10-1.02 Dust Palliative

Dust palliative shall be applied when deemed necessary by the City. Dust palliative may be used for dust control on disturbed soil areas, haul roads and staging areas. Dust palliatives are to be submitted to the City for approval prior to use and applied per manufacturer’s recommendation. Costs for dust palliatives will be born solely by Contractor.

10-1.03 Measurement and Payment

Full compensation for applying water and/or dust palliatives for dust control is included in the prices paid for the various items of work involved and no additional compensation will be paid.

10-2 AIR POLLUTION CONTROL

The Contractor shall comply with all Federal, State, City, regional air district (Placer County Air Pollution Control District), and local air pollution control rules, regulations, ordinances, and statutes that apply to the Work. The Contractor shall also comply with the requirements of any permits issued to the City as noted in the Special Provisions.

10-3 BURNING

Unless otherwise provided in the Special Provisions or approved by the City in writing, material shall not be burned on site.

10-4 EROSION, SEDIMENT, AND WATER POLLUTION CONTROL

10-4.01 General

The Federal Clean Water Act requires construction sites to prevent pollutants entering storm drain systems. Storm drain systems include both constructed and natural facilities, including streams, waterways, and other bodies of water. The Contractor shall protect the local storm drain system from pollution, and shall conduct and schedule operations to avoid erosion and sediments. Where erosion may cause water pollution due to the nature of the material or the season, the Contractor's operations shall be scheduled so temporary or permanent erosion 301

129
General Provisions

control features are installed concurrently with, or immediately following, grading operations.

The Contractor is responsible for organizing and scheduling the Work to prevent, control, and/or abate water pollution. In order to provide effective and continuous control of water pollution, it may be necessary for the Contractor to perform the Work in small or multiple units, on an out-of-phase schedule, and/or with modified construction procedures. The Contractor shall coordinate water pollution control work with all other Contract work.

10-4.02 City Requirements

Unless specified otherwise in the Contract, all construction projects in the City of Rocklin must have a water pollution control program as follows:

• Construction projects disturbing more than the threshold number of acres as defined in the State General Construction Permit [currently one (1) acre] must have a Storm Water Pollution Prevention Plan (SWPPP). (See Section 10-4.04 below.) • Construction involving the grading, filling, excavating, storage, or disposal of fifty (50) cubic yards or more of soil, or the clearing or grubbing of one (1) acre or more must have an Erosion and Sediment Control Plan (ESCP). (See Section 10-4.05 below.) • All other construction must comply with the City of Rocklin Municipal Code. (See Section 10-4.06 below.)

Before starting the Work, the Contractor shall develop a program for the control of water pollution during the Work. The program shall indicate how the Contractor proposes to effectively control water pollution and provide drainage during the Work. The program shall also describe how the Contractor plans to monitor the effectiveness of the program. The program shall show erosion control work and all water pollution control measures the Contractor plans to implement in connection with the Work. The Contractor shall not perform any clearing, grubbing or earthwork on the project, other than that specifically authorized in writing by the City, without a water pollution control program. When requested by the City, the Contractor shall submit the program for review.

The City is not liable to the Contractor for any portion of the water pollution control program or subsequent revisions nor for any delays to the Work due to the Contractor’s failure to prepare and implement a program nor for any delays as a result of City review.

10-4.03 Regulations, Ordinances, Permits, and Specifications

The Contractor is responsible for compliance with all Federal, State, City and local permits, rules, regulations, ordinances, statutes, and City directions that apply to erosion, sediment, and water pollution control. The Contractor, at a minimum, shall comply with the most stringent regulation, ordinance, permit, or specification of the following applicable to the Work:
• This Chapter or the Special Provisions
• Chapter 8.30 of Title 15 of the City Municipal Code
• Chapter 15.28 of Title 15 of the City Municipal Code
• State of California Construction Activities Storm Water General Permit • Specific or general National Pollution Discharge Elimination System (NPDES) or other permits that cover the Work or are specific to the area of the Work • The City of Rocklin Joint Municipal NPDES Permit
302

130
General Provisions

The Contractor’s responsibility to provide water pollution control under this Chapter ends at Field Acceptance of the Work. (See Section 7-21 above.)

10-4.04 Storm Water Pollution Prevention Plan

For construction projects disturbing more than one (1) acre, the Contractor must obtain coverage under the State Water Resources Control Board (SWRCB) General Storm Water Permit to Discharge Storm Water Associated with Construction Activity (General Permit).

General Permit coverage is obtained by certifying and filing a Notice of Intent (NOI) with the Regional Board. The Contractor will prepare and the City will file the NOI unless specified otherwise in the Special Provisions.

Additionally, unless specified otherwise in the Special Provisions, the Contractor shall prepare a SWPPP in accordance with the General Permit or other permit specified in the Special Provisions. The SWPPP shall be prepared by an individual qualified and certified about storm water pollution prevention methods and requirements, and shall be signed by the preparer of the SWPPP. The SWPPP shall be implemented by the Contractor before Work commences.

The Contractor may not be allowed to mobilize until the plan is accepted. The SWPPP shall be kept onsite at all times, updated for the various phases of the project, and made immediately available for City and Regional Board Inspectors upon request. Updates shall be submitted to the City immediately for review. At a minimum, the SWPPP shall include all elements as specified in the State’s order.

10-4.05 Erosion and Sediment Control Plan

Construction projects involving the grading, filling, excavating, storage, or disposal of fifty (50) cubic yards or more of soil, or the clearing or grubbing of one (1) acre or more, are required to comply with the provisions of Chapters 15.28 of Title 15 of the City Municipal Code.

