7/1/2025
1 RiversideCA.gov1
RiversideCA.gov
FIRST AMENDMENT TO CHARGING STATION SITE LICENSE AGREEMENTWITH ELECTRIFY AMERICACity CouncilJuly 15, 2025Public Utilities Department RiversideCA.gov2

1. Located at 3750 University Avenue City acquired the building on October 13, 20152. RPU funded the purchase and is the building landlord3. 127,533 square feet of rentable office and retail space4. Six-story building, plus a basement level 5. 490 parking stall garage6. 2.5 acres of landMISSION SQUARE BUILDING

7/1/2025
2 RiversideCA.gov3

1. On September 26, 2017, the City Council approved a Supercharger Agreement with Tesla, Inc. for the installation of:a. 12 Tesla Supercharger Stations on the 3rdlevel of the Parking Garage b. 2 Tesla Supercharger Stations on 1stlevel2. On December 12, 2023, the City Council approved a Charging Station Site License Agreement with Electrify America for the construction of six electric vehicle charging stations on Level 1 of the Mission Square Parking GarageBACKGROUND RiversideCA.gov4
First Amendment with Electrify America:1. Increases the number of electric vehicle charging stations from 6 to 8.2. 2 charging stations on Level 1a. ADA designatedb. Improves previous bank drive-thru area currently not utilized 3. 6 charging stations on Level 34. $6,720 site license annual revenueDISCUSSION 7/1/2025
3 RiversideCA.gov5
SITE MAP LEVEL 1
2 ADA EV Stalls with Path of TravelProposed transformerAdd bollardsSwitchboard & 1 power unit with options to punch up to Lvl. 3 RiversideCA.gov6
SITE MAP LEVEL 33 Power Units6 EV stalls
7/1/2025
4 RiversideCA.gov7

1. Term: Ten-year.ௗௗ2. Premises: 8 charging stations on 1,512 square feet and 540 squarefeet for equipment located at 3750 University Avenue, Level 1 andLevel 3 Parking Garage.ௗ3. Effective Date: Date of execution of First Amendment.ௗௗௗ4. Term Commencement: Date on which charging station is firstoperational, or six (6) months after the effective date.5. Termination: May be terminated by Riverside if charging stationsare not operational within twelve (12) months of Effective Date.FIRST AMENDMENT TERMS RiversideCA.gov8

1. Maintenance: Electrify America will be responsible for maintenance costs of chargingstations, charging infrastructure and parking stalls for the duration of the Agreement.ௗௗௗ2. Options to Extend: Electrify America shall have two options to renew for an additionalfive years.ௗௗ3. Expansion: Electrify America shall have the option to expand an additional 1,170square feet for additional charging stations, with approval by the City.4. Infrastructure Improvements:ௗElectrify America accepts the Premises in an “as-is”condition. Electrify America will be responsible for installing any infrastructureimprovements it deems necessary for the installation and operation of the EVcharging stations, at Electrify America’s sole cost and expense.ௗௗ5. Electric Utility Service: Electrify America will be the customer of record for the electricservice required for the EV charging stations and will be responsible for paying allelectric service costs, infrastructure and billing.UNCHANGED AGREEMENT TERMS 7/1/2025
5 RiversideCA.gov9
That the City Council:1. Approve the First Amendment to the Charging Station SiteLicense Agreement with Electrify America for the constructionof eight (8) electric vehicle charging stations at the MissionSquare Parking Garage, located at 3750 University Avenue;and2. Authorize the City Manager, or designee, to execute the LeaseAgreement including making non-substantiative changes.RECOMMENDATIONS