
Reference PUC 10010.1(a), HSC 116908 (a)(1)
Any residential Customer who has initiated a complaint or requested an investigation within 5 working days of receiving a contested bill shall not have service discontinued for nonpayment during the pendency of an investigation. Customer may be required to pay an estimated bill per Rule No. 21. Reference PUC 10010.(c)
Discontinuance of Residential Service Dangerous to the Health of Customer:
The Utility will not terminate residential service for non-payment upon certification by a primary care provider that said termination will be life threatening and the Customer is financially unable to pay for service within the normal payment period and is willing to enter into an amortization agreement with the Utility for the delinquent amount due.
Reference PUC 10010(3), HSC 116910 (a)
Inability to Pay Residential Utility Bill:
Any residential Customer who has, within 13 days of mailing of the Urgent Notice, made a request for an extension of the payment period of a bill asserted to be beyond the means of the Customer to pay in full during the normal period for payment, shall be given an opportunity for review of the request by a review manager of the Utility. The review shall include consideration of whether the Customer shall be permitted to amortize the Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside Discontinuance and Restoration of Electric Service Public Utilities Department 7-4
unpaid balance of the account over a reasonable period of time, not to exceed 12 months. Reference PUC 10010 (c), HSC 116910(a) A Customer shall not have utility services discontinued for nonpayment if they are complying with an amortization agreement entered into with the Utility, provided the Customer also keeps current their account for utility services as charges accrue in each subsequent billing period.
Reference PUC 10010.(c)
However, service may be terminated to any Customer who does not comply with an installment payment agreement or keep current the account for utility services as charges accrue in each subsequent billing period.
Reference PUC 10010. (c), HSC 116910(b)
The Utility shall make available to Customers, upon request, information regarding agencies and/or organizations that may provide financial assistance. Reference PUC 10010.1(d)
If a residential Customer fails to comply with an amortization agreement, the Utility shall not terminate service without giving notice to the Customer at least five (5) working days prior to termination of the conditions the Customer is required to meet to avoid termination, but, such notice shall not entitle the Customer to further investigation by the Utility.
Reference PUC 10010.1(e), HSC 116910 (b)(3)
5. Discontinuance for Unpaid Utility Bill at a Previous Address A Customer's service may be discontinued for nonpayment of a bill for service previously rendered them at any location served by the Utility provided such bill is not paid within 13 days after presentation of an Urgent Notice. Reference PUC 10010.1(a)
In no case will residential service be discontinued because of nonpayment of bills for non-residential service.
6. Discontinuance of Service when Trying to Avoid Payment of Utility Bill The Utility may discontinue or deny service for nonpayment of a bill where the Utility determines that the same person or persons continue to occupy the service address. However, the Utility will not deny service to the renters of Premises whose owners or prior unrelated tenants have delinquent unpaid bills.
Adopted by Board of Public Utilties: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside Discontinuance and Restoration of Electric Service Public Utilities Department 7-5
7. Discontinuance of Service due to Fraud
The Utility may refuse or discontinue service if the acts of the Customer or the conditions upon the Customer's Premises are such as to indicate an intent to defraud the Utility.
8. Discontinuance of Service at More Than One Location
If a Customer is receiving service at more than one location, service at any or all locations may be discontinued if bills for service at any location are not paid within the time specified, except that a residential service account shall not be discontinued for failure to pay bills for non-residential service.
9. Discontinuance of Service when Utility's Business Office is Closed Service will not be discontinued by reason of delinquency in payment for utility services on any Saturday, Sunday, legal holiday, or at any time during which the business offices of the Utility are not open to the public.
Reference PUC 10011.
10. Discontinuance of Residential Service at Individually Metered Detached Single-Family Dwelling, Multiunit Residential Structure, Mobile Home Park, or Labor Camp
This section applies if there is a landlord-tenant relationship between the residential occupants and the owner, manager, or operator of the dwelling.
Reference PUC 10009. (a)
Where utility service is provided to individually metered residential occupants in a detached single-family dwelling, a multiunit residential structure, mobile home park or permanent residential structure in a labor camp, as defined in section 17008 of the Health and Safety Code, and the owner, manager, or Customer of record, the Utility shall make every good faith effort, when the account is in arrears, to inform the residential occupants by means of written notice that service will be discontinued.
Reference PUC 10009. (b)
(1) A 10-day notice of discontinuance shall inform the residential occupants of their right to become Customers, to whom the service will then be billed, without being required to pay any amount which may be due on the delinquent account. The notice shall be written in English, Spanish, Chinese, Tagalog, Vietnamese, and Korean, as specified in Section 1632 of the Civil Code.
Reference PUC 10009.(b)
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside Discontinuance and Restoration of Electric Service Public Utilities Department 7-6
(2) The Utility is not required to make service available to the residential occupants unless each residential occupant agrees to the terms anc conditions of service and meets the requirements of law and the Utility's Rules and Schedules. However, if one or more of the residential occupants are willing and able to assume responsibility for the subsequent charges to the account to the satisfaction of the Utility, or if there is a physical means, legally available to the Utility, of selectively terminating service to those residential occupants who have not met the requirements of the Utility's Rules and Schedules, the Utility shall make service available to the residential occupants who have met those requirements. Reference PUC 10009. (c) (3) The residential occupant must establish credit to the satisfaction of the Utility. However, where a residential occupant is establishing service under the provisions of this section and prior service for a period of time is a condition for establishing credit with the Utility, residence and proof of prompt payment of rent or other credit obligation acceptable to the Utility for that period of time is a satisfactory equivalent. Reference PUC 10009.(d)
(4) Any residential occupant who becomes a Customer of the Utility pursuant to this section whose periodic payments, such as rental payments, include charges for residential electric service, where these charges are not separately stated, may deduct from the periodic payment each payment period all reasonable charges paid to the Utility for electric service during the preceding payment period.
Reference PUC 10009.(e)
There will be a trip charge for posting of the field notification.
11. Discontinuance of Service at a Master Metered Multiunit Residential Structure, Mobile Home Park, or Labor Camp.
For discontinuance of service to residential occupants in a multiunit residential structure, mobile home park, or labor camp, as defined in sectior 17008 of the Health and Safety Code, who are master metered by the Utility, and the owner, manager, or operator of the structure or park is listed by the Utility as the Customer of record, the Utility shall make every good faith effort to inform the residential occupants, when the account is in arrears, by means of written notice, that service will be discontinued.
Reference PUC 10009.1(a)
(1) A written 15-day notice of discontinuance shall be posted on the door of each residential unit prior to discontinuance; éxcept that, if it is not reasonable or practicable to post the notice on the door of each residential unit, the Utility shall post two copies of the notice in each Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside Discontinuance and Restoration of Electric Service Public Utilities Department 7-7
accessible common area and at each point of access to the structure or structures. The notice shall be written in English, Spanish, Chinese, Tagalog, Vietnamese, and Korean as specified in Section 1632 of the Civil Code. Reference PUC 10009.1(a)
The notice will specify:
a. The date on which service will be discontinued.
b. That the residential occupants have the right to become Customers, to whom the service will then be billed, without being required to pay any amount which may be due on the delinquent account.
What the residential occupants are required to do in order to prevent the termination of service or to reestablish service. d. The estimated monthly cost of service.
e. The title, address, and telephone number of a representative of the Utility who can assist the residential occupants in continuing service.
f. The address and telephone number of a legal services project as defined in Section 6213 of the Business and Professions Code, which has been recommended by the local county bar association. Reference PUC 10009.1(a)
The Utility is not required to make service available to the residential occupants unless each residential occupant or a "representative of the residential occupants" agrees to the terms and conditions of service and meets the requirements of law and the Utilities Rules and Schedules. However, if one or more of the residential occupants or the representative of the residential occupants are willing and able to assume responsibility for subsequent charges to the account to the satisfaction of the Utility, or if there is a physical means, legally available to the Utility, of selectively terminating service to those residential occupants who have not met the requirements of the Utility's Rules and Schedules or for whom the representative of the residential occupants is not responsible, the Utility shall make service available to those residential occupants who have met those requirements or on whose behalf those requirements have been met.
As used herein, "representative of the residential occupants" does not include a tenants' association. Reference PUC 10009.1(b) Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside Discontinuance and Restoration of Electric Service Public Utilities Department 7-8
(3) Credit must be established to the satisfaction of the Utility. Where prior service for a period of time or other demonstration of credit worthiness is a condition for establishing credit with the Utility, residence and proof of prompt payment of rent or other obligation during that period of time acceptable to the Utility is a satisfactory equivalent. Reference PUC 10009.1(c)
(4) Any residential occupant who becomes a Customer of the Utility pursuant to this section whose periodic payments, such as rental payments, includes charges for residential electric service, where these charges are not separately stated, may deduct from the periodic payment each payment period all reasonable charges paid to the Utility for electric service during the preceding payment period.
Reference PUC 10009.1(d)
(5) Where the Utility furnished service under a Residential rate schedule to a multiunit residential structure, mobile home park or labor camp, through a master meter, the Utility may not discontinue service in any of the following situations:
During the pendency of an investigation by the Utility of a Customer dispute or complaint. Reference PUC 10009.1(e) When the Customer has been granted an extension of the
period for payment of a bill. Reference PUC 10009. 1(e) c. For an indebtedness owed by the Customer to any other public agency or when the obligation represented by the delinquent account or other indebtedness was incurred with any public agency other than the Utility. Reference PUC 10009.1(e) d. When a delinquent account relates to another property owned, managed, or operated by the Customer.
Reference PUC 10009.1(e)
When a public health or building officer certifies that disconnection would result in a significant threat to the health or safety of the residential occupants or the public.
Reference PUC 10009.1(e)
There will be a trip charge for posting of the field notification.
12. State law pertaining to Discontinuance of Service
Should there be a conflict between this Rule No. 7 and State law, as amended from time to time, State law shall govern, except to the extent that Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside Discontinuance and Restoration of Electric Service Public Utilities Department 7-9
the provisions of this Rule are more favorable for the Customer or a residential occupant.
E. RESTORATION OF SERVICE
Amount due to Restore Service
All past due bills at the time of reconnect, applicable service charges, and deposits shall be paid by Customer prior to restoration of service. In addition, the City and/or Utility may require inspection of electrical facilities prior to reconnect at the Customer's expense. After hours for fee assessment purposes are hours outside the following windows: 8AM to 4PM Monday through Friday and 9AM to 1PM Saturdays and legal holidays.
2. Re-establishment of Service Deposit
If service is terminated, or if a notice of discontinuance has been given, the Utility will require the Customer to pay a deposit or an additional deposit equal to an estimated average three month bill.
3. Reconnect Service Charge
All charges are cumulative and each trip to the Premises will incur additional charges. In order to restore service discontinued under the provisions above, there shall be a charge for the expense of turning the service on.
4. Self-Restoral Service Charge
In the event anyone has turned on the electric service after it has been turned off for any of the above reasons, there shall be a charge in addition to other amounts due from the Customer before service is restored.
Administrative Fee
If energy diversion occurs, an additional service charge will be assessed, as prescribed in Rule No. 19, ENERGY DIVERSION.
Electric Meter Removal
If the meter is removed, a service charge will be billed in addition to other amounts due. An inspection will be required at the Customer's expense (prior to re-installation of meter).
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside Discontinuance and Restoration of Electric Service Public Utilities Department
7. Termination at Overhead or Underground
If service has been terminated by an electrical crew at the overhead or underground, there will be an additional service charge prior to restoring the service.
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside Electric Service Facilities
Public Utilities Department 11-1
ELECTRIC RULE 11
ELECTRIC SERVICE FACILITIES
A. GENERAL
Electric service connection facilities for supplying service to Customers, in accordance with good utility engineering practice, shall be provided by the Utility subject to conditions specified in this Rule. Before a new, relocated, or rebuilt service is connected, the installation must be inspected and approved by the Utility in addition to receiving any necessary approvals from other governing agencies. The installation must be constructed in accordance with Utility supplied plans, meet all current Utility specifications, Utility approved EUSERC (Electric Utilities Service Equipment
Requirements Committee) configurations, and applicable California PUC General Orders 95 and 128 requirements.
2. An application for installation of service shall be made on a form furnished by the Utility. This application shall specify the size of the service connection desired, the property to be served and the purpose for which the electricity is to be used. The information supplied by the Applicant shall be considered as authoritative and final. If any error in the application causes the installation of a service connection that is improper either in type, size or location, the cost of all changes required shall be paid by the Applicant.
Conditions and allowances prescribed in this Rule relate only to service connection facilities, and are based on the assumption that general distribution facilities within practical reach of the premises to be served are existing or will be installed in accordance with the Utility distribution system additions policy under Rule No. 10.
The Utility shall install only one service per building, and one meter per single-family residence or single non-residential enterprise in building or Premises, except as follows:
a. Where more than one service is required by reason of the Utility's operating convenience and necessity, the Utility shall specify the number and location of the services to be
installed.
b. Where a single building or other structure is sufficiently large to make two or more services necessary.
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution No:
Effective Date:
City of Riverside Electric Service Facilities
Public Utilities Department 11-2
C. Where a building will be occupied by two or more
Customers, individually metered and billed by the Utility, separate services of the same voltage and phase may be
provided for each Customer. All such services shall
terminate insofar as practical at the same general location, as designated by the Utility.
Materials or equipment furnished and installed on Customer premises by the Electric Utility will at all times be and remain the sole property of the Utility, and may be repaired or replaced by the Utility at any time, and removed at the termination of service, and may also be used to supply other Applicants for service. Applicant shall provide easements to the Utility when requested.
The Customer shall exercise reasonable care to prevent the facilities of the Utility upon the premises from being damaged or destroyed, and shall not relocate or otherwise interfere with them, and, if any defect is discovered, shall promptly notify the Utility.
Due to the long lead times for engineering, material acquisition, crew scheduling and construction, application for service must be made as far in advance as possible. Depending on the complexity of the installation and assuming timely completion of all necessary steps by the Applicant, lead time of 6 months or more may be necessary. After receipt of fees, service charges and deposits and clearance from the inspection agency having jurisdiction, the Utility shall endeavor to complete within a reasonable time the installation of the necessary facilities. However, the Utility shall not be liable for any delays encountered in completing the installation.
If, for any reason of the Applicant, installation of a service cannot Day in lanced de eated dost or the ours overine sta
extent that it exceeds any costs included in other charges.
8. The Utility shall be obligated to provide facilities adequate to serve only the load initially specified and connected, regardless of the rating of the service equipment, service switch or breaker.
Increased loads will be considered as new installations, and the Customer shall pay the net cost of any changes required in the Utility facilities in accordance with Section B, Rule No. 11 and may be required to make specified changes in the service facilities or equipment to accommodate the increased load or the type of service to be supplied by the Utility.
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution No:
Effective Date:
City of Riverside Electric Service Facilities
Public Utilities Department 11-3
9. Before beginning construction or installation of any facilities related to the electric service, the Applicant shall supply switchgear drawings to the Utility and approval of the Utility must be received prior to the fabrication of the switchgear. The location of the service entrance facilities, metering transformers, and meter shall be as specified by the Utility.
10. See Electric Appendix A for fees related to new electrical service panels, upgrades, and associated meter spots that may result in disconnects and reconnects for electric facilities for panel upgrades.
11. See Electric Appendix A for fees associated with Building and Public Works Utility Plan Checks, California Environmental Quality Act (CEQA) and project Plan Check cancellations. The project Plan Check cancellations are applicable to non-building and safety submittal plan checks.
12. See Electric Appendix A for fees related to electric vehicle meter adapter and associated costs.
B. SERVICE CHARGES
Non-Commercial and Non-Industrial Services
The total cost of the Utility facilities installed to serve the Applicant, exclusive of metering costs for non-commercial and non-industrial services, shall be paid by the Applicant for all new or increased loads, relocated, or overhead to underground conversion installations. The payment shall be made in advance of installation of Utility facilities. Costs for facilities that will be used by more than one Customer will be shared proportionately.
2. Commercial and Industrial Services
The Utility's standard least cost facilities to serve an Applicant's new or increased commercial or industrial load shall be installed by the Utility and be paid by the Applicant in advance of installation.
The extra cost for any additional facilities or accommodations required beyond a standard least cost service as determined by the Utility shall be paid by the Applicant in advance of installation.
Extraordinary facilities or service provisions will be handled under Rule No. 16, Added Facilities.
relocations or overhead to underground conversions shall be paid by the Applicant in advance of installation.
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution No:
Effective Date:
City of Riverside Electric Service Facilities
Public Utilities Department 11-4
C. SERVICE DESIGN AND ENGINEERING
All service designs and engineering shall require an upfront deposit as determined by the Utility. The design work will then be scheduled along with other eligible Applicants. A deposit for early design will be credited to the cost of the design and installation of the service or refunded as appropriate.
The cost of multiple designs to explore options or redesigns required by changes beyond the control of the Utility shall be paid by the Applicant.
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution No:
Effective Date:
City of Riverside Electric Service Facilities
Public Utilities Department 11-5
D. UNDERGROUND SERVICE
Underground Service Mandatory
Installation of electrical service facilities for all new services shall be underground and installed according to Utility design standards, underground structures standards, the latest edition of RPU approved EUSERC configurations and Utility plans and
specifications supplied for each specific installation. a. The requirements of this section may be waived if technical or physical conditions make underground installation
infeasible in the Utility's judgment.
b. Premises may be served overhead from existing facilities if underground service is not feasible in the Utility's judgment.
But, the Customer may be required to provide Utility
approved facilities to accommodate future conversion to underground service.
C. When a service to an existing building being served
overhead is relocated, rebuilt or increased in size, the service shall be installed underground unless, in the Utility's judgment, there are technical or physical impediments that make undergrounding infeasible.
2. Trench, Structures, and Conduit
The Applicant, at the Applicant's expense, shall provide the necessary trenching, conduit, backtill, compaction, trench resurfacing and substructure installation on the Customer property and to distribution facilities in adjacent rights-of-way on either side of the street or in a City easement adjacent to the parcel to be served. The Customer shall own and maintain the service conduits, substructures, pads and protective barriers on the premises. A line extension, other than the service, will be as specified in Rule No. 10.
Cable Installations
a. The Utility shall install all service cable from its distribution facilities to the Customer terminating pull box, switchboard pull section, or other terminating enclosure and make all Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution No:
Effective Date:
City of Riverside Electric Service Facilities
Public Utilities Department 11-6
For each service connection, the Customer shall install a set of service entrance conductors which extend from the point of service delivery at the point of termination of the Utility's service conductors within the Customer underground
terminating enclosure, to the Customer meter or switchgear lugs. The service entrance conductors shall be of a type and be in an enclosure which meets with the approval of the Utility and any inspection authorities which have jurisdiction.
E. OVERHEAD SERVICE
New overhead services will be allowed only when underground service is not feasible.
2. The Applicant shall provide a suitable location for the termination of the overhead service wires and an adjacent weather head. The location of the termination and weather head is subject to approval of the Utility and any inspection authority having jurisdiction and must meet all applicable codes.
Overhead service wires shall in all cases be furnished and installed by the Utility. The Applicant shall install the service entrance tors to the conductors from the point of termination of the Utility's service wires to the Applicant's meter or switchgear lugs.
The Applicant may be required to provide Utility approved facilties to accommodate future conversion to underground service.
Overhead service capacity shall be limited to 100 kVA single phase or 300 kVA three phase.
F. TRANSFORMERS ON CUSTOMERS PREMISES
nstallation of transformer racks, enclosures, pads, vaults, ol elated equipment on Applicant's premises shall be as specified b the Utility.
The Applicant shall make adequate provisions for the necessar electrical equipment. The provisions, at the option of the Utility shall be either:
a. A concrete or other suitable base and enclosure, located outside the building, and furnished and installed by the Applicant;
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution No:
Effective Date:
City of Riverside Electric Service Facilities
Public Utilities Department 11-7
b. An underground vault or individual transformer enclosure furnished and installed by the Applicant; or
c. An indoor transformer room provided by the Applicant and conforming to Utility specifications, suitably ventilated, illuminated and complying with the requirements of all other agencies having jurisdiction.
The Applicant shall provide necessary easements and rights-of- way, and provide and maintain necessary legal clearances from adjacent buildings and adequate access to supply lines, underground riser pole, outside enclosure, vault, padmounted equipment, or transformer room, whether inside or outside of buildings, and to allow for movement of trucks, workers, materials and construction equipment.