The Erosion and Sediment Control Plan (ESCP) shall be prepared by a qualified and certified practitioner. When requested by the City, the ESCP shall be reviewed by the City before work commences. Unless otherwise approved by the City, the Contractor will not be allowed to mobilize until the plan is prepared. If the Contractor’s methods fail to prevent erosion or siltation, the Contractor shall revise and adjust the control measures to provide effective control, and shall be responsible for any damage, fine, and/or administrative civil liabilities resulting from erosion or siltation originating on the Work site and any other site the Contractor controls or passes through.

10-4.06 Minimum City Requirements – Best Management Practices for Construction Activities.

All construction contractors performing work in the City shall conform to adopted City standards.

In addition to any adopted BMPS or other requirements for construction projects adopted by the City, the following requirements shall apply to all projects undergoing construction in the City.

The requirements set forth below shall apply.

1. Sediment, construction waste and other pollutants from construction sites and parking areas, including runoff from equipment at construction sites, shall be retained on the site to the maximum extent practicable.
303

131
General Provisions

2. Any sediment or other materials that are not retained on the site shall be removed the same day as the projects are completed. Where determined as necessary by the director, a temporary sediment barrier shall be installed.

3. Plastic covering may be utilized to prevent erosion of an otherwise unprotected area, along with runoff devices to intercept and safely convey the runoff.

4. Excavated soil or stockpiled base materials shall be located on the site in a manner that minimizes the amount of sediments running into the street or adjoining properties. Soil and materials piles shall be covered until the soil is either used or removed. Soil and materials shall not be placed on paved streets or sidewalks without specific permission of the City.

5. No washing of construction or other industrial vehicles shall be allowed on a construction site or property adjacent to a construction site.

6. Drainage controls shall be utilized as needed, depending on the extent of the proposed grading and topography of the site, including but not limited to the following: detention ponds, sediment ponds, infiltration pits, dikes, filter berms, ditches, down drains, chutes, or flumes.

Notification to the Project Manager shall be required within twenty-four (24) hours following the failure of authorized measures to prevent erosion or sediment from leaving the construction site, the deposit of debris or material on adjoining property or public rights -of-ways, or the interference with any existing watercourses or drainage facilities.

10-4.07 Compliance

Compliance with the provisions in this Chapter does not relieve the Contractor of the responsibility for compliance with other Contract provisions.

The Contractor shall perform routine inspection and maintenance of BMP’s. Inspections shall be done prior to, during, and after each rain event. The Contractor is solely responsible for preparing and maintaining inspection and monitoring records; and for including those records in the SWPPP or, in the case of Erosion and Sediment Control Plans, the site or project Maintenance Log, copies of which shall be available to the City for review upon request.

The Contractor shall immediately correct or replace any ineffective BMP. If the measures taken by the Contractor are inadequate to effectively control water pollution, the City may direct the Contractor to revise the operations and water pollution control program. The City may restrict work from being performed until the water pollution control measures are adequate and, if required, a revised water pollution control program is in place. Continued noncompliance may result in the City suspending the Work in accordance with Section 5-21, above. The City reserves the right to take corrective action and withhold City costs for corrective action from progress payments or final payment in accordance with Section 8-8, above.

Any fines, including third-party claims, levied against the City as a result of Contractor's non- compliance are the Contractor's sole responsibility and will be withheld from progress payments or final payment in accordance with Section 8-8, of the General Provisions.

10-4.08 Payment

Except as otherwise provided in the Special Provisions, full compensation for compliance with all applicable erosion and sediment control and storm water pollution and prevention requirements will be included in the prices paid for the various Contract items of work and no 304

132
General Provisions

additional compensation will be allowed.

10-5 CONTROL OF WATER IN THE WORK

When groundwater or surface run-off water is encountered, the Contractor shall furnish, install, maintain, and operate all necessary machinery, appliances, and equipment to keep excavations and wet areas reasonably free from water. De-watering operations shall remain in effect until the Work has been completed, inspected, and approved, and all danger of flotation and other damage is eliminated. Water pumped from waterways, trenches, excavations, or low spots shall be disposed as specified in the Special Provisions or as directed by the City.

The Contractor is not allowed to dispose of any water that contains sediment or other contaminants. The Contractor is responsible for providing filtration, settlement, or disposal facilities as required to comply with the requirements of Section 10-4, above.

10-6 NOISE CONTROL

The Contractor shall comply with all local noise control and noise level rules, regulations, and ordinances that apply to the Work. The Special Provisions may contain specific or additional requirements. Internal combustion engines used for any purpose on the Work must be equipped with a muffler recommended by the manufacturer.

10-7 CONTAMINATED AND HAZARDOUS MATERIALS OR ENVIRONMENTS

10-7.01 Contaminated or Hazardous Materials

The Contractor shall comply with all Federal, State and local rules, regulations, ordinances, and statutes that apply to the handling, storage, and disposal of contaminated and hazardous materials. All work involving material containing asbestos must be performed in accordance with California Labor Code, Sections 6501.5 through 6510 and California Code of Regulations, Title 8, Section 5208 and any other pertinent regulations.

10-7.02 Hazardous Environments

Existing sewers and appurtenances exposed to sewage and industrial wastes are considered contaminated with disease-causing organisms. The Contractor shall advise all personnel (including Subcontractor personnel) in contact with contaminated facilities, debris, wastewater, or similar items of the necessary precautions to avoid disease. It is the Contractor's responsibility to urge all personnel to observe a strict regimen of proper hygienic precautions, including any inoculations recommended by the local public health officer.

10-8 USE OF EXPLOSIVES

The Contractor shall not use explosives on the Work unless the City grants permission in writing or the use of explosives is specified in the Contract Documents, and then only under such conditions as the City prescribes.

