AWARD BID NO. 8165 FOR THE SPC JESUS S. DURAN EASTSIDE LIBRARY PROJECT AT 2060 UNIVERSITY AVENUE TO HORIZONS CONSTRUCTION COMPANYCity CouncilJuly 15, 2025Library RiversideCA.gov2
1. 2019: City Council selects 2060 University Avenue as the site for the new SPC Jesus S. Duran Eastside Library; appropriates $100,000 for architectural design services2. 2023: City Council approves architectural design services for – Phase II – Schematic Design3. 2024: City Council accepts $10,000,000 grant from the California State Library with a $2,500,000 city match4. 2024: City Council accepts $4,500,000 State Targeted Grant from the California State LibraryBACKGROUND 7/3/2025
2 RiversideCA.gov3
JESUS S. DURAN EASTSIDE LIBRARY
RiversideCA.gov4
JESUS S. DURAN EASTSIDE LIBRARY
7/3/2025
3 RiversideCA.gov5
February 26, 2025, Request for Bids publishedMarch 11, 2025, 41 vendors attended pre-bid meetingApril 2, 2025, bid closed with 15 responses received12 of the 15 submissions determined to be responsiveBIDS RiversideCA.gov6
TOTALLOCATIONVENDOR$16,128,715Orange, CAHorizon Construction Company1 $16,410,000Sun Valley, CACABD Construction Inc.2 $16,683,000Ontario, CASpec Construction Co., Inc.3 $16,798,000Los Alamitos, CAPCN3, Inc.4 $17,319,900Ontario, CAPerera Construction5 $17,675,662Long Beach, CANewman Midland Corp.6 $17,695,000Anaheim, CAKeystone Builders Inc.7 $18,500,000Santa Ana, CAArchico Design Build Inc.8 $18,830,000Arcadia, CARoyal Construction Corp.9 $19,160,599Irvine, CAFEC Future Contractors and Engineers Inc.10$19,993,401Tehachapi, CABowe Contractors Inc.11$22,065,000Azusa, CAACC Contractors Inc.12$15,881,380*Anaheim, CA*D.F. Perez Construction Inc.13$16,228,000*Las Vegas, NV*Builders United LLC14$16,335,956*Redlands, CA*Robert Clapper Construction Services Inc.15*Nonresponsive VendorsBID RESULTS 7/3/2025
4 RiversideCA.gov7
REPLACEMENT PARKLAND
•Bobby Bonds Playground•Land and Water Conservation Fund grant •Purchase Replacement land and convert to parkland maintaining compliance RiversideCA.gov8
TOTAL PROJECT BUDGETDescription$ 16,128,715 Construction Agreement (including $150,000 allowance)$ 1,612,872 Contingency 10%$ 17,741,587 Total Construction Cost$ 1,700,000 Architectural Design Services $ 500,000 Project Management, Utility Fees and Permits$ 1,137,515 Furniture, Fixtures, and Equipment (FF&E)$ 500,000 Parkland Replacement$ 21,579,102 SPC Jesus S. Duran Eastside Library Project 7/3/2025
5 RiversideCA.gov9
TOTAL PROJECT FUNDINGTOTAL PROJECT FUNDINGAmountFunding Sources$10,000,000 State Library Round 2 Grant$2,500,000 City Match 25% for State Library Round 2 Grant – General Fund Infrastructure Reserves Appropriation FY23/24$4,500,000 State Targeted Grant$2,100,000 FY2023-2024 Budget Adjustment City Council 6/27/23 - (Measure Z Capital Projects)$1,000,000 General Fund Infrastructure Reserves Appropriation FY23/24$350,8942025/2026 Library Department Land and Building Rental Account (lease)$128,211 McGregor Trust Interest Bearing Account$1,000,000 General Fund Infrastructure Reserves Appropriation FY25/26$21,579,105 Total RiversideCA.gov10
September 2025:Groundbreaking 2ndQuarter 2027: Ribbon Cutting!TIMELINE
7/3/2025
6 RiversideCA.gov11
Strategic Priority No. 1 Arts, Culture & Recreation Goal 1.1 - Strengthen Riverside’s portfolio of arts, culture, recreation, senior and lifelong learning programs and amenities through expanded community partnerships, shared use opportunities and fund development. Cross-Cutting ThreadsSTRATEGIC PLAN ALIGNMENT RiversideCA.gov12
That the City Council:1.Award Bid No. 8165 for the SPC Jesus S. Duran Eastside LibraryProject at 2060 University Avenue to Horizons ConstructionCompany, Orange, California, Including Demolition,Hazardous Abatement, and New Construction, in the Amountof $16,128,715;2. Approve 10% construction contingency in the amount of$1,612,872, for unforeseen conditions or design changes;3. Authorize the City Manager, or designee, to execute theConstruction Services Agreement, including making minor andnon-substantive changes;RECOMMENDATIONS 7/3/2025
7 RiversideCA.gov13
4. Authorize the Chief Financial Officer, or designee, to record aninterdepartmental and interfund transfer and a supplemental appropriationin the amount of $350,894 from the General Fund, Library Land and BuildingRental account to the Capital Outlay Fund, Eastside Library projectaccount;5. With at least five affirmative votes, authorize the Chief Financial Officer, ordesignee, to record a supplemental appropriation and interfund transfer inthe amount of $1,000,000 from the General Fund Infrastructure Reserves intothe Capital Outlay Fund, Eastside Library project account; and6. With at least five affirmative votes, authorize the Chief Financial Officer, ordesignee, to record a supplemental appropriation in the amount of$128,211 in the Grants and Restricted Programs Fund, Eastside Libraryproject account offset by funds transferred from the Interest-Bearing SpecialDeposit Fund Library-Daniels/Miller et al Trust account.RECOMMENDATIONS