4. All primary and secondary cable, transformers, high voltage fusing or switching equipment, blowers (except building ventilation systems for transformer rooms within buildings) and other related equipment shall be furnished and installed by the Utility.
When bus duct is required by the Utility in lieu of secondary cable, it shall be furnished and installed for the Utility by the Applicant in accordance with the Utility's specifications. The bus duct shall remain the property of the Applicant who will operate and maintain it.
G. HIGH VOLTAGE
Service at 6930/12000 volts may be provided for loads exceeding 1000 KVA of estimated demand where distribution facilities at this voltage are available. Conduit and cable installation for high voltage services shall be the same as indicated in this Rule for other services. Loads in excess of 6000 kVA will require multiple services or special services as covered in Rule No. 20.
The Applicant's primary protection and metering must be submitted to the Utility for review and approval. If requested by the Utility, the Applicant shall furnish and install primary switchgear or a circuit breaker containing battery or Utility approved tripping and phase and ground relays to insure coordination with the Utility's remote relays.
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution No:
Effective Date:
City of Riverside Electric Service Facilies
Public Utilities Department
H. CONVERSION OF DISTRIBUTION FACILITIES AND SERVICES FROM
OVERHEAD TO UNDERGROUND
The Utility, for reasons of economy of operation, simplification of its distribution system, or for other reasons, may elect to convert an area from overhead to underground distribution, and shall install at its expense all of the underground facilities necessary to supply service to the existing loads. If an area or service is converted from overhead to underground at the request of others, the cost will be paid by the requester in accordance with Rule No. 10, paragraph E.2. or in accordance with City ordinance if an underground district is formed.
1. ABANDONMENT OF SERVICE
Upon notification by the Customer, the Utility will remove the service and the conductors, transformers and other equipment exclusively used to serve the Customer. The removal of the ducts, vaults, pads and related equipment originally installed by the Customer will be the responsibility of the Customer. If a service is disconnected for more than 1 year, the service will be considered abandoned and the Utility may remove its facilities without notice. Should the Customer later request that the service be reactivated, the service shall be treated as new and the Customer shall pay all applicable costs for reinstalling the facilities.
J. IMPLEMENTATION OF COMMERCIAL AND INDUSTRIAL CHARGE
MODIFICATIONS
For commercial and Industrial services energized after June 1, 1995, the charges will be recalculated in accordance with new Rule Nos. 10 and 11.
Any excess charges already paid will be refunded.
SPECIAL PROVISIONS
Special Provisions have been enacted for infill development and apply to those single family residential parcels identified and defined in the Residential Infill Strategy, as adopted by the City Council.
The Special Provisions are as follows:
a. Street lighting unit of benefit charges shall be considered paid.
Overhead services shall be permitted where overhead facilities already exist.
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution No:
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-1
ELECTRIC RULE 22
DISTRIBUTED GENERATION FACILITIES INTERCONNECTION
A. APPLICABILITY
Applicability. This Rule describes the interconnection, operating and metering requirements for Generating Facilities to be connected to the Riverside Public Utilities (RPU) Distribution System. Subject to the requirements of this Rule, RPU will allow the interconnection of Generating Facilities with its Distribution System.
Definitions: Capitalized terms used in this Rule, and not otherwise defined, shall have the meaning ascribed to such terms in Section H. The definitions in this Rule shall only apply to this Rule and may not apply to RU's other rate schedules.
B. GENERAL RULES, RIGHTS AND OBLIGATIONS
1. Authorization Required to Operate. A Producer must comply with this Rule, execute an Interconnection Agreement with RPU, and receive RU's express written permission to operate a Generating Facility in parallel with the Distribution System. RPU shall apply this Rule in a non-discriminatory manner and shall not unreasonably withhold its permission to interconnect an Electric Producer's Generating Facility.
2. Separate Arrangements Required for Other Services. A Producer requiring other electric services from RPU including, but not limited to, Distribution Service during periods of curtailment or interruption of a Generating Facility, must enter into separate arrangements with RPU for such services, in accordance with RPU Board and City Council approved rate schedules.
3. Transmission Service Not Provided with Interconnection. Interconnection with RPU's Distribution System under this Rule does not provide a Producer any rights to utilize RU's Distribution System for the transmission or distribution, or wheeling of electric power, nor does it limit those rights.
Compliance with Laws, Rules, and Tariffs. A Producer shall ascertain and comply with RPU rules, rate schedules, and regulations of RPU; applicable Federal Energy Regulatory Commission approved rules, tariffs, and regulations; and any local, state or federal law, statue or regulation which applies to the design, siting, construction, installation, operation, or any other aspect of the Producer's Generating Facility and Interconnection Facilities.
Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-2
5. Design Reviews and Inspections. RPU shall have the right to review the design of a Producer's Generating Facility and Interconnection Facilities and to inspect a Producer's Generating and Interconnection Facilities prior to the commencement of Parallel Operation with RU's Distribution System. RPU may require a Producer to make modifications as necessary to comply with the requirements of this Rule. RU's review and authorization for Parallel Operation shall not be construed as confirming or endorsing the Producer's design or as warranting the Generating or Interconnection Facilities' safety, durability or reliability. RPU shall not, by reason of such review or lack of review, be responsible for the strength, adequacy, or capacity of such equipment.
6. Right to Access. A Producer's Generating Facility and Interconnection Facilities shall be reasonably accessible to RPU personnel as necessary for RPU to perform its duties and exercise its rights under its rate schedules and rules, and any Interconnection Agreement between RPU and the Producer.
Confidentiality of Information. Any information pertaining to Generating or Interconnection Facilities provided to RPU by a Producer shall be treated by RPU in a confidential manner. RPU shall not use information contained in the Application to propose discounted rates to the Customer unless authorized to do so by the Customer or the information is provided to RPU by the Customer through other means.
Prudent Operation and Maintenance Required. A Producer shall operate and maintain its Generating Facility and Interconnection Facilities in accordance with Prudent Electrical Practices and shall maintain compliance with this Rule.
Curtailment or Disconnection. RPU may limit the operation or disconnect or require the disconnection of a Producer's Generating Facility from RPU's Distribution System at any time, with or without notice, in the event of an Emergency, or to correct Unsafe Operating Conditions. However, RPU must provide written notice as soon as possible following such disconnect. RPU may also limit the operation or disconnect or require the disconnection of a Producer's Generating Facility from RPU's Distribution System upon the provision of reasonable written notice: 1) to allow for routine maintenance, repairs or modifications to RPU's Distribution System; 2) upon RPU's determination that a Producer's Generating Facility is not in compliance witt this Rule; or, 3) upon termination of the Interconnection Agreement. Upon the Producer's written request RPU shall provide a written explanation of the reason for such curtailment or disconnection.
Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-3
C. APPLICATION AND INTERCONNECTION PROCESS
Application Process
a. Applicant Initiates Contact with RPU. Upon request, RPU will provide information and documents (such as sample agreements, the Application, technical information, listing of Certified Equipment, application fee information, applicable rate schedules and metering requirements) in response to a potential Applicant's inquiry. Unless otherwise agreed upon, all such information shall normally be sent to an Applicant within three (3) business days following receipt of the initial request from the Applicant. RPU will establish an individual representative as the single point of contact for an Applicant, but may allocate responsibilities among its staff to best coordinate the Interconnection of an Applicant's Generating Facility.
b. Applicant Completes and Files an Application. All Applicants shall be required to complete and file an Application and supply any relevant additional information requested by RPU. The filing must include the completed Application and a fee for processing the application and performing the Initial Review to be completed by RPU pursuant to Section C.1.c. The application fee shall vary with the type of the proposed Generating Facility. See Electric Appendix A for Net Energy Metering (per Public Utilities Code Section 2827) amounts.
Fifty percent of the fees associated with the Initial Review will be returned to the Applicant if the Application is rejected by RPU or the Applicant retracts the Application.
The Applicant may propose and RPU may negotiate specific costs for processing non-standard applications such as multi-units, multi-sites, or otherwise as conditions warrant. The costs for the Initial Review and the Supplemental Review contained in this Section, as well as the language provided in Sections C.1.c and C.1.d, do not apply under these circumstances.
Within ten (10) business days of receiving an Application, RPU shall normally acknowledge its receipt and state whether the Application has been completed adequately. If deficiencies are noted, RPU and Applicant shall cooperate in a timely manner to establish a satisfactory Application.
c. RPU Performs an Initial Review and Develops Preliminary Cost Estimates and Interconnection Requirements.
Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-4
(1) Upon receipt of a satisfactorily completed Application and any additional information necessary to evaluate the Interconnection of a Generating Facility, RPU shall perform an Initial Review using the process defined in Section I. The Initial Review determines if (a) the Generating Facility qualifies for Simplified Interconnection, (b) the Generating Facility can qualify for Interconnection subject to additional requirements, or (c) it will be necessary for RPU to perform an Interconnection Study to determine the Interconnection Requirements.
(2) The RPU shall complete its Initial Review, absent any extraordinary circumstances, within 10 business days, upon determination that the Application is complete, if the Generating Facility qualifies for Simplified Interconnection. If the Initial Review determines that the proposed facility can be
interconnected by means of a Simplified Interconnection, RPL vill provide the Applicant with a written description of th equirements for interconnection and a draft Interconnectio Agreement pursuant to Section C. 1.e.
(3) If the Generating Facility does not qualify for Simplified Interconnection as proposed, RPU will notify the Applicant and perform a Supplemental Review as described in Section I. The Supplemental Review will provide either (a) Interconnectior Requirements beyond those for Simplified Interconnection, an a draft Interconnection Agreement, or (b) a cost estimate an schedule for an Interconnection Study. The Supplemental Review shall be completed, absent any extraordinary
circumstances, within 20 business days upon determination that the Application is complete. Payment for the Supplemental Review shall be submitted to RPU within 10 calendar days after the results of the Supplemental Review are provided to the Applicant.
When Required, Applicant and RPU Commit to Additional
Interconnection Study Steps. When an Initial Review reveals that the proposed facility cannot be interconnected to RU's Distribution System by means of a Simplified Interconnection, or that significant RPU Interconnection Facilities or Distribution System improvements must be installed or made to RPU's Distribution System to accommodate the interconnection of an Applicant's Generating Facility, RPU and Applicant shall enter into an agreement that provides for RPU to perform additional studies, facility design, and engineering and to provide detailed cost estimates for fixed price or actual cost billing, to the Applicant at the Applicant's expense. The interconnection study agreement shall set forth RPU's schedule for completing such work and Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-5
the estimated or fixed price costs of such studies and engineering.
Upon completion of an Interconnection Study, RPU shall provide the Applicant with the specific requirements, costs and schedule for interconnecting the Generating Facility to accommodate execution of agreements pursuant to Section C.1.e.
e. Applicant and RPU Enter Into a Generation Interconnection Agreement and, Where Required, a Financing and Ownership Agreement for Interconnection Facilities or Electric System Modifications. The RPU shall provide the Applicant with an executable version of the Generating Facility Interconnection Agreement, net energy metering agreement, or Power Purchase Agreement appropriate for the Applicant's Generating Facility and desired mode of operation. Where the Initial Review or Interconnection Study performed by RPU has determined that modifications or additions are required to be made to its Electric System, or that additional metering, monitoring, or protection devices will be necessary to accommodate an Applicant's Generating Facility, RPU may also provide the Applicant with other interconnection facilities financing and ownership agreements. These agreements shall set forth the Applicant's responsibilities, completion schedules, and estimated or fixed price costs for the required work.
Where Applicable, RPU or Producer Installs Required
Interconnection Facilities or Modifies RU's Distribution System.
After executing the applicable agreements, RPU or Producer will commence construction/installation of the modifications or metering and monitoring requirements identified in the agreements. The parties will use good faith efforts to meet the schedules and cost estimates.
Producer Arranges for and Completes Commissioning Testing of Generating Facility and, Where Applicable, Producer Installed Interconnection Facilities. The producer is responsible for testing new Generating Facilities and associated Interconnection Facilities, according to Section J.5 to ensure compliance with the safety and reliability provisions of this Rule, and RPU rules and regulations prior to being operated in parallel with RU's Distribution System.
RPU Authorizes Parallel Operation or Momentary Parallel Operation. The Producer's Generating Facility shall be allowed to operate in Parallel Operation or Momentary Parallel Operation, as applicable, with RU's Distribution System upon satisfactory compliance with the terms of all applicable agreements and express written permission. Compliance may include, but not be limited to, provision of any required documentation and satisfactorily completing Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-6
any required inspections or tests as described herein or in the agreements formed between the Producer and RPU.
i. RPU Reconciles Costs and Payments. If the Producer selected a fixed price billing for the Interconnection Facilities or Distribution System modifications, no reconciliation will be necessary. If the Producer selected actual cost billing, a true-up will be required. RPU will reconcile its actual costs related to the Producer's facility against any advance payments made by the Producer for interconnection facilities or Distribution System modifications. The Producer will receive either a bill for any balance due or a reimbursement for overpayment as determined by RU's reconciliation. The Producer shall be entitled to a reasonably detailed and understandable report detailing RU's reconciliation process.
D. GENERATING FACILITY DESIGN AND OPERATING REQUIREMENTS
1. General Interconnection and Protection Requirements
a. Protective Functions Required. The Protective Functions for Generating Facilites operating in parallel with RU's Distribution System shall include:
(1) Over and under voltage trip functions and over and under frequency trip functions;
(2) A means for disconnecting the Generating Facility from RPU's Distribution System when a protective function initiates a trip; (3) An automatic means to prevent the Generating Facility from energizing a de-energized Distribution System circuit and to prevent the Generating Facility from reconnecting with the Distribution System unless the Distribution System service voltage and frequency is of specified settings and is stable for at least 60 seconds;
(4) A means to prevent the Generating Facility from contributing to the formation of an Unintended Island.
Momentary Paralleling Generating Facilities. With RPU's approval, the transfer switch or system used to transfer the Producer's loads from RPU's Distribution System to Producer's Generating Facility may be PU Distribution used in lieu of the Protective Functions required for Parallel Operation. c. Purpose of Protective Functions. The Protective Functions and requirements of this Rule are designed to protect RPU's Distribution Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-7
System and not the Generating Facility. A Producer shall be solely responsible for providing adequate protection for its Generating Facility and Interconnection Facilities. The Producer's protective equipment shall not impact the operation of other protective devices utilized on the Distribution System in a manner that would affect RU's capability of providing reliable service to its Customers.
d. Suitable Equipment Required. Circuit breakers or other interrupting devices located at the Point of Common Coupling must be Certified or "Listed" (as defined in Article 100, the Definitions Section of the National Electrical Code) as suitable for their intended application. This includes being capable of interrupting the maximum available fault current expected at their location. Producer's Generating Facility and Interconnection Facilities shall be designed so that the failure of any one device shall not potentially compromise the safety and reliability of RPU's Distribution System.
e. Visible Disconnect Required. The Producer shall furnish and install a manual disconnect device that has a Visible Disconnect to isolate the Generating Facility from RU's Distribution System. The device must be accessible to RPU personnel and be capable of being locked in the open position. Generating Facilities with Non-Islanding inverters totaling 1 kVA or less are exempt from this requirement.
Single-Phase Generators. For single-phase Generators connected to a shared single-phase secondary system, the maximum Net Nameplate Rating of the Generating Facilities shall be 20 kVA.
Generators applied on a center-tapped neutral 240-volt service must be installed such that no more than 6 kVA of imbalance in capacity exists between the two sides of the 240-volt service. For Dedicated Distribution Transformer services, the maximum Net Nameplate Rating of a single-phase Generating Facility shall be the transformer nameplate rating.
g. Drawings Required. RPU, prior to Parallel Operation or Momentary Parallel Operation of the Generating Facility, shall approve the Producer's protection and control diagrams of the Generating Facility.
Generating Facilities equipped with a protection and control scheme previously approved by RPU for system-wide application or with Certified Equipment only may satisfy this requirement by reference to previously approved drawings and diagrams.
Generating Facility Conditions Not Identified. In the event this Rule does not address the interconnection requirements for a particular Generating Facility, RPU and Producer may agree upon other requirements.
Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-8
Prevention of Interference.
The Producer shall not operate equipment that superimposes upon RU's Distribution System a voltage or current that interferes with RPU operations, service to RPU Customers, or RPU communication facilities. If such interference occurs, the Producer must diligently pursue and take corrective action at its own expense after being given notice and reasonable time to do so by RPU. If the Producer does not take timely corrective action, or continues to operate the equipment causing interference without restriction or limit, RPU may, without liability, disconnect the Producers equipment from the Distribution System, in accordance with Section B.9 of this Rule.
To eliminate undesirable interference caused by operation of the Generating Facility, each Generating Facility shall meet the following criteria:
a. Normal voltage operating range. The voltage operating range limits for Generating Facilities shall be selected as a protection function that responds to abnormal Distribution System conditions and not as a voltage regulation function.
(1) Generating Facilities (11 kVA or less). Generating Facilities with a Gross Nameplate Rating 11 kVA or less shall be capable of operating within the limits normally experienced on the Distribution System. The operating range shall be selected in a manner that minimizes nuisance tripping between 106 volts and 132 volts (88-110% of nominal voltage) on a 120-volt base.
Generating Facilities shall cease to energize RPU circuits whenever the voltage at the Point of Common Coupling deviates from the allowable voltage operating range.
(2) Generating Facilities (Greater than 11 kVA). RPU may have specific operating voltage ranges for Generating Facilities with Gross Nameplate Ratings greater than 11 kVA and may require adjustable operating voltage settings. In the absence of such requirements, the Generating Facility shall operate at a range between 88% and 110% of the apolicable interconnection
voltage.
(3) Voltage Disturbances. System voltage assumes a nominal 120 V base. The Generator should sense abnormal voltage and respond accordingly. The following conditions should be met, with voltages in root mean square and measured at the Point of Common Coupling, as described in Table D-1.
Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-9
Table D-1: Voltage Trip Setting
Voltage at Point of Maximum Trip Setting
Common Coupling
(Assuming 60 cycles per
(Assuming 120V base) Second)
Less than 60 Volts 10 Cycles
Greater than or equal to 120 Cycles
60 Volts but less than
106 Volts
Greater than or equal to Normal Operation
106 volts but less than or
equal to 132 Volts
Greater than 132 volts 120 cycles
But less than or equal to
165 Volts (30 cycles for facilities greater
than 11 kVA)
Greater than 165 Volts 6 cycles
*"Maximum Trip time" refers to the time between the onset of the abnormal condition and the Generating Facility ceasing to energize the Distribution System. Protective Function sensing devices and circuits may remain connected to the Distribution System to allow sensing of electrical conditions for use by the "reconnect" feature.
The purpose of the time delay is to allow Generating Facility to "ride through" short- term disturbances to avoid nuisance tripping. For Generating Facilities with a Gross Nameplate Rating of 11 kVA or less, the set points are to be non-user adjustable. For Generating Facilities with a Gross Nameplate Rating greater than 11 kVA, different voltage set points and trip times from those in Table D-1 may be negotiated with RPU. b. Flicker. Any voltage flicker at the Point of Common Coupling caused by the Generating Facility should not exceed the limits defined by the "Maximum Borderline of Irritation Curve" identified in IEEE 519 (IEEE Recommended Practices and Requirements for Harmonic Control in Electric Power Systems, IEEE STD 519-1992, Institute of Electrical and Electronic Engineers, Piscataway, NJ April 1992) This requirement is necessary to minimize the adverse voltage effects experienced by other customers on RU's Distribution System. Induction Generators may be connected and brought up to synchronous speed (as an induction motor) provided these flicker limits are not exceeded.
Frequency. RPU controls system frequency, and the Generating Facility shall operate in synchronism with the_Distribution System.
Generating Facilities with a Gross Nameplate Rating of 11 kVA or less shall have a fixed operating frequency range of 59.3-60.5 Hertz. The Generating Facility must cease to energize RU's Distribution System in a maximum of ten cycles should Distribution System remain outside of the frequency limits. The purpose of the time delay is to allow the Generating Facility to ride through short-term disturbances to avoid nuisance tripping. RPU may require adjustable operating frequency Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-10
settings for Generating Facilities with a Gross Nameplate Rating greater than 11 KVA.
d. Harmonics. Harmonic distortion shall be in compliance with IEEE 519.