305

133
General Provisions

10-9 SANITARY REGULATIONS

The Contractor shall comply with all Federal, State and local rules, regulations, ordinances, and statutes with respect to sanitation. The Contractor shall obey and enforce such sanitary requirements, and shall take precautions against contagious or infectious diseases. Sanitary conveniences for the use of the workers shall be constructed or installed and maintained by the Contractor. The Contractor shall strictly enforce use of such facilities.

10-10 CONFINED SPACES

10-10.01 Contractor Responsibilities and Qualifications

When working in a confined space, the Contractor shall comply with all confined space requirements of Title 8, General Industry Safety Orders (Cal-OSHA), Article 108, Sections 5156 through 5159.

Prior to any confined space entry, the Contractor shall submit for City review a copy of the entry permit and associated documentation. The Contractor's submittal shall be made thirty (30) days prior to any confined space entry in accordance with Section 5-8, above. The Contractor will not be allowed to make a permit-required confined space entry until the City has reviewed the Contractor’s qualifications and proposed methods.

The Contractor shall conform to the procedures established by the Contractor’s submittal during all confined space operations. Contractor shall provide all monitoring and safety equipment necessary to perform pre-entry checks of confined spaces. The Contractor shall also provide all monitoring, safety, and communications equipment required for confined space operations.

10-10.02 City Responsibilities for Permit Confined Spaces

The Contractor shall be provided with information regarding known hazards and known or potential permit spaces. After the City has reviewed the Contractor’s submittal to perform permit-required confined space entry work, the Contractor will be provided with the following:

• Notification of the location, physical characteristics, known hazards, etc. regarding the permit-required confined space the Contractor anticipates entering. • Information regarding safety items (e.g. nearby emergency equipment), precautions, procedures, safeguards, etc. installed or implemented and that may be available to the Contractor's employees in or near the permit-required confined space.

The City’s failure to identify a confined space does not relieve the Contractor of the responsibility for compliance with the requirements of Article 108 (Cal-OSHA) and this Chapter.

10-10.03 Existing Sewers and Storm Drains

Because of the potential danger of solvents, gasoline, and other hazardous material in existing sewers and storm drain pipes, these areas shall be treated as permit-required confined spaces unless it has been proven, through appropriate testing, that no hazards exist or are expected to develop.
306

134
General Provisions

10-10.04 Joint City – Contractor Entries

Unless otherwise directed in writing by the City, when City employees work alongside the Contractor in a permit-required confined space, the permit procedures for both the City and the Contractor shall be used. The Entry Supervisor shall coordinate the requirements of both permit procedures prior to entry.

10-11 CLEANING UP

The Contractor shall keep the site in a neat and presentable condition. The Contractor shall dispose of surplus materials, clean out all drainage ditches and structures, and repair any fences or other property damaged during the progress of the Work. When material is disposed of outside of an easement, street, or highway right-of-way, or other City-owned properties, the Contractor shall do so in accordance with the Contract Documents.

10-12 ARCHEOLOGICAL AND CULTURAL RESOURCES

If archeological or cultural resources are discovered during the Work, the Contractor shall cease all construction operations in the vicinity of the discovery until a qualified archeologist can assess the value of these resources and make recommendations to the State Historic Preservation Officer. Archeological and cultural resources include artifacts, large amounts of bone, shell, or flaked stone, and other evidence of human activity. If the State Historic Preservation Officer or the City directs that work be temporarily ceased at the location of an archeological or cultural find, the Contractor shall temporarily suspend work at the location.

If the City or the State Historic Preservation Officer temporarily suspends a portion of the Work for cultural purposes, any associated delays are considered excusable in accordance with Section 7-12.02, “Excusable Delays”, above.

10-13 PROTECTION OF EXISTING TREES

Special attention shall be given to protection of certain native and ornamental trees or shrubs, landmark trees, and all native oak trees. Additional requirements for specific trees may be shown on the Plans, or designated in the Special Provisions or by the City. No native oak trees shall be removed or disturbed unless specifically designated for removal on the Plans or by the City. Every reasonable effort shall be made to avoid creating conditions adverse to the tree’s health. The natural ground three (3) fee outside of the drip line of protected trees shall remain as undisturbed as possible. All protected trees within the Work area that require pruning for construction clearance shall be pruned prior to commencement of construction.

Native oak trees that require pruning of branches larger than two inches (2”) in diameter shall be pruned by a Certified Arborist.

307

135
General Provisions

CHAPTER 11 – PRECONSTRUCTION PHOTOGRAPHS AND RECORD DRAWINGS

TABLE OF CONTENTS

Section Page
11-1 GENERAL ................................ ................................ ................................ ................ 136 11-2 PRECONSTRUCTION PHOTOGRAPHS ................................ ................................ . 136 11-3 RECORD DRAWINGS ................................ ................................ ............................. 136 11-4 MEASUREMENT AND PAYMENT ................................ ................................ ........... 137

308

136
General Provisions

CHAPTER 11 PRECONSTRUCTION PHOTOGRAPHS AND RECORD DRAWINGS

11-1 GENERAL
Preconstruction photographs will only be required when specified in the Special Provisions.

Record Drawings are required on all City Work, unless directed otherwise in writing by the City.

11-2 PRECONSTRUCTION PHOTOGRAPHS

Preconstruction digital photographs shall be taken by the Contractor at one-hundred foot (100’) intervals along the route of the Work before any construction begins. The view in each photograph shall show the date; and include name of the Project, lateral or street, and applicable station designation in the form of a sign or legend in the record book. The views in preconstruction photographs shall include the entire construction zone and, in particular, show the interface between the right-of-way and construction zone, and abutting property features such as, but not limited to, condition of existing streets, sidewalks, driveways, fences, landscaping, buildings abutting work site, and existing surface utility facilities on and close to the Work. All essential features of the project area shall be shown accurately. The City may order additional photographs showing additional features or orientations, if the City determines that all essential features are not accurately or adequately shown.

