APPENDIX D: PART 4
Project WQMP
www.ContechES.com/filterra | 800-338-112212
Maintenance Checklist
Filterra Inspection & Maintenance Log
Filterra System Size/Model: _____________________________Location: ____________________________________________ Drainage
System Failure Problem Conditions to Check Condition that Should Exist Actions Inlet
Excessive
sediment or trash
accumulation.
Accumulated sediments or
trash impair free flow of water
into Filterra.
Inlet should be free of
obstructions allowing free
distributed flow of water into
Filterra.
Sediments and/or trash should
be removed.
Mulch Cover Trash and floatable
debris accumulation.
Excessive trash and/or debris
accumulation.
Minimal trash or other debris
on mulch cover.
Trash and debris should be
removed and mulch cover raked
level. Ensure bark nugget mulch
is not used.
Mulch Cover “Ponding” of water
on mulch cover.
“Ponding” in unit could be
indicative of clogging due
to excessive fine sediment
accumulation or spill of
petroleum oils.
Stormwater should drain
freely and evenly through
mulch cover.
Recommend contact
manufacturer and replace mulch
as a minimum.
Vegetation Plants not growing
or in poor condition.
Soil/mulch too wet, evidence of
spill. Incorrect plant selection.
Pest infestation. Vandalism to
plants.
Plants should be healthy and
pest free. Contact manufacturer for advice.
Vegetation Plant growth
excessive.
Plants should be appropriate
to the species and location of
Filterra.
Trim/prune plants in accordance
with typical landscaping and
safety needs.
Structure Structure has visible
cracks.
Cracks wider than 1/2 inch
or evidence of soil particles
entering the structure through
the cracks.
Vault should be repaired.
Maintenance is ideally to be performed twice annually.
Date
Mulch &
Debris
Removed
Depth of
Mulch
Added
Mulch
Brand
Height of
Vegetation
Above
Grate
Vegetation
Species
Issues with
System Comments
1/1/17 5 – 5 gal
Buckets 3”
Lowe’s
Premium
Brown Mulch
4’ Galaxy
Magnolia
- Standing water in
downstream structure
- Removed blockage in downstream
structure
www.ContechES.com/filterra | 800-338-1122 13
Filterra Activation Package | Page 1
* UNPREPARED SITE FEE NOTE: A charge of $1500.00 will be invoiced for each activation visit requested by customer where Contech determines that the site does not meet the conditions required for Activation AND/OR acceptable plants are not provided by the contractor. ONLY Contech authorized representatives can perform Activation of Filterra systems; unauthorized activations will void the system warranty and waive manufacturer supplied activation and final inspection.
The Filterra system will be (or has been) delivered to you with protection in place to resist intrusion of construction related sediment which can contaminate the biofiltration media and result in inadequate system performance. These protection devices are intended as a best practice and cannot fully prevent contamination. It is the purchaser’s responsibility to provide adequate measures to prevent construction related runoff from entering the Filterra system.
Included with your purchase is Activation of the Filterra system by the manufacturer as well as a 1-year warranty from delivery of the system and a Final Site Assessment (assessment of unit condition, mulch replacement, debris removal, and pruning of vegetation) scheduled between 6 months and 1 year after Activation, upon request.
Activation of the Filterra system is a procedure completed by the manufacturer to place the system into working condition. This involves the following items:
• Removal of construction runoff protection devices
• Planting of the system’s vegetation (provided by the purchaser) • Placement of pretreatment mulch layer using mulch acceptable for use in Filterra systems.
Activation MUST be provided by the manufacturer to ensure proper site conditions are met for Activation, proper installation of the vegetation, and use of pretreatment mulch acceptable for use in Filterra systems. The purchaser should request Activation from Contech after the site is stabilized, but prior to turning over the site to the owner. Please allow 1-2 weeks to schedule Activation.
The purchaser must ensure that the site is acceptable for Filterra Activation. A checklist (included as page 3 of this document must be completed and submitted to the Contech Activation Coordinator. The minimum 4 requirements for Filterra Activation are as follows:
1. The purchaser must have sourced vegetation meeting the requirements outlined in “Plant Selection for Filterra Systems” starting on page 4 of this document.
FILTERRA® VAULT ACTIVATION PACKAGE
ENGINEERED SOLUTIONS
Appendix 1 – Filterra® Vault Activation Package
~ filterra·
www.ContechES.com/filterra | 800-338-112214
Filterra Activation Package | Page 2
* UNPREPARED SITE FEE NOTE: A charge of $1500.00 will be invoiced for each activation visit requested by customer where Contech determines that the site does not meet the conditions required for Activation AND/OR acceptable plants are not provided by the contractor. ONLY Contech authorized representatives can perform Activation of Filterra systems; unauthorized activations will void the system warranty and waive manufacturer supplied activation and final inspection.
2. The site landscaping must be fully stabilized, i.e. full landscaping installed and some grass cover (not just straw and seed) is required to reduce sediment transport. Construction debris and materials should be removed from surrounding area.
3. Final paving must be completed. Final paving ensures that paving materials will not enter and contaminate the Filterra system during the paving process, and that the plant will receive runoff from the drainage area, assisting with plant survival for the Filterra system.
4. Where curb inlets are included as part of the Filterra system, Filterra throat opening should be at least 4” clear in order to ensure adequate capacity for inflow and debris.
~ .. ·_.:' '. /j·
CAST-lN•PLACE GUTTER ANO THROAT • • .'
OPENING (BY CONTRACTOR PER
LOCAL STANDARDS)
THROAT PROTECTION DEVICE
DO f\lOT REfv!OVE - l~VE IN PLACE
UNTIL SIT~ rs SiABILIZEO ANO
FIL TERRA IS ACTIVATED
~ filterra·
www.ContechES.com/filterra | 800-338-1122 15
Filterra Activation Package | Page 3
* UNPREPARED SITE FEE NOTE: A charge of $1500.00 will be invoiced for each activation visit requested by customer where Contech determines that the site does not meet the conditions required for Activation AND/OR acceptable plants are not provided by the contractor. ONLY Contech authorized representatives can perform Activation of Filterra systems; unauthorized activations will void the system warranty and waive manufacturer supplied activation and final inspection.
Filterra® Vault Activation Checklist
Project Name: ________________________________________Company: ______________________________________________ Site Contact Name: _______________________________________ Site Contact Phone/Email: ____________________________ Site Owner/End User Name: _________________________Site Owner/End User Phone/Email: ____________________________ Preferred Activation Date: ___________________________________ (provide 2 weeks minimum from date this form is submitted) Site
Designation
Top Opening
Type
Final Pavement
Complete
Landscaping
Complete /
Grass Emerging
Construction
materials /
Piles / Debris
Removed
Throat Opening
Measures 4” Min.
