12/22/2025
1 RiversideCA.gov1
RiversideCA.gov
MEASURE Z - BID 8168FY 2024/2025 ARTERIAL AND MINOR STREET MAINTENANCECity CouncilJanuary 6, 2026Public Works Department RiversideCA.gov2

1. The Public Works Department utilizes a Pavement Management Program and receives service requests from residents to plan various maintenance improvements throughout the City. 2. Every fiscal year, the Public Works Department budgets a portion of State Gas Tax, County Measure A, and City Measure Z revenues for street rehabilitation of City arterial and minor streets. This project will focus on rehabilitation of streets in poor condition and preserve streets in good condition.BACKGROUND1 2 12/22/2025
2 RiversideCA.gov3

3. On September 17, 2024, the City Council received a list of proposed maintenance locations to be completed with the various Fiscal Year 2024/2025 funding sources. 4. The maintenance improvements in Bid 8168, are locations included in the complete list provided in the report from September 2024. BACKGROUND RiversideCA.gov4

1. Provide rehabilitation improvements for the following arterial streets:•Chicago Avenue from University Avenue to Martin Luther King Boulevard (Resurface 0.49 miles)•Canyon Crest Drive from El Cerrito Drive to Central Avenue (Resurface 0.26 miles)CURRENT PROJECT3 4 12/22/2025
3 RiversideCA.gov5

2. Provide reconstruction, rehabilitation, or preservation improvements for the following collector streets:•Vine Street from Fourteenth Street to Mission Inn Avenue (Resurface 0.32 miles, and Preserve 0.23 miles)•Massachusetts Avenue from Kansas Avenue to Central Avenue (Resurface 0.50 miles)•Dewey Avenue from Hillside Avenue to Juanro Way (Reconstruction 0.45 miles)CURRENT PROJECT RiversideCA.gov6

3. Rehabilitate 0.56 miles of minor streets within four neighborhoods;4. Provide reconstruction or asphalt millings treatment for 0.66 miles of alleyway;5. Reconstruct damaged concrete curbs, gutters, sidewalks, driveways, and non-compliant pedestrian ramps within all rehabilitation locations;CURRENT PROJECT5 6 12/22/2025
4 RiversideCA.gov7

6. Replace existing concrete curb/gutter with pervious curb/gutter on Mulberry Avenue between Marsh Way and Marsh Way;7. Repair 56 linear feet of steel pedestrian handrailing and concrete foundations on Columbia Avenue between Primer Street and East La Cadena Drive;8. Remove hardscape and install drought tolerant plantings and mulch for porkchop islands on First Street and Lemon Street, Lime Street, and Mulberry Street.CURRENT PROJECT RiversideCA.gov8

9. Install new signing and striping throughout as necessary; and10. Install additional traffic bollards at the intersection of Alessandro Boulevard and Trautwein Road.CURRENT PROJECT7 8 12/22/2025
5 RiversideCA.gov9

LOCATION MAP
RiversideCA.gov10

EXISTING CONDITIONSVINE STREET CHICAGO AVENUE
9 10
12/22/2025
6 RiversideCA.gov11

EXISTING CONDITIONSCANYON CREST DRIVE DEWEY AVENUE
RiversideCA.gov12

1. Award a construction contract for Bid No. 8168 for FY 2024/2025 Arterial and Minor Streets Maintenance to Onyx Paving Company, Inc., of Yorba Linda, California, in the amount of $5,555,000; and2. Authorize the City Manager, or his designee, to execute the construction contract, including making minor and non-substantial changes, subject to the availability of budgeted funds.RECOMMENDATIONS11 12