11-3 RECORD DRAWINGS

The Contractor shall maintain a neat and accurately marked set of Record Drawings (as- builts), which shall be provided to the City for review and approval prior to final acceptance of the Work. The Record Drawings shall represent the Work as constructed and document changes to the Work shown on the Project Plans, and shall show the actual as-constructed conditions of installed or modified systems, equipment, and material.

Record Drawings shall be produced by marking a full size copy of the Project Plans as follows:

Red - Additions including notes and dimensions.

Green - Deletions (by hash marks or appropriate lines through the deletion.) Graphite (gray) - General comments and notes used by Contractor or City and not required on the as-built.

Yellow – Work completed as shown and used by the City in field review of the as-built, during the submittal phase.

Blue – City verification and notes required to be added and noted by the City in review of the as-built, during submittal phase.

The Record Drawings shall show, by field measured dimensions, the exact locations of all underground work, including all sprinkler system piping and components, and the final elevations and locations of all improvements constructed, modified or adjusted. Record Drawings shall be available for inspection by the City at all times and shall be updated at least weekly with all changes pertinent to Field Directives, other written directives, RFI responses, and Change Orders shown thereon. Progress payments or portions thereof may be withheld if Record Drawings are not kept up to date.

309

137
General Provisions

Unless otherwise specified in the Special Provisions, the Contractor shall submit two (2) sets of Record Drawings to the City at the final inspection for review. Upon approval, the Contractor shall submit one paper set and electronic versions (AutoCAD, PDF, or TIF) on CD or flash drive. These Record Drawings shall include certification by the Contractor that the Record Drawings are a true representation of the Work as actually constructed. The Work will not be formally accepted until the Record Drawings are provided to and approved by the City. Final payment or a portion thereof may be withheld if final Record Drawings are not provided.

11-4 MEASUREMENT AND PAYMENT

When the Contract includes a separate item for preconstruction photographs, preconstruction photographs will be paid for at a lump sum price. The lump sum price paid for preconstruction photographs includes full compensation for furnishing all labor, materials, tools, equipment, and incidentals and for doing all the work involved in taking and submitting preconstruction photographs, or optional video tape, as specified in these Specifications and the Special Provisions, and as directed by the City. When the Contract does not include a payment item for preconstruction photographs, full compensation for preconstruction photographs is included in the prices paid for the various items of work and no separate payment will be made.

Full compensation for Record Drawings is included in the prices paid for the various items of work and no separate payment will be made.

310

SPECIAL PROVISIONS
SPECIAL PROVISIONS - 1

FOR THE

BLUE OAKS BOULEVARD PEDESTRIAN SIGNAL, SIERRA COLLEGE BOULEVARD

WIDENING, CREST DRIVE AT VALLEY VIEW ELEMENTARY PEDESTRIAN

IMPROVEMENTS, AND SCHOOL ZONE SIGNAGE AND PAVEMENT MARKINGS

PROJECTS
The Special Provisions contained herein have been prepared by or under the direction of the following Registered Engineer.

CIVIL & ELECTRICAL (CREST DRIVE PEDESTRIAN IMPROVEMENTS)

HUNTER YOUNG

REGISTERED CIVIL ENGINEER

CIVIL (BLUE OAKS PEDESTRIAN SIGNAL AND SIERRA COLLEGE

BOULEVARD WIDENING)

DANIEL CARLEY

REGISTERED CIVIL ENGINEER

ELECTRICAL (BLUE OAKS PEDESTRIAN SIGNAL AND

SIERRA COLLEGE BOULEVARD WIDENING)

ROBERT PADERNA

REGISTERED CIVIL ENGINEER
06/30/24
C76304

DANIEL CARLEY
12/31/24
C73262

ROBERT PADERNA
311

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 2

TABLE OF CONTENTS

1.00 GENERAL ..........................................................................................................................................................5

1.01 LOCATION .........................................................................................................................................................5

1.02 DESCRIPTION OF PROJECT ...........................................................................................................................5

1.03 TIME OF COMPLETION ....................................................................................................................................5

1.04 LIQUIDATED DAMAGES ...................................................................................................................................6

1.05 COORDINATION ................................................................................................................................................6

1.06 ORDER OF WORK ............................................................................................................................................6

1.07 HOURS OF WORK ............................................................................................................................................7

1.08 DUST CONTROL ...............................................................................................................................................7

1.09 PUBLIC NOTIFICATION ....................................................................................................................................8

1.10 PUBLIC CONVENIENCE ...................................................................................................................................8

1.11 SUBMITTALS .....................................................................................................................................................8

1.12 AS-BUILT PLANS ...............................................................................................................................................9

1.13 PROJECT APPEARANCE .................................................................................................................................9

1.14 STAGING AREA .............................................................................................................................................. 10

1.15 PROPERTY AND FACILITY PRESERVATION .............................................................................................. 10

1.16 PRECONSTRUCTION PHOTOGRAPHS ....................................................................................................... 10

1.17 MEASUREMENT AND PAYMENT.................................................................................................................. 10

2.00 MOBILIZATION ............................................................................................................................................... 11

2.01 MEASUREMENT AND PAYMENT.................................................................................................................. 11

3.00 TRAFFIC CONTROL SYSTEM ....................................................................................................................... 12

3.01 MATERIALS .................................................................................................................................................... 12

3.02 EXECUTION .................................................................................................................................................... 12

3.03 PUBLIC ACCESSIBILITY ................................................................................................................................ 13

3.04 ON-STREET PARKING ................................................................................................................................... 15