Height
(where applicable)
Vegetation
Sourced by
Contractor
Tree Grate
Full Grate
(No tree opening)
Bioscape Vault
(Open Planter)
Verified Verified Verified Verified Species on FT
Plant List
Container Grown
(15 gal. max)
4’ Tall Min. (Tree
grate units only)
____ Qty provided
Tree Grate
Full Grate
(No tree opening)
Bioscape Vault
(Open Planter)
Verified Verified Verified Verified Species on FT
Plant List
Container Grown
(15 gal. max)
4’ Tall Min. (Tree
grate units only)
____ Qty provided
Tree Grate
Full Grate
(No tree opening)
Bioscape Vault
(Open Planter)
Verified Verified Verified Verified Species on FT
Plant List
Container Grown
(15 gal. max)
4’ Tall Min. (Tree
grate units only)
____ Qty provided
Tree Grate
Full Grate
(No tree opening)
Bioscape Vault
(Open Planter)
Verified Verified Verified Verified Species on FT
Plant List
Container Grown
(15 gal. max)
4’ Tall Min. (Tree
grate units only)
____ Qty provided
NOTE: A charge of $1500.00 will be invoiced for each activation visit requested by customer where Contech determines that the site does not meet the conditions required for activation AND/OR acceptable plants are not provided by the contractor. ONLY Contech authorized representatives can perform activation of Filterra systems; unauthorized activations will void the system warranty and waive manufacturer supplied activation and final inspection.
Attach additional sheets as necessary.
Signature Date
ENGINEERED SOLUTIONS
Ct~NTECH®
□ □ □ □ □ □
□
□
□
□
□ □ □ □ □ □
□
□
□
□
□ □ □ □ □ □
□
□
□
□
□ □ □ □ □ □
□
□
□
□
~ filterra·
www.ContechES.com/filterra | 800-338-112216
Filterra Activation Package | Page 4
* UNPREPARED SITE FEE NOTE: A charge of $1500.00 will be invoiced for each activation visit requested by customer where Contech determines that the site does not meet the conditions required for Activation AND/OR acceptable plants are not provided by the contractor. ONLY Contech authorized representatives can perform Activation of Filterra systems; unauthorized activations will void the system warranty and waive manufacturer supplied activation and final inspection.
Planting Selection for Filterra® Vault Systems
All Filterra systems require vegetation for proper long-term performance. As indicated in the Activation Package, the Contractor is responsible for sourcing the proper vegetation prior to Activation. Contech or a Contech representative will install the vegetation during the Activation process.
Contractors should identify the Top Opening style for each Filterra requiring Activation on the Activation Checklist. Contech offers three types, which are detailed on page 5 of this document:
• Vault with Tree Grate
• Vault with Full Grate
• Bioscape / Open Planter
Contractors must ensure the vegetation meets the following 4 requirements:
1. Select plant(s) as specified in the engineering plans and specifications AND that are listed on Contech’s Configuration Specific Plant Lists**.
2. All plants MUST be container-grown in nursery containers no larger than 15 gallons. Crated and/or Ball/Burlap plants are NOT permitted.
3. For Vaults with Tree Grates, plant height must be 4’ Minimum, from soil surface to top of plant.
4. Provide plant quantities per the following guidance:
• Vault with Tree Grate – 1 per Tree Grate
• Vault with Full Grate – 4-5 Small or Extra Small Grasses per Full Grate • Bioscape – Quantities should be selected based on plant palette options found starting on page 6 of this document.
If Contech or Contech’s representative shows up for Activation and any of the 4 requirements above are not met, Activation cannot be performed and the Contractor will be billed a $1,500 Unprepared Site fee*.
Some additional vegetation recommendations for the best possible Activation and Installation are as follows:
• Select plant(s) with full root development but not to the point where root bound. • For Filterra systems with a Tree Grate, select plants with taller trunks. Lower branches can be pruned away provided there are sufficient branches above the grate for tree or shrub development. • For Filterra systems with a Tree Grate, plant(s) should have a single trunk at installation. • Plant species shall not have a mature height greater than 30 feet. ** In some cases, Contech may consider alternate plant species as approved by the Product Manager. Please list the plant name in the space below and submit this sheet to your Contech Activation Coordinator. If the plant species is approved, either the Product Manager or the Activation Coordinator will sign the form and return to you for inclusion with your Activation Checklist.
Requested Plant Species: ___________________________________________ Approved: _______________________________ Date: ____________________________________
~ filterra·
www.ContechES.com/filterra | 800-338-1122 17
Filterra Activation Package | Page 5
* UNPREPARED SITE FEE NOTE: A charge of $1500.00 will be invoiced for each activation visit requested by customer where Contech determines that the site does not meet the conditions required for Activation AND/OR acceptable plants are not provided by the contractor. ONLY Contech authorized representatives can perform Activation of Filterra systems; unauthorized activations will void the system warranty and waive manufacturer supplied activation and final inspection.
Figure 1a. Filterra with Tree Grate Drawing
Figure 2a. Filterra with Full Grate Drawing
Figure 3a. Filterra Bioscape Vault Drawing
Figure 1b. Filterra with Tree Grate Photo (not yet planted) Figure 2b. Filterra with Full Grate Photo
Figure 3b. Filterra Bioscape Vault Photo
Filterra® Top Opening Examples
Filterra® Vault with Tree Grate
Filterra® Vault with Full Grate
Filterra® Bioscape Vault
r(OJ(
a.EA"'WI
(CJ\.'IT•I•
~
~
--L_---/-....l:::::=====l --J_.!...._ _j
F~'tFACC
OfCIJE(B
3,a-~~Tll:EE
GMTE
(CA$ TSN)
.llt".)(3&- At;i,
flA.lGAAlE
!CAST•f~)
~ filterra·
www.ContechES.com/filterra | 800-338-112218
Filterra Activation Package | Page 6
* UNPREPARED SITE FEE NOTE: A charge of $1500.00 will be invoiced for each activation visit requested by customer where Contech determines that the site does not meet the conditions required for Activation AND/OR acceptable plants are not provided by the contractor. ONLY Contech authorized representatives can perform Activation of Filterra systems; unauthorized activations will void the system warranty and waive manufacturer supplied activation and final inspection.
Filterra® Bioscape Vault Plant Palettes
KEY: (refer to plant lists for species sizing)
4x4 Media Bay A.
3 A.
5 A.
6 A.
6 A.
9 A.
12 A.
15 A. 20 B. 6 C. 3 D. 2
B.