Exception: The harmonic distortion of a Generating Facility located at a Customer's site shall be evaluated using the same criteria as for the loads at that site.
Direct Current Injection. Generating Facilities should not inject Direct Current greater than 0.5% of rated output current into RPU's Distribution System.
f. Power Factor. Each Generator in a Generating Facility shall be capable of operating at some point within a power factor range of 0.9 leading and 0.9 lagging. Operation outside this range is acceptable provided the reactive power of the Generating Facility is used to meet the reactive power needs of on-site loads or that reactive power is otherwise provided under tariff by RPU. The Producer shall notify RPU if it is using the Generating Facility for power factor correction.
Control, protection and safety equipment requirements
a. Technology Specific Requirements
(1) Three-phase Synchronous Generators. For three-phase Generators, the circuit breakers shall be three-phase devices with electronic or electromechanical control. The Producer shall be responsible for properly synchronizing its Generating Facility with the Distribution System by means of either a manual or automatic synchronizing function. Automatic synchronizing is required for all synchronous generators, which have a Short Circuit Contribution Ratio (SCCR) exceeding 0.05. A Generating Protective Functions suitable for detecting loss of synchronism and rapidly disconnecting the Generating Facility from the Distribution System. Unless otherwise agreed to between the Producer and RPU, synchronous generators shall automatically regulate power factor, not voltage, while operating in parallel with the Distribution System. Power system stabilization functions are specifically not required for Generating Facilities under 10 MW Net Nameplate Rating, Synchronization means that at the time of connection, the frequency difference shall be less than
0.2 Hz, the voltage difference shall be less than 10%, and the phase angle difference shall be less than 10 degrees.
Adopted by Board of Public Utilties: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-11
(2) Induction Generators. Induction Generators do not require a synchronizing function. Starting or rapid load fluctuations on induction generators can adversely impact the Distribution System's voltage. Corrective step-switched capacitors or other techniques may be necessary and may cause undesirable
ferroresonance. When these counter measures (e.g. additional capacitors) are installed on the Producer's side of the Point of Common Coupling, RPU must review these measures.
Additional equipment may be required as determined in a Supplemental Review or an Interconnection Study.
(3) Inverter Systems. Utility-interactive inverters do not require separate synchronizing equipment. Non-utility-interactive o stand-alone" inverters shall not be used for parallel operatior with the Distribution System.
Supplemental Generating Facility Requirements
(1) Unintended Islanding For Generating Facilities that fail the Export Screen (Section I.3.b.) Generating Facilities must mitigate their potential contribution to an Unintended Island. This can be accomplished by one of the following options: (1) corporating cerified Non sanding can tocal loads suficient! or (2) veritying that local loads sutticienti
exceed the Net Nameplate Rating of the Generating Facility, or (3) incorporating a transfer trip or an equivalent Protective Function.
(2) Fault Detection. A Generating Facility with an SCCR exceeding
0.1 or that does not meet any one of the options for mitigating Unintended Islands in D.3.b.1 shall be equipped with Protective Functions designed to detect Distribution System faults, both line-to-line and line-to-ground, and promptly cease to energize the Distribution System in the event of a fault. For a Generating Facility that cannot detect these faults within two seconds, a transfer trip or equivalent function may be required. Reclose blocking of RPU's affected reclosers) may also be required by RPU for generators that exceed 15% of the peak load on the Line Section.
INTERCONNECTION FACILITY OWNERSHIP AND FINANCING
Scope and Ownership of Interconnection Facilities
a. Scope. The interconnection of a Producer's Generating Facility with RU's Distribution System is made through the use of Interconnection Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-12
Facilities. Such interconnection may also require Distribution System improvements. The type, extent and costs of Interconnection Facilities and Distribution System Improvements shall be consistent with this Rule and determined through the Initial Review and Interconnection Study described in Section C.
Ownership. Interconnection Facilities installed on Producer's side of the Point of Common Coupling may be owned, operated and maintained by the Producer or RPU. Interconnection Facilities installed on RPU's side of the Point of Common Coupling and Distribution System improvements shall be owned operated and maintained by RPU.
2. Responsibility for Costs of Interconnecting a Generating Facility a. Study and Review Costs. A Producer shall be responsible tor the reasonably incurred costs of the reviews and studies conducted pursuant to Section C.1 of this Rule.
Facility Costs. A Producer shall be responsible for all costs associated with Interconnection Facilities owned by the Producer. The Producer shall also be responsible for any costs reasonably incurred by RPU in providing, operating, or maintaining Interconnection Facilities and Distribution System improvements required solely for the interconnection of the Producer's Generating Facility with RPU's Distribution System.
c. Separation of Costs. Should RPU combine the installation of separate or incremental facilities in the amounts billed to the Producer for the Interconnection Facilities or Distribution System Improvements required pursuant to this Rule.
Installation and Financing of Distribution System Improvements a. Agreement Required. Costs for Added Facilities shall be paid by the Producer pursuant to the provisions contained in the Generating Facility Interconnection Agreement. Where the type and extent of the Interconnection Facilities and Distribution System Improvements warrant additional detail, the detail shall be found in a separate agreement between the Producer and RPU, and RU's applicable rate schedules and rules for Added Facilities.
Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-13
b. Attachments and Modifications to Distribution System. Except as provided for in Section E.3.c of this Rule, Interconnection Facilities connected directly to RU's Distribution System and Distribution System Improvements shall be provided, installed, owned and maintained by RPU as Added Facilities.
C. Reservation of Unused Facilities. When a Producer wishes to reserve RPU-owned Interconnection Facilities or Distribution System Improvements installed and financed as Added Facilities for the Producer, but idled by a change in the operation of the Producer's Generating Facility or otherwise, Producer may elect to abandon or reserve such facilities consistent with the terms of its agreement with RPU. If Producer elects to reserve idle Interconnection Facilities or Distribution System Improvements, RPU shall be entitled to continue to charge Producer for the costs related to the ongoing operation and maintenance of the Added Facilities.
d. Refund of Salvage Value. When a Producer elects to abandon the Added Facilities for which it has either advanced the installed costs or constructed and transferred to RPU, the Producer shall, at a minimum, receive from RPU a credit for the net salvage value of the Added Facilities.
METERING, MONITORING AND TELEMETRY
General Requirements. All Generating Facilities shall be metered in accordance with this Section and shall meet all applicable standards of RU's applicable rate schedules, rules, and published RPU manuals dealing with metering specifications. The requirements in this Section do not apply to metering of Generating Facilities operating under RU's net metering tariff pursuant to California Public Utilities Code Section 2827.
2. Metering by Third Parties. The ownership, installation, operation, reading, and testing of metering for Generating Facilities shall be by RPU.
Net Generation Metering. For purposes of monitoring Generating Facility operation for determination of standby charges and applicable non-bypassable charges as defined in RU's rate schedules, and for Distribution System planning and operations, consistent with Section B.4 of these Rules, RPU shall have the right to specify the type, and require the installation of, Net Generation Metering. RPU shall require the provision of generator output data to the extent reasonably necessary to provide information for the utility to administer its tariffs or to operate and plan its system. RPU shall only require Net Generating Metering to the extent that less intrusive and/or more cost effective options for providing the necessary generator output data are not Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-14
available. In exercising its discretion to require Net Generation Metering, RPU shall consider all relevant factors, including but not limited to:
a. Data requirements in proportion to need for information; b. Customer election to install equipment that adequately addresses RPU's operational requirements;
Accuracy and type of required metering consistent with purposes of collecting data;
Cost of metering relative to the need for and accuracy of the data; e. The project size relative to the cost of the metering/monitoring; f. Other means of obtaining the data (e.g. generator logs, proxy data, etc.);
Requirements under any power purchase agreement with the Customer.
4. Point of Common Coupling Metering. For purposes of assessing RPU charges for retail service, the Electricity Producer's Point of Common Coupling Metering shall be a bi-directional meter so that power deliveries to and from the Electricity Producer's site can be separately recorded. Alternately, the Electricity Producer may, at its sole option and cost, require RPU to install multi-metering equipment to separately record power deliveries to the Distribution System and retail purchases from RPU. Such Point of Common Coupling Metering shall be designed to prevent reverse registration.
5. Telemetering. If the nameplate rating of the Generating Facility is 1 MW or greater, Telemetering equipment at the Net Generator Metering location may be required at the Electricity Producer's (and Customer's) expense. lf the Generating Facility is interconnected to a Distribution System operating at a voltage below 10 kV, then Telemetering equipment may be required on Generating Facilities 250 kW or greater. RPU shall only require Telemetering to the extent that less intrusive and more cost effective options for providing the necessary data in real time are not available.
Location. Where RPU-owned metering equipment is located on the Electricity Producer's (or Customer's) premises, Electricity Producer (and Customer) shall provide, at no expense to the RPU, a suitable location for all such
7. Costs of metering. The Electricity Producer (and Customer) will bear all costs of the metering required by this Rule, including the incremental costs of operating and maintaining the metering.
G. DISPUTE RESOLUTION PROCESS
Any disputes arising from this Rule shall be submitted in writing by the Producer or Customer to the Board of Public Utilities for resolution. Their decision shall be final.
Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-15
H. DEFINITIONS
Active Anti-Islanding Scheme: A control scheme installed with the Generating Facility that senses and prevents the formation of an Unintended Island.
Applicant: The entity submitting an Application for Interconnection pursuant to this Rule.
Application: A standard RPU form submitted to RPU requesting Interconnection of a Generating Facility.
Certification Test: A test pursuant to this Rule that verifies conformance of certain equipment with RPU-approved performance standards in order to be classified as Certified Equipment. Certification Tests are performed by NRTLs.
Certification; Certified; Certificate: The documented results of a successful Certification Testing.
Certified Equipment: Equipment that has passed all required Certification Tests.
Commissioning Test: A test performed during the commissioning of all or part of a Generating Facility to achieve one or more of the following:
Verify specific aspects of its performance;
Calibrate its instrumentation;
• Establish instrument or Protective Function set-points.
Customer: The entity that receives or is entitled to receive Distribution Service through the Distribution System.
Dedicated Transformer; Dedicated Distribution Transformer: A transformer that provides electricity service to a single Customer. The Customer may or may not have a Generating Facility.
Distribution Service: All services required by, or provided to, a Customer pursuant to the approved rate schedules and rules of RPU.
Distribution System: All electrical wires, equipment, and other facilities owned or provided by RPU by which RPU provides Distribution Service to its Customers.
Emergency: An actual or imminent condition or situation, which jeopardizes the Distribution System integrity.
Field Testing: Testing performed in the field to determine whether equipment meets RPU's requirements for safe and reliable Interconnection.
Generating Facility: All Generators that are included in an Interconnection Agreement.
Generator: An individual electrical power plant (including required equipment, appurtenances, protective equipment and structures) that is capable of Distributed Generation. A Generator is part of a Generating Facility.
Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-16
Gross Nameplate Rating: The total gross generating capacity of a Generator or Generating Facility as designated by the manufacturer of the Generator.
Host Load: Electrical power that is consumed by the Customer at the property on which the Generating Facility is located.
Initial Review: The review by RPU, following receipt of an Application, to determine the following:
a) the Generating Facility qualifies for Simplified Interconnection; or b) the Generating Facility can be made to qualify for Interconnection with Supplemental Review determining any potential additional requirements; or c) if neither a nor b, provides the cost estimate and schedule for performing an Interconnection Study.
In-rush Current: The current determined by the In-rush Current Test.
Interconnection; (Interconnected): The physical connection of a Generating Facility in accordance with the requirements of this Rule so that Parallel Operation with the Distribution System can occur (has occurred).
Interconnection Agreement: An agreement between RPU and the Producer that gives certain rights and obligations to effect or end Interconnection. Customers with Generating Facilities qualifying under the Self-Generation Program do not require an Interconnection Agreement.
Interconnection Facilities: The electrical wires, switches and related equipment that are required in addition to the facilities required to provide electric Distribution Service to a Customer to allow Interconnection. Interconnection Facilities may be located on either side of the Point of Common Coupling as appropriate to their purpose and design. Interconnection Facilities may be integral to a Generating Facility or provided separately. Interconnection Facilities may be owned by either Producer or RPU.
Interconnection Study: A study to establish the requirements for Interconnection of a Generating Facility.
Island; Islanding: A condition on the Distribution System in which one or more Generating Facilities deliver power to Customers using a portion of the Distribution System that is electrically isolated from the remainder of the Distribution System.
Line Section: That portion of the Distribution System connected to a Customer bounded by automatic sectionalizing devices or the end of the distribution line.
Momentary Parallel Operation: The interconnection of a Generating Facility to the Distribution System for one second (60 cycles) or less.
Nationally Recognized Testing Laboratory (NRTL): A laboratory accredited to perform the certification testing requirements under this Rule.
Net Energy Metering: Metering for the receipt and delivery of electricity between the Producer and RPU pursuant Section 2827 of the Public Utilities Code. Over a given time frame (typically a month) the difference between these two values yields either Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-17
net consumption or surplus. The meter registers are ratcheted to prevent reverse registration. If available, a single meter may be allowed to spin backward to yield the same effect as a directional, two meter (or register) arrangement.
Net Generation Metering: Metering of the net electrical power or energy output in KW or kWh, respectively, from a given Generating Facility. This may also be the measurement of the difference between the total electrical energy produced by a Generating Facility and the electrical energy consumed by the auxiliary equipment necessary to operate the Generating Facility. For a Generating Facility with no Host Load or no Public Utilities Code Section 218 Load, Metering that is located at the Point of Common Coupling. For a Generating Facility with Host Load or Section 218 Load, Metering that is located at the Generating Facility bus after the point of auxiliary load(s) and prior to serving Host Load or Section 218 Load.
Net Nameplate Rating: The Gross Nameplate Rating minus the consumption of electrical power of a Generator or Generating Facility as designated by the manufacturer(s) of the Generators).
Network Service: More than one electrical feeder providing Distribution Service at a Point of Common Coupling.
Non-Export; Non-Exporting: Designed to prevent the transfer of electrical energy from the Producer to RPU.
Non-Islanding: Designed to detect and disconnect from a stable Unintended Island with matched load and generation. Reliance solely on under/over voltage and frequency trip is not considered sufficient to qualify as Non-Islanding.
Parallel Operation: The simultaneous operation of a Generator with power delivered or received by RPU while Interconnected. For the purpose of this Rule, Parallel Operation includes only those generators that are interconnected with the Distribution System for more than one second (60 cycles).
Periodic Test: A test performed on part or all of a Generating Facility at pre- determined time or operational intervals to achieve one or more of the following:
• Verify specific aspects of its performance;
• Calibrate instrumentation;
• Verify and re-establish instrument or Protective Function set-points.
Point of Common Coupling Metering: Metering located at the Point of Common Coupling. This is the same Metering as Net Generation Metering for Generating Facilities with no Host Load or no Section 218 Load.
Point of Common Coupling (PCC): The transfer point for electricity between the electrical conductors of RPU and the electrical conductors of the Producer.
Point of Interconnection: The electrical transfer point between a Generator or a Generating Facility and the electrical system. This may or may not be coincident with the Point of Common Coupling.
Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconne2-08 Public Utilities Department
Power Purchase Agreement (PPA): An arrangement for the sale of electricity by the Producer to RPU.
Producer: The entity that executes an Interconnection Agreement with RPU. The Producer may or may not own or operate the Generating Facility, but is responsible for the rights and obligations related to the Interconnection Agreement.
Production Test: A test performed on each device coming off the production line to verify certain aspects of its performance.
Protective Function(s): The equipment, hardware or software in a Generating Facility (whether discrete or integrated with other functions) whose purpose is to protect against Unsafe Operating Conditions.
Prudent Electrical Practices: Those practices, methods, and equipment, as changed from time to time, that are commonly used in prudent electrical engineering and operations to design and operate electric equipment lawfully and with safety, dependability, efficiency, and economy.
Scheduled Operation Date: The date specified in the Interconnection Agreement when the Generating Facility is, by the Producer's estimate, expected to begin operation pursuant to this Rule.
Secondary Network: A network supplied by several primary feeders suitably interlaced through the area in order to achieve acceptable loading of the transformers under emergency conditions and to provide a system of extremely high service reliability. Secondary networks usually operate at 600 V or lower.
Section 218 Load: Electrical power that is supplied in compliance with California Public Utilities Code Section 218. Public Utilities Code 218 defines an "Electric Corporation" and provides conditions under which a generator transaction would not classify a generating entity as an Electric Corporation. These conditions relate to "over-the-fence" sale of electricity from a generator without using the Distribution System.
Self-Generation Program: Applicable to all end-use Eligible Customer-Generators.
An Eligible Customer Generator is a residential, commercial, industrial or agricultural Customer who uses a Renewable Electrical Generation Facility, or a combination of those facilities, with a capacity of not more than 5,000 kilowatts, that is located on the Customer's owned, leased, or rented premises, and is interconnected and operates in parallel with the Utility's distribution facilities, and is intended primarily to offset part or all of the Customer's own electrical requirements on the premises. Under this program maximum net export of the Generation Facility shall not exceed 1,000 kilowatts.
Simplified Interconnection: Interconnection conforming to the minimum requirements under these rules, as determined by Section I.
Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-19
Short Circuit Contribution Ratio (SCCR): The ratio of the Generating Facility's short circuit contribution to RU's short circuit contribution for a three-phase fault at the high voltage side of the distribution transformer connecting the Generating Facility to RPU's system.
Single Line Diagram; Single Line Drawing: A schematic drawing, showing the major electrical switchgear, protection devices, wires, generators, transformers and other devices, providing sufficient detail to communicate to a qualified engineer the essential design and safety of the system being considered.
Stabilization; Stability: The return to normalcy of the RPU Distribution System, following a disturbance. Stabilization is usually measured as a time period during which voltage and frequency are within acceptable ranges.
Starting Voltage Drop: The percentage voltage drop at a specified point resulting from In-rush Current. The Starting Voltage Drop can also be expressed in percentage on a particular base voltage, (e.g. 6 volts on a 120-volt base, yielding a 5% drop).
Supplemental Review: A process wherein RPU further reviews an Application that fails one or more of the Initial Review Process screens. The Supplemental Review may result in one of the following: a) Simplified Interconnection; b) approval of Interconnection with additional requirements; or c) cost and schedule for an Interconnection Study.
System Integrity: The condition under which a Distribution System is deemed safe and can reliably perform its intended functions in accordance with the safety and reliability rules of RPU.
Telemetering: The electrical or electronic transmittal of metering data in real-time to RPU.
Transfer Trip: A Protective Function that trips a Generating Facility remotely by means of an automated communications link controlled by RPU.
Type Test: A test performed on a sample of a particular model of a device to verify specific aspects of its design, construction and performance.
Unintended Island: The creation of an island, usually following a loss of a portion of the Distribution System, without the approval of RPU.
Unsafe Operating Conditions: Conditions that, if left uncorrected, could result in harm to personnel, damage to equipment, loss of System Integrity or operation outside pre-established parameters required by the Interconnection Agreement.
Visible Disconnect: An electrical switching device that can separate the Generating Facility from the Distribution System and is designed to allow visible verification that separation has been accomplished. This requirement can be met by opening the enclosure to observe the contact separation.
Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-20
Initial Review Process for Applications to Interconnect a Generating Facility Introduction. This Initial Review Process was developed to create a path for selection and rapid approval for the Interconnection of those Generating Facilities that do not require an Interconnection Study. The Initial Review process includes a screening to determine if a supplemental review is required.
2. Purpose. The Initial Review determines:
a. If a Generating Facility qualifies for Simplified Interconnection; b. If a Generating Facility can be made to qualify for Interconnection with Supplemental Review determining any potential additional requirements, or
If an Interconnection Study is required, the cost estimate and schedule for performing the Interconnection Study.
NOTE: Failure to pass any screen of the initial Review means only that further review or studies are required before the Generating Facility can be approved for interconnection with the RPU Distribution System. It does not mean that the Generating Facility cannot be interconnected.
Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-21
Initial Review Process Flow Chart
Applicant provides completed Application.
Yes
1. Is the PCC on a Networked Secondary System? •
No
Yes
2. Will Power be exported across the PCC?
No
3. Is the Interconnection Equipment Certified for the
proposed application? or No
Does the Interconnection Equipment have
Interim RPU Approval?
