DESIGN-BUILD AGREEMENT
FOR
DIGESTER 5 REHABILITATION
RFP No. 2222
This Agreement for Construction ("Agreement") is entered into on this _, by and between the CITY OF RIVERSIDE, a California charter city and a municipal corporation ("City") and Anaergia Technologies, LLC, a Delaware limited liability company, 705 Palomar Airport Rd, Ste 200, Carlsbad, CA, 92011, State Contractor's License No. 1038691, ("Design-Build Entity"). Hereinafter, the City and the Design-Build Entity nay be referred to collectively as the "Parties.

ARTICLE 1 - SCOPE OF WORK AND DESIGN SERVICES

1.1 Scope of Work. Design-Build Entity shall furnish all engineering design, labor, equipment and materials for, and perform the work of Digester 5 Rehabilitation located at 5950 Acorn Street, Riverside, CA, 92504, which is covered in Design-Build Entity's Scope of Work (the "Work").

1.2 Contract Documents. Design-Build Entity shall perform the Work in accordance with the provisions and requirements of the following Contract Documents:
(1) Request for Proposals No. 2222;
(2) Design-Build Entity's Proposal dated February 3, 2023; (3) Design-Build Entity's Scope of Work attached hereto as Exhibits "B-1" through "E"; (4) This Agreement, as signed by the Parties, including Exhibit "A" - Workers' Compensation Certification, and all documents, maps, texts and items referred to in the foregoing documents;
(5) Change Orders and other modifications issued after execution of this Agreement; (6) Permits from the City's Building, Fire, Planning, Public Works and Public Utilities Departments and similar governmental approvals for the Work required by applicable law; (7) The 2021 Edition of the Standard Specifications for Public Works Construction ("Standard Specifications") written by Public Works Standards, Inc., and any special provisions; The specific terms and conditions of this Agreement shall control and have precedence over any contradictory or inconsistent terms or conditions included in any of the Contract Documents and shall be controlling in questions of interpretation. The Design-Build Entity's Scope of Work dated May 10, 2024 shall control and have precedence over any contradictory or inconsistent terms or conditions with the Request for Proposals No. 2222 and/or Design-Build Entity's Proposal dated February 3, 2023.

The Contract Documents are incorporated herein and are intended to be correlative and constitute Design-Build Entity's performance obligations.

1.3. Project Design. City does not intend to contract for, pay for, or receive any design services which are in violation of any professional licensing laws, and by execution of this Agreement, Design-Build Entity acknowledges that City has no such intent. It is the intent of the Parties that Design-Build Entity is fully responsible for furnishing the design of the Project, although the appropriately licensed Design Consultant will perform the design services required by the Contract Documents. Nothing in this article shall create a contractual relationship between such persons and the City.

1.4. Standard of Care. All design Services to be performed by Design-Build Entity, its design consultant, subcontractors, and their employees identified by the Design-Build Entity or other persons approved by the City shall be performed in an expeditious and professional manner using architects, engineers and other professionals properly licensed and duly qualified in the jurisdiction in which the Project is located. The professional obligations of such persons shall be undertaken and performed in the interest of the Design-Build Entity. All design services performed pursuant to this Agreement shall be performed with the degree of skill and learning ordinarily possessed by architects and engineers in good standing in the community regularly engaged in the design and construction of an improvement such as this Project and must apply that knowledge with the diligence ordinarily exercised by reputable architects and engineers under similar circumstances ("Standard of Care").

Interpretation. In the event of any conflict between any of the Contract Documents, the document highest in the order of precedence shall control. The order of precedence shall be the same as that set forth in Section 3-7.2 of the 2021 Edition of the Standard Specifications for Public Works Construction.

1.6 Entire Agreement. This Agreement together with all other Contract Documents represents the entire and integrated agreement between City and Design-Build Entity and supersedes any prior written or oral agreements between them concerning the subject matter contained in the Contract Documents. There are no representations, agreements, arrangements or understandings, oral or written, between the Parties hereto, relating to the subject matter contained in the Contract Documents, which are not fully expressed herein.

ARTICLE 2 - CONTRACT PRICE AND PAYMENT

2.1 Contract Price. City shall pay Design-Build Entity the Contract Price of Nine Million Five Hundred Eight Thousand ($9,508,000) which includes all California sales or use tax and County and City taxes, in consideration for the Design-Build Entity's full, complete and timely performance of all of the Work required by the Contract Documents. The Contract Price includes any Alternative/Additive Bid Items which were awarded with the Contract. 2 In accordance with Section 22300 of the California Public Contract Code, Design- Build Entity may substitute securities for any monies withheld by City to ensure performance of the Contract. Such substitution shall be made at the request and expense of Design-Build Entity.

Securities equivalent to the amount withheld may be deposited with City or with a state or federally chartered bank as escrow agent. Securities eligible for substitution shall include those listed in Section 16430 of the Government Code, bank or saving and loan certificates of deposit, interest bearing demand deposit accounts, standby letters of credit, or any other security mutually agreed to by Design-Build Entity and City.

2.2 Changes to the Contract Price. Design-Build Entity shall not be compensated for any extra materials used or time expended over and above the Contract Price, unless prior written approval for the same has been granted by the City.

2.3 Payment Procedures. Without extending the prompt payment requirements applicable to this project as set forth in California Public Contract Code sections 7107 and 20104.50, within sixty (60) calendar days after City accepts final completion of the work and issues the Notice of Completion, City shall pay Design-Build Entity the amounts City deducted and retained from Design-Build Entity's progress payments, except such sums which are required by applicable law or authorized by the Contract to be further retained. In the event of a dispute between City and Design-Build Entity concerning the amount of final payment due, the City may withhold from final payment, including Liquidated Damages provided forth in the Contract Documents, together with an amount not to exceed 150% of the value of disputed amounts for incomplete or non- conforming work.

ARTICLE 3 - TIME FOR PERFORMANCE

3.1 Date of Commencement/Notice to Proceed. The date of commencement of the Work shall be established in a written Notice to Proceed issued by the City. The City will not issue a Notice to Proceed to the Design-Build Entity until this Agreement, bonds and insurance documents have been executed and/or approved by the City.

Contract Time. Design-Build Entity shall perform the Work in a diligent manner and shall complete all of the Work of the Contract, excluding any Plant Establishment, if applicable, within eighteen (18) calendar months after the date specified to Design-Build Entity in the Notice to Proceed issued by City.

ARTICLE 4 - LIQUIDATED DAMAGES

4.1 Amounts of Liquidated Damages.

4.1.1 Delay in Substantial Completion of the Work. Failure of Design-Build Entity to complete the Work within the time allowed will result in damages being sustained by City. Such damages are, and will continue to be, impracticable and extremely difficult to determine. For each consecutive calendar day in excess of the time specified for the completion of Work and which delay is caused by Design Build Entity, Design-Build Entity shall pay to City, or have withheld from monies due the Design-Build Entity, the sum of Two Hundred Fifty Dollars ($250.00), with 3 a total maximum of 5% of the Contract Price. Execution of this Agreement shall constitute agreement by City and Design-Build Entity that said sum is the minimum value of the costs and actual damage caused by the failure of Design-Build Entity to complete the Work within the allotted time. Such sum is liquidated damages and shall not be construed as a penalty, and may be deducted from payments due Design-Build Entity if such delay occurs.

ARTICLE 5 - CLAIMS AND DISPUTES
Notice of Claims. Design-Build Entity acknowledges and agrees that its failure to submit any claim arising under this Contract, shall constitute a waiver of Design-Build Entity's right to additional compensation and/or extension of time.

5.2 Government Code Claims Procedures. Design-Build Entity further acknowledges that Design-Build Entity must comply with the claims procedures set forth in Government Code sections 900 et seq. prior to filing a lawsuit against the City for any such claim. Failure to submit a Government Code claim shall bar Design-Build Entity from bringing and maintaining a valid lawsuit against the City.

ARTICLE 6 - LOCAL BUSINESS LICENSE, TAXES AND FEES

6.1 Business Tax Certificate and Governmental Approvals. As a condition of the Agreement, Design-Build Entity and all subcontractors shall, during the term of this Agreement, secure and annually renew business tax certificates pursuant to Chapter 5.04 of the Riverside Municipal Code to operate in the City of Riverside, and shall also secure and maintain at all times during performance of the Work, any other licenses, fees, permits or similar Governmental Approvals required by Applicable law.

6.2 Offsets. Design-Build Entity acknowledges and agrees that with respect to any debt which is rightfully owed, or which becomes owed, by Design-Build Entity to City, City reserves the right to withhold and offset said amounts from any payments, refunds or reimbursements owed by City to Design-Build Entity under the Agreement. Notice of such withholding and offset shall promptly be given to Design-Build Entity by City in writing. Without waiving any prompt payment requirements under applicable law, in the event of a dispute as to the amount owed or whether such amount is owed to City, City will hold such disputed amount until either the appropriate appeal process has been completed or until the dispute has been resolved.

ARTICLE 7 - BONDS

7.1 Performance and Payment Bonds. Prior to City's execution of this Agreement, Design- Build Entity shall furnish to the City two (2) duly executed surety bonds using the forms included herein, one (1) as security for the faithful performance of the Contract and one (1) as security for Contract. Both bonds shall be in the amount of one hundred percent (100%) of the Contract Price and shall be subscribed by an Admitted Surety Insurer which is authorized to transact surety insurance business in the State of California with a policy holder's rating of A or higher and a Financial Class of VII or larger. Should any bond or surety become insufficient, Design-Build 4 Entity shall furnish City a new bond within ten (10) days after receiving notice from City. No payments will be due or paid under the Contract until any and all bond deficiencies have been remedied. Design-Build Entity, by execution of this Agreement acknowledges that the bonds are not Contract Documents, but are separate obligations.

ARTICLE 8 - WORKERS' COMPENSATION INSURANCE

8.1 Workers' Compensation Insurance Certificate. By executing this Agreement, Design- Build Entity certifies that Design-Build Entity is aware of and will comply with Section 3700 of the Labor Code of the State of California requiring every employer to be insured against liability for workers' compensation or to undertake self-insurance before commencing any of the Work Design-Build Entity shall comply with Labor Code Section 1861 by signing and filing the workers' compensation certification attached hereto as Exhibit "A" and incorporated herein by reference.

8.2 Evidence of Coverage. Prior to the City's execution of this agreement, Design-Build Entity shall file with the City either 1) a certificate of insurance or self-insurance evidencing that such insurance is in effect, or that Design-Build Entity is self-insured for such coverage; or 2) a certified statement that Design-Build Entity has no employees, and acknowledging that if Design- Build Entity does employ any person, the necessary certificate of insurance will immediately be filed with City. Any Certificate filed with the City shall provide that City shall be given ten (10) days prior written notice before modification or cancellation thereof.

8.3 Carrier Rating. Design-Build Entity's workers' compensation insurance carrier shall be authorized to transact insurance business in the State of California with a policy holder's rating of A or higher and a Financial Class of VII or larger.

8.4 Subcontractor Worker's Compensation Insurance. Design-Build Entity shall require each of its Subcontractors to obtain and maintain for the duration of this Agreement, complete workers' compensation insurance, meeting or exceeding the coverage's and amounts that California law requires.

ARTICLE 9 - DESIGN-BUILD ENTITY'S LIABILITY INSURANCE

9.1 Minimum Scope. Prior to City's execution of this Agreement and Design-Build Entity's commencement of Work, Design-Build Entity shall secure, submit proof of and shall thereafter maintain without interruption, until completion of the Design-Build Entity, such commercial general, automobile liability, professional liability, builders risk and/or installation floater insurance as shall protect Design-Build Entity, its Subcontractors and the Additional Insured's from any and all claims for damages for personal injury, including accidental death, as well as any and all claims for property damage which may arise from or which may concern operations under the Contract, whether such operations be by or on behalf of Design-Build Entity, any subcontractor or anyone directly or indirectly employed by, connected with or acting for or on behalf of any of

9.2 Carrier Ratings. All liability insurance shall be issued by an insurance company or companies authorized to transact liability insurance business in the State of California with a policy holder's rating of A or higher and a Financial Class of VII or larger.

9.3 Minimum Limits. Design-Build Entity shall maintain minimum limits of insurance as follows:

9.3.1 Commercial General Liability: Design-Build Entity's commercial general liability insurance policy shall cover both bodily injury (including death) and property damage (including, but not limited to, premises operations liability, products-completed operations liability, independent contractor's liability, personal injury liability, and contractual liability) in an amount not less than $1,000,000 per occurrence, an aggregate limit for products/completed operations in the amount not less than $2,000,000.