1 B.
2 B.
2 B.
2 B.
3 B.
3 B.
4 C.
1 C.
1 C.
1 D.
1 D.
1 D.
1 D.
1 D.
1 C.
1 C.
2 C.
2 C.
2 4x6/6x4 Media Bay
4x8/8x4 &
4.5x7.83/7.83x4.5
Media Bay
6x6 Media Bay
6x8/8x6 Media
Bay
6x10/10x6 &
8x8 Media Bay
6x12/12x6 Media
Bay
7x13/13x7/12x8 &
14x8 Media Bay
A. EXTRA SMALL GRASS
• Up to 2’ mature spread
• 1-2 gallon typical (1 gal. minimum)
B. SMALL GRASS/SHRUB
• 2’-4’ mature spread
• 1-7 gallon typical
C. MEDIUM SHRUB
• 4’-6’ mature spread
• 1-7 gallon typical
D. LARGE SHRUB OR EXTRA LARGE SHRUB OR TREE
• 6’ mature spread and greater, 30’ max. mature
height
• Up to 15 gallon maximum
NOTE: For larger vaults and in-ground
Filterra Bioscape systems, palettes can be
scaled (i.e. Qty 6 of the 22x8 Palette can be
used for a 1056 sf Filterra Bioscape).
MIX & MATCH SUBSTITUTION OPTIONS:
1 Large Shrub or Extra Large Shrub or Tree
• 2 Medium Shrubs
• 4 Small Grass/SHrubs
• 12 Extra Small Grasses
1 Medium Shrub
• 2 Small Grass/Shrubs
• 6 Extra Small Grasses
1 Small Grass/Shrub
• 3 Extra Small Grasses
~ filterra·
www.ContechES.com/filterra | 800-338-1122 19
Filterra Activation Package | Page 7
* UNPREPARED SITE FEE NOTE: A charge of $1500.00 will be invoiced for each activation visit requested by customer where Contech determines that the site does not meet the conditions required for Activation AND/OR acceptable plants are not provided by the contractor. ONLY Contech authorized representatives can perform Activation of Filterra systems; unauthorized activations will void the system warranty and waive manufacturer supplied activation and final inspection.
A. 24
A. 28
A. 32
A. 36
B. 8
B. 8
B. 10
B. 10
C. 4
C. 4
C. 5
C. 5
D. 2
D. 2
D. 3
D. 3
16x8 & 15x9
Media Bay
18x8 Media Bay
20x8 Media Bay
22x8 Media Bay
~~~~~~~~ 1 ~~~~~ 1 ~~~~~~~~ ~~~~~
~~~~~~~~ ~~~~~
~~~~~~~~ ~~~~~
...____________ '-------------- .____I L---
~ filterra·
Appendix 2 – Filterra® Tree Grate Opening Expansion Procedure The standard grates used on all Filterra configurations that employ Tree Grates are fabricated with a 6” opening that is designed with a breakaway section that can be removed, allowing the grate opening to be expanded to 12” as the tree matures and the trunk widens.
The following tools are required to expand the opening:
• Mini sledgehammer (3 lb. or greater)
• Safety Glasses / Goggles
The following guidelines should be followed to properly expand the tree opening from 6” to 12”:
1. Remove the grate from the Filterra frame, place it flat on a hard surface, and support the grate by stepping on the edge or using other weighted items such as a few mulch bags if this is being done during a Filterra maintenance event. Put on safety glasses/goggles. Align the mini sledgehammer as shown in the figure to the left. The head of the sledgehammer should be aimed just inside the wide cast iron bar between the larger grate section and the breakaway section.
2. Repeatedly hit the grate at this spot with the mini sledgehammer.
3. After several hits, the breakaway section should snap cleanly off of the larger grate section. Reinstall the grate into the Filterra grate frame. Recycle or dispose of the breakaway section per local guidelines.
Notes
___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ Notes
___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ Notes
___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ PDF 1/23
© 2023 Contech Engineered Solutions LLC, a QUIKRETE Company 9100 Centre Pointe Drive, Suite 400
West Chester, OH 45069
[email protected] | 800-338-1122
www.ContechES.com
ALL RIGHTS RESERVED. PRINTED IN THE USA.
NOTHING IN THIS CATALOG SHOULD BE CONSTRUED AS A WARRANTY . APPLICATIONS SUGGESTED HEREIN ARE DESCRIBED
ONLY TO HELP READERS MAKE THEIR OWN EVALUATIONS AND DECISIONS, AND ARE NEITHER GUARANTEES NOR WARRANTIES OF SUITABILITY FOR ANY APPLICATION. CONTECH MAKES NO WARRANTY WHATSOEVER, EXPRESS OR IMPLIED, RELATED TO THE APPLICATIONS, MATERIALS, COATINGS, OR PRODUCTS DISCUSSED HEREIN. ALL IMPLIED WARRANTIES OF MERCHANTABILITY AND ALL IMPLIED WARRANTIES OF FITNESS FOR ANY PARTICULAR PURPOSE ARE DISCLAIMED BY CONTECH.
SEE CONTECH’S CONDITIONS OF SALE (AVAILABLE AT WWW.CONTECHES.COM/COS) FOR MORE INFORMATION.
ENGINEERED SOLUTIONS
® fi lterra:
Bioretention Systems
STORMWATER POLLUTANT SOURCES/SOURCE CONTROL CHECKLIST
IF THESE SOURCES WILL BE ... THEN YOUR WQMP SHOULD INCLUDE THESE SOURCE CONTROL BMPs, AS APPLICABLE ON THE PROJECT SITE ... 1 2 3 4
Potential Sources of Permanent Controls-Show on Permanent Controls-List in WQMP Operational BMPs-lnclude in WQMP Runoff Pollutants WQMP Drawings Table and Narrative Table and Narrative □ K. Vehicle/Equipment □ Accommodate all vehicle □ State that no vehicle repair or In the Stormwater Control Plan, note Repair and equipment repair and maintenance maintenance will be done outdoors, that all of the following restrictions Maintenance indoors. Or designate an outdoor or else describe the required apply to use the site:
work area and design the area to features of the outdoor work area. □ No person shall dispose of, nor permit prevent run-on and runoff of □ State that there are no floor drains the disposal, directly or indirectly of stormwater. or if there are floor drains, note the vehicle fluids, hazardous materials, or □ Show secondary containment for agency from which an industrial rinsewater from parts cleaning into exterior work areas where motor waste discharge permit will be storm drains. oil, brake fluid, gasoline, diesel obtained and that the design meets □ No vehicle fluid removal shall be fuel, radiator fluid, acid-containing that agency's requirements. performed outside a building, nor on batteries or other hazardous □ State that there are no tanks, asphalt or ground surfaces, whether materials or hazardous wastes are used or stored. Drains shall not be containers or sinks to be used for inside or outside a building, except in installed within the secondary parts cleaning or rinsing or, if there such a manner as to ensure that any are, note the agency from which an spilled fluid will be in an area of containment areas. industrial waste discharge permit secondary containment. Leaking □ Add a note on the plans that states will be obtained and that the vehicle fluids shall be contained or either (1) there are no floor drains, design meets that agency's drained from the vehicle immediately. or (2) floor drains are connected to requirements. No person shall leave unattended drip wastewater pretreatment systems □ parts or other open containers prior to discharge to the sanitary containing vehicle fluid, unless such sewer and an industrial waste containers are in use or in an area of discharge permit will be obtained. secondary containment.