Yes Perform Supplemental Review
4. Is the aggregate Generating Facility Capacity on the No Line Section less than 15% of Line Section peak load?
Yes
5. Is the Starting Voltage Drop screen met?
Yes
6. Is the Gross Nameplate Rating of the Generating
Facility Capacity 11 kVA or less?
No
7. Is the Short Circuit Current Contribution
screen met?
Yes
No
8. Is the Line Configuration screen met?
Does Supplemental Review determine requirements?
Yes No
Generating Facility qualifies for Generating Facility qualifies for EC provides cost estimate Simplified Interconnection Simplified Interconnection and schedule for subject to the provisions of subject to the provisions of Rule Interconnection Rule 22 Study
Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-22
3. Initial Review Process Details
a. Screen 1: Is the PCC on a Networked Secondary System? If No, continue to next screen
: If Yes, the Generating Facility does not qualify for Simplified Interconnection.
Perform Supplemental Review.
Significance:
Special considerations must be given to the Generating Facilities proposed to be installed on networked secondary distribution systems because of the design and operational aspects of network protectors. There are no such considerations for radial b. Screen 2: Will power be exported across the PCC?
if Yes, the Generating Facility does not qualify for Simplified Interconnection.
If No, the Generating Facility must incorporate one of the following four Default setting shall be 0.1% (export) of transformer rating, with a maximum 2.0 second time delay.
To ensure at least minimum import of power an under-power Protective Function must be implemented at the PCC.
Default setting shall be 5% (import) of the Generating Facility Gross Nameplate Rating, with maximum 2.0 second time delay.
To tim the incidental export of power, all of the following conditions must be met:
The aggregate capacity of the Generating Facility must be no more than 25% of the nominal ampere rating of the Customer's Service Equipment The total aggregate Generating Facility capacity must be no more than 50% of the service transformer rating. (This capacity requirement does not apply to Customers taking primary service without and intervening transformer); The Generating Facility must be certified as Non-Islanding.
To ensure that the relative size (capacity) of the Generating Facility compared to facility load results in no export of power without the use of additional devices, the Generating Facility capacity must be no greater than 50% of the Customer's verifiable minimum load over the last 12 months.
if it can be assured that the Generating Facility will not export power, RPU's (2) profeti use of reverse-power relaying at the PC as positive antislanding Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-23
Screen 3: Is the Interconnection Equipment Certified for the Application or does the Interconnection Equipment have Interim RPU Approval? • If No, the Generating Facility does not qualify for Simplified Interconnection.
Perform Supplemental Review.
• If Yes, continue to next screen.
Significance:
If the Generating Facility has been Certified or previously approved by RPU, RPU does not need to repeat its review and/or test of the Generating Facility's Protective Functions scheme. Site Commissioning Testing may still be required to ensure that the system is connected properly and that the protective functions are working properly.
Certification indicates the following criteria have been tested and verified:
- Basic protective function requirements.
- Harmonic distortion limits.
- Synchronizing requirements.
- Power factor regulation requirements.
- Non-Islanding requirements
- If used, reverse power function requirement.
- If used, under-power function requirement.
d. Screen 4: Is the aggregate Generating Facility capacity on the Line Section less than 15% of Line Section Peak Load?
• If Yes, continue to next screen.
• If No, Generating Facility does not qualify for Simplified Interconnection.
Perform Supplemental Review to determine cumulative impact on Line Section.
Significance:
Low penetration of Generating Facility installations will have a minimal impact on Distribution System and load operation and power restoration.
The operating requirements for a high penetration of Generating Facilities may be different since the impact on RU's Distribution System operation will no longer be minimal, therefore requiring additional study or controls. e. Screen 5: Is the Starting Voltage Drop Within Acceptable Limits? If Yes, continue to next screen
: If No, the Generating Facility does not quality for Simplified Interconnection.
Section Supplemental Review to determine cumulative impact on Line NOTICE: This screen only applies to Generating Facilities that start by motoring the Generator.
RPU has two options in determining whether Starting Voltage Drop could be a problem; which option to use is at RPU's discretion.
RPU may determine that the Generating Facility's starting Inrush Current is equal to or less than the continuous ampere rating of the Customer's service equipment.
Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-24
PU may determine the impedances of the service distribution transformer (if present) and secondary conductors to Customer's service equipment and perform a voltage drop calculation. Alternatively, RPU may use tables or nomographs to determine the voltage drop. Voltage drops caused by starting a Generating Unit as a motor must be less than 2.5% for primary interconnection and 5% for secondary interconnection.
Significance:
(1) This screen addresses potential voltage fluctuation problems for generators that (2) When starting, a Generating Facility should have minimal impact on the service (3) Passing this screen does not relieve the Producer from ensuring that its Generating Facility complies with the flicker requirements of this Rule, Section D.
F. screen 6: Is the Gross Nameplate Rating of the Generatin acility 11 kVA or less
If Yes, the Generating Facility qualifies for Simplified Interconnection. Skip remaining screens.
• If No, continue to next screen
Significance:
The Generating Facility has minimal impact on fault current levels and any potential line overvoltages from loss of system neutral grounding. g. Screen 7: Is Short Circuit Current Contribution Within Acceptable Limits?
• If No, the Generating Facility does not qualify for Simplified Interconnection.
Perform Supplemental Review.
• if Yes, continue to next screen.
(2) Contributo the prosed emer in Facily must fees than or tual te No significant Generating Facility impact on:
1) Distribution System's short circuit dut
2) Distribution Svstem fault detection sensitivit
(3) Distribution System relay coordination
(4) Distribution System fuse-saving schemes
If the Generating Facility passes this screen it can be expected that it will have no significant impact on RU's Distribution System's short circuit duty, fault detectior sensitivity, relay coordination or fuse-saving schemes.
Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-25
h. Screen 8: Is the Line Configuration Acceptable for Simplified Interconnection?
• If No, then the Generating Facility does not qualify for Simplified Interconnection.
Perform Supplemental Review.
• If Yes, the Generating Facility qualifies for Simplified Interconnection.
Line Configuration Screen:
Identify primary distribution line configuration that will serve the proposed Generating Facility. Based on the type of Interconnection to be used for the Generating Facility, determine from the following table if the proposed Generating Facility passes the screen.
Primary Distribution Line Type of Interconnection Result/Criteria Type to Primary Distribution
Line
Three-phase, three wire Any Pass screen
Three-phase, four wire Single-phase, line-to- Pass screen neutral
Three-phase, four wire All others To pass, aggregate
(For any line that has Generating Facility
such a section OR mixed Capacity must be less
3 wire & 4 wire) than or equal to 10% of
Line Section Peak
Load.
Significance:
If the primary distribution circuit serving the Generating Facility is of a three-wire type, or if the Generatina Facilitv's Interconnection transformer is single-phase and connected in a line-to-neutral configuration, then there is no concern about overvoltages to RU's or other Customer's equipment caused by loss of system neutral grounding during the operating time of anti-islanding protection.
Testing and Certification Criteria
Introduction
This Section describes the test procedures and requirements for equipment used for the Interconnection of a Generating Facility to RU's Distribution System. Included are Type Testing, Production Testing, Commissioning Testing, and Periodic Testing. The procedures listed rely heavily on those described in applicable Underwriters Laboratory (UL), Institute of Electrica and Electronic Engineers (IEEE), and International Electrotechnical Commission (IEC) documents - most notably UL 1741 and IEEE 929 - as well as the testing described in the New York State Public Service Commission's Interconnection requirements'. These procedures and requirements were developed prior to the completion of IEEE P1547.
1 "New York State Standardized Interconnection Requirements, Application Process, Contract & Application Forms For New Distributed Generators, 300 Kilovolt - Amperes or Less, Connected In Parallel with Radial Distribution Lines", November 9, 2000.
Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-26
Standard for Distributed Resources Interconnected with Electric Power Systems, and should be revisited once that standard is published. The tests described here, together with the technical requirements in Section D of this Rule, are intended to provide assurance that the Generating Facility's equipment will not adversely affect RU's Distribution System and that a Generating Facility will cease providing power to RU's Distribution System under abnormal conditions. The tests were developed assuming a low level of Generating Facility penetration. At high levels of Generating Facility penetration, other requirements and corresponding test procedures may need to be defined.
This test specification also provides a means of certifying equipment. Once a Generating Unit or device has been Certified per this Certification Process, it may be considered to be suitable for use as part of a Generating Facility interconnected with RU's Distribution System. Subject to the exceptions described in this Section, RPU will not require a Producer to repeat the design review or test the Protective Functions of equipment that has been Certified.
It should be noted the Certification process is intended to facilitate Generating Facility interconnections. Certification is not a prerequisite to interconnect a Generating Facility. The use of non-certified equipment may be acceptable subject to testing and approval by RPU as discussed below.
2. Certification Criteria
Equipment tested and approved (e.g. listed) by a NRTL as having met both the Type Testing and Production Testing requirements is considered to be Certified Equipment for purposes of Interconnection with RU's Distribution System. Certification may apply to either a pre-packaged system or an assembly of components that address the necessary functions. Type Testing may be done in the factory/test lab or in the field. At the discretion of the testing laboratory, field-certification may apply only to the particular installation tested.
In such cases, some or all of the tests may need to be repeated at other installations.
The use of Certified Equipment is not a requirement for interconnection.
However, the use of Certified Equipment will simplify the interconnection approval process by reducing Commissioning and additional test requirements. For non-certified equipment, some or all of the tests described in this document may be required by RPU for each Generating Facility. The manufacturer or a laboratory acceptable to RPU may perform these tests. Test results for non-certified equipment must be submitted to RPU as part of the application process for RPU's review and approval under the Supplemental Review. Approval by RPU for equipment used in a particular application does not guarantee RPU approval for use in other applications or by other California electric utilities.
Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-27
When equipment is Certified by a NRTL, the NRTL shall provide to the manufacturer, at a minimum, a Certificate with the following information for each device:
a. Administrative:
(1) Effective date of certification or applicable serial number (range or first in series), other proof that certification is current
(2) Equipment model number (s)
(3) Software version, if applicable
(4) Test procedures specified (including date or revision number)
(5) Laboratory accreditation (by whom and to what standard) b. Technical (As appropriate)
(1) Device rating (KW, KVA, V, A, etc.)
(2) Maximum available fault current, A
(3) In-rush current, A
(4) Trip points, if factory set (trip value and timing) (5) Trip point and timing ranges for adjustable settings (6) Nominal power factor or range if adjustable
(7) If the device/system is certified for non-export and the nethod used (reverse power or under power
(8) If the device/system is certified non-islanding
It is the responsibility of the equipment manufacturer to ensure that certification information is made publicly available by the manufacturer, the testing laboratory, or by a third party. A sample certification information form is provided in Appendix 1.
3. Type Testing
Type testing provides a basis for determining that equipment is designed appropriately and meets the specifications for being designated as Certified Equipment under this Rule. The requirements described in this section cover only issues related to Interconnection and are not intended to address device safety or other issues outside the needs of the relationship between RPU and Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-28
The following table defines the test requirements by technology. Test References that are preceded by "UL 1741" refer to the section numbers of the document that describe the test requirements.? While UL 1741 was written specifically for photovoltaic inverters, the requirements are readily adapted to inverter-based Generating Facilities, synchronous machines, induction machines, as well as single/multi-function controllers and protection relays.
Until a standardized test procedure is specified, RPU or NRTL shall adapt the procedures referenced in the following table as appropriate and necessary for a machine's performance and its control and protection system functions.
Type Tests and Requirements for Interconnection Equipment Certification Synchronous Induction
Type Test Reference' Inverter Machine Machine
Utility interaction | UL 1741 - 39
DC Isolation UL 1741 - 40.1
Simulated PV Array
(Input)Requirements UL 1741 - 41.2
.....
Dielectric Voltage Withstand UL 1741 - 44
Power Factor UL 1741 - 45.2.2
Harmonic Distortion UL 1741 - 45.4
DC Injection UL 1741 - 45.5
Utility Voltage and
Frequency Variation UL 1741 - 46.2
Reset Delay UL 1741 - 46.2.3
Loss of Control Circuit | UL 1741 - 46.4
Short Circuit UL 1741 - 47.3
Load Transfer UL 1741 - 47.7 ×=0xxxxx. !£00xxx*xx
Surge Withstand | J.3.a
Anti Islanding J.3.b
Non-Export J.3.0 (3)
In-Rush Current _ J.3.dr (4)
Synchronization J.3.e 5)
Notes: X= Required; - = Not required
Table Notes:
(1) Reference refers to section number in either UL 1741 or this Rule. References within UL1741 to "photovoltaics" or "inverter" may have to be interrupted by the testing laboratory to appropriately apply (2) Request trianging designation is desired.
(3) Required only if Non-Export designation is desired. (5) nected to Roll synchronous machines as well as inverters that operate as voltage soures when 2 UL 1741, Inverters, Converters and Charge Controllers for use in Independent Power Systems, Revised January 2001
Adopted by Board of Public Utlities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-29
a. Anti-Islanding Test
Devices that are tested to and pass the Anti-Islanding test procedure described in UL 1741 Section 46.3 will be considered Non-Islanding for the purposes of these interconnection requirements. This test is required only for devices for which a certified Non-Islanding designation is desired.
b. Non-Export Test
Devices that pass the Non-Export test procedure described in Section J.7.a. will be considered Non-Exporting for the purposes of these interconnection requirements. This test is required only for devices for which a certified Non-Export designation is desired.
c. In-rush Current Test
Will be tested using the procedure defined in Section J.7.b. to determine the maximum current drawn during this startup process. The resulting in-rush current is used to estimate the starting voltage drop. d. Surge Withstand Capability Test
Interconnection equipment shall be tested for surge withstand capability (SWC), both oscillatory and fast transient, in accordance with the test procedure defined in IEEE/ANSI C62.45 using the peak values defined NS 06241 Tae CO in IEEE/ANSI C62.41 Tables 1 and 2 for location category B3. An acceptable result occurs even if the device is damaged by the surge, but is unable to operate or energize RU's Distribution System. If the device remains operable after being subject to the surge conditions, previous type tests related to RPU protection and power quality will need to be repeated to ensure the unit will still pass those tests following the surge test.
e. Synchronization Test
This test verifies that the unit synchronizes within the specified voltage/frequency/phase angle requirements. It is applied to Seneraig Faciate he root in special on l her e is brought within specification prior to synchronization. Repeat the fest five times for each of the three Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-30
For manual synchronization with synch check or manual control with auto synchronization, the test must verify that paralleling does not occur until the parameters are brought within specifications.
4. Production Testing
As a minimum, the Utility Voltage and Frequency Variation Test procedure described in UL1741 under Manufacturing and Production Tests, Section 68 shall be performed as part of routine production (100 percent) on all equipment used to interconnect Generating Facilities to RPU's Distribution System. This testing may be performed in the factory or as part of a Commissioning Test (Section J.5).
5. Commissioning Testing
Commissioning Testing, where required, will be performed on-site to verify protective settings and functionality. Upon initial Parallel Operation of a Generating Facility, or any time interface hardware or software is changed that may affect the functions listed below, a Commissioning Test must be performed. An individual qualified in testing protective equipment (professional engineer, factory-certified technician, or licensed electrician with experience in testing protective equipment) must perform commissioning testing in accordance with the manufacture's recommended test procedure to prove the settings and requirements of this Rule.
The RPU has the right to witness Commissioning Tests as described below, or to require written certification by the installer describing which tests were performed and their results.
Functions to be tested during commissioning, particularly with respect to non- certified equipment, may consist of the following:
Over-and under-voltage
Over- and under-frequency
Anti-Islanding (if applicable)
Non-Export (if applicable)
e. Inability to energize dead line
f. Time delay restart after utility source is stable
g. Utility system fault detection (if used)
Synchronizing controls (if applicable)
i. Other interconnection protective functions that may be required as part of the Interconnection Agreement
Other checks and tests that may need to be performed include:
a. Verifying final protective settings
Trip test
c. In-service test
Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-31
a. Certified Equipment
Generating Facilities qualifying for Simplified Interconnection incorporate Certified Equipment that have, at a minimum, passed the Type Tests and Production Tests described in this document, are judged to have little or no potential impact on RU's Distribution System. For such Generating Facilities, it is necessary to perform only the following test:
Protection settings that have been changed after factory testing will require field verification. Tests will be performed using injected secondary voltages and currents, applied waveforms, a test connection using a generator to simulate abnormal utility voltage or frequency, or varying the set points to show that the device trips at the measured (actual) utility voltage or frequency.
2. Non-Islanding function, if included, will be checked by opening a load break disconnect switch to verify the interconnection equipment ceases to energize the line and does not re-energize for the required time delay after the switch is closed.
Non-Export function, if included, will be checked using secondary injection techniques. This function may also be tested by adjusting the Generating Facility output and local loads to verify that the applicable non-export criteria (i.e., reverse power or under power) are met.
The Supplemental Review or an Interconnection Study may impose additional components or additional testing.
b. Non-Certified Equipment
Non-certified equipment shall be subjected to the appropriate tests described in Type Testing (Section J.3.) as well as those described ir reduced set of tests for a particular application or, for example, if it determines it has sufficient experience with the equipment.
Verification of Settings
If the testing is part of the commissioning process, then, at the completion of such testing, the Producer shall confirm all devices are set to RPU-approved settings. This step shall be documented in the Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-32
d. Trip Test
Interconnection protective devices (e.g. reverse power relay) that have not previously been tested as part of the interconnection system with their associated interrupting devices (e.g. contactor or circuit breaker) shall be trip tested during commissioning. The trip test shall be adequate to prove that the associated interrupting devices open when the protective devices operate.
Interlocking circuits between protective devices or between interrupting devices shall be similarly tested unless they are part of a system that has been tested and approved during manufacture.
In-service Test
Interconnection protective devices that have not previously been tested as part of the interconnection system with their associated instrument transformers or that are wired in the field shall be given an in-service test during commissioning. This test will verify proper wiring, polarity, CT/PT ratios, and proper operation of the measuring circuits. The in- service test shall be made with the power system energized and carrying a known level of current. A measurement shall be made of the magnitude and phase angle of each ac voltage and current connected to the protective device and the results compared to expected values.
For protective devices with built-in metering functions that indicate current and voltage magnitudes and phase angles, or magnitudes of the metered values may
be used tor ase ree ted reactive peer he porter al
voltmeters, and phase-angle meters shall be used.
Periodic Testing of Interconnection-related Protective Functions shall be performed as specified by the manufacturer, or at least every four years. All periodic tests prescribed by the manufacturer shall be performed. The Producer shall maintain periodic test reports or a log for inspection by RPU Periodic Testing conforming to RPU test intervals for the particular line sectiol may be specified by RPU under special circumstances, such as high fire hazard areas.
A system that depends upon a battery for trip power shall be checked and logged once per month for proper voltage. Once every four years, the battery must be either replaced or a discharge test performed.
7. Detailed Type Test Procedures and Requirements
This section describes the additional Type Test procedures necessary to qualify a device as Certified, for use on the RPU Distribution System. These Type Tests are not contained in Underwriters Laboratories UL 1741 Standard Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-33
Inverters, Converters and Controllers for Use in Independent Power Systems, or other referenced standards.
a. Non-Export Test Procedure
The non-export test is intended to verify the operation of relays, controllers and inverters designed to limit the export of power and certify the equipment as meeting the requirements of Screen 2, Options 1 and 2, of the Initial Review Process. Tests are provided for discrete relay packages and for controllers and inverters that include the intended function.
(1) Reverse Power Relay Test
This version of the Non-Export test procedure is intended for stand-alone reverse power and under power relay packages provided to meet the requirements of Options 1 and 2 of the Non- Export Screen. It should be understood that in the reverse power application, the relay will provide a trip output with power in the export (toward RPU system) direction.
Step 1: Power Flow Test at Minimum, Midpoint and Maximum Pickup Level Settings
Determine the appropriate secondary pickup current for the desired export power flow of 0.5 secondary watts (the agreed- upon minimum pickup setting assumes 5 Amp and 120V CT/PT secondary). Apply nominal voltage with minimum current setting at 0 degrees in the trip direction. Increase the current to pick up level. Observe the relay's (LCD or computer display) indication of power values. Note the indicated power level at which the relay trips. The power indication should be within 2 percent of the expected power. For relays with adjustable settings, repeat this test at the midpoint, and maximum settings.
