Section II: Project Schedule
he local agency is expected to deliver the project per the HSIP Program Delivery requirements. Assuming the HSIP Cycle 12 project elected for funding will be programmed by January 1, 2025, please enter your best estimated dates for the followin Implementation milestones. Leave blank if not applicable.
Will this project use HSIP funds for Preliminary Engineering (PF) Phase? Yes Will an external consultant be hired to do the PE work? Yes Delivery Milestones to be met: PE Authorization by 9/30/2025; CON Authorization by 6/30/2028.
PE Authorization Date: 9/30/2025
Environmental Clearance Date: 9/30/2026
Right of Way Clearance Date: 9/30/2026
Final PS&E Date: 9/30/2026
CON Authorization Date: 6/30/2028
Construction Contract Award Date: 12/30/2028
Construction Completion Date: 6/30/2029
Project Close Out Date: 12/30/2029