9.3.2 Automobile Liability Insurance: Design-Build Entity's automobile liability policy shall cover both bodily injury and property damage in an amount not less than $1,000,000 per occurrence. All of Design-Build Entity's automobile and/or commercial general liability insurance policies shall cover all vehicles used in connection with Design-Build Entity's performance of this Agreement, which vehicles shall include, but are not limited to, Design-Build Entity owned vehicles, Design-Build Entity leased vehicles, Design-Build Entity's employee vehicles, non-Design-Build Entity-owned vehicles and hired vehicles.

9.3.3. Installation Floater Insurance. Contractor shall obtain, at Contractor's expense, and keep in effect during the term of this Agreement, an Installation Floater for coverage of Contractor's labor, materials and equipment to be used for completion of the work performed under this Agreement. The minimum amount of coverage to be carried shall be equal to the full amount of the Contractor's labor, equipment, materials, or fixtures to be installed, in transit, or stored off-site or on-site during the performance of this Agreement. The policy shall include as loss payee, the City of Riverside, the Contractor, and its sub-contractors as their interest may appear. The City shall not be responsible for the theft of any materials, equipment in the possession and control of Contractor.

9.3.5 Professional Liability.

9.3.5.1 The Design-Build Entity's professional liability policy must 1) Include professional malpractice, errors and omissions; and 2) Provide coverage for claims arising from acts, errors or omissions from professional services performed by or on behalf of Design-Build Entity, its Design Consultants, Subcontractors, or by anyone directly employed by any of them, or by anyone for whose acts any of them may be liable, including liability assumed under and arising from the Agreement. The Design-Build Entity is responsible for collecting professional liability insurance from any of its subcontractor, individual, or consultant which Design-Build Entity hired for the project.

The Design-Build Entity's professional liability policy must provide limits of liability in an amount not less than: one million dollars ($1,000,000) per claim; and two million dollars ($2,000,000) in the aggregate. Design-Build Entity shall be responsible for the full amount of all deductibles/self-insured retention per claim for coverage under the Professional Liability 6 Insurance policy. These minimum amounts of coverage shall not constitute any limitation or cap on Design-Build Entity's indemnification obligation.

The Design-Build Entity shall require that each Design Consultant maintain professional liability coverage. Each Design-Consultant's professional liability policy must provide coverage for claims arising from the negligent acts, errors or omissions from professional design services performed by Design Consultant, including liability assumed under and arising from the Agreement.

Each Design-Consultant's professional liability policy must provide limits of liability in an amount not less than: one million dollars ($1,000,000) per claim; and two million dollars ($2,000,000) in the aggregate. Design Consultant shall be responsible for the full amount of all deductibles/self-insured retention per claim for coverage under the Professional Liability Insurance policy.

9.4 Notice of Cancellation and Renewals. The policies shall not be canceled unless thirty (30) days prior written notification of intended cancellation has been given to City by certified or registered mail (this obligation may be satisfied in the alternative by requiring such notice to be provided by Design-Build Entity's insurance broker and set forth on its Certificate of Insurance provided to City). Design-Build Entity agrees that upon receipt of any notice of cancellation or alteration of the policies, Design-Build Entity shall procure within five (5) days, other policies of insurance similar in all respects to the policy or policies to be cancelled or altered. Design-Build Entity shall furnish to the City copies of any endorsements that are subsequently issued amending coverage or limits within fourteen (14) days of the amendment.

9.5 All Coverages. The insurance policy or policies shall also comply with the following provisions:
a. General Liability: Policies shall include premises/operations, products completed operations, independent contractors, owners and contractors' protection, explosion, collapse, underground hazard, broad form contractual, personal injury with employment exclusion deleted, and broad form property damage.

The policy shall be endorsed to waive any right of subrogation against the City and its subconsultants, employees, officers, agents and directors for work performed under this Agreement.

C. If policies are written on a claims made basis, the certificate should so specify and the policy must continue in force for five (5) years after completion of the Project.

The retroactive date of the coverage must also be listed. d. The policy shall specify that the insurance provided by Design-Build Entity will be considered primary and not contributory to any other insurance available to the City of Riverside. Design-Build Entity shall provide Form No. CG 20010413 or the equivalent to City.
7 e. All policies of insurance shall name the City as an Additional Insured and shall contain the following language: "Solely with respect to work done by and on behalf of the name insured for the City of Riverside, it is agreed that the City of Riverside, and its officers and employees are added as additional insureds under this policy."

9.6 Certificates of Insurance, Additional Insured Endorsements and Deductibles. Prior to execution of the Agreement, and thereafter upon City's request, Design-Build Entity shall furnish City with original certificates of insurance and additional insured endorsements setting forth evidence of all insurance coverage required by this Article. Each certificate and endorsement is to be signed by a person authorized by that insurer to bind coverage on its behalf. The City of Riverside, its City Council and all of its respective officials, officers, directors, employees, managers, commission members, representatives, agents and council members shall be named as additional insured's under each policy.

9.7 Design-Build Entity's Failure to Provide Required Insurance. Failure to maintain required insurance at all times shall constitute a default and material breach. In such event, Design- Build Entity shall immediately notify City and cease all performance under this Contract until further directed by the City. In the absence of satisfactory insurance coverage, City may, at its discretion and sole option: (a) procure insurance with collection rights for premiums, attorneys' fees and costs against Design-Build Entity by way of set-off or recoupment from sums due Design- Build Entity; (b) immediately terminate or suspend Design-Build Entity's performance of the Contract; (c) pay Design-Build Entity's premiums for renewal of Design-Build Entity coverage; or (d) self-insure the risk, with all damages and costs incurred, by judgment, settlement or otherwise, including attorneys' fees and costs, being collectible from Design-Build Entity, by way of set-off or recoupment from any sums due Design-Build Entity. Upon demand, Design-Build Entity shall repay City for all sums that City paid to obtain, renew, reinstate or replace the insurance, or City may offset the cost against any monies that the City may owe Design-Build Entity.

9.8 Verification of Coverage. City shall have the right to obtain, upon request, the Design- Build Entity's insurance policies (including, but not limited to, the declarations page, form list and riders), endorsements or certificates required under the Design-Build Entity Documents.

9.9 Reassessment of Insurance Requirements. At any time during the duration of this Contract, the City may require that Design-Build Entity obtain, pay for, and maintain more or less insurance depending on the City's assessment of any one or more of the following factors, provided that such change will be subject to change order procedures: (1) the City's risk of liability or exposure arising out of, or in any way connected with, Design-Build Entity's services under this Contract; (2) the nature or number of accidents, claims, or lawsuits arising out of, or in any way connected with, Design-Build Entity's services under this Contract; or (3) the availability, or affordability, or both, of increased liability insurance coverage.

9.10 Design-Build Entity's Insurance for Other Losses. The Design-Build Entity and its Subcontractors of every tier shall assume full responsibility for all loss or damage from any cause whatsoever to any tools, Design-Build Entity's (or Subcontractors') employee owned tools, machinery, equipment, or motor vehicles owned or rented by the Design-Build Entity, or the Design-Build Entity's agents, suppliers or Subcontractors as well as to any temporary structures, scaffolding and protective fences.

9.11 No Limitation. Design-Build Entity's maintenance of insurance as required by the Contract Documents shall not be construed to limit the liability of the Design-Build Entity's or its Subcontractors of any tier to the coverage provided by such insurance, or otherwise limit the City's recourse to any remedy available at law or in equity.

9.12 Subcontractors' Insurance. The Design-Build Entity's shall include in all subcontracts a requirement that the Subcontractors of every tier shall obtain and maintain, at a minimum, all insurance required by Articles 9 and 10 of this Agreement except that the limits of liability and deductibles shall be in amounts determined by the Design-Build Entity, based on the degree of hazardous exposure according to the Work performed by each Subcontractor and the size of each subcontract.

Design-Build Entity's shall ensure that any professional engineer retained on its behalf to provide supplemental plans and engineering calculations required in conjunction with the Work, maintains professional liability insurance during the entire term of this Agreement.

Such insurance shall be in the minimum amount of $1,000,000 to protect City from claims resulting from the engineers) activities. This minimum amount of coverage shall not constitute any limitation or cap on Design-Build Entity's indemnification obligations set forth herein.

The City reserves the right to request certificates of insurance from the Design-Build Entity for each Subcontractor. The Design-Build Entity acknowledges that regardless of insurance obtained by its Subcontractors, the Design-Build Entity will be responsible to the City for any and all acts of its Subcontractors.

ARTICLE 10 - INDEMNITY/LIMITATION OF LIABILITY

10.1 Indemnity.
(a) Design-Build Entity shall defend, indemnify and hold harmless City, its elected and appointed officials, officers, employees, agents and volunteers, from any and all actual or alleged third party claims, demands, causes of action, liability, loss, or damage for personal injury or tangible property damage ("Claims") arising from the acts of the Design-Build Entity, its personnel, employees, agents or subcontractors in connection with the performance of this Agreement. This indemnification will not apply in the event a Claim is caused by the sole negligence or willful misconduct of City or its employees or agents. (b) City shall indemnify, defend and hold harmless Design-Build Entity and its directors, officers, employees and agents for, from and against any Claims to the extent of any sole negligence or willful misconduct of City in performance of this Agreement. This indemnification will not apply to the extent that a Claim is caused by the negligence or willful misconduct of Design-Build Entity or its employees or agents.
9 10.2 Limitation of Liability. Neither Party shall be liable to the other for lost revenues or consequential, special, or punitive damages. Aside from the obligations set forth in this Agreement for payment of the contract price, and except for claims of personal injury or property damage covered by insurance or involving Design-Build Entity's gross negligence, the total aggregate liability of each Party to the other shall be limited to one million dollars ($1,000,000.00).

10.3 Subcontractor Requirements. In addition to the requirements set forth hereinabove, Design-Build Entity shall ensure, by written subcontract agreement, that each of Design-Build Entity's Subcontractors of every tier shall protect, defend, indemnify and hold harmless the Indemnitees with respect to Indemnity Claims arising out of, in connection with, or in any way related to each such Subcontractors' Work on the Project in the same manner in which Design- Build Entity is required to protect, defend, indemnify and hold the Indemnitees harmless. In the event Design-Build Entity fails to obtain such defense and indemnity obligations from others as required herein, Design-Build Entity agrees to be fully responsible to the Indemnitees according to the terms of this Article.

10.4 No Limitation or Waiver of Rights. Design-Build Entity's obligations under this Article are in addition to any other rights or remedies which the Indemnitees may have under the law or under the Contract Documents. Design-Build Entity's indemnification and defense obligations set forth in this Article are separate and independent from the insurance provisions set forth in the Agreement and do not limit, in any way, the applicability, scope, or obligations set forth in such insurance provisions. The purchase of insurance by the Design-Build Entity with respect to the obligations required herein shall in no event be construed as fulfillment or discharge of such obligations. In any and all claims against the Indemnitees by any employee of the Design-Build Entity, any Subcontractor, any supplier of the Design-Build Entity or Subcontractors, anyone directly or indirectly employed by any of them, or anyone for whose acts any of them may be liable, the obligations under this Article shall not be limited in any way by any limitation on the amount or type of damages, compensation or benefits payable by or for the Design-Build Entity or any Subcontractor or any supplier of either of them, under workers' or workmen's compensation acts, disability benefit acts or other employee benefit acts. Failure of the City to monitor compliance with these requirements imposes no additional obligations on the City and will in no way act as a waiver of any rights hereunder.

10.5 Withholding to Secure Obligations. In the event an Indemnity Claim arises prior to final payment to Design-Build Entity, the City may, in its sole discretion, reserve, retain or apply any monies due Design-Build Entity for the purpose of resolving such Indemnity Claims; provided, however, the City may release such funds if the Design-Build Entity provides the City with reasonable assurances of protection of the Indemnitees' interests. The City shall, in its sole discretion, determine whether such assurances are reasonable.

10.6 Survival of Indemnity Obligations. Design-Build Entity's obligations under this Article are binding on Design-Build Entity's and its Subcontractors' successors, heirs and assigns and shall survive the completion of the Work or termination of the Design-Build Entity's performance of the Work.
10 10.7 Independent Contractor. Design-Build Entity shall at all times during its performance of the Work retain its status as an independent contractor. Design-Build Entity's employees and agents shall under no circumstances be considered or held to be employees or agents of City and City shall have no obligation to pay or withhold state or federal taxes or provide workers' compensation or unemployment insurance for or on behalf of Design-Build Entity or its employees and agents.