Phat tat at pay does No operate measured dats wis be ero try Step 2: Leading Power Factor Test
Apply rated voltage with a minimum pickup current setting (calculated value for system application) and apply a leading Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-34
At nominal voltage and with the minimum pickup (or ranges determined in Step 1, adjust the current phase angle to 84 or 21 degrees. Increase the current level to pickup (about 10 times higher than at 0 degrees) and verity that the relay operates.
Repeat for angles 90, 180, and 270 degrees and verify that the Step 4: Negative Sequence Voltage Test
Using the pickup settings determined in Step 1, apply rated rela! voltage and current at 180 degrees from tripping direction, to simulate normal load conditions (for 3-phase relays, use la at 180, Ib at 60 and Ic and 300 degrees). Remove Phase-1 voltage and observe that the relay does not operate.
Repeat for phase-2 and 3.
Step 5: Load Current Test
Using the pickup settings determined in Step 1, apply rated voltage and current at 180 degrees from the tripping direction, to simulate normal load conditions (use la at 180, Is at 300 and lo at 60 degrees). Observe that the relay does NOT operate.
Step 6: Unbalanced Fault Test
Using the pickup settings determined in Step 1, apply rated voltage and 2 times rated current, to simulate an unbalanced fault in the non-trip direction (use Va at 0 degrees, Vo and Vo at 180 degrees, la at 180 degrees, Ib at O degrees and lo at 180 degrees). Observe that the relay, especially single phase, does not misoperate.
Step 7: Time Delay Settings Test
Apply Step 1 settings and set time delay to minimum setting.
Adjust the current source to the appropriate level to determine operating time, and compare against calculated values. Verify that the timer stops when the relay trips. Repeat at midpoint and maximum delay settings.
Step 8: Dielectric Test
minuten the test described in IEC 414 using 2 KV RMS for 1 Step 9: Surge Withstand
Perform the surge withstand test described in IEEE
C37.90.1.1989 or the surge withstand test described in Section J.3.g.
Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-35
(2) Under Power Relay Test
In the underpower application, the relay will provide a trip output when import power (toward the Producer) drops below the specified power level.
Note: For an underpower relay, pickup is defined as the highest power level at which the relay indicates that the power is less than the set setting.
Step 1: Power Flow Test at Minimum, Midpoint and Maximum Determine the appropriate secondary pickup current for the desired power flow pickup level of 5% of peak load (the agreed- upon minimum pickup setting). Apply rated voltage and current setting at 0 degrees in the direction of normal load current Decrease the current to pickup level. Observe the relay's (LCD or computer display) indication of power values. Note the indicated power level at which the relay trips. The power indication should be within 2 percent of the expected power. For relays with adjustable settings, repeat the test at the midpoint, and maximum settings.
Repeat at phase angles of 90, 180, and 270 degrees and verify that the relay operates (measured watts will be zero or negative).
Step 2: Leading Power Factor Test
Using the pickup current setting determined in step 1, apply rated voltage and rated leading power factor load current in the normal load direction (current leading voltage by 45 degrees). Decrease the current to 145% of the pickup level determined in Step 1 and verify that the relay does NOT operate. For relays with adjustable settings, repeat the test at the minimum, midpoint, and maximum settings.
Step 3: Minimum Power Factor Test
It roominal voltage and with the minimum picke for res
1, adjust the current phase angle to 84 or 27t
degrees. Decrease the current level to pickup (about 10% of the value at 0 degrees) and verify that the relay operates. Repea for angles 90, 180 and 270 degrees and verify that the relay Step 4: Negative Sequence Voltage Test
stimulate light load conditions. Remove Phase-A voltage and Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-36
observe that the relay does not operate, repeat for phase-B and C.
Step 5: Unbalanced Fault Test
Using the pickup settings determined in Step 1, apply rated voltage and 2 times rated current, to stimulate an unbalanced fault in the normal load direction (use Va at O degrees, Vo and Vo at 180 degrees, la at 0 degrees, l at 180 degrees, and Ic at C degrees). Observe that the relay, especially single phase, operates properly.
Step 6: Time Delay Settings Test
Apply Step 1 settings and set time delay to minimum setting.
Adjust the current source to the appropriate level to determine operating time, and compare against calculated values. Verify that the timer stops when the relay trips. Repeat at midpoint and maximum delay settings.
Step 7: Dielectric Test
minormn the test described in IEC 414 using 2 KV RMS for 1 Step 8: Surge withstand
Perform the surge withstand test described in IEEE
C37.90.1.1989 or the surge withstand test described in Section
1.3. g.
(3) Functional Test for Inverters and Controllers
Inverters and controllers designed to provide reverse or under power functions shall be tested to certify the intended operatior of this function. Two methods are provided
Method 1: If the controller utilizes external current/voltage measurement to determine the reverse or underpower condition, then the controller shall be functionally tested by application of appropriate secondary currents and potentials as described in the Reverse Power Relay Test, Section J.7.a.(1) of this Rule.
Method 2: If external secondary current or potential signals are not used, then unit-specific tests must be conducted to verify that power cannot be exported across the PCC for a period
exceeding two seconds. These tests may be factory tests, if the measurement and control points are part of a single unit, or may be provided for in the field.
Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-37
b. In-Rush Current Test
This test will determine the maximum in-rush current drawn by the unit. (1) Locked-Rotor Method
Use the test procedure defined in NEMA MG-1 (manufacturer's data is acceptable if available).
(2) Start-up Method
Install and setup the Generating Facility equipment as specified by the manufacturer. Using a calibrated oscilloscope or data acquisition equipment with appropriate speed and accuracy, measure the current draw at the Point of Interconnection as the Generating Facility starts up and parallels with RU's Distribution System. Startup shall follow the normal, manufacturer-specified procedure.
Sufficient time and current resolution and accuracy shall be used to capture the maximum current draw within five percent. In-rush current is defined as the maximum current draw from RPU's Distribution System during the startup process, using a 10-cycle moving average.
During the test, the utility source, real or simulated, must be capable of maintaining voltage within +/-five percent of rated at the connection to the unit under test. Repeat this test five times. Report the highest 10- cycle current as the in-rush current.
A graphical representation of the time-current characteristic along with the certified in-rush current must be included in the test report and made available to RPU.
Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-38
Appendix 1
Utility Interconnection Equipment Certification Form
Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-39
Utility Interconnection Equipment Certification
The information on this form is provided to indicate the compliance of the generation equipment listed below with the utility interconnection certification requirements defined in this Rule.
Certifying Laboratory The information on this form is provided by the following Nationally Recognized Test Laboratory:
Laboratory:
Contact Name:_ Phone:_ E-mail:
Address:_
City: _State: Zip:_
Accredited by: _ Date:
Accredited to (test standards) :
Equipment Specification The information on this form applies to the following equipment:
Equipment Manufacturer:
Address:
City: State: Zip:_
Model Number(s):
Software Version(s):_
Effective 2:
Device Description 3:
Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-40
Test results 4
Mark the box next to each requirement that has been met and each test that has been performed and successfully passed. Provide an explanation of any exceptions or omissions on a separate sheet. List additional test documents used on separate sheet.
UL 1741: (Section number listed)
141-39 11-40.1 141-41.2 141-44 11-45.2.2 11-45.4 111-45.5 11-46.2 144-46.2.3 14-46.4 141-47.3 141-47.7 Optional 11-46.3 M1 - IEEE/ANSI C62.45/C62.41 (location Category B3)
California Rule 21: I4t-J.3.e Non-export it1-J.3.f. In-Rush Current It-J.3.h. Synchronization Device Rating*:
Maximum available fault current, A
In-rush current, A
Trip settings?:
Setting 1 | Setting 2 Setting 3 Setting 4 Setting 5 Factory Settings 8
Fast Over [Setting
Voltage Measured
Fast Over Setting
Voltage Measured
Fast Over Setting
Voltage Measured
Fast Over Setting
Voltage Measured
Fast Over Setting
Voltage Measured
Fast Over Setting
Voltage Measured
Nominal Power Factor (Range, if adjustable)
Non Islanding: Yes _ No . Maximum trip time:
Non Export: Yes No Method: _
Other 8:
Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Distributed Generation Facilities Interconnection Public Utilities Department 22-41
NOTES
1 Accreditation must apply to tests standards listed herein 2 Note here the date of certification, applicable serial number (range or first in series), or other information that indicates which units the certification applies to. 3 List appropriate functions, capabilities, applications, limitations, etc. Use additional sheets as necessary.
4 List all test documents (i.e. UL 1741, IEEE C62.45) and specific procedures (i.e. UL 1741 Sec 39.1 - 39.5, etc.) used to evaluate device's suitability for utility interconnection.
5 KW, KVA, V, A, etc. as appropriate
For devices that use grid power to motor to speed
Trip value (Voltage in volts or frequency in Hz) and timing (in cycles). Devices with adjustable settings shall provide test results over the range of settings. For each test setting provide the setting values in the upper box and measured results in the lower box. List device ranges, if adjustable.
8 Provide any additional information that may be useful in evaluating these results such as test configurations, device settings used to meet requirements, etc. Use additional sheets if necessary.
Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Appendix A -1
Public Utilities Department
Electric Utility
APPENDIX A
ELECTRIC FEES AND CHARGES SCHEDULE
APPLICABILITY
Applicable to all classes of service provided in accordance with the Electric Rules and Regulations. Does not supersede any fees and charges listed in the rules which are not included on this schedule.
RULE DESCRIPTION FEE AMOUNT
NUMBER
4 Minimum Deposit/Residential $200.00
4 Minimum Deposit/All other classes Twice the estimated average bill or
$200.00 minimum
4 Minimum Deposit/Reconnection/ Three times the
All Classes of Service estimated average
bill or $200.00
minimum
4 Service Turn-on Charge (Same fee applies $48.50 next day whether turning on one service or both. AMI $62.75 same day remote fee applicable with AMI remote $77.00 after hours meter and electric-only service.) $ 6.00 AMI Remote
5 Non-Sufficient Funds (NSF) Processing Fee
Initial NSF Fee $30.00
Subsequent NSF Fee (Each) $45.00
6 Meter Test/Second Request $364.00 paid in
Within One Year Period advance (if error is
found, fee will be
refunded)
Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Appendix A -2
Public Utilities Department
Electric Utility
RULE DESCRIPTION FEE AMOUNT П
NUMBER
6 Re-Read/second request within six months $48.50 (if error is found fee will be
refunded)
7 48-Hour Field Notification (Master Metered $31.75 plus Accounts receive Multi-Unit notification) $6.50 for each additional
notice per account
7 Trip charge for additional field visit (cut-off $34.50 for non pay (CONP), etc.)
7 Service Reconnection Charge (Same fee $48.50 next day applies whether reconnecting for CONP $62.75 same day
one service or both. AMI remote fee $77.00 after hours
applicable with AMI remote meter and $ 6.00 AMI Remote
electric-only service.)
7 Additional Fee will be added to Reconnect Add Time and S.O. if Customer has self-restored Material to
Reconnect Service
Order Fee
7 Reconnection Charge/Additional - OH $460.00
Service Terminated by electrical crew
7 Reconnection Charge/Additional - UG $902.00
Service Terminated by electrical crew
7 Reconnection Charge/Additional - $460.00
Service Drop Removed by electrical crew
7 Reconnection Charge/Additional - UG $902.00
Service Cable removed by electrical crew
8 Temporary Overhead Electric Service $955.00
8 Temporary Overhead Electric Service/ $1,310.00
Additional - Transformer Required
Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Appendix A -3
Public Utilities Department
Electric Utility
8 Temporary Underground Electric Service $1,200.00
RULE DESCRIPTION FEE AMOUNT
NUMBER
8 Temporary Underground Electric Service/ Time & Material Additional - Temporary Padmounted
Transformer Required
8 Temporary Service Larger than 200 amps Time & Material 8 Temporary Meter Removal for Main Breaker $177.50
Repair
10 Line Extensions for new or increased loads - $500.00 per lot Deposit
Line Extensions for new or increased loads Time & Material 11 Design Deposit
Multi-family Residential (100 units or less) $4,068.00
Multi-family Residential (101 units or more) $6,785.00
Commercial (0 - 200A) $ 748.00
Commercial and Industrial (400A - 800A) $1,815.00
Commercial and Industrial (1000A - 3000A) $2,687.00
Commercial and Industrial (4000A and above) $7,897.00
11 Meter Spot
Service Disconnect/Reconnect $1,133.00
Midspan $1,133.00
Initial Inspection $ 92.75
Plan Check for Building and Public Works $ 519.00
11 Non-Building and Safety Plan Check
Submittal Cancellation Fee $ 819.00
11 California Environmental Quality Act Reviews $1,650.00 11 EV Meter Adapter Installation
Permit $ 903.00
Existing 240v Outlet $ 214.00
New 240v Outlet $ 214.00
Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside Appendix A -4
Public Utilities Department
Electric Utility.
13 Appointment based meter reads $28.50
RULE DESCRIPTION FEE AMOUNT
NUMBER
14 Temporary Turn On or Turn Off of Electric $162.00 per hour or Service for Repair (normal working hours) fraction thereof first aggregate hour is free
14 Temporary Turn On or Turn Off of Electric $182.00 per hour or Service for Repair (after normal working fraction thereof hours Minimum of $182.00 for first hour
15 Street Lighting - Unit of Benefit Charge - $19,695.00 Residential Streets
15 Street Lighting - Unit of Benefit Charge - $22,435.00 Arterial Streets
19 Cost to Investigate Energy Diversion The higher of
$571.00 plus
Material or Time
and Material
22 Distributed Generation application and
processing fee- Net Energy Metering- Initial
Review
Residential $260.00
Commercial- Flat and Demand $722.00
Commercial- Time of Use (TOU) $722.00
22 Distributed Generation application and $722.00
processing fee - Initial Review
22 Distributed Generation application and $722.00
processing fee - Supplemental Review
22 Distributed Generation application and Actual Cost
processing fee - Full System Study
Adopted by Board of Public Utilties: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside
Public Utilities Department 4-1
WATER RULE 4
DEPOSITS AND SERVICE TURN-ON CHARGE
A. DEPOSITS
Deposits will be required when a customer is otherwise unable to satisfactorily establish or re-establish credit as set forth in Rule No. 3.
B. AMOUNT OF DEPOSIT TO ESTABLISH SERVICE
A minimum deposit will be required to establish residential service. The amount of deposit required to establish non-residential service will be equal to twice the estimated average monthly bill for water service, but in no event less than a minimum residential deposit as established by the Board of Public Utilities and City Council. The amount of the deposit required for Utility furnished metering and backflow equipment shall be as defined in Rule No. 8.
C. AMOUNT OF DEPOSIT TO RE-ESTABLISH SERVICE
If service is terminated for any reason other than customer requested turn off, or if a notice of discontinuance has been given, the Utility may require the Customer to pay a deposit, or an additional deposit, up to an estimated average three-month bill. In no case shall the amount of deposit be less than the minimum deposit as set forth in APPENDIX A, WATER FEES AND CHARGES SCHEDULE.
D. PAYMENT OF DEPOSIT
Deposits are due upon application for service and delinquent 14 days later.
2. Deposits will not be used as payment for past-due bills to avoid discontinuance of service.
E. RETURN OF DEPOSIT
Upon discontinuance of service, the Utility shall apply the Customer's deposit and accrued interest to the unpaid bills and refund any balances that exceed $10 by mail. Any refunds with a balance of less than $10 will be refunded to Customers upon request.
After the Customer has maintained a good payment record for twelve (12) consecutive months, the Utility shall apply the Customer's deposit, including accrued interest, to the Customer's bill.
3. The Utility may apply the deposit to the Customer's account at any time upon request, provided the Customer's credit may otherwise be established in accordance with Rule No. 3, ESTABLISHMENT AND RE-ESTABLISHMENT OF CREDIT.
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside
Public Utilities Department 4-2
F. INTEREST ON DEPOSITS
Simple interest as established annually by the Board of Public Utilities will be accrued for the period that the deposit is held by the Utility.
The ust may only be applied to the Customer's active account at the discretion of
SERVICE TURN-ON CHARGE
A service turn-on charge shall be made for turning on water service during normal working hours on the following workday. There will be an additional charge for the same day and after-hours turn-on of service when specifically requested by the Customer. A service charge will be assessed for each additional field visit required to complete the service turn-on order.
2. The Utility shall not be liable for any loss or damage caused by the improper installation, maintenance or malfunction of any water apparatus or appliance, or for damage caused by the turning on and off of water service by the Utility Forces.
Adopted by Board of Public Utilities: oard Resolution Ni Approved by City Council: ouncil Resolutior
Effective Date:
City of Riverside 10-1
Public Utilities Department General Requirements
WATER RULE 10
WATER SYSTEM AND FEE REQUIREMENTS
A. GENERAL
1. Applicability of Rule
a. Water system installations shall be made in accordance with the provisions of this Rule.
See Rule No. 8, "Temporary Water Service," for provisions applicable to installations for temporary services.
c. Water service fees and charges will be determined in accordance with the provisions of this Rule and Rule No. 11.
Design and Construction of Water Facilities
a. All design and construction shall be in accordance with the Water Utility's standard plans and specifications.
b. Water facilities within private developments shall only be accepted for maintenance by the Water Utility if authorized by the Director.
Developers may request that water facilities within their private developments be accepted for maintenance by the Water Utility, subject to the following:
(1) Easements (30 feet minimum width) shall be provided to the City for water mains and access across the entire width of private streets and with adequate additional easements
provided for water system appurtenances (water meters, fire hydrants, etc.);
(2) Standard concrete six-inch (6") curbs and gutters shall be constructed within development; and,
(3) Compliance with any special requirements of the Water Utility. c. Specific methods to meet adequate fire flow requirements specified by the Fire Department or other agencies exercising jurisdiction over the facilities will be determined by the Director.
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside 10-2
Public Utilities Department General Requirements
3. Ownership of Water Facilities
Water distribution system installations, however provided, shall become property of and under control of the Water Utility.
B. WATER SERVICE FEES AND CHARGES
General
a. Water service fees and charges shall generally include:
Backup Facility Capacity Charge
Elevation Fee
Distribution System Fee
Water Service and Meter Connection Charges
Special Conditions
b. The legal description, plot plan and/or field check for a parcel to be provided water service shall be used to establish the Backup Facility Capacity Charge, Elevation Fee, Distribution System Fee and possible special conditions.
c. When a property with an existing water service is divided, water service fees and charges for the parcel which the existing Water Service Connection will continue to serve, shall be considered paid, except that, at the Director's discretion water fees and charges may be levied if a water main replacement is required. All other parcels shall pay the applicable charges.
When a property use changes, , and a new building permit and/or a new Water Service. Connection is applied for, previously paid Backup Facility Capacity Charges, based on water meter size, shall be considered as a credit toward any higher Backup Facility Capacity Charge. Under no circumstances will there be a refund of previously paid Backup Facility Capacity Charges.
e. When a property use changes, and a new building permit and/or new water Service Connection is applied for, and a previously undersized water main has been replaced fronting the developer's/ owner's property, the developer/owner shall pay the Distribution System Fee, less any frontage distance previously paid. Fees collected will be reimbursed to developers/owners who replaced water mains as provided under terms of any applicable Water Utility reimbursement agreement previously executed by the City.
Adopted by Board of Public Utilties: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside 10-3
Public Utilities Department General Requirements
f. If water use of a parcel is extended beyond the paid area of that parcel being serviced by an existing water meter, all water fees and charges covering the extended area shall be charges and collected by the Water Utility.
g. If the boundaries of a parcel, which has a Water Service Connection, are adjusted so as to encompass an area which does not have a Water Service Connection, all water fees and charges applicable to the addition shall be collected by the Water Utility. Payment must be made prior to finalization of the lot line adjustment.
All applicable water fees and charges shall be paid prior to the issuance of building permits, approval of final subdivision maps or parcel maps, or approval of any Water Service Connection requests. i. In Residential Zones, all applicable parcel map recordation water fees and charges will not be collected when a parcel is to remain undeveloped and is capable of further subdivision into two (2) or more parcels. The Backup Facility Capacity Charges, Elevation Fees, Distribution System Fees, and Service Connection Charges for these undeveloped parcels shall be charged when water service is requested in accordance with Rule No. 10 B.1.h.
j. If a Covenant and Agreement is requested from the Water Utility by the developer/owner to satisfy a water service requirement, and said request is approved by the Director, a processing fee will be paid by the developer/owner to cover administrative costs in conjunction with the preparation and approval of the Covenant and Agreement. See Water Appendix A for amount.
k. A Covenant and Agreement shall be required to be executed by the developer/owner of residential development within the "Arlington Greenbelt Area" when partial fees and charges are paid to the Utility.
