Body
Riverside City Council
Original file
807 KB
Text extracted from the city's file for reading and search. Open the original on riversideca.legistar1.com. That file is the official record.

7/25/2024
1 RiversideCA.gov1
RiversideCA.gov
MEASURE Z – BID 8081FY 2023/24 STREET PRESERVATIONCity CouncilAugust 20, 2024Public Works Department RiversideCA.gov2

1. Public Works budgets a portion of the State Gas Tax, the County Measure A Sales Tax, and the City’s Measure Z and uses tax revenues for pavement rehabilitation and preservation of city streets.2. The Public Works Department (Public Works) utilizes a Pavement Management Program (PMP) to collect and analyze pavement data to prioritize maintenance and repair projects. BACKGROUND1 2 7/25/2024
2 RiversideCA.gov3

3. This project aims to preserve streets in fair to good condition to extend their pavement life using the City’s Measure Z funds.4. Preventative maintenance is used on streets with pavement condition index (PCI) scores of 60 and higher. The cost for these surface treatments is low compared to resurfacing. BACKGROUND RiversideCA.gov4

BACKGROUND
3 4
7/25/2024
3 RiversideCA.gov5
www.riversideca.gov/pavingmapBACKGROUND
RiversideCA.gov6

1. Slurry preservation and minor pavement resurfacing of 27 street centerline miles including collector roads:–Collett Ave, Diana Ave, Wells Ave, De Anza Ave, Comer Ave; and Ransom Rd2. New traffic pavement markings and signage upgrades at all preservation locations.CURRENT PROJECT5 6 7/25/2024
4 RiversideCA.gov7

LOCATION MAP
RiversideCA.gov8
Strategic Priority No. 6 Infrastructure, Mobility and ConnectivityGoal No. 6.2 – Maintain, protect, and improve assets and infrastructure within the City’s built environment to ensure and enhance reliability, resiliency, sustainability, and facilitate connectivity.Cross-Cutting Threads STRATEGIC PLAN ALIGNMENT7
8 7/25/2024
5 RiversideCA.gov9

1. Award a construction contract for Bid No. 8081 for Fiscal Year 2023/24 Streets Preservation to American Asphalt South, Inc., of Riverside, California, in the amount of $2,765,667.24; and2. Authorize the City Manager, or designee, to execute the construction contract, including making minor non-substantial changes.RECOMMENDATIONS9