ARTICLE 11 - PREVAILING WAGES

11.1 Public Work Project.

This Project is a public work as defined in California Labor Code Section 1720. Design- Build Entity and all Subcontractors of any tier are required to pay all workers employed in the execution of the Work not less than the general prevailing wage rates of per diem wages and overtime and holiday wages determined by the Director of the Department of Industrial Relations ("DIR") under Section 1720 et seq. of the California Labor Code and implemented by Resolution No. 13346 of the City Council of the City of Riverside. The Director's determination of prevailing rates is available on-line at www.dir.ca.gov/dlsr/DPreWageDetermination.htm and is referred to and made a part hereof; the wage rates therein ascertained, determined and specified are referred to and made a part hereof as though fully set forth herein. Per Senate Bill 854 (2014), Design- Build Entity and subcontractors shall register with the Department of Industrial Relations (DIR) in order to bid and perform public works projects. Design-Build Entity and subcontractors on all public works projects shall submit electronic certified payrolls to the Labor Commissioner and City unless excused from this requirement.

11.2 California Labor Code. Design-Build Entity is aware of and stipulates that Design-Build Entity will also comply with the following sections of the California Labor Code:
a. Section 1775 prescribing sanctions for failure to pay prevailing wage rates; b. Section 1776 requiring the making, keeping and disclosing of detailed payroll records and prescribing sanctions for failure to do so; Section 1777.5 prescribing the terms and conditions for employing registered apprentices;
d. Section 1810 providing that eight hours of labor shall be a day's work; and e. Section 1813 prescribing sanctions for violations of the provisions concerning eight-hour work days and forty-hour work weeks.
f. Sections 1725.5 and 1771.1 requiring all general contractors and subcontractors to be registered with DIR. Registration can be accomplished through the DIR website by using this link: http://www.dir.ca.gov/Public- Works/PublicWorks.html
ARTICLE 12 - MISCELLANEOUS

12.1 Non-Discrimination. Except as provided in Section 12940 of the California Government Code, during Contractor's performance of the Agreement, Contractor shall not discriminate on the grounds of race, religious creed, color, national origin, ancestry, age, physical disability, mental 11 disability, medical condition including the medical condition of Acquired Immune Deficiency Syndrome (AIDS) or any condition related thereto, marital status, gender, gender identity, genetic information, gender expression, sex or sexual orientation, military and veteran status, in the selection and retention of employees and subcontractors and the procurement of materials and equipment. Contractor shall also comply with the requirements of the Americans with Disabilities Act in the performance of the Agreement.

12.2 Notice. Whenever any provision of the Contract Documents requires the giving of written notice, including notices, bills, invoices or other documents required or permitted under this Agreement, service shall be sufficient if sent by one party to the other by overnight courier, or by registered, certified or United States first class mail, postage prepaid and addressed as follows:

City Design-Build Entity
City of Riverside Anaergia Technologies, LLC
Attn: Gilbert Hernandez, Director Attn: Legal Department 3900 Main Street [email protected]
Riverside, CA 92522 705 Palomar Airport Road, Suite 200 Carlsbad, CA 92011

12.3 City's Right to Access and Audit Design-Build Entity's Project Documents.

12.3.1 If the Design-Build Entity submits a claim to the City for additional compensation, the City shall have the right, as a condition to considering the claim, and as a basis for evaluation of the claim, and until the claim has been settled, to audit the Design-Build Entity's books to the extent they are relevant. This right shall include the right to examine books, records, documents, and other evidence and accounting procedures and practices, sufficient to discover and verify all direct and indirect costs of whatever nature claimed to have been incurred or anticipated to be incurred and for which the claim has been submitted. The right to audit shall include the right to inspect the Design-Build Entity's plant, or such parts thereof, as may be or have been engaged in the performance of the Work. The Design-Build Entity further agrees that the right to audit encompasses all subcontracts and is binding upon subcontractors. The rights to examine and inspect herein provided for shall be exercisable through such representatives as the City deems desirable during the Design-Build Entity's normal business hours at the office of the Design-Build Entity. The Design-Build Entity shall make available to the City for auditing, all relevant accounting records and documents, and other financial data, and upon request, shall submit true copies of requested records to the City.

12.3.2 The City and/or its authorized auditors or representatives, shall have access to and the right to examine, audit, excerpt, transcribe, and reproduce any of the Design-Build Entity's records for a period of at least three (3) years after termination of the Design-Build Entity and/or Final Payment. Such records include without limitation, journals, ledgers, records of accounts payable and receivable, profit and loss statements, bank statements, invoices, receipts, subcontracts, agreements, notes, correspondence, memoranda, and any documents generated and received in Design-Build Entity's performance of this Contract. Upon written notice by the City, Design-Build Entity shall promptly make all such records available to Owner and/or its authorized auditors or representatives and cooperate with the Owner and its 12 authorized auditors or representatives in examining, auditing, excerpting, transcribing and reproducing the records.

12.4 Venue. Any action at law or in equity brought by either of the parties hereto for the purpose of enforcing a right or rights provided for by this Agreement shall be tried in the Superior Court in Riverside County, State of California, and the parties hereby waive all provisions of law providing for a change of venue in such proceedings to any other county.

12.5 No Estoppel or Waiver by City. No action or failure to act by the City shall constitute a waiver of any right or duty afforded City under this Agreement, nor shall any such action or failure to act constitute an approval of or acquiescence in any breach thereunder, except as may be specifically provided in this Agreement or as may be otherwise agreed in writing. The waiver by the City of any breach or violation of any term, covenant or condition of this Agreement or of any provision, ordinance, or law shall not be deemed to be a waiver of any other term, covenant, condition, ordinance, or law or of any subsequent breach or violation of the same or of any other term, covenant, condition, ordinance, or law. The subsequent payment of any monies or fee by the City which may become due hereunder shall not be deemed to be a waiver of any preceding breach or violation by Design-Build Entity or any term, covenant, condition of this Agreement or of any applicable law or ordinance.

12.6 Signature Authority. The individuals executing this Agreement and the instruments referenced herein on behalf of Design-Build Entity each represent and warrant that they have the legal power, right and actual authority to bind Design-Build Entity to the terms and conditions hereof and thereof.

12.7 Severability. Each provision, term, condition, covenant and/or restriction, in whole and in part, in this Agreement shall be considered severable. In the event any provision, term, condition, covenant and/or restriction, in whole and/or in part, in this Agreement is declared invalid, unconstitutional, or void for any reason, such provision or part thereof shall be severed from this Agreement and shall not affect any other provision, term, condition, covenant and/or restriction of this Agreement and the remainder of the Agreement shall continue in full force and effect.
[signatures on the following page]
13 IN WITNESS WHEREOF, the parties hereto have caused this Agreement to be duly executed on the day and year first above written.

CITY OF RIVERSIDE, a California and Anaergia Technologies, LLC, municipal corporation a Delaware limited liability company By: Yaniv Scherson (May 30, 2024 14:39 PDT)
By:

City Manager
Yaniv Scherson, COO
Attest:

City Clerk
Certified as to Availability of Funds:

Chief Financial Officer
APPROVED AS TO FORM:

By:

Deputy City Attorney
Rev: 11/08/18
14 Exhibit "A"

WORKERS' COMPENSATION CERTIFICATION
I am aware of the provisions of Section 3700 of the Labor Code which require every employer to be insured against liability for workers' compensation or to undertake self- insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the work of this contract.

DATED: (**Insert Name of DESIGN BUILD
ENTITY**|,
By.

Printed Name and Title
(Appropriate Certificate to be attached to Agreement for Construction)

CERTIFICATE
(if Corporation)

STATE OF
SS:

COUNTY OF
I, HEREBY, CERTIFY that during a meeting of the Board of Directors of the _ a corporation existing under the
laws of the State of _ held on _ 20_ - the following
resolution was duly passed and adopted:
"RESOLVED, that _ of the
Corporation, be and is hereby authorized to execute the Agreement for _ between the City of
Riverside and this corporation and that his execution thereof and with the Corporate Seal affixed, shall be the official act and deed of this Corporation." I further certify that said resolution is now in full force and effect.

IN WITNESS WHEREOF, I have hereunto set my hand and affixed the official seal of the corporation this _ day of _, 20
Secretary
(SEAL)
(Appropriate Certificate to be attached to Agreement for Construction)

CERTIFICATE
(if Joint Venture)

STATE OF
SS:

COUNTY OF
I, HEREBY, CERTIFY that during a meeting of the Principals of the _ a joint venture existing under the
laws of the State of _ held on
20 , the following resolution was duly passed and adopted:
"RESOLVED, that
of the Joint Venture, be and is hereby authorized to execute the Agreement for between the City of
Riverside and this joint venture and that his execution thereof shall be the official act and deed of this Joint Venture."
I further certify that said resolution is now in full force and effect.

IN WITNESS WHEREOF, I have hereunto set my hand this _ day of 20 Managing Partner
(Appropriate Certificate to be attached to Agreement for Construction)

CERTIFICATE
(if Partnership)

STATE OF
SS:

COUNTY OF
I, HEREBY, CERTIFY that during a meeting of the Partners of the _ a Partnership existing under the
laws of the State of _ held on
20 _ _ the following resolution was duly passed and adopted:
"RESOLVED, that
of the Partnership, be and is hereby
authorized to execute the Agreement for
between the City of
Riverside and this partnership and that his execution thereof shall be the official act and deed of this Partnership."
I further certify that said resolution is now in full force and effect.

IN WITNESS WHEREOF, I have hereunto set my hand this _ day of 20_
Partner
Exhibit "B-1"

SCOPE OF WORK
Design-Build Entity will provide design-build services for the below scope of work to rehabilitate and reintegrate Digester 5 for return to service (by others) and as set forth in Exhibits B-2 through E, attached hereto and incorporated herein.

Demolition
• Digester Control Building Basement
• Demolish P-6803 and P-6804
• Demolish HE-6801 and HE-6802
• Demolish P-6801 and P-6802
• Demolish associated 6-CS-DI6, 4-HW-DI6
• Digester #5
• Demolish Digester 5 roof
• Demolish biogas piping 6-SG-S6
• Demolish internal draft tubes
• Demolish 14" mixer piping and blind flange
• Demolish abandoned piping to nearest above ground point and cap Mechanical/Equipment
• Install new actuated valve (6" MV41102) in Digester 1-2 Building (in Digester 1 & 2 basement)
• Install Flow Meter FIT 40102 with 2 isolation valves (in Digester 1 & 2 basement) • Install new isolation valves MV41101 Digester 5 mixing header • Install new digester heating pump P41101
• Install new hot water circulation pump p41102 with 3-way valve TWV-41101 • Install new Heat Exchanger HX41101
• Install other associated valves and instruments, as shown in Exhibit B-2 • Install new stainless-steel piping from digester roof to new condensate trap • Install 2 new activated carbon vessels and associated valves • Install new telescoping valve on overflow structure
• Install 2 service boxes with Anaergia PSM 1200 mixers on new digester roof Structural
• Install new roof on Digester 5
• Repair Digester 5 concrete as outlined in Update of the Integrated Master Plan for the Wastewater Collection and Treatment Facilities, Volume 4, Chapter 11, Appendix 11A:

Digester No. 5 - Food Waste Evaluation, Section 5.1 (June 2019) • Apply coating to top 10 ft of digester wall
Prepare surface per SSPC-SP 13
Shot blast, high-pressure water jet, or mechanical scarification as required to remove contaminants, laitance, weak concrete, and existing coatings • ICRI Concrete Surface Preparation: CSP 4-6
• Air blast and detergent water cleaning to remove loose material, dust, oil and grease
• Apply coating per manufacturer's written recommendations • Acceptable products
• TNEMEC, Series 434, 125 mils, with topcoat Series G435, 15 mils • Sancon Technologies, Sancon 100, 60 to 125 mils
• Zebron Corporation, Zebron, 20 mils min.
• Belzona International Ltd., Belzona 5811, 2 coats, 16 mils min. • Or approved equal
Electrical/Instrumentation
• Demolish Existing MCCR
• Install new Electrical Gear with Breakers to feed Mixer Control Panel • Digester 5 PLC will be located in new PLC Panel
• Install new Mixer Control Panel
• Install new 100A lighting panel to replace existing LP in MCC R • MCC to include, as shown in Exhibit B-2
• 15 HP VFD for Digester Sludge Pump
• 5 HP DOL for Hot Water Recirculation Pump
• 100 AMP Breaker for Mixer Control Panel
• Provide at least 1 blank section for future use
• Connect Digester #5 PLC to Plant SCADA (pull new 6 pair single mode cable between FTU-47 and FTU-46)
• Provide new SCADA screens
• SCADA integration by others
Civil/Yard Piping
• Install 8" BG (HDPE) piping from Digester 5 to the biogas header near the flare - 500 ft • Install 4" Hot Water Supply are Return (2 lines) between Existing Boiler Loop to Digester 5 Control Building Basement - 100 ft each way (200 ft total) • Install 6" Digester Feed from existing digester feed loop between Digester 1-2 to Digester 5 mixing header
• Install 8" Digester 5 Overflow to Digestate Storage Tank 8" DI - 220 ft • Patch trench to meet existing road conditions
Clarifications & Exclusions
• Design-Build Entity has not completed a comprehensive review of existing site conditions or completed all necessary testing. In the event that conditions differ from stated assumptions, an equitable adjustment will be made via change order procedures. • Anaergia to provide Digester 5 start up and re-seeding plan and supervision. Emptying and purging of Digester 5, provision of seed from existing digesters, and operations to execute plan by City.