The developer/owner paying partial fees and charges shall be given credit against subsequent fees and charges applicable when and if parcel is legally subdivided, or further developed in the future.
Backup Facility Capacity Charges
a. Backup Facility Capacity Charges shall apply to all Water Service Connections provided by the Water Utility, except as specified in Special Provisions section of this Rule.
Backup Facility Capacity Charge shall be paid prior to the issuance of a building permit, approval of a final subdivision map or parcel map or in conjunction with a Water Service Connection request.
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside 10-4
Public Utilities Department General Requirements
c. When a larger Water Service Connection is requested by Applicant, the Backup Facility Capacity Charge for the existing Water Service Connection will be credited toward the new Backup Facility Capacity Charge in effect at the time the larger connection is requested. No refund shall be made if a reduction in size is requested.
Elevation Fee
Elevation fee shall apply to all Water Service Connections supplied from Water Utility pressure zones above the Gravity Pressure Zone, except as specified in Special Provisions section of this Rule.
Distribution System Fee
Distribution System Fee shall apply to all water service areas of the Water Utility, except as specified in Special Provisions section of this Rule. If the Applicant has constructed or is making arrangements to construct water mains at his expense adjoining the subject property, then no Distribution System Fee shall be collected for the frontage adjoining said water mains.
Distribution System Fee shall be computed by multiplying the applicable charge per foot by the actual distance which the parcel abuts all adjacent public streets or City public easements. c. The Distribution System Fee for the following corner parcels shall be applied using one-half the entire parcel frontage for the following:
(1) Existing individual corner lots zoned R-1 for single family dwelling which cannot be subdivided.
However, comer lots created by new subdivision are excluded Home ver. from the one-half frontage provision and the Distribution System Fee shall be applied using the entire frontage.
(2) Corner lots in areas zoned for single family dwellings with the requirement of minimum five (5) acre parcels;
However, if a corner parcel is proposed to be subdivided, the Distribution System Fee shall be applied using one-half the entire frontage for only the corner lot resulting from the subdivision process. The Distribution System Fee for the other parcel or parcels of the subdivision shall be based on full frontage.
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside 10-5
Public Utilities Department General Requirements
When a development or use requires a water supply greater than that which can be supplied by an eight-inch (8) water main for Residential Zones or twelve-inch (12) water main for Commercial/Industrial Zones, the cost of the oversized pipe required shall be paid for by the developer/owner as determined by the Director.
e. The Distribution System Fee will be considered satisfied for an existing developed or partially developed parcel, which has existing domestic water service from the Water Utility, when such parcel is proposed to be further developed and the developer/owner requests a larger or an additional Water Service Connection. This is subject to the parcel remaining as one undivided parcel. An exception to the • Distribution System Fee being considered satisfied is when the property use changes, in which event Section B.1.e. of this Rule shall apply.
C. SCHEDULE OF WATER SERVICE FEES AND CHARGES
Water Service Fees and Charges
a. Backup Facility Capacity Charge
For Each Water Metered Service Connection
3/4-inch meter $ 2,250
1-inch $ 5,060
1-1/2-inch $ 9,560
2-inch $ 14,400
3-inch $ 25,300
4-inch 39,380
6-inch $ 73,130
8-inch $ 108,000
10-inch $ 135,000
In the event a larger water meter is needed for any type of service for fire protection purposes resulting in a size larger than needed for normal uses, the charge will be based on the size needed for normal uses. In the event an existing water meter service connection is lanned to be utilized for an expanded development, additiona charges shall be required based on the difference between existin size of service and service size needed for expanded normal water uses. Applicant shall submit calculations from a validly licensed architect or engineer.
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside 10-6
Public Utilities Department General Requirements
The Backup Facility Capacity Charge shall be paid prior to the issuance of a building permit, approval of a final subdivision map o arcel map or in conjunction with a Water Service Connection reques Backup Facility Capacity Charge shall not apply to Fire Service Connections.
Elevation Fee
The Elevation Fee is based on booster pumping to higher elevation pressure zones. If the cost of water facilities required to serve a development substantially exceeds the average cost of water facilities recoverable by application of the Elevation Fee, the Director shall determine appropriate charges with the developer/owner for approval by the Board.
For pressure zones not identified in this Rule, the Director shall establish the Elevation Fee.
Elevation Fee Schedule
Elevation Fee
(Per Acre or Nominal Zone
Pressure Zone Portion Thereof Designation
001, 002, 071, 072 $- Gravity
073 $- 925
501, 561 340 1037
164 $ 420 1080
101, 102, 103, 151 $ 600 1100
162, 163, 201 $ 780 1160
$1,000 1200
311. 32. 213,221.251
$1,380 1300
412, 413, 421,422, 423,441, 442,451,452,461 $1,720 1400 611, 613, 621, 631, 641 $ 2,480 1600
632, 642 $2,730 1680
721,741 $ 3,090 1750
Distribution System Fee
Distribution System Fee shall be $49.00 per foot of parcel or lo rontage and in accordance with Section B.4. of this Rule Water Service and Meter Connection Charges
(See Rule No. 11)
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside 10-7
Public Utilities Department General Requirements
2. Installation • of On-Site and/or Off-Site Water Facilities By Developer/Owner - (See Section D of this Rule)
a. Applicant shall make a deposit for engineering plan checking and review services upon first plan submittal with the Water Utility to cover the actual cost of staff time and materials to review submitted plans.
Upon determination that the deposit amount is inadequate to cover the actual costs for plan checking services, Applicant shall make additional deposits as necessary with the Water Utility. Further plan checking services shall be suspended until additional deposit is made.
Upon acceptance of the constructed water facilities by the Water Utility, the Water Utility will refund any remaining deposit balance. b. The inspection fees are listed in Water Appendix A and shall be paid prior to scheduling a preconstruction meeting.
(1) Normal construction allows for inspection as needed during a period of thirty (30) calendar days for each 2,000 lineal feet of constructior
which is not completed within the time for "normal construction" shall be considered "extended construction" and an additional (2) Normal construction allows for two (2) inspection visits after Additional inspection visIt
and will be during normal working hours. See Water Appendix (3) Water Service Connection(s) For Individual Premises of four- inch (4") or larger, a Cash Refundable Bond (per connection) to guarantee final completion by private pipeline contractor of required four-inch (4") or larger Water Service Connection(s) and/or Fire Protection Service(s). Bond will be refunded to developer/owner upon final completion and acceptance of connection(s) by the Water Utility. See Water Appendix A for amount.
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside 10-8
Public Utilities Department General Requirements
c. Backup Facility Capacity Charge, Elevation Fee and Distribution System Fee.
(1) Backup Facility Capacity Charge shall be levied where applicable. (See Section C.1.a. of this Rule)
(2) Elevation Fee shall be levied where applicable. (See Section C.1.b. of this Rule)
(3) Distribution System Fee shall be charged on public streets and City public easements abutting the development. (See Section C.1.c. of this Rule).
d. Water Main Connection Charge
The developer/owner shall pay the water main connection charges as determined by the Director. Consideration shall be given to size, location and difficulty of each connection. Water main connection charges shall be valid for a period of six (6) months from the date they are determined. Thereafter, the Director will re-estimate the charges and the developer/owner shall pay the difference.
e. Water Meter Charge
(1) The Applicant shall pay water meter installation charges (meter only). See Water Appendix A for amounts.
D. INSTALLATION OF ON-SITE WATER FACILITIES
1. Applicability
a. The developer/owner shall have the responsibility for the installation of on-site water facilities within the boundaries of subdivisions, shopping centers, industrial parks or lots as shown on the record map.
Water fees and charges related to the installation of on-site water facilities shall be paid prior to commencement of work. Work shall commence within six (6) months of payment of all water fees and charges or the water fees and charges which are in effect when work is commenced shall apply. (See Section B. of this Rule).
Water facilities, which become the property of the Water Utility, shall generally be located within the public right-of-way. Water facilities will only be permitted within easements at the discretion of the Director.
Adopted by Board of Public Utlities: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside 10-9
Public Utilities Department General Requirements
2. Installation of On-Site Water Facilities by Developer/Owner a. Developer's/Owner's Responsibilities
The developer/owner shall have the responsibility for engineering, constructing, sanitizing and testing of the pipelines, appurtenances, service laterals and installation of water meter vaults, in accordance with the Water Utility's standard plans and specifications and are subject to Water Utility inspection and acceptance. The developer/owner shall pay to the Water Utility the established charges as set forth in Section C.2. of this Rule.
(1) Complete engineering shall be by a civil engineer registered in the State of California and shall include submission of a full set of detailed improvement plans to the Water Utility along with a (2) After all changes, modifications and additions requested by the Water Utility have been made on the water plans, and they have been approved, developer/owner shall supply a complete set of original plans to the Water Utility. Said original plans shall become the property of the Water Utility.
(3) The developer/owner shall have the required installation erformed by a licensed contractor, and shall furnish a cas leposit or faithful performance bond in an amount equal t 125% of the Water Utility's estimated cost of installation. Cash deposit or bondable estimated installation costs shall be based pon the estimated construction cost ot the water system and applicable fees and charges
(4) All laboratory analyses required in connection with chlorination and sanitizing the newly-installed systems shall be performed by a State of California laboratory licensed and certified to perform such tests. All charges in connection therewith shall be borne by the developer/owner with test results forwarded to (5) All Water Utility fees and charges must be paid prior to commencing construction of water facilities.
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside 10-10
Public Utilities Department General Requirements
b. City Provided Services
The City shall provide services including engineering plan review, inspection, setting of water meters and water system connections to the existing water mains.
(1) Plans submitted to the Building and Safety or Public Works departments will be examined for conformance with the Water Utility's standard specifications and other requirements. A separate water plan submittal may be required if water system improvements, upgrades, or relocations are required. Please see Appendix A for fees associated with Building and Safety and Public Works plan review.
(2) The submitted water plans will be examined for conformance with the Water Utility's standard specifications and other requirements. Errors and omissions, if any, will be indicated on the plans and they will be returned to the engineer for correction.
(3) Water Utility personnel or their agent will inspect water facilities installed by the developer's/owner's contractor to ensure compliance with the water plans and specifications.
(4) Water Utility forces will schedule and set all water meters upon filing of the appropriate water service application form and payment of water fees by the Applicant.
Reimbursement for Pipe Oversizing
(1) If at the Water Utility's request, the developer/owner is required to install a pipeline of a larger diameter than normally necessary for the development, the developer/owner shall be reimbursed for the extra cost in accordance with Section D.2 c.(5) of this Rule.
(2) Payments for pipe oversizing will be made upon acceptance of the installed pipeline.
(3) Under no circumstances will reimbursements be made for eight-inch (8") or smaller pipelines in single family Residential Zones or twelve-inch (12") or smaller in all other zones. (4) Sizing of water facilities will include consideration of Fire Department requirements.
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside 10-11
Public Utilities Department General Requirements
(5) Water Main Oversizing Reimbursement - See Water Appendix A for amounts.
Acceptance and Release
(1) The security given for faithful performance of the work, whether cash or bond, may be released, in part, upon final completion and acceptance of the water facilities by the Water Utility; except that an amount equal to ten percent (10%) of the surety bond, but not less than $1,000 will be withheld to cover the costs of possible maintenance, repair and replacements. Final release shall be made one (1) year after acceptance of the water system.
(2) If the developer/owner fails to complete all of the specified improvements in accordance with the approved water plans and specifications within the twelve (12) months after
commencing said work, the Director may order such work
performed by the Water Utility forces, and may utilize the cash deposit, if furnished, or call upon the surety company for funds to cover reimbursement.
E. INSTALLATION OF OFF-SITE WATER FACILITIES (WATER MAIN
EXTENSIONS AND REPLACEMENTS)
General
a. Developers/owners shall be responsible for the off-site water main extensions and replacements necessary to reach and front their properties/developments from existing Water Utility facilities having adequate capacity.
Replacement of water mains shall be required when existing water mains are undersized/inadequate to supply domestic and/or fire flows to/for proposed developments.
b. The Director reserves the right to have off-site water facilities installed by Water Utility forces at the expense of developer/owner-based upon actual cost of water main installation.
The Director is authorized to execute water main reimbursement agreements on behalf of the Water Utility for water main installations paid for or constructed by developers/owners. The purpose of these agreements is to provide partial or full reimbursement to developers/owners who pay for or install off-site water facilities.
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside 10-12
Public Utilities Department General Requirements
d. The water main reimbursement agreements shall contain brief descriptions of the properties to be served with water, the length and location of water mains, as well as the total estimated costs in accordance with Section C.1.c. of this Rule. These agreements shall remain in effect for a maximum of twenty (20) years, after which no further reimbursements will be made.
Water main reimbursement agreements shall be executed for a value over five hundred dollars ($500.00). Reimbursements shall be computed in accordance with Section C.1.c. of this Rule.
Reimbursement payments for water main extensions shall not exceed total estimated costs as provided in the Water Main Reimbursement Agreement.
2. Water Main Extensions (Installation by Water Utility Forces) a. If water main extensions are installed by Water Utility forces, developers/owners shall pay to the Water Utility the actual cost of water main extensions including appropriate construction, engineering and administration charges.
Engineering and installation shall not commence until the Water Utility has actually received payment for the estimated cost of work. Work shall commence within six (6) months after receipt of total estimated cash payment. If commencement of work is delayed for more than six (6) months by circumstances outside of the control of the Water Utility, developers/owners may be required to pay additional estimated costs. c. Developers/owners will receive either a partial refund or an invoice to cover the actual costs of water main extensions after all final costs are known.
Water Main Extensions (Installation by Developers/Owners) Developer's/owner's appropriately licensed contractors are subject to the Water Utility's approval prior to scheduling the construction of water main extensions. All fees and charges shall be paid prior to commencement of work. Requirements shall conform to those established in Section D.2. of this Rule.
Water Main Relocations
Developers/owners shall be responsible for relocating existing water main(s) which would not be located within paved roadways of streets or would have pipe cover of either less than three feet (3') or more than ten feet (10') as a result of a developer's/owner's improvements. Relocations shall be in Adopted by Board of Public Utilties: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside 10-13
Public Utilities Department General Requirements
accordance with Water Utility requirements and at developer's/owner's expense.
Water Supply Assessments
Where required by the California Environmental Quality Act (CEQA), Water Supply Assessments (WSA) shall be prepared by the Water Utility and provided to the developer/owner at the developer/owner's expense. Please see Appendix A for SA preparation fees.
F. Special Provisions
1. General
a. Special Provisions have been enacted for development within the following areas and shall take precedence over General Provisions of this Rule
• Arlington Heights Greenbelt Area for Prop. "R" & "C"
• Sungold Agreement Areas
• 1911 Act Areas
• Temporary/Remote Water Service
• Infill Parcels
With Water Utility approval, Special Provisions may apply to allow temporary/remote (off-site location) Water Service Connections not fronting the property being served.
Special Provisions shall only apply to the above listed areas as outlined herein. General Provisions of this Rule shall apply to all other areas.
All other provisions of the Water Rules shall apply to the above-listed areas except as modified in these Special Provisions.
2. Arlington Heights Greenbelt
a. The Arlington Heights Greenbelt is the area within the City Limits generally located southeasterly of Victoria Avenue, westerly of Washington Street and northeasterly of La Sierra Avenue. The exact boundaries are shown on map located in the City of Riverside Planning Department.
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside 10-14
Public Utilities Department General Requirements
The Distribution System Fee for development within the "Arlington Heights Greenbelt Area" shall be computed using the actual distance of street frontage of the area to be developed, including landscape area, or a minimum of 150 feet, whichever is greater.
Elevation Fee for residential development within the "Arlington Heights Greenbelt Area" shall be computed using actual area to be developed including landscape areas, or a minimum of one (1) acre, whichever is greater.
Water service will be subject to all other water installation and fee requirements applicable under the General Provisions of this Rule.
3. Sungold Agreement
The Sungold Agreement covers certain properties located in the easterly portion of the City of Riverside Water Service Area as shown on map located in the Water Engineering Division of the City of Riverside Public Utilities Department.
Special Provisions are as follows:
a. No Distribution System Fee for properties fronting public street water mains, 12-inch diameter or smaller, and having adequate capacity to provide required water flows thereto.
Elevation Fee is $40.00 per acre for elevations 1100-feet and higher.
No Elevation Fee for elevations less than 1100-feet.
Required water main replacements, extensions and costs along with the other applicable Water Fees, not listed above, will be subject to the general installation and fee provisions of this Rule. 1911 Acts
a. Whitegate Improvement District
1. The Whitegate 1911 Act Improvement District covers the Overlook Parkway area served by Whitegate No. 1 and No. 2 Reservoirs, as shown on map located in the Water Engineering Division of the City of Riverside Public Utilities Department.
The Elevation Fee is not applicable in this area. Water service will be subject to all other water installation and fee requirements applicable under the General Provisions of this Rule.
Adopted by Board of Public Utilties: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside 10-15
Public Utilities Department General Requirements
Mt. Vernon Water Improvement District
The Mt. Vernon 1911 Act Water Improvement District covers the Mt. Vernon Avenue area located northerly of Mt. Vernon Booster, as shown on map located in the Water Engineering Division of the City of Riverside Public Utilities Department.
The Distribution System Fee is not applicable for existing parcels only. Water Service will be subject to all other water installation and fee requirements under the General Provisions of this Rule. Special Provisions do not apply to subdivided parcels and all requirements will be applicable under the General Provisions of this Rule.
5. Temporary/Remote Water Service - Temporary Off-Site Location Upon approval of the Water Utility, water may be provided through a temporary/remote service connection from the nearest existing main of adequate size, subject to fulfillment of the following conditions:
a. Applicant shall pay all applicable fees and charges including Backup Facility Capacity Charge, Elevation Fee, Distribution System Fee, Water Service Connection and Meter Charge.
b. Applicant shall secure any public and/or easements deemed necessary by Department to facilitate temporary/remote water service. c. Applicant shall execute a recordable agreement, approved by the City Attorney, regarding the temporary/remote water service. d. City shall have all temporary remote service agreement recorded through the County of Riverside Recorder's Office.
Infill
Those single family residential parcels identified and defined in the Residential Infill Strategy, when and as adopted by the City Council.
Special Provisions are as follows:
a. Distribution System Fee shall be considered paid.
Elevation Fee shall be considered paid.
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside 11-1
Public Utilities Department
WATER RULE 11
WATER SERVICE CONNECTIONS, WATER METERS AND RELATED APARATUS A. GENERAL
Water Service Connections shall front the individual lots or parcels they serve and shall be constructed within the public right-of-way, or within Water Utility approved easements as determined by the Director.
a. More than one Water Service Connection per parcel/lot shall require the advance approval of the Water Utility and may require the installation of an Approved Backflow Prevention Assembly.
When the water meter and water meter vault cannot reasonably be located in the public right-of-way, they shall be located on the Customer's Premises adjacent to the crossing of the service laterals with the property line, or such other location as may be agreed upon by the Customer and the Director.
c. No rent or other charge shall be levied against the Water Utility for Water Service Connections which must be located on the Customer's property.
New Water Service Connections and fire hydrant connections will not be allowed from transmission mains larger than twelve-inches (12) in diameter.
The Water Utility shall own and maintain all Water Service Connections up to and through the rear water meter union whether located on private property or in the public right-of-way.
The Customer shall, at his own expense and risk, furnish, install and maintain all apparatus and appliances which are required to receive, control, regulate, and utilize the pressure and flow of water as furnished by the Water Utility.
The Water Utility shall not be liable for any loss or damage caused by the improper installation, maintenance or malfunction of such apparatus. The Water Utility shall not be responsible for damage or inconvenience occasioned by the misuse of water after it has left the water meter, nor for any damage caused by the turning on and off of water service by Water Utility forces.
The Water Utility shall not be liable for any damage to the Customer's plumbing caused by tree roots or any other natural causes.