3.05 PORTABLE CHANGEABLE MESSAGE SIGNS ............................................................................................. 15

3.06 MEASUREMENT AND PAYMENT.................................................................................................................. 16

4.00 CONSTRUCTION STAKING .......................................................................................................................... 17

4.01 MEASUREMENT AND PAYMENT.................................................................................................................. 17

5.00 POTHOLING ................................................................................................................................................... 18

5.01 MEASUREMENT AND PAYMENT.................................................................................................................. 18

6.00 WATER POLLUTION CONTROL PLAN (WPCP) .......................................................................................... 19

6.01 WPCP PREPARATION, APPROVAL, AND UPDATES .................................................................................. 19

6.02 WPCP IMPLEMENTATION AND MAINTENANCE ......................................................................................... 20

6.03 MEASUREMENT AND PAYMENT.................................................................................................................. 21

7.00 CLEARING AND GRUBBING ........................................................................................................................ 22

7.01 EXISTING IRRIGATION SYSTEM .................................................................................................................. 22

7.02 EXISTING VEGETATION ................................................................................................................................ 22

7.03 MEASUREMENT AND PAYMENT.................................................................................................................. 23

8.00 REMOVE TREE............................................................................................................................................... 24

8.01 NESTING BIRD SURVEY ............................................................................................................................... 24

8.02 MEASUREMENT AND PAYMENT.................................................................................................................. 24

312

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 3

9.00 REMOVE CONCRETE .................................................................................................................................... 25

9.01 MEASUREMENT AND PAYMENT.................................................................................................................. 25

10.00 ROADWAY EXCAVATION ........................................................................................................................... 26

10.01 MEASUREMENT AND PAYMENT................................................................................................................ 26

11.00 COLD PLANING ........................................................................................................................................... 27

11.01 MEASUREMENT AND PAYMENT................................................................................................................ 27

12.00 AGGREGATE BASE .................................................................................................................................... 28

12.01 DAILY SUBMITTAL ....................................................................................................................................... 28

12.02 MEASUREMENT AND PAYMENT................................................................................................................ 29

13.00 CONCRETE ................................................................................................................................................... 30

13.01 EXECUTION .................................................................................................................................................. 30

13.02 DETECTABLE WARNING SURFACE .......................................................................................................... 32

13.03 DAILY SUBMITTAL ....................................................................................................................................... 32

13.04 MEASUREMENT AND PAYMENT................................................................................................................ 33

14.00 HOT MIX ASPHALT ...................................................................................................................................... 35

14.01 MATERIALS .................................................................................................................................................. 35

14.02 EXECUTION .................................................................................................................................................. 35

14.03 DAILY SUBMITTAL ....................................................................................................................................... 36

14.04 MEASUREMENT AND PAYMENT................................................................................................................ 37

15.00 TRAFFIC STRIPING AND PAVEMENT MARKINGS................................................................................... 38

15.01 PAVEMENT MARKERS/DELINEATORS/STRIPING/PAVEMENT MARKINGS .......................................... 38

15.02 TEMPORARY STRIPING AND PAVEMENT MARKINGS ............................................................................ 38

15.03 MATERIAL ..................................................................................................................................................... 39

15.04 APPLICATION ............................................................................................................................................... 39

15.05 TOLERANCES AND APPEARANCE ............................................................................................................ 40

15.06 PAVEMENT MARKERS ................................................................................................................................ 40

15.07 OBJECT MARKERS ...................................................................................................................................... 40

15.08 MEASUREMENT AND PAYMENT................................................................................................................ 40

16.00 ROADSIDE SIGNS AND BARRICADES ..................................................................................................... 42

16.01 MEASUREMENT AND PAYMENT................................................................................................................ 42

17.00 METAL FENCE ............................................................................................................................................. 44

17.01 MEASUREMENT AND PAYMENT................................................................................................................ 44

18.00 ELECTRICAL SYSTEMS .............................................................................................................................. 45

18.01 TRAFFIC SIGNAL SCHEDULE OF VALUES ............................................................................................... 45

18.02 SALVAGING ELECTRICAL EQUIPMENT .................................................................................................... 45

18.03 MAINTAINING EXISTING AND TEMPORARY ELECTRICAL SYSTEMS ................................................... 46

18.04 SIGNAL ACTIVATION ................................................................................................................................... 46

18.05 FOUNDATIONS............................................................................................................................................. 47

18.06 STANDARDS, POLES, PEDESTALS, AND POSTS .................................................................................... 47

18.07 CONDUIT ...................................................................................................................................................... 47

18.08 PULL BOXES ................................................................................................................................................ 48

18.09 CONDUCTORS AND WIRING ...................................................................................................................... 48

18.10 SIGNAL FACES AND SIGNAL HEADS ........................................................................................................ 49 313

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 4

18.11 PEDESTRIAN SIGNALS ............................................................................................................................... 49

18.12 PHOTOELECTRIC CONTROLS ................................................................................................................... 49

18.13 SERVICE EQUIPMENT ENCLOSURE ......................................................................................................... 50

18.14 ACCESSIBLE PESDESTRIAN SIGNAL ....................................................................................................... 50

18.15 LOOP DETECTION SYSTEM ....................................................................................................................... 50

18.16 LUMINAIRES ................................................................................................................................................. 51

18.17 FLASHING BEACON SYSTEMS .................................................................................................................. 51

18.18 BLINKER SIGN SYSTEMS ........................................................................................................................... 52

18.19 PG&E SERVICE CONNECTION ................................................................................................................... 52

18.20 MEASUREMENT AND PAYMENT................................................................................................................ 52

19.00 QUALITY ASSURANCE PROGRAM ........................................................................................................... 54

19.01 ACCEPTANCE TESTING ............................................................................................................................. 54

19.02 CERTIFICATE OF COMPLIANCE ................................................................................................................ 54

19.03 MEASUREMENT AND PAYMENT................................................................................................................ 55 314

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 5

1.00 GENERAL
All references to the State Standard Specifications means the 202 3 State of California Standard Specifications issued by the California Department of Transportation.