General
• Proposal is based on overall project schedule of 18 months • Proposal is based on receiving NTP July 2024
• Includes Payment & Performance Bond
• Excludes 3"d party testing (Concrete / Compaction / Welding) Underground/Earthwork
• Proposal includes an Existing Utility Investigation of 5 days of Ground Radar Penetration, and Potholing - 64 each locations for existing utilities shown on as-builts drawings provided.
• We have assumed that all trenching can be excavated using traditional equipment.

Blasting or percussion method (Excavator with hammer) is excluded. • Basis of costing assumed all trench excavation subgrade (Bottom of Trench) to be 5ft below existing asphalt.
• Proposal includes SE 30 Fill Sand for bed and zone around all new underground pipes. • We assumed that all excavated native soil will be re-used for backfill, with concurrence from a geotechnical engineer (City to provide geotechnical engineer). • Proposal includes demolition and replacement of asphalt per City standard drawing no. 453. Basis of costing assumed four inches of asphalt, and placing eight inches of Class 2 Base beneath the new asphalt.
• We have excluded rock excavation, handling of contaminated or hazardous soils, groundwater dewatering, soil import, environmental soil testing, shoring or removal of shoring, cost of water and/or water meter charges, removal or export of hazardous or contaminated waste.

Concrete
• Slab and wall dimensions based on the Repair Digester Concrete per Carollo MEMO, June 2019 FINAL, OPTION 1
• (sheet 26). We have included a marked up drawing showing detailed size assumptions. • Edge of slab at 9'-0" from interior face of existing digester wall and slab thickness scaled to 1'-3".
• Top of wall at 11'-0" from top of slab 1'-3" thick and wall thickness scaled to 1'-0". • Drill & epoxy #6 rebar dowels: 15 dowels per row; 1'-6" spacing at wall radius; 157 rows X 15 = 2,355 dowels.
• Ероху HIT-RE 500 V3, per HILTI App calculator, and 16.9 fl oz cartridges: #6 rebar, 10" deep, 10 cartridges/100
• (+10% waste).
• Use 5000 psi water pressure washer to clean existing concrete and remove laitance. (No Sandblasting included)
• Mixer Post supports (Anaergia Markups 1/18/2024): 2 each, 3'Dia × 1.5'H, D&E #6 @ 12"o.c. & 10" emb.
• Pump Equipment Pads (Anaergia Markups 1/18/2024): 2 each, 5'Lx2.5'Wx0.5'H, D&E #6 @ 12"o.c. & 10"emb.
• We have assumed 200 Ib/cy for reinforcing steel at a cost of $2.00/lb installed Equipment
Installation of the following equipment:

Digester #5 Upgrades
Item P&ID Sheet Tag No. lty
Electric Actuator for valve connecting existing 1 MV-41102 1 piping in Dig 1-2 Control Building
Flow Indicating Transmitter 1 FT-40102 1
Three-Way Safety Selector Valve 1 TWV-41102 1
Combination Biogas Pressure Relief Valve/Flame PSV-41101/2 2 Arrestor Assemblies
Condensate Trap Inlet Isolation Valve 1 MV-41107
Condensate Trap Bypass Valve MV-41108
Condensate Trap 1 TRP-41101
Condensate Trap to Drip Trap Isolation Valve MV-41110
Drip Trap TRP-41102
Drip Trap Drain Isolation Valve (this valve is an 1 MV-41121 1 integral part of the drip trap and may be an
automated float valve))
Condensate Trap Discharge Isolation Valve MV-41109
Biogas Line Isolation Valves 1 MV-41133 1
Level Indicating Transmitter Isolation Valve MV-41130 1 Level Indicating Transmitter LIT-41101 1
Biogas Discharge Line Isolation Valve 1 MV-21125 1
Biogas Discharge Line Pressure Transmitter 1 MV-41106 1 Isolation Valve
Biogas Discharge Line Pressure Transmitter 1 DS-41101 1 Diaphragm Seal
Biogas Discharge Line Pressure Transmitter 1 PIT-41101 1 Biogas Insertion Flow Transmitter Isolation Valve 1 MV-41103 Condensate Trap Flow Indicating Transmitter FIT-41103
Digester Mixers MX411-1/2 2
Digester Mixer Service Boxes SB-41101/2 2
Digester Mixer Service Box Pressure Equalization MV-41131/32 2 Isolation Valves
Digester Roof 1 R-41101 1
Digester Overflow Box Level Transmitter 1 LIT-41102 1
Digester Overflow Box Telescoping Valve 1 TSV 41101 1
Digester #5 Heating System Upgrades
Item P&ID Sheet Tag No. lty
Heating Loop Sludge Inlet Valve 2 MV-41103
Heating Loop Sludge Recirculation Pump Inlet 2 MV-41111 1 Isolation Valve
Heating Loop Sludge Recirculation Pump 2 P-41101 1
Heating Loop Sludge Drain Valve 2 MV-41113 1
Heating Loop Sludge Line Annuar Ring Type 2 DS-23001 1
Seal
Heating Loop Pump Discharge Pressure Switch 2 MV-41116 1 Isolation Valve
Heating Loop Pump Discharge Pressure Switch 2 PSH-41101 1 Heating Loop Pump Discharge Pressure Gauge 2 MV-41117 1 Isolation Valve
Heating Loop Pump Discharge Pressure Gauge 2 PI-41101 1 Heating Loop Sludge Recirculation Pump 2 MV-41112 1
Discharge Isolation Valve
Heat Exchanger Sludge Inlet Temperature 2 TIT-41101 1
Indicating Transmitter
Heat Exchanger Sludge Inlet Isolation Valve 2 MV-41112
Heat Exchanger 2 HX-41101
Heat Exchanger Sludge Discharge Temperature 2 TIT-41101 Indicating Transmitter
Heat Exchanger Sludge Discharge Isolation 2 MV-41115 1
Valve
Heating Loop Sludge Flow Indicating Transmitter FIT-41101 1 Heating Loop Sludge Discharge Isolation Valve 2 MV-41120 1 Hot Water Line Inlet Isolation Valve 2 MV-41122 1
Hot Water Line Three-Way Diverting Valve 2 TWV-41101 1
Hot Water Circulation Pump 2 P-41102 1
Hot Water Line Temperature Indicating 2 TIT-41103 1
Transmitter
Hot Water Line Heat Exchanger Inlet Isolation 2 MV-41119 1 Valve
Hot Water Line Return Line Isolation Valve 2 MV-41124 1 Digester #5 Upgrades - Additional Items
Item P&ID Sheet Tag No. lty
Biogas pressure Relief Line Activated Carbon 1 MV-41126/7 2 H2S Vessel Inlet Isolation Valves
Activated Carbon Vessels 1 AC-41101/2 2
Activated Carbon H2S Vessel Discharge Isolation 1 MV-41128/9 2 Valves
Painting & Coating
• Concrete Coating of upper 10' of the Digester 5 wall, per following requirements:
• Prepare surface per SSPC-SP 13
• Shot blast, high-pressure water jet, or mechanical scarification as required to remove contaminants, laitance,
• weak concrete, and existing coatings
• ICRI Concrete Surface Preparation: CSP 4-6
• Air blast and detergent water cleaning to remove loose material, dust, oil and grease • Apply coating per manufacturer's written recommendations • Acceptable products
• TNEMEC, Series 434, 125 mils, with topcoat Series G435, 15 mils • Sancon Technologies, Sancon 100, 60 to 125 mils
• Zebron Corporation, Zebron, 20 mils min.
• Belzona International Ltd., Belzona 5811, 2 coats, 16 mils min. • Or approved equal
• We have included an allowance of $51,000 for field coating of pipe & equipment Piping
• We have included detailed assumptions on the attached marked up site plan. • We have excluded the purchase of all valves (by Anaergia), WML to install them only • We have included an allowance of $20,000 for pipe insulation exposed HWR & HWS lines (no insulation on
Electrical
• See quote provided by Southern Contracting with list of inclusions/exclusions • No underground ductbank is included, assuming that conduits can be run in existing concrete trench between Digester No. 3 Bld & No. 4 Building • MCC 5 as quoted; submittals 8-12 weeks and manufacturing lead times estimate of 35-37 weeks.
• This proposal is based on stainless steel conduit support and retention systems and PVC-coated RGS conduit systems
• This proposal assumes digester 5 walls and roof are suitable for mechanical wedge anchors and that conduit can be run across digester 5 roof to equipment connection points.
• This proposal accounts for testing of existing feeders for MCC to be replaced, and assumes reuse of those feeders for new MCC.
• The concrete trough connecting control building #3 and digester #1/ digester #2 control building is assumed to have room enough for additional conduit indicated to be run there.
• Instruments, mixer control panel (MCP), mixers and service boxes to be provided by Anaergia; PLC and
• SCADA screens to be furnished by WML
• Digester 5 PLC Panel to include:
• Freestanding NEMA 3R Enclosures (2-Sections)
Main Circuit Breaker
• Surge Protection Device 'SPD'
• 24VDC Power Supply
• Distribution Breakers as Required
• Operator Interface Terminal 'OIT' (Magelis Harmony)
• (2) Programmable Logic Controller 'PLC" (Modicon M580) Hot Standby Unmanaged Ethernet Switch
Fiber Patch Panel
Uninterruptible Power Supply 'UPS'
• GFCI Receptacle
Panel Light & Switch
Panel Fan Kit
Panel Heater & Thermostat
Terminal Blocks, Relays & Nameplates as Required
Engineering (Submittals and O&M Manuals) Interconnection Wiring Diagrams. • PLC & OIT Programming (Modicon M580)
• Networking & Telemetry: Ethernet Switch Configuration • Manufacturing Services
• Field Services (Start-Up & Commissioning of Provided Equipment) Digester No. 4 Building Mechanical - ALLOWANCE
• We have priced the work in this area as an allowance - pricing can be adjusted based on final design
• No detailed design is available and exact pipe routing could not be determined • The exact pipe routing will need to be field verified as there are many existing lines, conduits and obstructions that will need to verify during the engineering phase and be worked around.
• We have included 45 shifts of a 4 man pipe crew and approximately $88,000 in material costs
Digester No. 5 Epoxy Injection and Xypex Waterproofing Coating - ALLOWANCE • We have priced this work as an allowance - pricing can be adjusted based on final design • Per the Carollo Report: We included costs for 200 LF of Epoxy Injection. • The Carollo Report also discusses Xypex coating: We included costs for Xypex coating on the interior of the digester: the section of wall above the new concrete wall and below the new coating, approximately 12'-6' section of wall around the circumference (approximately 2,950 SF) - Cost is approximately $80,000 Clarifications and Exclusions
• The Scope of Work is based on the following clarifications and exclusions:
• Equipment & Services by Others (Excluded)
• Fiber Optic Cable
• Fiber Optic Termination and Testing to be performed by others • Typical Equipment & Services Exclusions (Unless Specifically Defined on the Above Scope)
• Local Control Stations
• Junction and Pull Boxes
• Disconnect Switches
• Security Equipment (Cameras, DVRs, Card Readers, Etc.) • Conduit, Field Wire and Tubing
• Basic Trade Materials (Screws, Bolts, Brackets, Stanchions, Sunshields, Anchor Bolts, Etc.)
• Fiber Optic Patch Panels, Fiber Optic Cable, Fiber Optic Cable Testing and Terminations
• 3rd Party Testing, Harmonic Testing / Analysis, Protective Device Coordination Studies, Short Circuit Studies, and Arc-Flash Hazard Analysis / Training
• Electrical Interconnection Wiring Diagrams, ISA Loop Diagrams and Signal Loop Diagrams for Equipment Not Provided by W.M. Lyles System Integration Division or When Specifications Do Not Define the Require for these Specific Professional Services
• Liquidated Damages when Manufacturer or Vendor Timeframe Constraints Occur Outside of the W.M. Lyles System Integration Division's Control
• Video Taping of Professional Services (3rd Party Video Taping is Acceptable)
• Approved Submittals are Considered to Meet the Needs of the Project Specifics Based on the Engineer of Records Review, Comments and Approval
• Requests for Modifications to the Equipment or Professional Services After Submittal Approval Will Require a Change Order Before Any Modifications Occur Regardless of Schedule
Constraints
• Equipment & Services Not Specifically Defined in the Above Scope of Work
Noise Mitigation Equipment and/or Noise Barriers
• Ventilation Equipment and Team Watch Resources for Work Required in Confined Spaces
• Removal, Replacement and/or Relocation of Existing Utilities • Excludes overtime, weekend, holiday work. Based on standard 8-hour workday.

Exhibit "B-2"

PRELIMINARY DESIGN BASIS
Preliminary design documents include:
• Piping and instrumentation diagram
Equipment list
• Electrical load and motor load list
Instrument list
• Valve list
• Electrical Layout Drawing (Conceptual)
• Digester 5 MCC R diagram
• Site Layout Drawing (Conceptual)

EXISTING FEEDER FOR ESTIMATION ONLY

NEW MCC
400A

CABLE SHALL BE THWN
ALL CONDUCTORS SHALL HAVE SLIP ON WIRE TAGS.

VFD FVNR [EVNR [с/в 4. PROVIDE CLASS 1 DIV 1 DISCONNECTS) AND CONTROL ¼ 15kVA JBOX(S) FOR MIXER

5. PROVIDE ELECTRICAL TESTING ON 400A FEEDER CABLE FROM 120/240V 1ø DISTRIBUTION STATION W TO MCC 5 TO evaluate CABLE LT-3 • 30 CIRC. CONDITON AND FITNESS FOR CONTINOUS OPERATION

6. MIXER PANEL MCP-411 FURNISHED BY ANAERGIA
MPC
P-41101 P-41102 MCP-411 EH-6801

HEATING HW MIXER MCP (EXIST)

PUMP PUMP EXH FAN
4#10 4#12 3#2+#8 4#12
1-1/4"
MCC-R MCP-411
NEW MIXER MCP-411 POWER PLC MIXER MPC
100A
VFD c/B MIXER SENSORS
CONTROLS • MIXER POWER
AUMA POWER SEE E-2 FOR

SEALS A CONDUCTOR

DETAILS

NF GLAND SEALS

CLON TH

CORD(S)
MX-41101 SB-41101 MX-41102 SB-41102 AUMA MIXER
MIXER 1 AUMA 1 MIXER 2 AUMA 2
4#10 4#12 4#10 4#12

MIXER MOP ONE LINE MIXER POWER/CONTROL DIAGRAM
REVE DESCAIPTION DAWN CHKO nATe DESIGNED: DRAVING NUMBER 2/16/2024 commercial or noncommercial purpose except as aushorized in written CHECKED CITY OF RIVERSIDE E-1

ISSUED FOR REVIEW
ogreement with ee other written consent granted ay said company, APPROVED Anaergia his drawing and all related document are orotected in all forms not known or Breaking Barriers to Sustainablity tilin d ench driwin de mileted donminte ayrint he huthread in a writtan PRODICTA ONE LINE agroement with or other written consent granted by said company.

NEW PLC (PROVIDED BY WML)
120V-30A FROM
MCC R 3#10 CONT.
24 00 11 12 13 17 18 19 20
FTU 47
SEE E-4

FOR LOCATION
FTU 46
6 FIBER CAT6 2#14 5#14 2#14 CAT6 10#14 10#14 10#14 3#14 3#14 18/2 OS 3#14 3#14 3#14 SINGLE MCC MCC MCC MIX EV FIT 18/2 OS PIT 18/2 OS 18/2 OS 18/2 OS MODE VFD VFD FVNR 41102 MPC 41101 41102 41102 40102 41101 18/2,05 TO PLANT p- AUMA AUMA 120V 40102 41102 41103 41103
SCADA 41101 LOS 41102 LOS 120V

IN EXIST

CONDUIT STATUS
> <
MCC#5 MIXER DIG 182 BLDG

CIRCUITS BASEMENT

NEW PLC I
MCP-411
CONT.
23 25 26 27 28
NOTES:
2: 18/210S UNS SATES 1 GA SEO PARD MITH OVERALL
SHIELD - BELDEN 1120A OR EQUAL

3. #14GA INDICATES THWN

4. PLANT COMMUNICATION CIRCUIT IS NEW 6 FIBER, SINGLE

MODE INSTALLED IN EXISTING CONDUIT

ON WIRE TAGS
3#14 (2)18/205 18/2 OS 5#14 18/2 OS 18/2 OS 3#14
6#14 6#14 6#14
41102 41103 41101 41101 4110240101
120V 41102 120V MX-41101 MX-41102

SENSORS SENSORS

BASEMENTS FOR ESTIMATION ONLY
15 DESCRIPTION DATE ATTENTION The entire content of this drawing and any related documents are and shall remain DESIGNED: MLB DIANG NUMBER ISSUED FOR REVIEW MLB • Anaergia CHECKED: CITY OF RIVERSIDE E-2 Breaking Barriers to Sustainability INSTRUMENTATION
agreement with or other written consent granted by said company. BLOCK DIAGRAM 20"Typ
20"' TyP
7T
480V • FU
FVNR 1SF 1SF
P-41102 BLANK BLANK
400A 120V
MAIN 1SF 1SF 1SF

BLANK BLANK BLANK
• N.C.

STOP P/L
FVNR 1SF
91' EF-6801 BLANK
HOA @ OL
VFD 1SF N.C.

LT -3
15HP BLANK
P-41101 30 CIRC 15kVA
100A XMFR 1SF
240 1ø BLANK AUX RUN
120/240 RUN N.O. STATUS
1ø P/L

LOS RUN
1SF
BLANK
SEC 1 SEC SEC 4

NEW MCC R FVNR PUMP CONTROL WD

1. MCC LAYOUT SPACE ALLOCATION IS ESTIMATION 1. RE-USE EXISTING LOCK OUT STATIONS (LOS)

ONLY - PROVIDE MANUF LAYOUT

LOCATED AT PUMP MOTOR(S)
PROVIDE 4 SECTIONS 20"W×20"D

3. NEMA 1A ENCLOSURE

FOR ESTIMATION ONLY
REV$ DESCAIPTION DAWN CHKD 1ATC DESIGNED: MLB
SSUED FOR REVIEW 217/2024 commercial or noncommercial purpose except as authorized in witten CITY OF RIVERSIDE E-3 • Anaergia aareement with or other written consent granted by said company, APPROVED his drawing and sil related document are orotected in ail forms not known orl Breaking Barriers to Sustainabllity PRODECT A NEW MCC R ELEVATION agroement with or other witten consent granted ty said company.

FTU-47
NEW MCP-411 FIRST FLOOR

DIGESTER CONTROL
BLDG 3

NEW PLC
NEW MCC#5
/MCC R MCC R
LIT-41102 (HI) BASEMENT HW PUMPS
TIT-41104
P&ID Pg 2

INSTRUMENTS

LOCATED

THIS AREA

SLUDGE PUMPS

DIGESTER
FIT-41103

FLOOR PLAN
PIT-41101 DIG CONTROL BLDG 3
MX 41102
41101
LIT-41101(LO) 15502
EV-41012
(NON-HAZ)
DIGESTER #5
FIT-40102/
FTU-46>
FTU-46 LOCATED IN ENCLOSED AREA

DIGESTER

2. CONTRACTOR MUST DETERMINE DISTANCES AND ELEVATIONS AND

EXAMINE ANY EXISTING DRAWINGS

3. NO SCALE IS SHOWS AND INSTRUMENTS IS APPROXIMATE ONLY

FOR ESTIMATION ONLY
16 REV$ DESCAIPTION DWN CHKD DATE DESIGNED: DREIGNUMER
BY
SSUEO FOR REVIEW @ Anaergia commercial or noncommercial purpose except as authorized in witten CHECKED: CITY OF RIVERSIDE E-4 aareement with or other written consent granted by said company, APPROVED his drawing and sil related document are orotected in ail forms not known orl wender dosised. leer may not cow. dounissd. ute or me taremi an Breaking Barriers to Sustainabllity GENERAL ARRANGEMENT agroement with of other witten consent granted ty said company.

BKR BKR
USAGE WATT L2 USAGE

AMP RELE
20/1 EXISTING 20/1 EXISTING
20/1 EXISTING 20/1 EXISTING
Bamt,_Ltg. West 920 pt El. 2tg. West
Bamt. Ltg, East 800 040 7st. El.2tg_Eos/
Dig. #5. Lights 420 20 8988R Alarme Panel 20/1 EXISTING 20/1 EXISTING Vaste Gos Burner 20 21-6701
SLR GBOF 500 5uP-4808
20/1 EXISTING
BLR- 6BOZ-
Receeti 600 20 800 Futare Forter \N
600 20/2/
Recepti 400
Spors Future Boiter 20
20/1 EXISTING
Spare 22
24 20/1 EXISTING
Bover G8a2 Cam 20/8
28 29 30 20/1 EXISTING - 20/1 SPARE
Space
34 PLC NEW 30/2 - 20/1 SPARE
36 40 20/1 SPARE - 20/1 SPARE
S/N 20/1 SPARE - 20/1 SPARE
11-CIRC 7-CIRC
Yain Breaker: 1004, 2P
L/

1. FOR REFERENCE ONLY

2. ALL BOILER CIRCUITS REMOVED
PANEL LT 3 120/240V 1Ø, 3W 4 3. PRICE 1/2 OF CIRCUITS WITH NEW WIRE (EXCEPT LOCATION: Mcc iR' Digester Control Bidg. No. 3 DIGESTER 5 LIGHTS)

4. NO NEW CONDUIT EXPECTED
EXISTING LT-3 5. ADD 30/2 FOR PLC

FOR ESTIMATION ONLY
DAWN CHKD nATe TENDEN DESIGNED:

BY
ISSUED FOR REVIEW commercial or noncommercial purpose except as authorized in witten CITY OF RIVERSIDE E-5 • Anaergia agareement with or other written consent granted by said company, LAPPROVED his drawing and sil related document are orotected in ail forms not known orl Breaking Barriers to Sustainabllity PANEL LT-3
agroement with or other witten consent granted ty said company.

CLIENT: RIVERSIDE PUBLIC WORKS
PROJECT: DIGESTER 5 REBAB
PLACE: 5950 ACORN ST,
RIVERSIDE, CA 92504
) Anaergia
Fueling a Sustainable World™
ABBREVIATIONS L1

TAGGING INFO
SYMBOLS L3
SYMBOLS L4
DIGESTER 5
DIGESTER 5 HEAT LOOP
REV NUM SCRIPTION SATE ATTENTION: DRAWN MP RIVERSIDE PUBLIC WORKS

DRAWING NUMBER
ISSUED FOR BID 03/19/2024
RE-ISSUED FOR BID 02/02/2024 • Anaergia DIGESTER 5 REBAB RIVERSIDE PROJ, MANAGER: ASO 5950 ACORN ST, RIVERSIDE, CA 92504
Fueling a Sustainable World'
FILE NAME: 0182 A00501 TABLE OF CONTENTS TOC DO

INSTRUMENT TAG IDENTIFICATION LINE IDENTIFICATION

PROCESS FLOW

TAG NAME HOA AG ENGTON ASA VATE SEE BEING YO THE RISHT

LINE COLOR GUIDE
TAG NUMBER HESE A MiNDER LICUD PROCESS LINES

SOLD PROCESS UNES

COMEUSTIBLE GAS STREANS

CHOMEALS

EXISTNO

SERVICE WATER, POTADLE WATER

FIRST LETTER INTANG ERABLE ALARM HIGH-HIGH ALARIA HIGH ALARM LOW ALARM LOW-LOW ALARM SENSOR FAULT ALARM BLIND CONTROLLER INDICATING CONTROLLER SENSOR (PRIMARY ELEMENT) GLASS INDICATOR PILOT LIGHT TOTALIZER RECORD SWITCH HIGH-HIGH SWITCH HIGH SWITCH LOW SWITCH LOV/LOW SWITCH BLIND TRANSMITTER INDICATING TRANSMITTER SOLOMPUTATION, COVERTER Y CONTROL VALVE VALVE FINAL CONTROL ELEMENT IDENTFCATION

SYMBOL DESCRIPTION PROCESS FLOW INTERFACE SYMBOLS
ANALYSIS лАнн лАн ARAG AS

BURNER, COMBUSTION

USER'S CHOICE
FROM ...

USER'S CHOICE E SHEET."
VOLTAGE ER ES ... = FROM SHEET NUMBER

AT ISCEN ESHH

FLOW SAT ORFICE PLATE
FLOW RATO SCAl
#I SHEET 1

USER'S CHOICE
HMS

NIRRENT IGI ECTRINAS TANI CH

POWER ISHH ISHH USH

TIME SCHEDULE LINE CLASS CHANGE
PEAL
THE TOTAL ‹@А КОАНН КОАН KOAL|| 0I KQL KOR KQS KOSHH KOSH KQSL KQSLL

LAHH LAH LALL

MOTOR CONTROL CHANGE OF SUPPLIER

USER'S CHOICE

USER'S CHOICE
PRESSURE OR VACUUM PAHH|РАН| PAL | PALL | PAT | PI PL PR PS PSHH PRESSURE SAFETY

TIE POINT
PRESSURE DIFFERENTIAL PDAP DAHH PDAH PDAL PDALL PDAT POC PDIC PCI PDL POR POS PDSHH PDSH PDSL POSLL PDT PDIT |POY PDCV

QUANTITY DAHH QAH

RADIATION GENERAL NOTES
SPEED OR FREQUENCY SA SAHH SAH SSH SPEED TONTROL 1. THERE IS NO INTENT TO SHOW ALL DETAIL OF EXISTING FACILIES ON THE PSID'S.

TEMPERATURE TA ТАНН ТАН TSH TW THERMOWELL 2. THIS IS A STANDARD LEGEND.

MULTI-VARIABLE 3. NOT ALL OF THE INFORMATION SHOWN ON THIS LEGEND WILL BE APPLICABLE TO THIS PROJECT.

VIBRATIAL SMECH VA VAHH VAH SI61
WEIGHT OR FORCE WA WAHH WAH WAL WALL WAT WC WICWE WWWO WAWS WWWWWWIT [wy wcv wy wz

UNCLASSIFED
Y EVENT, STATE OR PRESENCE YI| YL
POSITION OR DIMENSION ZAO-OPEN ZAC-CLOSE ZAT ZIC zE zG ZSO-OPEN ZSC-CLOSE zT zIT zY zCV zv zz REV NUM DATE TIENTION: DRAVAN RIVERSIDE PUBLIC WORKS ORAWING NUMBER ISSUED FOR BID 01/19/2024
RE-ISSUED FOR BID 02/02/2024 DIGESTER 5 REBAB RIVERSIDE • Anaergia
PROJ, MANAGER: ASO 5950 ACORN ST, RIVERSIDE, CA 92504
Fueling a Sustainable World" STATUR-
FILE NAME: 0182 A00501 ABBREVIATIONS 11 OF L4 DO
11 EQUIPMENT AND VALVE TAG ABBREVIATIONS PROCESS BLOCK NUMBERING LINE DESIGNATION

TAG NUMBER BLOCK NUMBERING LINE IDENT EICATION SYMBOLS
2 SECURES TENT BROCK AND TIE SOLIDS SEPARATION & LOAROUT A: ALPHA CHARACTER DENOTING REDUNDANT ECLIPMENT OR ALTERNATE TRAINS SLUOGE SCREENNG

COMPRESSED AR LICUID SCAID SEPARATION - HEAT TRACING

FOUPMENT AFBREVATIONS NATURAL GAS DEWATERED CAKE STORAGE LUID DESICNATISA #PING CLASS
COMPRESSOR FOR SEPARATOR (UTS FSP) SEWERISTORM WATER FILTRATE STORAGE TANK MATERILL SPEC• 200ES ROCK OF COGN

ACCESS HATCH SIGHT GLASS HOTICOLD WATER PASTEURIZATION (FILTRATE) SECTION NUMEER ANNULAR SEAL SHREDDER COOR CONTROL RESERVED (NES "EASED ON ANAERO SID PING SPEC

AUGER SILENCER POLYMER CHEMICALS RESERVED FLUID DESIGNATION FLUID DENTIFICATION SYNROLS

SKO RESERVED RESERVED

WREATIN AR INSTRUMENT AR

BICFILTER ALTER SCREW PRESS RESERVED RESERVED

ARTIC ACT

BLOWER GENERATOR SLOGE SCREW DEWATERED RESERVED RESERVED

BURNER SLOGE SCREW THICKENER AFM ANTI FOAMING LEACHATE/DRAINS GATE BECEPTKA: ELTRATE MANAGEMENT:

BOULER HOPPER AMS AMMONIUM SULFATE LIQUID SEPARATE

STRANER SCALE WASTEWATER PRETREATMENT

TLITY AI IQUID WASTE

CABRATION COLIN HEATER SUMP SUND RECEIVINO STATION AMMONIA RECOVERY (AMR)

IGA HAGAS ION PRESSURE
CENTRIFUGE · THICKENER RECEPTION TANK BIOLOGICAL TREATMENT

HAS MENI DRESSIE MUNKIPAL SOLID WASTE

TANK RECEPTION FIT

BIOGAS HIGH PRESSURE NIROGEN GAS
CHP THERMAL OXIDIZER RECEIVING BP: SCLIDS SEPARATION

COMFRESSED AR OXYGEN GAS
CHT

FEEDING HOPPER RO SYSTEM SOCIUM HYDROXIDE

COMPACTOR

STORAGE SILOS/BUNKERS BRINE MANAGEMENT

CONVEYOR HYD TRUCK WASHING STATION EFFLUENT STORAGE & DISCHARGE

PROCESS LIQUOR

CRANEHOIST INJECTOR RESERVED RESERVED

CONDENSATE LIQUOR POLYMER SCLUTION

CRUMBLER RESERVED RESERVED

CARBON DIOXIDE STABLE WATER
5 COOUNG TOWER MOTOR
@BETREATMENT PREPROCESSING BIOGAS CONDITIONING & UTILIZATION: CON RAS RETURN ACTIVATED SLUDGE

CYLINDER

DYNAMIC CYCLONE FEEDER BIOGAS STORAGE CHR COLO WATER RETURN REJECT

BAG OPENER SHREDDER HES REMOVAL COLD WATER SUPPLY RNG RENEWABLE NATURAL GAS

CIFFUSER SCREENNA BIOGAS BOOSTER & AFTER COOLER & DEHYDRATION ROC RO CONCENTRATE

CRYER ROP

EPARATION RO PERNEATE

CRAN MPER EVC EVAPORATOR CONCENTRATE SSA SOLID PHASE AFTER SEPARATION

SORTING

CHAPHRAGM SEAL VE EVAPORATOR PERMEATE SOURCE SEPARATED ORGANIS CREX BRID ENTRY UNIT sSO

CRIP TRAP
CY ARLES MANACEMENT YARE • TAL CAC TREATMENT FOUL AR SULFURIC ACID

EJECTOR PUMP
RANCER AND PRICET TREATHEAT FRESH BIASS MIX g TAIL GAS

EVA EVAPORATOR FERRICFERRUS CHLORIDE TRACE ELEMENTS
ExP EXPANSION VESSEL PKG PACKAGE RESERVED RESERVED
RESERVED RESERVED FLT FI.TRATE TWAS THICKENED WAS

FLAME ARRESTOR PAU
FEEOSTOCX CONDERANE SOLIDS MANAGEMENT: FIRE WATER UREA

FLEX COUPLING

LIQUID-SOLID HOMOGENIZATION GLYCERINE UTILITY WATER

YALVE ARRGEVJATKANS

PARTICLE SEE RECUCTION DRIED SO RE STORAGE HYDROCHORIC ACID WAS WASTE ACTIVATEO SLUDGE

SCRUBBER AR RELEASE VALVE PRE-THICKENNO HSO HIGH SOLIDS ORGANES WET FRACTION

SCN SCREEN
AUTOMATIC VALVE • FANREY IN ASTIC & ELM REMOVA I COMPOSTING HOT WATER RETURN WST GENERIC WASTE FEEDSTOCK

AVR AIR AND VACUUM RELEASE VALVE GRITREX (GRIT REMOVAL) PYROLYSIS HOT WATER SUPPLY

BACK FLOW PREVENTER RESIDUAL PROCESSING ERTILIZER ALENDING HYP SOCIUM HYPOCHLORITE

BACK PRESSURE VALVE THERMAL PRETREATMENT -ESERVEN
CHECK VALVE RESERVED PRQUECT SPECIEI ELUDE:

ELECTRICAL VALVE RESERVED RESERVED

PEE SPECEKAION

FLOW CONTROL VALVE RESERVED RESERVED
SST 304
FLOAT VALVE PRESTON: PROJECT SPECIEL SST 316

MANUAL VALVE RESERVED HOPE FOR UNDERGROUND PROCESS LINES PRESSURE REGULATING VALVE ANAEROBIC DIGESTER - PRIMARY RESERVED 2 HDPE FOR UNDERGROUND BIOGAS LINES PRESSURE RELIEF VALVE MEROERC CIGESTER • SECONDARY POLYETHYLENE FOR UNDERGROUND HEATING WATER ROTARY VALVE MAEROBIC NICESTER. TERYIARI

RESERVED PVC

SHEAR VALVE RESERVED CARBON STEEL

SOLENOID VALVE HYGENATION
SERVED CARBON STEEL • FOR HOGAS

TEMPERATURE CONTROL VALVE CIGESTATE STORAGE
SERVED SST 316 - SAMPRES SYSTEM
THREE WAY VALVE CIVERTER dESERVER

RESERVED GALVANIZED CARBON STEEL
WEIGHTED CHECK VALVE 2ESERVEN

RESERVED

WEIGHTED SHEAR VALVE RESERVED RESERVED
REV NUM DESCRIPTION DATE ATTENTION: DRAWN: RIVERSIDE PUBLIC WORKS DRAWING NUMBER

ISSUED FOR BID
RE-ISSUED FOR BID 02/02/2024 • Anaergia ARARE AD DIGESTER 5 REBAB RIVERSIDE PROJ, MANAGER: ASO 5950 ACORN ST, RIVERSIDE, CA 92504
FILENAME: 0182 ACOS01 TAGGING INFO L2'OF L4 DO
12 =

VALVE SYMBOLS PUMP AND COMPRESSOR SYMBOLS HEAT EXCHANGER AND HEATER SYMBOLS MIXER AND STRAINER SYMBOLS

Y STRAINER

BALL VALVE SWING CHECK VALVE GENERAL PUMP

BUTTERFLY VALVE BALL CHECK VALVE
1•1

SHREDDER

SALVE DISCHECK

KNIFE GATE VALVE EXCHANGE REAT

STATIC MIXER

SOLENOID VALVE

GLOBE VALVE SCRUBBER/DEMISTER

THREE-WAY VALVE

NEEDLE VALVE FLOATING-HEAD TUBE

PRESSURE CONTROL SCREW MIXER

VALVE HOSE PUMP

PINCH VALVE

MEMBRANE MODULE

PRESSURE RELIEF

PLUG VALVE VALVE U-TUBE BUNDLE HEAT

EXCHANGER

PROGRESSIVE

CAVITY PUMP

ACTUATOR SYMBOLS TRUCKS AND CRUMBLER

SPIRAL HEAT

EXCHANGER

ELECTRIC PNEUMATIC SPRING TANKER TRUCK

OPEN GENERAL

CRUMBLER
•- PNEUMATIC PNEUMATIC SPRING
CLOSED

NEUMATIC WITH LOBE PUMP OFF LOADING

HYDRAULIC DUMP TRUCK HAMMER

SOLENOID

CRUMBLER

GENERAL COMPRESSOR GENERAL HEAT

HEATER AND COOLDOWN SYMBOLS EXCHANGER

LOADING DUMP

TRUCK CRUMBLER

BURNER FINNED TUBE HEAT
1HH EXCHANGER

BELT DRYER CENTRIFUGAL

COMPRESSOR

FRONT END ROLLER

LOADER/BOBCAT CRUMBLER

BURNER / PLATE HEAT

COMBUSTION EXCHANGER

CHAMBER ROTARY COMPRESSOR

DRUM DRYER CONVEYOR SYMBOLS

MISCELLANEOUS SYMBOLS
SCREW COMPRESSOR 44444444 SCREW CONVEYOR INJECTOR
BOILER

COIL HEATER BELT CONVEYOR FLANGE SARIRAGM
BLOWER

HOSE CONNECTION SHALLAR

GENERAL CONVEYOR
FLARE

COMPICK/ QUICK GENERATOR

ELECTRIC HEATER

METAL SEPARATOR EJECTOR ELECTRIC MOTOR
REV NUM DESCRIPTION DATE ATTENTION: DRAWN: RIVERSIDE PUBLIC WORKS ORAWING NUMBER ISSUED FOR BID 01/19/2024 CHECKED: AD
RE-ISSUED FOR BID 02/02/2024 • Anaergia APPROVED: AD DIGESTER 5 REBAB RIVERSIDE PROJ, MANAGER: ASO 5950 ACORN ST, RIVERSIDE, CA 92504
FILENANE: 0182A60501 SYMBOLS L3 OF L4 DO