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution No.
Effective Date:
City of Riverside 11-2
Public Utilities Department
5. As defined in the current applicable Uniform Plumbing Code, as adopted by the City, Section 608.2, when static water pressure inside a building is in excess of eighty (80) pounds per square inch, an approved type pressure regulator and pressure relief valve shall be installed and properly maintained by Applicant so that the water pressure is reduced to eighty (80) pounds per square inch or less.
The Customer shall compensate the Water Utility for any and all damage to Water Service Connections under the Water Utility's ownership, which is caused by carelessness or neglect of the Customer.
It shall be the Customer's or property owner's responsibility to maintain free and clear access for the Water Utility's representatives to all water meters, water meter vaults, backflow prevention assemblies, fire hydrants and other water facilities supplying his Premises. Refer to Standard CWD 631 and CWD 632.
Inasmuch as ownership of all Water Service Connections as described in Section A.2, above, is vested in the Water Utility, only authorized representatives and employees of the Water Utility are permitted to connect or disconnect the service lateral to the water main, or tum the service on or off at the water meter. Tampering with the service lateral or water meter in any way by unauthorized persons is a violation of these Rules and may result in a penalty and/or the discontinuance of water service.
Whenever the owner or his representative has ordered a Water Service Connection removed, abandoned, or disconnected at the water main, said owner shall sign a release waiving all rights and interest in the Water Service Connection. Re-establishment of service to the Premises shall be evaluated, and charged as a new Water Service Connection with Backup Facility Capacity Charge, Distribution System Fee, and Evaluation Fee considered paid.
B. WATER SERVICE CONNECTIONS FOR INDIVIDUAL PREMISES
Upon payment of the applicable fees and charges and completion of the appropriate application forms, the Water Utility shall furnish, install and maintain the service lateral, water meter and water meter vault. a. Applicant shall pay the Water Service Connection charges as specified in Section G.1.b. of this Rule, and shall also pay Backup Facility Capacity Charge, Distribution System Fee and Evaluation Fee as set forth in Rule No. 10, Section C.1.
Applicants for individual Off-Site Water Service Connections four-inch (4") or larger have the option of having the Water Utility forces or a City of Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution No.
Effective Date:
City of Riverside 11-3
Public Utilities Department
Riverside approved, responsible, licensed contractor install the required connection(s).
a. If Water Utility forces install said connections, the Applicant shall pay to the Water Utility the established charges as set forth in Rule No. 10, and Section G.1.b. of this Rule.
If a private contractor is selected, said installation shall be in accordance with the Water Utility's standard plans and specifications and subject to Water Utility inspection and acceptance. The Applicant shall deposit with the Water Utility the established charges as set forth in Rule No. 10.C.2. (Backup Facility Capacity Charge, Distribution System Fee, Elevation Fee, inspections fees and water meter charges).
c. If a private contractor is selected, Applicant will be required to submit to the Water Utility the following:
(1) Street opening permit;
(2) Liability Insurance; and,
(3) An executed Hold Harmless agreement approved by the City's Legal Department.
Bacteriological Testing for Water Meters Two-Inch (2") or Larger and Fire Protection Services
Customer piping served by a water meter two-inch (2") or larger and Fire Protection Services will not be tested until a twenty-four (24) hour period between the final flushing and the taking of bacteriological samples is completed. Following this period, the Contractor shall have qualified laboratory approved by the Water Utility perform bacteriological tests.
Samples shall be taken in the field and transported to the laboratory by a laboratory technician or by a representative of an approved testing firm. A minimum of one (1) successful bacteriological test per 500 feet of water main will be required. All samples must be absent for total coliform and E coli/fecal bacteria and have a heterotrophic plate count of less than 200.
All laboratory testing shall be at the Contractor's expense. One copy of the test results shall be mailed directly to the Water Utility from the laboratory.
A flushing testing charge will be collected in advance for each installation requiring bacteriological testing. The fee will be charged each and every time flushing testing is required. See Water Appendix A for amount. The flushing Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution No.
Effective Date:
City of Riverside 11-4
Public Utilities Department
testing charge will allow maximum flushing time of ninety (90) minutes.
Upon successful completion of bacteriological testing, the sanitary condition of Customer's piping will be accepted and the water meter and/or Fire Protection Service will be released for Customer Service and use.
C. WATER SERVICE CONNECTIONS IN SUBDIVISIONS (TRACT MAPS), PARCEL
MAPS, RECORDS OF SURVEY, SHOPPING CENTERS, MOBILE HOME PARKS
AND INDUSTRIAL DEVELOPMENTS
Water Service Connections within the development shall be installed in conjunction with the other On-Site water facilities under the provisions of Rule No. 10. Water meter charges as specified in Rule No. 10, shall apply.
2. Work shall commence within six (6) months of payment of all water fees and charges or the fees and charges which are in effect when work is commenced shall apply. All fees and charges which are applicable shall be paid prior to commencement of installation.
D. RELOCATION AND REPLACEMENT OF WATER SERVICES LATERALS Water relocation or moving of water service laterals shall be performed by Water Utility forces at the Customer's expense. The charges shall be estimated by the Water Utility. Maximum lateral relocation shall be five feet (5).
The charges to relocate Water Service Connections over one-inch (1") shall be at actual cost of relocation.
b. If at the Customer's request the water service lateral must be extended or shortened, it will be done at Customer's expense.
Water service laterals which are or become defective without fault on the part of the Customer shall be replaced at the Water Utility expense. When a defective water service lateral is scheduled for replacement, the Customer may obtain a larger size meter by paying the difference between the water meter charges as set forth below in addition to any applicable Backup Facility Capacity Charges. See Water Appendix A for three-quarter inch to 1" inch meter increase charge amount
Other combinations not covered shall be charged at the difference in the Water Utility's costs for labor and materials.
When a Customer requests a water meter size increase with no change to the water service lateral, the difference in water meter costs plus an Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution No.
Effective Date:
City of Riverside 11-5
Public Utilities Department
additional charge in addition to any other applicable fees. See Water Appendix A for that charge.
Charges for relocating fire hydrants and Fire Protection Services shall be levied when such relocation is for convenience of the Customer or is necessitated by improvements initiated by him. These charges shall include costs for labor, materials, and overhead expenses. The charge for replacing a Fire Protection Service shall be the charge for a new service, but with Elevation Fee and Distribution System Fee considered paid.
E. REPAIR OF WATER FACILITIES
The cost of repairing water facilities damaged by persons other than Water Utility personnel shall be at actual labor, material, equipment and field overhead costs plus a fee for the cost of general Water Utility overhead and processing for each incident.
This charge may be waived at the Water Utility's discretion. See Water Appendix A for that fee.
F. FIRE PROTECTION SERVICE - USAGE
Private fire protection system services shall be used only for the discharge of water to extinguish fires, and shall be equipped with a backflow device detector assembly and bypass meter. It shall be unlawful to install any taps, hose bibs or other outlets for the use of water for any other purpose. The taking of water from a private fire system for any unauthorized use shall constitute cause for the discontinuance of the water supply at that service, or the installation at the Customer's expense of a fully-metered Water Service Connection with enforcement of the applicable water rates to such water meter.
Fire Flow Test Data
Available fire flow data is available from the Water Utility upon request. Fire flow test data will generally be provided using the Water Utility's hydraulic model and supplemented with physical flow testing where required. Fees for fire flow testing are shown in Appendix A.
Backflow Prevention
The Fire Protection Service to a Premise shall be subject to the same ackflow prevention regulations and requirements as the Domestic Wate ervice to that property
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution No.
Effective Date:
City of Riverside 11-6
Public Utilities Department
G. SCHEDULE OF WATER SERVICE CONNECTION CHARGES
Domestic Water Service Connection Charges
a. Domestic Water Service Connection Charges shall be levied unless installed by property owner.
The charges to be collected by the Water Utility for new Domestic Water Service Connections installed by Water Utility forces, are as set forth below including the water meter and water meter vaults, and are in addition to the charges and conditions noted in Rule No. 10.
Backflow prevention assemblies, where required, are the responsibility of the Customer, and are not installed by the Water Utility. See Water Appendix A for charges.
When ten (10) or more Water Service Connections are installed in a subdivision or shopping center, the Applicant may elect to have jumpers installed (in place of the water meter) for no more than one hundred twenty (120) days from the date of installation. This type of service is to provide construction water only. The monthly charge for this type of service is shown in Water Rate Schedule WA-2 - Flat Rate - Temporary Service.
2. Fire Protection Service Connection Charges
a. Fire Protection Service connection charges shall be levied where applicable.
The charges to be collected by the Water Utility for Fire Protection Service shall be as set forth below and said charge is in addition to the charges and conditions noted in Rule No. 10.
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution No.
Effective Date:
City of Riverside 11-7
Public Utilities Department
(1) Fire Protection Service Connection Requiring Backflow Protection
The Water Utility determines the Degree Of Hazard associated with the Fire Protection Service connection. When Backflow Protection is necessary, the following installation will be applicable:
Fire Protection Service Connection Above-Ground: The Water Utility installation shall generally include tapping the water main, laying a service lateral, and installing an above ground riser and flange.
All piping, valves, regulators and attachments on the
Applicant's side of the riser flange shall be the Applicant's responsibility to install and maintain.
An approved double check detector assembly (DCDA) or an approved reduced pressure principle detector assembly
(RPDA) shall be furnished and installed by Applicant. The location of this assembly must be approved by the Water Utility's Backtlow Program Administrator. The assembly is the property of the Customer and it is the Customer's responsibility to test and maintain the unit. The detector meter on the bypass piping of the detector assembly becomes the property and maintenance responsibility of the Water Utility. This water meter shall be protected by a steel enclosure with a hinged meter reading lid. The steel enclosure shall be approved in advance by the Water Utility prior to fabrication. Also this water meter shall be primed and painted as approved by the Water Utility.
Size of Service Connection Charge
2-inch and larger At Estimated Cost of Installation
(2) If the required Distribution System Fee and Elevation Fee have not been paid with a Domestic Water Service connection, then these fees as outlined in Rule No. 10.C.1.b. & c. shall be assessed and paid with the Fire Protection Service connection payment.
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution No.
Effective Date:
City of Riverside 11-8
Public Utilities Department
H. TEMPORARY WATER SERVICE CONNECTIONS FOR AGRICULTURAL USES
1. Temporary Water Service Connections as determined by the Director may be provided for parcels of land that are to be under agricultural uses.
The Distribution System Fee may be deferred with the Director's approval until such time as parcels are developed with permanent structures or facilities.
Backup Facility Capacity Charge and Elevation Fee may be deferred, with Director's approval, for a maximum period of two (2) years. After the two (2) year period, the Backup Facility Capacity Charge and the Elevation Fee shall be immediately paid by the Applicant, or paid in four (4) equal annual payments.
In the event the above Fees and Charges are deferred, the Applicant shall execute a standard recordable agreement approved by the City Attorney. •
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution No.
Effective Date:
City of Riverside 14-1
Public Utilities Department
WATER RULE 14
TURN-ON AND TURN-OFF OF
WATER SERVICE FOR REPAIR BY CUSTOMER
Customer requests to the Water Utility for turn-off or turn-on of water service for the urpose of making repairs, or changes to their plumbing at times other than normal working lours, will be billed a minimum service call charge as follows Monday through Friday.... ....Charge
6:00 p.m. to 10:00 p.m............... ...See Water Appendix A 10:00 p.m. to 7:30 p.m. .......... .... See Water Appendix A Weekends and Holidays.. ....Charge
3:30 p.m. to 7:30 p.m. .................. See Water Appendix A 7:30 p.m. to 7:30 a.m. .................... ..... See Water Appendix A he service call charge may bewared the trottor turns necessitated by al emergency over which the Customer has no control. The Water Utility will have the sole discretion of determining the validity of such an emergency.
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution No.
Effective Date:
City of Riverside 16-1
Public Utilities Department
WATER RULE 16
CONVEYANCE OF WATER RIGHTS
AND
WATER STOCK
A. WATER RIGHTS AND STOCK TO CITY
Applicable to all parcels of land with a gross acreage of less than 2-1/2 acres and having received irrigation water from a mutual water company except for Gage Canal Company.
All lands under a gross acreage of less than 2-1/2 acres of land shall forfeit all water rights or water stock which are appurtenant to the property and convey same to the City as a condition of receiving domestic water. The water rights or water stock will be donated to the City unless previous contractual agreements are on record with the City.
B. STOCK AND CONTRACT TRANSFERS
Whenever a water stock certificate or water contract must be changed or reissued by the City, a processing fee will be charged for the following water companies:
Gage Canal Company (Contracts Only)
See Water Appendix A for amount.
C. GAGE CANAL COMPANY WATER ENTITLEMENTS
Subject to conditions outlined in various City and Gage Canal Company Agreements, such as "Agreement for Operation of Gage Canal Facilities", the "By- Laws of the Gage Canal Company", and the "Stipulation for Judgment in Eminent Domain and Final Order of Condemnation", the following procedures shall be utilized when either contracting or transferring water entitlements:
Transfer of Shares or Contracts to new owner of existing property to which the shares are appurtenant for continued agricultural use. This action is defined ir Section #8 of the "Agreement for Sale of Gage Canal Company Shares" (Sales Agreement) and does not require. City consent. Does not impact existing City water supplies.
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution No.
Effective Date:
City of Riverside 16-2
Public Utilities Department
Turning in Shares to City without a request for "Contract for Delivery of Irrigation Water" (Contract). This is the completion of the original Sales Agreement and final payment of $175 is made by the City. The City receives the shares and the water and the water entitlement represented by the shares for domestic use.
Conversion of Shares to Contract for Delivery of Irrigation Water to other lands within the Gage Canal service area. The original shareholder with shares excess to their needs offers, through the Gage Canal Company, to make these shares available. Other property owners, by virtue of Sales Agreement Item #7, within the service area contract with the City for the water entitlement represented by the shares. The City receives the Gage shares but not the water entitlement. City approval is required per Section 4 of the "Agreement for Operation of Gage Canal Facilities". This approval is required but must be given.
The following types of transfers or contracts which would subtract from existing Water Utility domestic water supply will not be approved.
Request for Water Contracts for land on which the Gage water shares have been sold or transferred to the City. These contracts would be based on shares that have been turned into the City, the final $175 payment has been made and the terms of the Sales Agreement are complete. This type of transaction would not receive City approval.
Request for Water Contracts for Additional Water added to existing shares up to a maximum of three (3) shares per acre (Negotiating Report Section D.2.h.) These contracts would be based on shares that have been turned in to the City and terms of the Sales Agreement are complete or the City has purchased shares outright. This type of transaction would not receive City approval.
Shares turned into City for which no Sales Agreement was signed. These shares do not have a commitment for a Contract. The City has agreed to purchase all shares of this type for $225 per share. Shareholders may transfer water entitlement from one parcel of land to another belonging to them (Negotiating Report Section D.4.h). City will not approve transfer of water entitlement to land not owned by shareholder.
Transfer of Contract for Delivery of irrigation water from one parcel of land to another parcel of land. The City will not allow the transfer as the Contract is appurtenant to the described parcel.
Adopted by Board of Public Utilities: Board Resolution No.
Affective Dat City Council: Council Resolution No.
City of Riverside 7-1
Public Utilities Department Discontinuance and Restoration of Water Service WATER RULE 7
DISCONTINUANCE AND RESTORATION OF WATER SERVICE
A. CUSTOMER'S REQUEST FOR SERVICE DISCONTINUANCE
When Customers desire to terminate their responsibility for service, they shall give the Utility not less than two working days' advance notice of their intention, state the date on which they wish the termination to become effective and provide access to the water meter. A field visit service charge will be assessed for each additional trip (after original attempt to turn service off) required to complete the turn-off request.
If a new application is not made for service, and the water meter serves more than one Premises, and Premises are occupied, the Utility will read the meter on the date requested and notify the occupants of their rights by posting of a 15-day notice, except as otherwise stated in this Rule. Any resident has the right to prevent this discontinuance by applying for service to the master meter in their own name.
Responsibility for service, for any Customer making application, will begin with that date and reading. There will be a charge for posting of the notice which will be the liability of the Customer making application.
Customers may be held responsible for all services furnished at the Premises until two working days after receiving a request for discontinuance of service by the Utility or until such time as the Utility has received an application for new service, provided access is available.
In the event access is not provided, the Customer discontinuing shall be held liable for all consumption until access is provided.
B. DISCONTINUANCE FOR UNSAFE EQUIPMENT
Service Detrimental to Other Customers
The Utility shall not provide service to any Premises where the use or connections made may be detrimental to the water service rendered by the Utility to other Customers or to the Utility's facilities.
C. DISCONTINUANCE FOR USE OF WATER WITHOUT APPLICATION
Use of Water Without Application For Service
When a new occupant who has not applied for water service, takes possession of a Premises and finds the water service turned on, the occupant shall notify the Utility of such findings within one working day.
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside 7-2
Public Utilities Department Discontinuance and Restoration of Water Service In the event the occupant turns on the water service, or fails to notify the Utility of finding the water service turned on within one working day of occupancy, the occupant will be billed for consumption back to their move in date and the owner shall be billed for any unresolved usage. If the Premises are unoccupied, or the Utility has not been notified of a new tenant by the owner, property manager, occupant or other representative of the owner, and water service is in use, the owner of the property shall be held responsible for payment of the bill. It is the responsibility of the owner to verify that the utility service has been transferred into the name of the new occupant and to settle disputes of responsibility between the occupant and the owner.
In the event that the occupant is charged for usage where the amount charged will be determined by the Utility, the amount billed will be based upon either the meter reading or on the basis of the estimated consumption for the length of time service was received by the occupant without proper application.
When the Utility finds that water is being used without proper application, the Utility may terminate the service without further notice. Any amount due in excess of the amount billed to the occupant shall be billed to the owner.
Only authorized Utility personnel are permitted to turn the service on at the meter. If the occupant restores water service, a self-restoration fee may be imposed.
D. DISCONTINUANCE FOR NONPAYMENT OF BILLS
1. Past Due (Delinquent) Bills
Bills will be considered past due (delinquent) if not paid within 19 days after the date of mailing. Reference PUC 10010.1(a)
2. Discontinuance of Service Notice
When a bill for water service has become past due and a discontinuance of service notice has been issued, service may be discontinued if the bill is not paid within the time required by such notice. A Customer's deposit to establish credit will not be used as payment to avoid discontinuance of service.
Reference PUC 10010.1(a)
If a bill is past due as set forth in Section 1 above, a Customer's service may be discontinued for nonpayment of a bill provided the Utility first gives a discontinuance of service notice to the Customer at least ten (10) working days prior to the proposed discontinuance. Such ten-day period shall not commence until five (5) working days after the mailing of the notice. However, in no case shall residential service be discontinued for nonpayment until payment has been delinquent for at least sixty (60) calendar days. No less than seven (7) working days before discontinuation of service for nonpayment, the Utility shall contact the Customer named on the account by telephone or provide written notice. If the Utility is unable to contact the Customer by mail or telephone, the Adopted by Board of Public Utllities: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside 7-3
Public Utilities Department Discontinuance and Restoration of Water Service Utility will provide a notice of imminent discontinuation of service for nonpayment. There shall be a charge for posting this notice of termination at the Premise. Notwithstanding the foregoing, residential Customers who are delinquent under the terms of an amortization agreement shall be subject to disconnection procedures required by State law.
Reference PUC 10010.1(a), HSC 116908 (a)(1)
Any residential Customer who has initiated a complaint or requested an investigation within 5 working days of receiving a contested bill shall not have service discontinued for nonpayment during the pendency of an investigation.
Customer may be required to pay an estimated bill per Rule No. 21.
Reference PUC 10010. (c)
Discontinuance of Residential Service Dangerous to the Health of the Customer
The Utility will not terminate residential service for nonpayment upon certification by a primary care provider that said termination will be life threatening and the Customer is financially unable to pay for service within the normal payment period and is willing to enter into an amortization agreement with the Utility for the delinquent amount due.
Reference PUC 10010. (3), HSC 116910 (a)
4. Inability to Pay Residential Utility Bill
Any residential Customer who has, within 13 days of mailing the Urgent Notice, made a request for an extension of the Payment period of a bill asserted to be beyond the means of the Customer to pay in full during the normal period for payment, shall be given an opportunity for review of the request by a review manager of the Utility. The review shall include consideration of whether the Customer shall be permitted to amortize the unpaid balance of the account over a reasonable time, not to exceed 12 months.