1.01 LOCATION
The work under this contract is located at the following locations as shown on the plan sheets:

1. Blue Oaks Boulevard between Tanager Way and Cassia Way.

2. Sierra College Boulevard between Rocklin Station/Schriber Way and Dominguez Road/Bass Pro Drive.

3. Intersection of Crest Drive and Fox Hill Drive.

4. Various school zones throughout the City of Rocklin.

1.02 DESCRIPTION OF PROJECT
The work to be performed consists, in general, of:

Blue Oaks Pedestrian Signal – removal of trees/vegetation and flatwork; installation of new curb, gutter, sidewalk, and curb ramps; traffic signal ; plug paving ; traffic striping, legends, and markings ; roadside signs, and all other work shown in the contract documents.

Sierra College Boulevard Widening – removal of vegetation, retaining wall, AC dike, and flatwork; installation of new curb, gutter, sidewalk, retaining curb, and curb ramp; traffic signa l modification and detector loops; pavement widening with cold plane and hot mix overlay; traffic striping, legends, and markings, and all other work shown in the contract documents.

Crest Drive at Valley View Elementary Pedestrian Improvements – new curb, gutter, sidewalk, curb ramps and median island ; plug paving; traffic striping, legends, and markings; roadside signs; and rectangular rapid flashing beacon system installation, and all other work shown in the contract documents.

School Zone Signage and Pavement Markings – new pavement markings and signs, and all other work shown in the contract documents.

1.03 TIME OF COMPLETION
For the purpose of this contract, all work for the projects under this contract shall be complete d within 100 WORKING DAYS beginning on the first effective working day as specified in the first issued Notice to Proceed (NTP).

The Contractor is hereby made aware that the City will not issue a NTP for construction a ctivity on the Blue Oaks Boulevard Pedestrian Signal and Sierra College Boulevard Widening , until the traffic signal poles have been delivered to the Contractor and until the acquisition of the right of way on Sierra College Boulevard, necessary to construct the improvements, has been finalized.

The City may issue the NTP for the Crest Drive Pedestrian Improvements and the School Zone Signage and Pavement Markings Projects separate to the NTP issued for the B lue Oaks Boulevard Pedestrian Signal and the Sierra College Boulevard Widening. The City may issue a temporary suspension of work as needed, during which, working days will not be counted. 315

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 6

1.04 LIQUIDATED DAMAGES
For the purpose of this contract, Liquidated Damages shall be set at the amount of Four Thousand Two Hundred Dollars ($4,200) per calendar day.

1.05 COORDINATION
The Contractor shall coordinate his activities in a manner that will provide the least interference with the City's operations, other contractors, and utility companies working in the area.

At a minimum, the Contractor shall coordinate his operations with the following:
• City Traffic Signals and Street Lighting
Contractor shall notify Naz Lazar at the City of Rocklin (916) 919-2523, a minimum of ten (10) working days before any electrical work begins, or to coordinate placement of traffic signals into flash mode.
• City Landscaping
Contractor shall notify Carl Miller at the City of Rocklin (916) 625-5577, a minimum of ten (10) working days before any clearing and grubbing work begins. • Pacific Gas and Electric (PG&E)
Contractor shall notify Naz Lazar at the City of Rocklin (916) 919 -2523, a minimum of ten (10) working days before any electrical work begins, or to coordinate installation of the electrical meter for the new traffic signal.
• Lifehouse Church
Prior to construction, the Contractor shall request contact information , from the City, for the Lifehouse Church Representative and shall notify the Representative a minimum of ten (10) working days before any construction activities are to occur on Sierra College Boulevard.

Lifehouse Church has planned improvements adjacent to the proposed project and coordination with their contractor may be required.

1.06 ORDER OF WORK
Order of work shall conform to the provisions in Section 5, " Control of Work," of the State Standard Specifications and these Special Provisions.

The following shall be performed prior to the Notice to Proceed:

1. Prepare and submit a work plan, progress schedule for all items of work and traffic and pedestrian control plans in a form provided by or acceptable to the Engineer. The work plan and schedule shall be updated weekly to reflect all items of work performed at the site and shall clearly indicate the proposed completed date. No work may begin under contract until the Progress Schedule and Traffic Control Plan have been approved by the Engineer. Time required for review and approval of these items shall not constitute a basis for time extension.

2. The prime contractor shall prepare and submit a City of Rocklin encroachment permit application to the Public Services Department located at 4081 Alvis Court . All fees for the encroachment permit will be waived.
316

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 7

3. The prime contractor shall prepare and submit a Caltrans encroachment permit application to the Office of Permits, District 3 for any traffic control signage within State right of way. All fees for the encroachment permit shall be included in the Mobilization bid item.

4. Prepare and submit a Water Pollution Control Program (WPCP), as specified in these Special Provisions, in a form acceptable to the Engineer. Work shall not commence until the plan is reviewed and approved by the Engineer.

5. Before commencement of any demolition work on the project, the Contractor shall visit each private property to verify existing conditions of private irrigation facilities that may be impacted by the project. The Contractor shall submit a log listing each address, the date of testing, and whether the existing system within the footprint of the project is functional; see the Clearing and Grubbing section of these Special Provisions for additional details.

The above item(s) shall clearly disclose the Contractor’s proposed procedures and methods of operation, including identifying any special equipment intended for use on the project and method of addressing traffic. It will be the responsibility of the Contractor to arrange for the towing and removal of any vehicles which have not been removed by the owner and which interfere with any operations.