Refer to "Automotive Maintenance & Car
Care Best Management Practices for Auto
Body Shops, Auto Repair Shops, Car
Dealerships, Gas Stations and Fleet
Service Operations". Brochure can be
found at http:LLrdlood.orgLstorm:i,£aterL
Refer to Outdoor Cleaning Activities and
Professional Mobile Service Providers for
many of the Potential Sources of
Runoff Pollutants categories below.
Brochure can be found at
http: L Lrdlood.orgLstormwater L
STORMWATER POLLUTANT SOURCES/SOURCE CONTROL CHECKLIST
IF THESE SOURCES WILL BE ... THEN YOUR WQMP SHOULD INCLUDE THESE SOURCE CONTROL BMPs, AS APPLICABLE ON THE PROJECT SITE ... □
1 2 3 4
Potential Sources of Permanent Controls-Show on Permanent Controls-List in WQMP Operational BMPs-lnclude in WQMP Runoff Pollutants WQMP Drawings Table and Narrative Table and Narrative L. Fuel Dispensing □ Fueling areas 6 shall have □ The property owner shall dry sweep Areas impermeable floors (i.e., portland the fueling area routinely. cement concrete or equivalent □ See the Fact Sheet SD-30, "Fueling smooth impervious surface) that Areas" in the CASQA Stormwater are: a) graded at the minimum Quality Handbooks at slope necessary to prevent ponding; www.cabmphandbooks.com and b) separated from the rest of the site by a grade break that
prevents run-on of stormwater to
the maximum extent practicable.
□ Fueling areas shall be covered by a
canopy that extends a minimum of
ten feet in each direction from each
pump. [Alternative: The fueling
area must be covered and the
cover's minimum dimensions must
be equal to or greater than the area
within the grade break or fuel
dispensing area 1.] The canopy [or
cover] shall not drain onto the
fueling area .
6 The fueling area shall be defined as the area extending a minimwn of 6.5 feet from the comer of each fuel dispenser or the length at which the hose and nozzle assembly may be operated plus a minimwn of one foot, whichever is greater.
STORMWATER POLLUTANT SOURCES/SOURCE CONTROL CHECKLIST
IF THESE SOURCES WILL BE ... THEN YOUR WQMP SHOULD INCLUDE THESE SOURCE CONTROL BMPs, AS APPLICABLE ON THE PROJECT SITE ... 1 2 3 4
Potential Sources of Permanent Controls-Show on Permanent Controls-List in WQMP Operational BMPs-lnclude in WQMP Runoff Pollutants WQMP Drawings Table and Narrative Table and Narrative □ M. Loading Docks □ Show a preliminary design for the □ Move loaded and unloaded items loading dock area, including indoors as soon as possible. roofing and drainage. Loading □ See Fact Sheet SC-30, "Outdoor docks shall be covered and/ or Loading and Unloading," in the graded to minimize run-on to and CASQA Stormwater Quality runoff from the loading area . Roof Handbooks at downspouts shall be positioned to www.cabmphandbooks.com direct stormwater away from the loading area. Water from loading
dock areas shall be drained to the
sanitary sewer, or diverted and
collected for ultimate discharge to
the sanitary sewer.
□ Loading dock areas draining
directly to the sanitary sewer shall
be equipped with a spill control
valve or equivalent device, which
shall be kept closed during periods
of operation.
□ Provide a roof overhang over the
loading area or install door skirts
( cowling) at each bay that enclose
the end of the trailer.
STORMWATER POLLUTANT SOURCES/SOURCE CONTROL CHECKLIST
IF THESE SOURCES WILL BE ... THEN YOUR WQMP SHOULD INCLUDE THESE SOURCE CONTROL BMPs, AS APPLICABLE ON THE PROJECT SITE ... 1 2 3 4
Potential Sources of Permanent Controls-Show on Permanent Controls-List in WQMP Operational BMPs-lnclude in WQMP Runoff Pollutants WQMP Drawings Table and Narrative Table and Narrative □ N. Fire Sprinkler Test □ Provide a means to drain fire □ See the note in Fact Sheet SC-41, Water sprinkler test water to the sanitary "Building and Grounds Maintenance," sewer. in the CASQA Stormwater Quality
Handbooks at
www.cabmphandbooks.com
O. Miscellaneous Drain □ Boiler drain lines shall be directly or Wash Water or Other or indirectly connected to the
Sources sanitary sewer system and may not
□ Boiler drain lines discharge to the storm drain
□ system .
□ Condensate drain lines Condensate drain lines may
□ Rooftop equipment discharge to landscaped areas if the □ Drainage sumps flow is small enough that runoff
will not occur . Condensate drain
□ Roofing, gutters, and lines may not discharge to the
trim . □
storm drain system .
□ Other sources Rooftop equipment with potential
to produce pollutants shall be
□ roofed and/ or have secondary
containment .
Any drainage sumps on-site shall
□ feature a sediment sump to reduce
the quantity of sediment in
pumped water .
□ Avoid roofing, gutters, and trim
made of copper or other
unprotected metals that may leach
into runoff.
Include controls for other sources
as specified by local reviewer.
STORMWATER POLLUTANT SOURCES/SOURCE CONTROL CHECKLIST
IF THESE SOURCES WILL BE ... THEN YOUR WQMP SHOULD INCLUDE THESE SOURCE CONTROL BMPs, AS APPLICABLE ON THE PROJECT SITE ... 1 2 3 4
Potential Sources of Permanent Controls-Show on Permanent Controls-List in WQMP Operational BMPs-lnclude in WQMP Runoff Pollutants WQMP Drawings Table and Narrative Table and Narrative Iii P. Plazas, sidewaJks, ii Sweep plazas, sidewaJks, and parking and parking lots. lots regularly to prevent accumulation of litter and debris. Collect debris from
pressure washing to prevent entry into
the storm drain system. Collect
washwater containing any cleaning
agent or degreaser and discharge to
the sanitary sewer not to a storm drain.
Appendix 9: O&M
Operation and Maintenance Plan and Documentation of Finance, Maintenance and Recording Mechanisms - 29 -
Recorder’s
(“Declarant”),
“A”,
Declarant has applied to the City of Riverside (“City”) for the construction maintain the Best Management Practices (“BMPs”) as described in the approved project specific WHEN RECORDED MAIL TO:
City Surveyor
City of Riverside
City Hall, 3900 Main Street
Riverside, CA 92522
Planning Case: TBD
For Office Use Only
COVENANT AND AGREEMENT
ESTABLISHING NOTIFICATION PROCESS AND RESPONSIBILITY FOR
WATER QUALITY MANAGEMENT PLAN IMPLEMENTATION AND MAINTENANCE
THIS COVENANT AND AGREEMENT FOR WATER QUALITY
MANAGEMENT PLAN IMPLEMENTATION AND MAINTENANCE is made and entered into this __ day of~-------~ 2 0 23, by _____________ _ with reference to the following facts:
A. Declarant is the fee owner of the real property ( the "Property") situated in the City of Riverside, County of Riverside, State of California, and legally described in Exhibit which is attached hereto and incorporated within by reference.
B.
of GP-2022-02467 located at 4618 Jones Avenue and 4663 Hedrick Avenue in Riverside C. As a condition of approval and prior to the map recordation and/or issuance of any permits, the City is requiring Declarant to execute and record an agreement stating that the future property owners shall be informed of the requirements to implement and Water Quality Management Plan.
D. Declarant intends by this document to comply with the conditions imposed by the City and to impose upon the Property mutually beneficial restrictions, conditions, covenants and agreements for the benefit of Property.
NOW, THEREFORE, for the purposes of complying with the conditions imposed by the City of Riverside for the approval of Planning Case TBD, Declarant hereby declares that the Property is and hereafter shall be held, conveyed, transferred, mortgaged, encumbered, leased, rented, used, occupied, sold and improved subject to the following declarations, limitations, covenants, conditions, restrictions and easements, all of which are imposed as equitable servitudes pursuant to a general plan for the development of the Property for the purpose of enhancing and protecting the value and attractiveness of the Property, and or Declarant’s attorney’s
each Parcel thereof, in accordance with the plan for the improvement of the Property, and to comply with certain conditions imposed by the City for the approval of TBD and shall be binding and inure to the benefit of each successor and assignee in interest of each such party.
Any conveyance, transfer, sale, assignment, lease or sublease made by Declarant of a Parcel of the Property shall be and hereby is deemed to incorporate by reference all the provisions of the Covenant and Agreement including, but not limited to, all the covenants, conditions, restrictions, limitations, grants of easement, rights, rights-of-way, and equitable servitude contained herein.
1. This Covenant and Agreement hereby establishes a notification process for future individual property owners to ensure they are subject to and adhere to the Water Quality Management Plan implementation measures and that it shall be the responsibility of the Declarant, its heirs, successors and assigns to implement and maintain all Best Management Practices (BMPs) in good working order.
2. Declarant shall use its best efforts to diligently implement and maintain all BMPs in a manner assuring peak performance at all times. All reasonable precautions shall be exercised by Declarant, its heirs, successors, and assigns, in the removal and extraction of any material(s) from the BMPs and the ultimate disposal of the material(s) in a manner consistent with all relevant laws and regulations in effect at the time. As may be requested from time to time by the City, Declarant, its heirs, successors, and assigns shall provide the City with documentation identifying the material(s) removed, the quantity, and disposal destination.
3. In the event Declarant, or its heirs, successors or assigns, fails to undertake the maintenance contemplated by this Covenant and Agreement within twenty-one (21) days of being given written notice by the City, or fails to complete any maintenance contemplated by this Covenant and Agreement with reasonable diligence, the City is hereby authorized to cause any maintenance necessary to be completed and charge the entire cost and expense to the Declarant successors or assigns, including administrative costs, reasonable fees and interest thereon at the maximum rate authorized by the Civil Code from the date of the notice of expense until paid in full. As an additional remedy, the Public Works Director may withdraw any previous urban runoff-related approval with respect to the Property on which BMPs have been installed and/or implemented until such time as Declarant, its heirs, successors, or assigns, repays to City its reasonable costs incurred in accordance with this paragraph.
4. Any person who now or hereafter owns or acquires any right, title or interest in or to any parcel of the Property shall be deemed to have consented and agreed to every covenant, condition, restriction and easement contained herein.
5. In addition, each of the provisions hereof shall operate as covenants running with the land for the benefit of the Property and each Parcel thereof and shall inure to the benefit of all owners of the Parcels thereof, their successors and assigns in interest, and shall apply to and bind each successive owner of each Parcel, their successors and assigns in interest.
6. The terms of this Covenant and Agreement may be enforced by the City, its successors or assigns, and by any owner, lessee or tenant of the Parcels of the Property. attorneys’
Should the City or any owner, lessee or tenant bring an action to enforce any of the terms of this Covenant and Agreement, the prevailing party shall be entitled to costs of suit including reasonable fees.
7. Subject to the prior written approval of the City by its Public Works Director, any provision contained herein may be terminated, modified or amended as to all of the Property or any portion thereof. No such termination, modification or amendment shall be effective until there shall have been executed, acknowledged, and recorded in the Office of the Recorder of Riverside County, California, an appropriate instrument evidencing the same including the consent thereto by the City.
IN WITNESS WHEREOF, Declarant has caused this Covenant and Agreement to be executed as of the day and year first written above.
Name:
Title:
APPROVED AS TO FORM:
Name:
Deputy City Attorney
APPROVED AS TO CONTENT
Name: Gilbert M. Hernandez
Public Works Department:
EXIIIBITA
(Legal Description)
ACKNOWLEDGMENT
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.
State of California
County of _______________ __,
On _____________ ~ before me, _____________ ~ a
notary public, personally appeared _________________ _, who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.
WITNESS my hand and official seal.
___________ (SEAL)
Signature
ACKNOWLEDGMENT
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.
State of California
County of _______________ __,
On _____________ ~ before me, _____________ ~ a
notary public, personally appeared _________________ _, who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.
WITNESS my hand and official seal.
___________ (SEAL)
Signature
All BMP included as part of the project WQMP are required to be maintained through regular scheduled operation and maintenance (refer to Section 8, Post Construction BMP Requirements, in the TGD for WQMP). Fully complete Form 5-1 summarizing all BMP included in the WQMP. Attach additional forms as needed. The WQMP shall also include a detailed Operation and Maintenance Plan for all BMP and may require a Maintenance Agreement (consult the jurisdictions LIP). If a Maintenance Agreement is required, it must also be attached to the WQMP.
Non-Structural Source Control BMPs
N1: Education for
Property Owners,
Tenants and
Occupants
Owner/Lessee
Have educational and BMP materials
(attachments) available to distribute/review to
tenants, employees, and contractors. Employees
and contractors must be trained on and aware of
this WQMP
Information to be
given to owner/rep
upon sale and
annually
thereafter.