Reference PUC 10010. (c), HSC 116910(a)
A Customer shall not have utility services discontinued for nonpayment if they are complying with an amortization agreement entered into with the Utility, provided the Customer also keeps current their account for utility services as charges accrue in each subsequent billing period.
Reference PUC 10010. (c)
However, service may be terminated to any Customer who does not comply with an installment payment agreement or keep current the account for utility services as charges accrue in each subsequent billing period.
Reference PUC 10010. (c), HSC 116910(b)
The Utility shall make available to Customers, upon request, information regarding agencies and/or organizations that may provide financial assistance.
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside 7-4
Public Utilities Department Discontinuance and Restoration of Water Service Reference PUC 10010.1 (d)(6)
If a residential Customer fails to comply with an amortization agreement, the Utility shall not terminate service without giving notice to the Customer at least five (5) working days prior to termination of the conditions the Customer is required to meet to avoid termination, but, such notice shall not entitle the Customer to further investigation by the Utility.
Reference PUC 10010.1 (e), HSC 116910 (b)(3)
Discontinuance for Unpaid Utility Bill at a Previous Address A Customer's service may be discontinued for nonpayment of a bill for service previously rendered them at any location served by the Utility provided such bill is not paid within 13 days after presentation of an Urgent Notice.
Reference PUC 10010.1(a)
In no case will residential service be discontinued because of nonpayment of bills for non-residential service.
6. Discontinuance of Service when Trying to Avoid Payment of Utility Bill The Utility may discontinue or deny service for nonpayment of a bill where the Utility determines that the same person or persons continue to occupy the service address. However, the Utility will not deny service to the renters of a Premises whose owners or prior unrelated tenants have delinquent unpaid bills.
7. Discontinuance of Service Due to Fraud
The Utility may refuse or discontinue service if the acts of the Customer or the conditions upon the Customer's Premises are such as to indicate an intent to defraud the Utility.
8. Discontinuance of Service at More Than One Location
If a Customer is receiving service at more than one location, service at any or all locations may be discontinued if bills for service at any location are not paid within the time specified above, except that a residential service account shall not be discontinued for failure to pay bills for non-residential service.
9. Discontinuance of Service when Utility's Business Office is Closed Service will not be discontinued by reason of delinquency in payment for utility services on any Saturday, Sunday, legal holiday, or at any time during which the business offices of the Utility are not open to the public.
Reference PUC 10011.
Adopted by Board of Public Utilties: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside 7-5
Public Utilities Department Discontinuance and Restoration of Water Service
10. Discontinuance of Residential Service at Individually Metered Detached Single-Family Dwelling, Multiunit Residential Structure, Mobile Home Park, or Labor Camp
This section applies if there is a landlord-tenant relationship between the residential occupants and the owner, manager, or operator of the dwelling.
Reference PUC 10009. (a)
Where utility service is provided to individually metered residential occupants in a detached single-family dwelling, a multiunit residential structure, mobile home park, or permanent residential structure in a labor camp, as defined in Section 17008 of the Health and Safety Code, and the owner, manager, or operator of the dwelling, structure, or park is listed by the Utility as the Customer of record, the Utility shall make every good faith effort, when the account is in arrears, to inform the residential occupants by means of written notice that service will be discontinued.
Reference PUC 10009. (b)
(1) A 10-day notice of discontinuance shall inform the residential occupants of their right to become Customers, to whom the service will then be billed, without being required to pay any amount which may be due on the delinquent account. The notice shall be written in English, Spanish, Chinese, Tagalog, Vietnamese, and Korean, as specified in Section 1632 of the Civil Code.
Reference PUC 10009. (b)
2) The Utility is not required to make service available to the residential occupants unless each residential occupant agrees to the terms and conditions of service and meets the requirements of law and the Utility's Rules and Schedules. However, if one or more of the residential occupants are willing and able to assume responsibility for the subsequent charges to the account to the satisfaction of the Utility, or if there is a physical means, legally available to the Utility, of selectively terminating service to those residential occupants who have not met the requirements of the Utility's Rules and Schedules, the Utility shall make service available to the residential occupants who have met those requirements.
Reference PUC 10009. (c)
(3) The residential occupant must establish credit to the satisfaction of the Utility. However, where a residential occupant is establishing service under the provisions of this section and prior service for a period of time is a condition for establishing credit with the Utility, residence and proo of prompt payment of rent or other credit obligation acceptable to the Utility for that period of time is a satisfactory equivalent.
Reference PUC 10009. (d)
Adopted by Board of Public Utilities: Board Resolution No.
Grecive Day City Council: Council Resolution:
City of Riverside 7-6
Public Utilities Department Discontinuance and Restoration of Water Service (4) Any residential occupant who becomes a Customer of the Utility pursuant to this section whose periodic payments, such as rental payments, include charges for residential water service, where these charges are not separately stated, may deduct from i the periodic payment each payment period all reasonable charges paid to the Utility for water service during the preceding payment period.
Reference PUC 10009. (e)
There will be a trip charge for posting of the field notification.
11. Discontinuance of Service at a Master Metered Multiunit Residential Structure, Mobile Home Park, or Labor Camp.
For discontinuance of service to residential occupants in a multiunit residential structure, mobile home park, or labor camp, as defined in section 17008 of the Health and Safety Code, who are master metered by the Utility, and the owner, manager, or operator of the structure or park is listed by the Utility as the Customer of record, the Utility shall make every good faith effort to inform the residential occupants, when the account is in arrears, to inform by means of written notice, that service will be discontinued.
Reference PUC 10009.1 (a)
(1) A written 15-day notice of discontinuance shall be posted on the door of each residential unit prior to discontinuance; except that, if it is not reasonable or practicable to post the notice on the door of each residential unit, the Utility shall post two copies of the notice in each accessible common area and at each point of access to the structure or structures. The notice shall be written in English, Spanish, Chinese, Tagalog, Vietnamese, and Korean, as specified in Section 1632 of the Civil Code. Reference PUC 10009.1 (a)
The notice will specify:
(a) The date on which service will be discontinued.
(b) That the residential occupants have the right to become Customers, to whom the service will then be billed, without being required to pay any amount which may be due on the delinquent account.
(c) What the residential occupants are required to do in order to prevent the termination of service or to reestablish service. (d) The estimated monthly cost of service.
(e) The title, address, and telephone number of a representative of the Utility who can assist the residential occupants in continuing service.
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside 7-7
Public Utilities Department Discontinuance and Restoration of Water Service (f) The address and telephone number of a legal services project as defined in Section 6213 of the Business and Professions Code, which has been recommended by the local county bar association. Reference PUC 10009.1 (a)
(2) The Utility is not required to make service available to the residential occupants unless each residential occupant or a "representative of the residential occupants" agrees to the terms and conditions of service and meets the requirements of law and the Utility's Rules and Schedules.
However, if one or more of the residential occupants or the representative of the residential occupants are willing and able to assume responsibility for subsequent charges to the account to the satisfaction of the Utility, or if there is a physical means, legally available to the Utility, of selectively terminating service to those residential occupants who have not met the requirements of the Utility's Rules and Schedules or for whom the representative of the residential occupants is not responsible, the Utility shall make service available to those residential occupants who have met those requirements or on whose behalf those requirements have been met. As used herein, "representative of the residential occupants" does not include a tenants' association. Reference PUC 10009.1(b)
(3) Credit must be established to the satisfaction of the Utility. Where prior service for a period of time or other demonstration of credit worthiness is a condition for establishing credit with the Utility, residence and proof of prompt payment of rent or other obligation during that period of time acceptable to the Utility is a satisfactory equivalent.
Reference PUC 10009.1(c)
(4) Any residential occupant who becomes a Customer of the Utility pursuant to this section whose periodic payments, such as rental payments, includes charges for residential water service, where these charges are not separately stated, may deduct from the periodic payment each payment period all reasonable charges paid to the Utility for water service during the preceding payment period.
Reference PUC 10009.1(d)
(5) Where the Utility furnished service under a Residential Rate Schedule to a multiunit residential structure, mobile home park or labor camp, through a master meter, the Utility may not discontinue service in any of the following situations:
(a) During the pendency of an investigation by the Utility of a Customer dispute or complaint. Reference PUC 10009.1(e) (b) When the Customer has been granted an extension of the period for payment of a bill. Reference PUC 10009.1(e)
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside 7-8
Public Utilities Department Discontinuance and Restoration of Water Service (c) For an indebtedness owed by the Customer to any other public agency other than the Utility. Reference PUC 10009.1(e) (d) When a delinquent account relates to another property owned, managed, or operated by the Customer.
Reference PUC 10009.1(e)
(e) When a public health or building officer certifies that disconnection would result in a significant threat to the health or safety of the residential occupants or the public.
Reference PUC 10009.1(e)
There will be a trip charge for posting of the field notification.
12. State law pertaining to Discontinuance of Service
Should there be a conflict between this Rule No. 7 and State law, as amended from time to time, State law shall govern, except to the extent that the provisions of this Rule are more favorable for the Customer or a residential occupant.
E. RESTORATION OF SERVICE
Amount Due to Restore Service
All past due bills at the time of reconnect, applicable service charges, and deposit shall be paid by Customer prior to restoration of service. In addition, the City and/or Utility may require inspection of water facilities prior to reconnect at the Customer's expense. After hours for fee assessment purposes are hours outside the following windows: 8AM to 4PM Monday through Friday and 9AM to 1PM Saturdays and legal holidays.
2. Re-establishment of Service Deposit
If service is terminated, or if a notice of discontinuance has been given, the Utility will require the Customer to pay a deposit or an additional deposit up to an estimated average three month bill.
Reconnect Service Charge
All charges are cumulative and each trip to the Premises will incur additional charges. In order to restore service discontinued under the provisions above, there shall be a charge for the expense of turning the service on.
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside 7-9
Public Utilities Department Discontinuance and Restoration of Water Service
4. Self-Restoration Service Charge
In the event anyone has turned on the water service after it has been turned off for any of the above reasons, there shall be a charge in addition to other amounts due from the Customer before service is restored.
Administrative Fee
If water diversion occurs, an additional service charge will be assessed, as prescribed in Rule No. 19, WATER DIVERSION.
Water Meter Removal
If the meter is removed, a service charge will be billed in addition to other amounts due.
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution:
Effective Date:
City of Riverside
Public Utilities Department
SCHEDULE WA-5
FIRE PROTECTION SERVICES AND FIRE HYDRANTS
FIRE PROTECTION SERVICE
APPLICABILITY:
fire protection service. This schedule is not applicable to Fire Protection Services installed with an above ground detector assembly. Above ground detector assemblies shall be maintained by the Customer anc st of maintenance, repair, replacement and testing of the above ground detector assembly shall be th splity of the Custome
TERRITORY:
City of Riverside and contiguous area.
RATES:
Size of Monthly Charge Monthly Charge
Service Inside City Outside City
4-inch $212.00 $224.00
6-inch 242.00 254.00
8-inch 272.00 284.00
10-inch 302.00 314.00
12-inch 332.00 251.00
FIRE HYDRANT AVAILABILITY
APPLICABILITY:
Applicable to all Utility fire hydrants outside the service area of the City of Riverside Fire Department. Fire hydrants shall be maintained by the Utility and cost of maintenance repair and replacement of fire hydrants shall be paid by the fire districts providing fire protection service or by the Customer receiving benefit of fire hydrant availability.
TERRITORY:
Contiguous area to City of Riverside.
RATES:
Fire Districts Monthly Charge
Inside Corona City Limits $10.71 per fire hydrant
Riverside County Area 1.36 per water service
SPECIAL CONDITIONS
1. Water Conservation Surcharge
The rates and charges above are subject to a surcharge (Water Conservation Surcharge) as dopted via City Council Resolution No. 22675 on April 22, 2014 and such surcharge as in effer om time to time. The Water Conservation Surcharge will be applied to the Customer's tot water usage charge including without limitation the quantity rates, customer and minimun charge for the applicable billing period
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution No.
Effective Date:
City of Riverside
Public Utilities Department
Schedule WA-5 Fire Protection Services and Fire Hydrants -2-
2. Applicable Rate Schedule
a. Applicable Rate Schedule
For Customers applying for service at an existing service address, the Utility will assign a water rate schedule based on the characteristics of the service address. The Utility will presume that any water rate previously assigned to that service address is the appropriate schedule, unless the Customer requests a review for another applicable rate schedule, rate, or optional provislon. In certain situations when a Customer does not qualify for a water rate previously assigned to that service address, the Utility will assign the applicable rate to the Customer. The Utility assumes no responsibility for advising the Customer of lower optional rates under existing schedules available as a result of the Customer's changes to the characteristics of the service address. b. Change of Rate Schedule
A change to the applicable rate schedule may be made if the Utility determines that the Customer no longer qualifies for the assigned rate schedule. The change will become effective for service rendered after the next regular meter reading following verification and approval by the Utility of such eligibility. Any change in rate schedules pursuant to this section shall be made prospectively only.
3. Water General Fund Transfer
The Water General Fund Transfer is a component of every customer's water bill, and is a transfer of up to 11.5% of revenues from the Water Fund to the City's General Fund. On June 4, 2013, the voters of the City of Riverside approved the Water General Fund Transfer as a general tax, pursuant to Article 13.C of the California Constitution.
Adopted by Board of Public Utilities: Board Resolution No.
Approved by City Council: Council Resolution No.
Effective Date:
City of Riverside
Public Utilities Department
Water Utility Appendix A-1
APPENDIX A
WATER FEES AND CHARGES SCHEDULE
APPLICABILITY
Applicable to all classes of service as provided in accordance with the Water Rules and Regulations. Does not supersede any fees and charges listed in the rules which are not
RULE DESCRIPTION FEE AMOUNT
NUMBER
4 Minimum Deposit/Residential (Initial Service) $40.00
4 Minimum Deposit/All other classes Twice the estimated average bill or $40.00 minimum
4 Minimum Deposit/Reconnection/All Classes Three times the estimated of Service average monthly water bill or
$40.00 minimum
4 Service Turn-on Charge (Same fee applies $48.50 Next day whether turning on one service or both $62.75 Same day
$77.00 After hours
5 Non-Sufficient Funds (NSF) Processing Fee
Initial NSF Fee $30.00
Subsequent NSF Fee (Each) $45.00
6 Meter Test/Second Request $328.75 Paid in advance
Within One Year Period (If error is found, fee will be
refunded)
6 Re-Read/second request within six months $48.50 (If error is found, fee will be waived)
7 48-Hour Field Notification (Master Metered $31.75 plus $6.50 per each Accounts receive Multi-Unit notification) additional notice per account Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside
Public Utilities Department
Water Utility Appendix A-2
RULE DESCRIPTION FEE AMOUNT
NUMBER
7 Trip charge for additional field visit $34.50
(Cut-off, non-pay, etc.)
7 Service Reconnection Charge (Same fee $48.50 Next day applies whether reconnection for CONP $62.75 Same day
one service or both $53.75 Same day (Low-Income)
$77.00 After hours
7 Additional Fee will be added to Reconnect Time and Material will be added Service Order if Customer has self-restored to applicable Service Order Fee 7 Reconnection Charge/Additional-Meter $277.00 plus Material Removed
8 Temporary Water Service Time and Material
8 Temporary Water Service-Fire Hydrant
Water Meter
- Processing Fee $ 88.75 per meter
- Deposit $2,000.00 per meter
8 Set, Move or Relocation of Temporary Fire Time and Material Hydrant Water Meter
8 Failure to Return Meter to Meter Shop for Schedule WA-2.B.3 Reading per month
8 Annual Testing of City Department Water $55.25 per meter Meters
8 Removal of Fire Hydrant Operating Nut $55.25
10 Covenant & Agreement Charge - $553.00
Preparation Charge
Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside
Public Utilities Department
Water Utility Appendix A-3
RULE DESCRIPTION FEE AMOUNT
NUMBER
10 Backup Facility Capacity Charges
¾ inch $ 2,250.00
1 inch $ 5,060.00
1½ inch $ 9,560.00
2 inch $ 14,400.00
3 inch $ 25,300.00
4 inch $ 39,380.00
6 inch $ 73,130.00
8 inch $108,000.00
10 inch $135,000.00
10 Elevation Fee (Per Acre or Portion Thereof)
Nominal Zone Designation
$ 0.00
925 $ 0.00
1037 $ 340.00
1080 $ 420.00
1100 $ 600.00
1160 $ 780.00
1200 $1,000.00
1300 $1,380.00
1400 $1,720.00
1600 $2,480.00
$2,730.00
1750 $3,090.00
10 Distribution System Fee (per lineal foot) $49.00
10 Plan Check Fee Time and Materials with Deposit
10 Sungold Agreement $40.00
Elevation Fee - 1100 feet and higher
(per acre)
10 Inspection Fees $2,281.00 plus $2.50 (per lineal
foot of pipeline)
10 Fire Hydrant (for each) $76.25
Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside
Public Utilities Department
Water Utility Appendix A-4
RULE DESCRIPTION FEE AMOUNT
NUMBER
10 Service Inspection (for each)
1 inch $ 34.00
2 inch $ 51.00
4 inch or larger $407.25
10 Initial Pressure Test (for each) . $1,324.00
10 Pressure Test (for each after initial) (re-test) $311.00 10 Extended Construction $2.50 per lineal foot
10 Additional Inspection Visits $102.00 per hour
10 For each wet tap witnessed by Water Utility $407.00
Inspectors
10 Water Service Connections for Individual $500.00
Premises of 4" or larger, Cash Refundable
Bond (per connection) to guarantee final
completion by private contractor
10 Water Meter Charges
¾ inch Meter $ 97.50
1 inch Meter $109.00
1 ½ inch Meter $276.00
2 inch Meter $322.00
3 inch Meter or Larger At Estimated Cost of Installation 10 Water Main Oversizing Reimbursement
8 inch Standard - 12 inch Oversized $ 24.00 per lineal foot 12 inch Standard - 16 inch Oversized $193.00 per lineal foot 10 Water Supply Assessment $5,670.00
10 Plan Check for Building and Public Works $45.50
11 Bacteriological Testing for Water Meters $438.00
2 inch and Larger Flushing Testing Charge
Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
City of Riverside
Public Utilities Department
Water Utility Appendix A-5
RULE DESCRIPTION FEE AMOUNT
NUMBER
11 Request for larger meter upon lateral
replacement
¾ inch to 1 inch $73.75
(in addition to any applicable Backup Facility
Capacity Charges)
11 Request for larger meter. No lateral $61.75
replacement (in addition to any other
applicable charges)
11 Relocation of fire hydrants Time and Material
11 Repair of Water Facilities Time and Material plus $122.00 11 Water Service Connection Charges
¾ inch Meter (2-lane/residential street) $3,277.00 plus Estimated Cost of Paving
¾ inch Meter (4-lane/non-residential) $5,265.00 plus Estimated Cost of Paving
1 inch Meter (2-lane/residential street) $3,288.00 plus Estimated Cost of Paving
1 inch Meter (4-lane/non-residential) $5,277.00 plus Estimated Cost of Paving
1½ inch meter Time and Material
2 inch meter Time and Material
3 inch meter Time and Material
11 Fire Service Connection above-ground At Estimated Cost of Installation (2 inch and larger)
11 Fire Flow Test Data $191.00
13 Test/Repair of Backflow Prevention Assembly $537.50 plus parts Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date:
•
City of Riverside
Public Utilities Department
Water Utility Appendix A-6
RULE DESCRIPTION FEE AMOUNT
NUMBER
14 Turn-on and Turn-off of Water Service for
Repair by Customer
Monday through Friday
6:00 pm to 10:00 pm $ 67.25
10:00 pm to 7:30 am $128.00
Weekend and Holidays
3:30 pm to 7:30 pm $ 67.25
7:30 pm to 7:30 am $ 67.25
16 Gage Canal Company (Contracts Only) $169.00
19 Cost to investigate Water Diversion The higher of $53.75 plus Material or Time and Materials
20 Appointment based meter reads $28.50
20 Monthly rental of Remote Metering to resolve $34.75
access issues
Adopted by Board of Public Utilities: Board Resolution
Approved by City Council: Council Resolution
Effective Date: