The Quality Plus Group Maintenance and Construction
U
November 18, 2024
Updated December 10, 2024
Updated December 18, 2024
Michael Combs
Sent via: [email protected]
Subject: Proposed Change Order- NO.4.R1 - Plumbing Drain work replacement
Site: Riverside Airport Restroom
City of Riverside Contract No.8080
Proposed Change to Scope of Work
Pursuant to request made in the field and scope following is proposed. •
Remobilization following Council approval of this change. • Installation of drains in men’s and women’s restrooms in trench by others.
• Women’s restroom install drains for 3 toilets, 2 lavy sinks and one floor drain and one clean out.
• Men’s restroom install drains for 1 toilet, 3 urinals, 2 lavy sinks, 1 floor drain and 1 clean out
• Install drains for mop sink in room adjacent to women’s restroom. • Connect plumbing to outside clay pipe
• All new plumbing, groundwork and vents will be in ABS. Piping will extend all the way to existing vent in space over restroom. New ABS will terminate above men’s restroom and at clay pipe outside of building .
• Complete backfill over install underground piping
• Complete concrete pad over new piping for new tile.
• Remove piping installed for original layout to acco mmodate new layout
• Complete new in wall piping for new layout of restroom fixtures • Provide and install additional urinal
• Frame and install drywall to accommodate new layout.
NOTES
Excavation and concrete removal by others
1655 E. 6 th St. • Suite A-3
Corona, California 92879
Tel: (951) 280 - 1872
Fax: (951) 280 - 1867
The Quality Plus Group Maintenance and Construction
U
PRICE:
Direct cost for Plumbing, backfill and concrete $ 40,191.57 Cost to complete assessment of line $ 1,500.00
Cost to frame urinal wall and frame back wall
with new ties in $ 6,278.48
Prime Contractor Overhead Markup $ 4,797.00
Prime Contract Profit Markup $ 2,398.50
Prime Bond Costs $ 2.206.62
Total Cost for Proposed change Order $57,372.17
Credit Option to Use ABS in Lieu of Cast iron $ 6,015.92 Total Using ABS $51,356.25
The above cost is net costs for the changes requested and includes all prevailing wage, sales tax, delivery and other charges to complete the proposed scope of work.
Price for material good till 30 January 2025.Payment Terms and Conditions per Current Contract .
If you have any questions or require additional information, please feel free to contact us.
Quality Plus Group
Dan Sola
RENOVATION OF TWO RESTROOMS AT THE RIVERSIDE MUNICI PAL AIRPORT 6951 Flight Rd., Riverside CA 92504.
Division 22
Item Description Measuring
Units Units Unit Cost Total Cost Total Item Cost Total Amount Division 22 - Plumbing 40,191.57$
Labour
Laborer HR 90 90.41$ 8,137.19$ 8,137.19$ Cement Mason HR 30 90.71$ 2,721.30$ 2,721.30$ Plumber HR 54 113.87$ 6,149.04$ 6,149.04$ Equipment
Tools Days 8 125.00$ 1,000.00$ 1,000.00$ Service Truck Days 8 240.00$ 1,920.00$ 1,920.00$ Material
Backfill Sand Load 1 400.00$ 400.00$ 400.00$ Cast iron/ABS replacement (See attachment LS 1 11,258.00$ 11,258.00$ 11,258.00$ copper Replacement LS 1 8,606.04$ 8,606.04$ 8,606.04$
RENOVATION OF TWO RESTROOMS AT THE RIVERSIDE MUNICI PAL AIRPORT 6951 Flight Rd., Riverside CA 92504.
Item Description Measuring
Units Units Unit Cost Total Cost Total Item Cost Total Amount Framing etc. 6,278.48$
Labour
Laborer HR 24 90.41$ 2,169.92$ 2,169.92$ Dry wall Installer HR 24 96.40$ 2,313.56$ 2,313.56$ Equipment
Tools Days 3 125.00$ 375.00$ 375.00$ Service Truck Days 3 240.00$ 720.00$ 720.00$ Material
Drywal Materials- Misc LS 1 700.00$ 700.00$ 700.00$
Line Quantity Part Price Ext.
1 8 10 feet cast iron pipe 312.22 2497.76
2 50 4" no hub bands 11.24 562
3 5 4" cast iron santee 76.88 384.4
4 8 4" cast iron comby 113.62 568.1
5 4 clost flange 136.71 546.84
6 4 closet bend 116.22 464.88
7 1 brass clean out 693.97 693.97
8 2 floor drain 464.94 929.88
9 2 2" cast iron ptrap 57.54 115.08
10 40 2' cast iron fittings 49.22 1968.8
11 60 2' no hubs 9.5 570
12 10 2' cast iron pipe 173.9 1739
total 10,472.61
tax 785.44
grand total 11,258