N2: Activity
Restrictions Owner/Lessee
Restrictions are to be presented to employees,
contractors, and tenants for activities that
contribute to stormwater pollution. Employees
and contractors shall be trained to monitor for
evidence of performed restricted activities.
Continuous
N3: SC-41 Common
Area Landscape
Management
Owner/Lessee
Maintenance trimming; mowing; weeding;
removal of litter; fertilizing; water conservation;
replacement of dead, diseased, or dying plants;
properly dispose of waste; minimize pesticide and
fertilizer use and apply in accordance with
governing regulations.
Bi-Weekly
N4: BMP
Maintenance Owner/Lessee
Identification of responsibility for
implementation of each non-structural BMP and
scheduled cleaning of all BMP structural facilities.
As required
N11: SC-41 Common
Area Litter Control Owner/Lessee Closing lids of waste receptacles. Keep trash receptacle area clean. Empty containers before
Weekly sweeping
and trash pick-up.
Operations and Maintenance Responsibility
for Post Construction BMP
Form 5-1 BMP Operation and Maintenance
(use additional forms as necessary)
BMP Reponsible Operation/ Maintenance
Party(s) Activities Required
Minimum Frequency
of Activities
6-1
they are full. Picking up litter and debris from
site.
Daily inspection of
trash receptacles.
N14: SC-44 Common
Area Catch Basin
Inspection
Owner/Lessee Remove waste and debris. Repair any damages.
Once every three
months, once
within 5 days of
October 1st, and
after every
rainstorm event.
N15:SC-43 Sweeping
of street and parking
structure
Owner/Lessee Sweep parking lot and properly dispose of trash and material.
Every two weeks,
and once within 5
days of October
1st.
Structural Source Control BMPs
S1: SD-13 Provide
storm drain system
stenciling and
signage
Owner/Lessee
All catch basins where applicable in paved areas,
will be marked or stenciled with Only Rain
Down the Storm Drain. This will be done in a
location that can be clearly seen by all and will
be routinely inspected and relabeled, as
necessary. Thereafter, the owner/ lessee shall
routinely inspect and re-label the catch basins,
as necessary
Catch basin labels
will be inspected
once annually
and relabeled as
necessary to
maintain
legibility.
S3: SD-32 Trash
Storage Areas Owner/Lessee
Closing lids of waste receptacles. Keep trash
receptacle area clean. Empty containers before
they are full. Picking up litter and debris from
site.
Weekly sweeping
and trash pick-
up. Daily
inspection of
trash receptacles.
S4: SD-12 Efficient
Irrigation Systems Owner/Lessee
Minimize timing and application methods for
watering project landscaping in common areas
to limit amount of non-storm water discharge.
Inspect irrigation system with landscaping
maintenance to ensure timers, shut off valves
and other automatic irrigation devices are
functioning adequately. Inspect system for
broken parts and replace as needed to prevent
leaks. BMP shall be implemented by the owner/
lessee, through the landscape maintenance
contractor.
Monthly with
landscaping
maintenance
activities.
S5 Finish grade of
landscaped areas at a
minimum of 1-2
Owner/Lessee Maintain vegetation height to ensure area has ponding capacity. Inspect area for standing
Monthly with
landscaping
maintenance
6-2
below top of curb,
sidewalk or
pavement
water, saturated soil or other nuisance
conditions. Repair as needed.
activities and
after irrigation or
storm events
Treatment BMPs
ADS-Flexstorm FTC
Insert Owner/Lessee
Empty filter bag, remove compacted silt, wring
PCP style bags to recover retained oils, dispose of
oil contaminated products and recovered oils in
accordance with EPA guidelines, inspect bags &
replace if needed.
Following rain
events greater
than ½, filter
inspections
minimum 3 times
per year, industrial
inspections 4
times per year.
Biotreatment BMP
Filterra
Owner/Lessee See attached maintenance manuals in Appendix 10: Educational Materials. As required
6-3
Appendix 10: Educational Materials
BMP Fact Sheets, Maintenance Guidelines and Other End-User BMP Information - 30-
FlexStorm Pure™
Inlet Filters
FlexStorm Pure inlet filters are the preferred choice for permanent inlet protection and stormwater runoff control. Constructed of stainless steel, FlexStorm Pure inlet filters will fit any drainage structure and are available with site-specific filter bags providing various levels of filtration.
Applications
• Carwashes
• Commercial
• Loading ramps
• Industrial
Features
• Custom stainless steel frames are configured to fit
into any drainage structure
• Flow and bypass rates meet specific inlet
requirements
• Works below grade with bypass to drain area if bag
is full
• Installed and maintained by one worker, without
additional equipment
///NY&.
• Gas stations
• Parking lots
• Dock drains
• Maintenance
Benefits
• Stainless steel frame provides extended service life
• Easily replaceable filter bags
• Meets stringent removal requirements:
- All bags rated >80% removal efficiency of street
sweep-size particles
- Optional FXP/PCP bags can be used for
hydrocarbon removal when required
FlexStorm Pure Inlet Filters Specification
Material and Performance
The filter is comprised of a stainless steel frame and a replaceable geotextile filter bag attached to the frame with a stainless steel locking band. The filter bag hangs suspended below the grate that shall allow full bypass flow into the drainage structure if the bag is completely filled with sediment. The standard woven polypropylene "FX" filters bags are rated for 200 gpm/sqft with a removal efficiency of 82% when filtering a USDA Sandy Loam sediment load. The post-construction PCP filter bags are rated for 137 gpm/sqft and have been third-party tested at 99% TSS removal.
Installation
1. Remove the grate from the inlet.
2. Clean debris from the ledges of the inlet.
3. Place the inlet filter onto the load bearing ledges of the structure.
4. Replace the grate and confirm it is not elevated more than 1/s" (3 mm).
Frequency of Inspections
1. Inspection should occur following rain events greater than½" (13 mm).
2. Filter inspections should occur a minimum of three times per year, and in snowfall affected regions, inspections prior to and after snowfall season.
3. Industrial application site inspections (loading ramps, wash racks & maintenance facilities) to be scheduled on a recurring basis no less than four times per year or as needed.
Maintenance Guidelines
1. Empty the filter bag manually or by industrial vacuum taking care not to damage the geotextile bag when more than half filled or during scheduled inspection period.
2. Remove compacted silt from sediment bag and flush with medium spray.
3. "PCP" style bags should be pressed or wrung to recover retained oils.
4. Oil skimmer pouches solidify and darken when saturated, indicating time for replacement.
5. Dispose of all oil-contaminated products and recovered oils in accordance with EPA guidelines. Oil skimmer pouches, since a solidifier, will not leach and can be disposed of directly.
