C. Schedule
For completed phases, provide supporting documentation such as copies of environmental clearance, title sheet of 100% plans with engineer's stamp, or right of way clearance and attach in section J.
Start End
PA & ED:
07/01/2025 06/30/2026
PS & E:
07/01/2025 06/30/2026
ROW:
01/01/2026 11/30/2026
Construction:
01/01/2027 03/31/2028
Close out: 06/30/2028
04/03/2028