MISCELLANEOUS SYMBOLS CONTINUED PROCESS SYMBOLS

VEERED HYDROCYCLONE

SIGHT GLASS ROLL UP DOOR
FILTER

FLAME ARRESTOR
CRANE
P-TRAP

GAS FILTER

DYNAMIC CYCLONE

CYLINDER

TIE POINT

HOSE BIBB CHP

SERVICE BOX FLIP FLOP SCREEN
OREX

DIFFUSER

EVAPORATOR
HOPPER
HOOD

DRAIN FLOCCULATOR

SCRUBBER
FAN

COOLING TOWER

SILENCER

IN-LINE GRINDER
VENT
REV NUM DESCRIPTION DATE ATTENTION: DRAWN: MP RIVERSIDE PUBLIC WORKS DRAWING NUMBER ISSUED FOR BID 01/19/2024 " "' CHECKED: AD
RE-ISSUED FOR BID 02/02/2024| • Anaergia APPROVED: A0 DIGESTER 5 REBAB RIVERSIDE PROJ, MANAGER: ASO 5950 ACORN ST, RIVERSIDE, CA 92504
STATUS:

FILE NAME: 0182 A005 01 SYMBOLS 140F 14 DO
12 10

TOP OF RESTED TO
6-9G-711.00-53316
TYP: H.
8807112455316
Đạt,
+ $ | 8-0-701.05-83318
M.-11169 MI-1111S TO BIOGAS
SEE NOTE 8. COMMON FLARE
HEADER
AC-41102 AC-41101 SB-41102 TRP-41102
SEE NOTE 3. DRIP TRAP
SB-41101
053 HP DON CONZ R-41101 TYP: H.

DIGESTER 5 ROOF
MCP-411
1, TOORAN
DIGESTER MICER CONTROL PANEL TSV-41101
25 KW FEEDER NEWMOCR
480v 3PH 60HZ TYPA TELEAVENG
ТУР: Н

ANAEROBK DIGESTER NS TANK OVERLON
TYP.P. SHH HE GUN EXTING
-0-
M/41102 1643103 ENTINO

FROM DIGESTER
8-034120121
SEE NOTE 1. HOLDING TANK
B (SHEETZ E60samna E-S:0541100-01 -12 (SHEET?)
SEE NOTE2.

CONTROL BLOS

HEATED SLUDGE
NOTE UNE 108 EURES A RESURE TEST STED.
3) FLANGES ON ROOF OF DIGESTER 5 ARE CL150,
6) MJ-41133 IS BURRIES WITH A NUT.

REV NUM DESCRIPTION DATE ATTENTION: DRAWN MP RIVERSIDE PUBLIC WORKS ORAWING NUMBER ISSUED FOR BID 01/19/2024 CHECKED: AD
RE-ISSUED FOR BID 02/02/2024 • Anaergia APPROVED: 10 DIGESTER 5 REBAB RIVERSIDE PROJ, MANAGER: ASO 5950 ACORN ST, RIVERSIDE, CA 92504
STATUS:

FILE NAME: 0182 A005 01 DIGESTER 5 1 OF 2 DO
12 ТУР. Н.

CABIDE
41416
HOT WATER SUPPLY 4641122
SEE NOTE 4.

HH: 100P31
100931
ГР Н
BE SHEET> 50641.0101 6-05-1110501 6-05-311.06-01 3 SHEETT! FROM DIGESTER 5 SLUGE RETURN
O DIGESTER 5

EXETING MAR
SHISHICACS ¢ ІН
M/-41128
RETURN
SEE NOTES.
4) HOT WATER SUPPLY TO CONNECTION IN OIGESTER
5) HOT WATER RETUN TO CONNECTION I DIGESTER
182 BASEMENT WITH ISOLATION PLUG VALVE.

REV NUM DESCRIPTION DATE ATTENTION: DRAWN MP RIVERSIDE PUBLIC WORKS DRAWING NUMBER ISSUED FOR BID CHECKED: AD
RE-ISSUED FOR BID 02/02/2024 • Anaergia APPROVED: AD DIGESTER 5 REBAB RIVERSIDE PROJ, MANAGER: ASO 5950 ACORN ST, RIVERSIDE, CA 92504
Fueling a Sustainable World" STATUS:

FILE NAME: 0182 A005 01 DIGESTER 5 HEAT LOOP 20F 2 DO

CONCRETE ASSUMPTIONS
CITY OF RIVERSIDE PUBLIC WORKS DEPARTMENT | APPENDIX 11A | DIGESTER NO. 5 - FOOD WASTE EVALUATION

5.1.9 Sloshing Wave Height
The sloshing wave height was estimated to be 4.2 ft. Based on the available construction documents, the current freeboard available from high water elevation is approximately 2.5 ft which can result in a net upward force applied to the steel dome. This complication can be resolved by limiting the operating water height as recommended in Sections 3.1 and 3.3. Otherwise, the dome may experience damage to the steel members, dome seal, and dome anchorage at the top of the wall.

EXISTING

CONG WALL
Adding dowels at both ends of
vertical distance: 12'H<0.5> =

11.5'H/8spaces = 1.44'o.c.

Tank
C.L.
- 37'-6" to (E) Face of Wall
Drill & Epoxy Dowels:

OPTION 2: MIT MAX WATER HT TO 26
At Slab: 4+2; Wall: 7+2 =
OPTION 1: THICKEN 1'-0"
BOTTOM OF WALL 15 dowels/row(hor.+vert)
95 CY of concrete Assuming 1.5'-0" spacing
Total concrete
between rows of debar at
182 CY existing wall:
1'-3" THICKEN SLAB FOR 37.5'R, Circumference =
BOTH OPTION 1 & 2 2'-0" M 235.619 / 1.5' spacing =
87 CY of concrete (157.1)~157 spaces × 15
dowels/row =
2,355 dowels.
+1204
EXIST CONC 4'-8"- 9'-C* MIN 9run:0.75rise, Нуp.: 9.0312 SLAB 37.5' -- Нуp.: 37.63(=R on 12:1 slope)
Slab edge R: 37.63-9.03 = 28.6'
#TYPICAL WALL SECTION
12run:1rise, Hуp.: 12.0416'

37.5'R →> Hyp. = 37.63'R
Figure 15 Conceptual Details

5.2 Process/Mechanical Assessment Adding 2 dowels at horizontal listance: 9'L <0.5>
.5'L/5spaces = 1.7'0

5.2.1 Digester Mixing
As described in Section 3, only one Vaughn chopper pump is currently available for mixing of Digester No. 5. Since having an installed standby will require major modifications to the piping, it is recommended that an uninstalled spare pump be stored in the warehouse to allow maintenance to switch pumps in a short period in case of failure.

Currently, for pump mixing, sludge is withdrawn from the top of the digester and discharged at the bottom via nozzle. There is a top discharge nozzle to be used for breaking up scum. However, (carollo®
26 | JUNE 2019 | FINAL

DIGESTATE

JOINING TANK
See W.M. Lyles markups with
assumptions and details in
Green
New epoxy Assumed
lined DIP existing 6"
line we tie
into below
grade at this
approximate
location.

Existing DIP
lines used.

Tested and
cleaned
CONTRO: DIGESTER #5
IDG NO 3
Sch 10|
316SS
New bare Piping
CS piping
New epoxy
Lined DIP
DIGESTER #1 DIGESTER ·2 DG HDPE
Burried

DIGESTER CONTROL
Assume existing 8"
HDPE line tied into
at this approx
location.
199.39 ฿ 100 00 0 1
For (bil. Sino Dug F.004

NOTE VALVE
0-0s- 01t INSTRUMENT
ADDED
-7-2N-5714
True Norto. Axio ¢Q.7255
UT-41102 TSV 4110} ASAMPLE SAR
1007-61101
OVERFLOW BOX Came Siab

DIGESTES CONTROL
DIGESTER N$ 5
6700 4-M3-021H 025-0re
6•CS•02-7 "
430-41
1-8310g|
LA-ME•DE/ H
MX-41101 |

1. 20102 p.670/)
441101
02%*
20-MS-026)
- 20k/€ Reducer
Taken off as
new epoxy
lined DIP.

DIGESTER #5
Existing DIP
lines used.

Tested and
deaned.

DIGESTER #5
14-MS-OF7-
ROOF PLAN SECTIONAL PLAN 9 EL 734.00
2 No.

RECORD DRAWING

CITY OF RIVERSIDE REPLACEN ENTY SACROJECTE
CAMP DRESSER & McKEE INC.

Sevtreesters. Regionel Chica PUBLIC WORKS DEPARTMENT T-14 CDM
beacon Caitors 91i
SHEETM-605 oF 55
DATE. 12022-32 TIE NO 2912-7-087
DIGESTER CONTROL BLDG NO.3
4- DR-CT 1
For Cant. Ser
Dwo. C-004
6-IW-DIE -STà
7- DR-CZ7-
+X-41101
*6 "Red 90 e/bow
Тур..
/-IW-S7
New bare carbon steel pipe
6800 buried coming off east side of
building
Tup о-Г NEW PIPING IN

DIGESTER
VE-6802) CONTROL BLOG
Srate
e 720.65 (l4p.) / MICTNC PIPN
MN4
3-DR-C7-1 ONTTOL BLDG

NEW PIPING
TIT-41103 EXISTING INSIDE

INDERGROUND PIPING
8 Ol-nor BLDG. NO.4
ć El. 726.82-
NEW PIPING MV-41124
6-56-54- VICTINA DIGESTER
6-60-53 6-CS-L C UNOERGROUNO SD OETOL
X MV-43103 BLS NO 4 HASTNG
инио
-To Waste MV.41122
Gas Burner 38S0
For Cont. IN DIGESTER
High Point — CONTTOL BLOG
See Dwg. C-004 720 84 (To) NEW PIPING IN
Existing lines on east
NEW PIPING IN ExIsTfinG side of control

EXISTING CONTRAN AINA
UNDERGROUND NO.3
DIGESTER PIPING building no 4.

MEECTER DOINE
NOTE: ALL NEW PIPING IN DIGESTER
CONTROL BLDG NO.3
Core existing
wall and i
penetrate
Existing DIP new

TYISTING EXISTING
Existing wall UNDERGROUND tested and HWS/HWR
penetrations cleaned i piping
utilized шина ами

EXISTING ABOVE

GROUND PIPING GROUND PIPING
54107 PSV-41102
WN 41101
For Gue Draw off.
1V.41120
eo ler 10 Pipe Seeive
you Tiwar
6 56-54-
Battom of Rim Flate
E1.746.00
HWL. EL 749.0
El, 748.50
Inkat Port
Scum Sceaker Deflector Vanes LN. EL.2420
Vorate
20" D/A Draft Tuc ND -41101
DIGESTER NO. E Below grade

DG HDPE
<700) COTT AN
a Sludge Suction Ta Neat Exch
# $ 5L. 723,00
COMMON
MN-41128 20-MS -DIG | TRP-41101D-
Sludge Disch. Jonale MV-41109
20% 4* Red.
8MV-11110
EL. 716.0 Above grade
TRP-41102
AC-41102 AC-41101 DG Sch 10
EL. 71305 316SS
Drain to grade. No existing drain
line appears to be at the location
of this equipment.

MATCHLINE - FOR CONTINUATION SEE SHEET NO. 000-0-097
FELO A AS NECESSAY FOR TO STRUCTION DIGESTER #5

OF SUMP AND CONCRETE SLAB
ENST

SSE PROCESS AREA

SEE PROCESS
03 SHEETE
T5 10ES

DG HDPE
Burried
4 ORN-CL

PROPOSED CONNECTION RA-A
CONNECT I 10" DG-HOPE
DETAIL
6 PEC-DISL CTS.

ED CONNECTION TO EXIST. MH
coRd

SEAL W/LINK SEAL AND EPOXY GROUT
INV 720.94
(5g Bag
Exhibit "C"

SCHEDULE OF VALUES
Item No. Description of Work Scheduled Value (SUSD)
1 Project Management & Engineering Design 1,106,800
2 New Digester Mixers & Heat Exchangers 1,314,000
3 Sitework / Site Piping 1,033,200
4 Demolition 111,100
5 Concrete 832,200
6 Coating 529,000
7 Mixer Installation 84,200
8 Equipment 77,100
9 Digester Roof - Demo 466,300
10 Digester Roof - New Roof Dome 1,619,300
11 Piping 695,500
12 Electrical & Instrumentation 1,225,000
Subtotal 9,093,700
13 - Allowance* Digester 4: Building Mechanical Upgrades 288,600 14 - Allowance** Digester 5: Epoxy Injection / Xypex 125,700 Waterproofing
TOTAL 9,508,000
*Item converts to lump sum upon completion of engineering design. **Item charged as Time & Materials during this scope of work.