6. Inspect and replace bag if torn or punctured.
Filter Bag Replacement
1. Remove the bag by loosening or cutting off clamping band.
2. Take the new correctly sized sediment bag and secure hose clamping band to the frame channel as previously removed.
3. Ensure bag is secure and there is no slack around perimeter.
ADS "Terms and Conditions of Sale" are available on the ADS website, www.adspipe.com.
ADS™, FlexStorm Pure™ and the Green Stripe are registered trademarks of Advanced Drainage Systems, Inc. © 2022 Advanced Drainage Systems, Inc. #10892 05/22 MH
adspipe.com
800-821-6710
Filterra® Maintenance Steps
Contech has created a network of Certified Maintenance Providers (CCMP’s) to provide maintenance on Filterra systems. To find a CCMP in your area please visit www.conteches.com/maintenance
1. Inspection of Filterra and
surrounding area
2. Removal of tree grate and
erosion control stones
3. Removal of debris, trash
and mulch
4. Mulch replacement
5. Clean area around Filterra
6. Complete paperwork and record plant
height and width
© 2015 Contech Engineered Solutions LLC
ENGINEERED SOLUTIONS
@
filterra:
Bioretention Systems
A Growing Idea in Stormwater F1ltrat1on
Filterra Activation Package | Page 1
* UNPREPARED SITE FEE NOTE: A charge of $1500.00 will be invoiced for each activation visit requested by customer where Contech determines that the site does not meet the conditions required for Activation AND/OR acceptable plants are not provided by the contractor. ONLY Contech authorized representatives can perform Activation of Filterra systems; unauthorized activations will void the system warranty and waive manufacturer supplied activation and final inspection.
The Filterra system will be (or has been) delivered to you with protection in place to resist intrusion of construction related sediment which can contaminate the biofiltration media and result in inadequate system performance. These protection devices are intended as a best practice and cannot fully prevent contamination. It is the purchaser’s responsibility to provide adequate measures to prevent construction related runoff from entering the Filterra system.
Included with your purchase is Activation of the Filterra system by the manufacturer as well as a 1-year warranty from delivery of the system and a Final Site Assessment (assessment of unit condition, mulch replacement, debris removal, and pruning of vegetation) scheduled between 6 months and 1 year after Activation, upon request.
Activation of the Filterra system is a procedure completed by the manufacturer to place the system into working condition. This involves the following items:
• Removal of construction runoff protection devices
• Planting of the system’s vegetation (provided by the purchaser) • Placement of pretreatment mulch layer using mulch acceptable for use in Filterra systems.
Activation MUST be provided by the manufacturer to ensure proper site conditions are met for Activation, proper installation of the vegetation, and use of pretreatment mulch acceptable for use in Filterra systems. The purchaser should request Activation from Contech after the site is stabilized, but prior to turning over the site to the owner. Please allow 1-2 weeks to schedule Activation.
The purchaser must ensure that the site is acceptable for Filterra Activation. A checklist (included as page 3 of this document must be completed and submitted to the Contech Activation Coordinator. The minimum 4 requirements for Filterra Activation are as follows:
1.The purchaser must have sourced vegetation meeting the requirements outlined in “Plant Selection for Filterra Systems” starting on page 4 of this document.
FILTERRA® VAULT ACTIVATION PACKAGE
ENGINEERED SOLUTIONS
~ filterra·
Filterra Activation Package | Page 2
* UNPREPARED SITE FEE NOTE: A charge of $1500.00 will be invoiced for each activation visit requested by customer where Contech determines that the site does not meet the conditions required for Activation AND/OR acceptable plants are not provided by the contractor. ONLY Contech authorized representatives can perform Activation of Filterra systems; unauthorized activations will void the system warranty and waive manufacturer supplied activation and final inspection.
2.The site landscaping must be fully stabilized, i.e. full landscaping installed and some grass cover (not just straw and seed) is required to reduce sediment transport. Construction debris and materials should be removed from surrounding area.
3.Final paving must be completed. Final paving ensures that paving materials will not enter and contaminate the Filterra system during the paving process, and that the plant will receive runoff from the drainage area, assisting with plant survival for the Filterra system.
4.Where curb inlets are included as part of the Filterra system, Filterra throat opening should be at least 4” clear in order to ensure adequate capacity for inflow and debris.
CAST-IN-PLACE GUTTER AND THROAT
OPENING (BY CONTRACTOR PER
LOCAL STANDARDS)
THROAT PROTECTION DEVICE
DO NOT REMOVE - LEAVE IN PLACE
UNTIL SITE IS STABILIZED AND
FIL TERRA IS ACTIVATED
~ filterra·
Filterra Activation Package | Page 3
* UNPREPARED SITE FEE NOTE: A charge of $1500.00 will be invoiced for each activation visit requested by customer where Contech determines that the site does not meet the conditions required for Activation AND/OR acceptable plants are not provided by the contractor. ONLY Contech authorized representatives can perform Activation of Filterra systems; unauthorized activations will void the system warranty and waive manufacturer supplied activation and final inspection.
Filterra® Vault Activation Checklist
Project Name: ________________________________________Company: ______________________________________________ Site Contact Name: _______________________________________ Site Contact Phone/Email: ____________________________ Site Owner/End User Name: _________________________ Site Owner/End User Phone/Email: ____________________________ Preferred Activation Date: ___________________________________ (provide 2 weeks minimum from date this form is submitted) Site
Designation
Top Opening
Type
Final Pavement
Complete
Landscaping
Complete /
Grass Emerging
Construction
materials /
Piles / Debris
Removed
Throat Opening
Measures 4” Min.
Height
(where applicable)
Vegetation
Sourced by
Contractor
Tree Grate
Full Grate
(No tree opening)
Bioscape Vault
(Open Planter)
Verified Verified Verified Verified Species on FT
Plant List
Container Grown
(15 gal. max)
4’ Tall Min. (Tree
grate units only)
____ Qty provided
Tree Grate
Full Grate
(No tree opening)
Bioscape Vault
(Open Planter)
Verified Verified Verified Verified Species on FT
Plant List
Container Grown
(15 gal. max)
4’ Tall Min. (Tree
grate units only)
____ Qty provided
Tree Grate
Full Grate
(No tree opening)
Bioscape Vault
(Open Planter)
Verified Verified Verified Verified Species on FT
Plant List
Container Grown
(15 gal. max)
4’ Tall Min. (Tree
grate units only)
____ Qty provided
Tree Grate
Full Grate
(No tree opening)
Bioscape Vault
(Open Planter)
Verified Verified Verified Verified Species on FT
Plant List
Container Grown
(15 gal. max)
4’ Tall Min. (Tree
grate units only)
____ Qty provided
NOTE: A charge of $1500.00 will be invoiced for each activation visit requested by customer where Contech determines that the site does not meet the conditions required for activation AND/OR acceptable plants are not provided by the contractor. ONLY Contech authorized representatives can perform activation of Filterra systems; unauthorized activations will void the system warranty and waive manufacturer supplied activation and final inspection.