1.07 HOURS OF WORK
The Contractor is to determine how to most efficiently complete the project, and may include a combination of day and night work. Day work shall be Mon day to Friday 7 AM to 5 PM while night work is defined as work Sunday night to Thursday night 9 PM to 6 AM. If performing work during the day in the City right of way, the Contractor shall only be permitted to close one lane in each direction between the hours of 8:30 AM and 3:30 PM. Should the Caltrans encroachment permit require hours or lane closure timeframes that differ from the City’s standard, the Contractor shall follow the Caltrans encroachment permit for work on Sierra College Boulevard.

The Contractor shall be aware that any work in or near a traffic signalized intersection, and which necessitates the traffic signal be placed in flash mode for the safety of the traveling public or the Contractor, as determined by the City, will automatically trigger night work. Should the City mandate night work for construction activities within or near a traffic signalized intersection, no additional payment will be made to the Contractor. For the purposes of this section, the term “near” shall mean within 400 feet of the stop bar/crosswalk of the traffic signal.

1.08 DUST CONTROL
Dust control shall conform to the provisions in Section 10 -5, “Dust Control ,” of the State Standard Specifications.

The Contractor shall provide adequate levels of watering to control dust as well as street sweeping. At a minimum, the Contractor shall sweep the street once a week, or more often as directed by the Engineer/Inspector, to ensure dust is controlled, especially during gr inding operations. The Contractor shall furnish all water necessary for dust control.

The Contractor shall:
• enclose, cover, or water twice daily all soil piles;
• water exposed soil with adequate frequency for continued moist soil; • water all haul roads twice daily; and
• cover loads of all haul/dump trucks securely.

317

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 8
The project area is serviced by Placer County Water Agency (PCWA) . The Contractor shall coordinate with the water provider for a hydrant meter. Water used for the contractor’s purposes shall be considered included in the price paid for various items of work and will not be paid separately.

1.09 PUBLIC NOTIFICATION
The Contractor shall be required to notify , in writing, the public, residents, businesses, public transit companies, utility companies and any other persons or agencies affected by this project at least two (2) weeks prior to starting construction. Other notifications may be required during project construction as outlined below. City staff will coordinate with law enforcement and fire districts.

Two-Week Notice: A written notice (in letter format) to residents and businesses within 500’ of the project locations to provide general information about the project, approximate range of dates on when construction will take place, time of work, and Contractor’s name and phone number. Notice to be approved by City prior to distributing to the public.
72-Hour Notice: Door hanger (or other approved notice) shall include date(s), times an d other pertinent information as directed by the Engineer with a link to the City’s project-specific website. The notice shall include the Contractor’s name and phone number for residents and businesses to contact with any concerns after hours and on weekends. Notice to be approved by City prior to distributing to the public.

Door hangers shall be provided for:
• Traffic delays and alternate routes
• Tree trimming or removals
• Driveway closures
• Water service interruptions
• Temporary relocation of bus stops

Failure to comply with the notification requirement will result in a stop work order. The Contractor shall maintain an updated and chronological record at the job site of all written notifications along with a list of recipients. Such records shall be made available upon request by the Engineer.

1.10 PUBLIC CONVENIENCE
The Contractor shall comply with Sections 7-1.03, “Public Convenience,” and 7-1.04, “Public Safety,” of the State Standard Specifications.

1.11 SUBMITTALS
The Contractor shall comply with the submittal requirements as set forth in Section 5-1.23, “Submittals,” of the State Standard Specifications and these Special Provisions.

The Contractor shall submit via the City’s online platform (e.g., Virtual Project Manager) one electronic PDF of each material submittal to the Engineer at minimum ten (10) days prior to using said material.

Submittals will be reviewed and one (1) copy will be returned to the Contractor with conditions and/or approvals.

The Contractor shall review the Quality Assurance Program section of these Special Provisions for materials requiring certificates of compliance (COCs); submit COCs with material submittals.

See individual sections for submittal requirements included in, but not limited to the following sections:

1. Progress Schedule

2. Water Pollution Control Plan
318

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 9

3. Traffic Control, Pedestrian Access, and Stage Construction Plan

4. Hot Mix Asphalt Design

5. Concrete Mix Design

6. Aggregate Base Mix Design

7. Pavement Striping and Marking Literature and Specifications

8. Roadside Signs and Mounting Literature and Specifications

9. Detectable Warning Surfaces

10. Certificates of Compliance

11. Traffic Signal Literature and Specifications

12. RRFB System Literature and Specifications

13. Blinker Sign System Literature and Specifications

14. Steel Reinforcement Tags

15. Qualifications/resume of I.S.A. certified arborist

16. As-Built Plans

17. Any other items required by the City

1.12 AS-BUILT PLANS
Upon completion of the work, the Contractor shall furnish to the City a complete set of as-built plans showing all changes or deviations from the plans taking care to note the location of objects not installed at the location shown on the plans. Improvements will not be accepted by the City for permanent maintenance until the Contractor has submitted all as-built plans to the Engineer. The as-built plans shall conform to the following:

1. The plans must be stamped or otherwise noted “AS-BUILT,” be neat, clear, and readable.

2. As-built plans must contain the Contractor’s name, permanent address, date prepared, and signature.

3. Disclaimer statements of any kind that differ from the obligations and protections provided by Sections 6735 through 6735.6 of the California Business and Professions Code must not b e included on the as-built plans.

1.13 PROJECT APPEARANCE
The Contractor shall maintain a neat appearance to the work. In areas visible to the public, the following shall apply:

A. When practicable, broken concrete and debris developed during construction activities shall be disposed of concurrently with its removal. Debris stockpiling is not allowed in the public right of way or on private property. If stockpiling is necessary, the Contractor is to stockpile at Contractor’s yard.