Exhibit "D»

PROJECT SCHEDULE
Project schedule is anticipated to be 18 months from NTP.

Task Name Duration Start Finish Qtr 3, 2024 /Otr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Mode Jun _ Aug Oct | Nov Dec | Feb Mar Apr May Jun Jul Aug Sep Oct Nov | Dec Council Approval & NTP 5 days Tue 6/25/24 Mon 7/1/24
Riverside Digester 5 DB 371 days Tue 7/2/24 Tue 12/2/25 Design 100 days Tue 7/2/24 Mon 11/18/24
Demolition Design 6 wks Tue 7/2/24 Mon 8/12/24
Structural Design 10 wks Tue 7/2/24 Mon 9/9/24
Mechanical Design 10 wks Tue 7/30/24 Mon 10/7/24
Electrical Design 20 wks Tue 7/2/24 Mon 11/18/24
Procurement 315 days Tue 7/2/24 Mon 9/15/25
Mixer Procurement 190 days Tue 7/2/24 Mon 3/24/25
Submittals - Mixer & Service Box 6 wks Tue 7/2/24 Mon 8/12/24 11 Submittals - Mixer Post & Gas Skirt 8 wks Tue 7/2/24 Mon 8/26/24 Submittals - Control Panel 10 wks Tue 7/2/24 Mon 9/9/24 13 Submittal Approvals 2 wks Tue 8/27/24 Mon 9/9/24
= Fabrication 20 wks Tue 9/10/24 Mon 1/27/25
15 Delivery 8 wks Tue 1/28/25 Mon 3/24/25
16 Digester Dome Procurement 165 days Tue 7/2/24 Mon 2/17/25 Submittals 10 wks Tue 7/2/24 Mon 9/9/24
18 Submittal Approvals 2 wks Tue 9/10/24 Mon 9/23/24
Fabrication 15 wks Tue 9/24/24 Mon 1/6/25
Delivery 6 wks Tue 1/7/25 Mon 2/17/25
21 Electrical Procurement 315 days Tue 7/2/24 Mon 9/15/25 Submittals 15 wks Tue 7/2/24 Mon 10/14/24
23 Submittal Approvals 2 wks Tue 10/15/24 Mon 10/28/24
24 Fabrication 40 wks Tue 10/29/24 Mon 8/4/25
Delivery 6 wks Tue 8/5/25 Mon 9/15/25
26 Below Grade Piping Procurement 70 days Tue 7/2/24 Mon 10/7/24 Submittals 6 wks Tue 7/2/24 Mon 8/12/24
28 Submittal Approvals 2 wks Tue 8/13/24 Mon 8/26/24
29 Lead Time 6 wks Tue 8/27/24 Mon 10/7/24
30 Above Grade Piping Procurement 115 days Tue 7/2/24 Mon 12/9/24 31 Submittals 6 wks Tue 7/2/24 Mon 8/12/24
Submittal Approvals 2 wks Tue 8/13/24 Mon 8/26/24
33 Lead Time 15 wks Tue 8/27/24 Mon 12/9/24
Concrete & Rebar Procurement 60 days Tue 7/2/24 Mon 9/23/24 Submittals 6 wks Tue 7/2/24 Mon 8/12/24
36 Submittal Approvals 2 wks Tue 8/13/24 Mon 8/26/24
Lead time 4 wks Tue 8/27/24 Mon 9/23/24
Task Inactive Task Manual Summary Rollup External Milestone Manual Progress Split Inactive Milestone Manual Summary Deadline
Project: Riverside Dig 5 - Sched Inactive Summary
Date: April 2024 Milestone Start-only Critical
Summary Manual Task Finish-only Critical Split
Project Summary Duration-only External Tasks Progress

Page 1 ends

Task Name Duration Start Finish
Mode Jul Aug Sep Oct Nov Dec May Jun Jul
38 Concrete Coating Procurement 10 wks Tue 7/2/24 Mon 9/9/24 39 Construction 370 days Tue 7/2/24 Mon 12/1/25
Mobilization 2 wks Tue 7/2/24 Mon 7/15/24
41 Potholing & Investigations 8 wks Tue 7/16/24 Mon 9/9/24 42 Underground Piping Site Work 15 wks Tue 11/19/24 Mon 3/3/25 43 Digester No. 5 220 days Tue 8/13/24 Mon 6/16/25
Existing Dome Demolition 6 wks Tue 8/13/24 Mon 9/23/24
Concrete Coating (Upper) 10 wks Tue 9/24/24 Mon 12/2/24 46 Concrete Reinforcement (Footing/Wall) 10 wks Tue 12/3/24 Mon 2/10/25 Digester Dome Installation 10 days Tue 2/18/25 Mon 3/3/25 48 Equipment Installation (Mixers) 6 wks Tue 3/25/25 Mon 5/5/25 49 Gas Piping Installation 6 wks Tue 5/6/25 Mon 6/16/25 50 Digester Control Building No. 3 270 days Tue 9/24/24 Mon 10/6/25 Existing Pipe & Equipment Demolition 6 wks Tue 9/24/24 Mon 11/4/24 Heat Exchangers & Pump Installation 6 wks Tue 3/25/25 Mon 5/5/25 Piping & Support Installation 6 wks Tue 5/6/25 Mon 6/16/25 Electrical Conduit, Wire, Terminations 10 wks Tue 6/17/25 Mon 8/25/25 Set MCC & Terminate 3 wks Tue 9/16/25 Mon 10/6/25
Digester Control Building No. 4 50 days Tue 6/17/25 Mon 8/25/25 Piping & Support Installation 10 wks Tue 6/17/25 Mon 8/25/25 58 Testing 8 wks Tue 10/7/25 Mon 12/1/25
Substantial Completion 1 day Tue 12/2/25 Tue 12/2/25
Task Inactive Task Manual Summary Rollup External Milestone Manual Progress Split Inactive Milestone Manual Summary Deadline
Project: Riverside Dig 5 - Sched
Date: April 2024 Milestone Inactive Summary Start-only Critical Summary Manual Task Finish-only Critical Split
Project Summary Duration-only External Tasks Progress

Page 2 ends

Exhibit "E"

SUBSTANTIAL COMPLETION
Substantial completion shall be achieved upon successful completion of testing that demonstrates Digester 5 system functionality:
• Hydrostatic testing with water
• Functional testing of mixers with clean water
• Heat exchanger testing
• Dome pressure testing
If for any reason beyond the control or responsibility of the Design-Build Entity, the Substantial Completion testing cannot be carried out within thirty (30) days of completion of Scope of Work, the Scope of Work shall be deemed complete, and City shall release final payments) due to the Design-Build Entity.

PERFORMANCE BOND
Bond No.

Premium:

KNOW ALL PERSONS BY THESE PRESENTS THAT:

WHEREAS, on _ the CITY OF RIVERSIDE ("CITY") awarded to contract for performance of the work described as (**Insert Name of Project**]; [**Insert RFP No._ **] ("CONTRACT), the terms and conditions of which are incorporated herein by reference; and
WHEREAS, the CONTRACT requires PRINCIPAL to furnish this Performance Bond ("BOND") to guarantee PRINCIPAL's faithful performance of all provisions of the CONTRACT; and WHEREAS, - _ ("SURETY"'), a corporation legally
authorized to execute and furnish performance bonds as sole surety in the State of California, is willing to act as PRINCIPAL's SURETY in the making and giving of this BOND.

NOW, THEREFORE, we PRINCIPAL and SURETY hereby hold and firmly bind ourselves to pay to CITY in lawful United States currency the principal sum of [**Insert written dollar amount, for example: One Thousand Two Hundred Thirty-Four Dollars**| [**Insert numeric amount, for example: $1,234.00**] for which payment well and truly to be made to CITY or CITY's successors or assigns we hereby bind ourselves and our heirs, legal representatives, successors and assigns, jointly and severally, firmly by these presents.

THE CONDITION OF THIS BOND IS THAT IF PRINCIPAL or PRINCIPAL's heirs, legal representatives, successors or assigns shall in all things stand to, abide by, and well and truly keep and faithfully perform all of the covenants, conditions and promises in the CONTRACT, including its work Guaranty, and all alterations thereof made as therein provided on PRINCIPAL's part to be kept and performed at the time and in the manner specified therein, and in all respects according to their true intent and meaning, and shall indemnify and save harmless CITY and CITY's officers, employees and agents as therein specified, then this obligation shall become null and void; otherwise, it shall be and remain in full force and binding effect.

SURETY hereby agrees that no change in the terms of the CONTRACT or the work to be performed thereunder, or any extension of time for completion thereof, shall in any way relieve it of its obligations under this BOND, and hereby waives notice of any change or extension thereof, and further waives the provisions of California Civil Code sections 2819 and 2845.

IN WITNESS WHEREOF, we sign and seal this BOND on 20_
Correspondence or claims relating to [**Insert Name of DESIGN BUILD ENTITY**], this BOND should be sent to SURETY at Principal
the following address:

By (Seal)
Typed Name and Title
Surety
_(Seal)
Attorney-In-Fact
Telephone Number
Note: Signatures of those executing for Typed Name and Title SURETY must be acknowledged, and a
Power of Attorney attached.

PAYMENT BOND
Bond No.

Premium:

KNOW ALL PERSONS BY THESE PRESENTS THAT:

WHEREAS, on _ the CITY OF RIVERSIDE ("CITY") awarded to **Insert Name of DESIGN BUILD ENTITY**], [**Insert business entity type, for example:
• California corporation, a limited partnership, a limited liability company, etc.**], [**Inseri nailing address**], State Contractor's License No. **Insert Number**, a contract for performance of the work described as **Insert Name of Project**; **Insert RFP No. ** ("CONTRACT'"), the terms and conditions of which are incorporated herein by reference; and
WHEREAS, the CONTRACT requires PRINCIPAL to furnish this Payment Bond ("BOND") to secure payment of the claims of persons described in California Civil Code section 3248(b); and WHEREAS, - ("SURETY"'), a corporation legally
authorized to execute and furnish payment bonds as sole surety in the State of California, is willing to act as PRINCIPAL's SURETY in the giving of this BOND.

NOW, THEREFORE, we PRINCIPAL and SURETY hold and firmly bind ourselves unto CITY and all persons and entities described in California Civil Code section 3248(b) whose claims are not paid by PRINCIPAL in the total sum [**Insert written dollar amount, for example: One Thousand Two Hundred Thirty-Four Dollars**| [**Insert numeric amount, for example:
$1,234.00**] for which payment well and truly to be made we bind ourselves and our heirs, legal representatives, successors and assigns, jointly and severally, firmly by these presents.

THE CONDITION OF THIS BOND IS THAT IF PRINCIPAL or PRINCIPAL's successors, assigns, or subcontractors fail to pay any of the persons described in California Civil Code section 3181, any amounts due under the California Unemployment Insurance Code with respect to work or labor performed under the CONTRACT or any amounts required to be deducted, withheld and paid over to the California Employment Development Department from the wages of employees of PRINCIPAL and PRINCIPAL's subcontractors pursuant to California Unemployment Insurance Code section 13020 with respect to such work and labor, SURETY will pay for the same in an amount not exceeding the sum stated above, plus all costs and reasonable attorney's fees awarded by any court of competent jurisdiction in any lawsuit brought upon this BOND.

THIS BOND SHALL INURE TO the benefit of all persons and entities described in California Civil Code section 3248(b) so as to give them or their assigns a right of action in any lawsuit brought upon this BOND, and is executed and filed to comply with the Public Works Payment Bond provisions of Chapter 7, Title 15, Part 4, Division 3 of the California Civil Code (commencing at Section 3247) and all amendments thereto, which provisions are incorporated herein by this reference.

IN WITNESS WHEREOF, we sign and seal this BOND on 20_
Correspondence or claims relating to [**Insert Name of DESIGN BUILD ENTITY**], this BOND should be sent to SURETY at Principal
the following address:

By _(Seal)
Typed Name and Title
Surety
_(Seal)
Attorney-In-Fact
Telephone Number
Note: Signatures of those executing for Typed Name and Title SURETY must be acknowledged, and a
Power of Attorney attached.