Attach additional sheets as necessary.
Signature Date
ENGINEERED SOLUTIONS
□ □ □ □ □ □
□
□
□
□
□ □ □ □ □ □
□
□
□
□
□ □ □ □ □ □
□
□
□
□
□ □ □ □ □ □
□
□
□
□
~ filterra·
Filterra Activation Package | Page 4
* UNPREPARED SITE FEE NOTE: A charge of $1500.00 will be invoiced for each activation visit requested by customer where Contech determines that the site does not meet the conditions required for Activation AND/OR acceptable plants are not provided by the contractor. ONLY Contech authorized representatives can perform Activation of Filterra systems; unauthorized activations will void the system warranty and waive manufacturer supplied activation and final inspection.
Planting Selection for Filterra® Vault Systems
All Filterra systems require vegetation for proper long-term performance. As indicated in the Activation Package, the Contractor is responsible for sourcing the proper vegetation prior to Activation. Contech or a Contech representative will install the vegetation during the Activation process.
Contractors should identify the Top Opening style for each Filterra requiring Activation on the Activation Checklist. Contech offers three types, which are detailed on page 5 of this document:
• Vault with Tree Grate
• Vault with Full Grate
• Bioscape / Open Planter
Contractors must ensure the vegetation meets the following 4 requirements:
1.Select plant(s) as specified in the engineering plans and specifications AND that are listed on Contech’s Configuration Specific Plant Lists**.
2.All plants MUST be container-grown in nursery containers no larger than 15 gallons. Crated and/or Ball/Burlap plants are NOT permitted.
3.For Vaults with Tree Grates, plant height must be 4’ Minimum, from soil surface to top of plant.
4.Provide plant quantities per the following guidance:
• Vault with Tree Grate – 1 per Tree Grate
• Vault with Full Grate – 4-5 Small or Extra Small Grasses per Full Grate • Bioscape – Quantities should be selected based on plant palette options found starting on page 6 of this document.
If Contech or Contech’s representative shows up for Activation and any of the 4 requirements above are not met, Activation cannot be performed and the Contractor will be billed a $1,500 Unprepared Site fee*.
Some additional vegetation recommendations for the best possible Activation and Installation are as follows:
• Select plant(s) with full root development but not to the point where root bound. • For Filterra systems with a Tree Grate, select plants with taller trunks. Lower branches can be pruned away provided there are sufficient branches above the grate for tree or shrub development. • For Filterra systems with a Tree Grate, plant(s) should have a single trunk at installation. • Plant species shall not have a mature height greater than 30 feet. ** In some cases, Contech may consider alternate plant species as approved by the Product Manager. Please list the plant name in the space below and submit this sheet to your Contech Activation Coordinator. If the plant species is approved, either the Product Manager or the Activation Coordinator will sign the form and return to you for inclusion with your Activation Checklist.
Requested Plant Species: ___________________________________________ Approved: _______________________________ Date: ____________________________________
~ filterra·
Filterra Activation Package | Page 5
* UNPREPARED SITE FEE NOTE: A charge of $1500.00 will be invoiced for each activation visit requested by customer where Contech determines that the site does not meet the conditions required for Activation AND/OR acceptable plants are not provided by the contractor. ONLY Contech authorized representatives can perform Activation of Filterra systems; unauthorized activations will void the system warranty and waive manufacturer supplied activation and final inspection.
Figure 1a. Filterra with Tree Grate Drawing
Figure 2a. Filterra with Full Grate Drawing
Figure 3a. Filterra Bioscape Vault Drawing
Figure 1b. Filterra with Tree Grate Photo (not yet planted) Figure 2b. Filterra with Full Grate Photo
Figure 3b. Filterra Bioscape Vault Photo
Filterra® Top Opening Examples
Filterra® Vault with Tree Grate
Filterra® Vault with Full Grate
Filterra® Bioscape Vault
.,
4 ~
• OUTU aT ..
I
!, .. --.
... ,L j .L~.Ll::==== L _ _l__ ____: _ _1
-----'
t
OFC~B
38" ~~TREE
ffiOflTF~CC
Of C.U~ti
GRAlc
(C1'¥T--IN)
PLAN"[ PROV!Oi;O
EIYCONTECH
(T'l'P I
~ filterra·
Filterra Activation Package | Page 6
* UNPREPARED SITE FEE NOTE: A charge of $1500.00 will be invoiced for each activation visit requested by customer where Contech determines that the site does not meet the conditions required for Activation AND/OR acceptable plants are not provided by the contractor. ONLY Contech authorized representatives can perform Activation of Filterra systems; unauthorized activations will void the system warranty and waive manufacturer supplied activation and final inspection.
Filterra® Bioscape Vault Plant Palettes
KEY: (refer to plant lists for species sizing)
4x4 Media Bay A.
3 A.
5 A.
6 A.
6 A.
9 A.
12 A.
15 A. 20 B. 6 C. 3 D. 2
B.
1 B.
2 B.
2 B.
2 B.
3 B.
3 B.
4 C.
1 C.
1 C.
1 D.
1 D.
1 D.
1 D.
1 D.
1 C.
1 C.
2 C.
2 C.
2 4x6/6x4 Media Bay
4x8/8x4 &
4.5x7.83/7.83x4.5
Media Bay
6x6 Media Bay
6x8/8x6 Media
Bay
6x10/10x6 &
8x8 Media Bay
6x12/12x6 Media
Bay
7x13/13x7/12x8 &
14x8 Media Bay
A. EXTRA SMALL GRASS
• Up to 2’ mature spread
• 1-2 gallon typical (1 gal. minimum)
B. SMALL GRASS/SHRUB
• 2’-4’ mature spread
• 1-7 gallon typical
C. MEDIUM SHRUB
• 4’-6’ mature spread
• 1-7 gallon typical
D. LARGE SHRUB OR EXTRA LARGE SHRUB OR TREE
• 6’ mature spread and greater, 30’ max. mature
height
• Up to 15 gallon maximum
NOTE: For larger vaults and in-ground
Filterra Bioscape systems, palettes can be
scaled (i.e. Qty 6 of the 22x8 Palette can be
used for a 1056 sf Filterra Bioscape).
MIX & MATCH SUBSTITUTION OPTIONS:
1 Large Shrub or Extra Large Shrub or Tree
• 2 Medium Shrubs
• 4 Small Grass/SHrubs
• 12 Extra Small Grasses
1 Medium Shrub
• 2 Small Grass/Shrubs
• 6 Extra Small Grasses
1 Small Grass/Shrub
• 3 Extra Small Grasses
~ filterra·