B. All streets, driveways, sidewalks, and haul routes within the project limits shall be kept clean and clear of debris, dirt and dust in a manner acceptable to the Engineer. The Contractor shall sweep works areas on a daily basis.

Failure to meet these requirements of this section ma y result in a “Stop Work” notice. The “Stop Work” notice will not be rescinded until the appearance of the work is acceptable to the Engineer.

At the end of each workday, all debris, branches, roots, removed fence, rubbish, and other debris in the work area shall be collected and placed in a suitable disposal bin or pile. Materials to be used later in construction shall be neatly stockpiled. All parts of the work shall be left in a neat and presentable condition at the end of the work shift.
319

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 10

1.14 STAGING AREA
The City will not provide a staging area for the work.

1.15 PROPERTY AND FACILITY PRESERVATION
Attention is directed to Section 5-1.36, “Property and Facility Preservation,” of the State Standard Specifications and these Special Provisions.

Existing hardscape, retaining walls, curb, utilities, trees, shrubs, other plants and irrigation facilities not called out on the plans to be removed, which are injured or damaged by reason of the Contractor's operations, shall be replaced or restored by the Contractor at the Contractor’s expense.

The minimum size of tree replacement shall be 24-inch box and the minimum size of shrub replacement shall be 5-gallon and maximum of 15-gallon, whichever is most appropriate for the species of plant, as determined by the Engineer. Replacement ground cover plants shall be from 1 -gallon containers and shall be planted 12 inches on center. Replacement planting shall conform to the requirements in Section 20-4.03F, “Replacement Plants,” of the State Standard Specifications. The Contractor shall water replacement plants in conformance with the provisions in Section 20-4.03G, "Watering," of the State Standard Specifications. Replacement planting of injured or damaged trees, shrubs, and other plants shall be completed prior to the start of the plant establishment period.

1.16 PRECONSTRUCTION PHOTOGRAPHS
Preconstruction photographs shall be taken by the Contractor before any construction begins. Each photograph shall be taken from a point between four feet (4’) and eight feet (8’) above the ground. All photographs shall show good details in both shadow and sunlit areas. The Contractor shall submit digital photography files either in .TIF or uncompressed .JPEG raster files. All photos shall be time and date stamped to confirm existing field conditions at the time the notice to proceed with construction is issued.

The Contractor shall submit all photos taken to the City via the City’s online platform (e.g., Virtual Project Manager). Photographs shall be grouped according to street, lateral or line, and in sequence.

The views in preconstruction photographs shall include the entire construction zone and, in particular, show the interface between the right-of-way and construction zone, and abutting property features such as, but not limited to, condition of existing streets, sidewalks, driveways, fences, landscaping, buildings abutting work site, and existing surface utility facilities on and close to the work.

A sample of six (6) photographs shall be submitted to the City for approval before proceeding with the remaining photographs. All photographs which do not conform to these Special Provisions, as determined by the City, shall be retaken.

1.17 MEASUREMENT AND PAYMENT
Full compensation for conforming to the requirements of this section of these Special Provisions shall be considered as included in the prices paid for the various items of work involved and no additional compensation will be allowed therefore.

320

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 11

2.00 MOBILIZATION
Mobilization shall conform to Section 9 -1.16D, “Mobilization,” of the State Standard Specifications and consist of preparatory work and operations, including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for the establishment of all facilities necessary for work on the project; and for all other work and operations which must be performed or costs incurred prior to beginning work on the various contract items on the project site.

It is the Contractor’s responsibility to plan and perform all work within the time of completion as allowed in this contract.

This section also includes all necessary permits required by the Contractor , including the Caltrans encroachment permit.

2.01 MEASUREMENT AND PAYMENT
Mobilization shall be measured and paid for as LUMP SUM and shall include full compensation for furnishing all labor, materials, tools, equipment, administrative cost, permit fees, and incidentals for doing all work involving m obilization as specified in these Special Provisions, the State Standard Plans and Specifications and as directed by the Engineer and no additional compensation will be allowed, therefore.

The City shall not pay additional mobilization compensation for a contract change order or for a second mobilization if the project is extended due to weather. Payment for mobilization will be subject to retention.

321

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 12

3.00 TRAFFIC CONTROL SYSTEM
This work shall include signage, flagging, traffic-handling equipment, devices and other related items to provide for safety and convenience to the public and traffic during construction.

3.01 MATERIALS
Traffic control shall conform to Section 12 , “Temporary Tr affic Control ,” Section 7-1.03, “Public Convenience,” and Section 7- 1.04, “Public Safety”, of the State Standard Specifications, and the Manual on Uniform Traffic Control Devices, current California edition , available at the following website:
https://dot.ca.gov/programs/safety-programs/camutcd.

3.02 EXECUTION
Prior to installation of temporary traffic control devices, the Contractor shall have a field meeting with the foreman overseeing installation of traffic control and the Engineer to review the approved traffic control plans and discuss their implementation. Traffic control will be an agenda item at each weekly construction meeting.

Traffic Control Plans (hereinafter "TCP") shall be developed for the Project to assure that adequate consideration is given to the safety and convenience of motorists, pedestria ns, bicyclists, and workers during construction. The TCP shall include all work within the City rights-of-way, and applicable, private streets adjacent to the construction zone. Individual TCP’s shall be submitted to the Engineer for review a minimum of ten (10) working days prior to starting any work covered by a particular TCP . Non - compliance with any stipulation of this Section will be justification for the City to stop work.

Pedestrian access shall be provided through out construction areas within the ri ght of way , and as appropriate, on private property where City construction may occur.

The Contractor shall notify interested parties and/or agencies required by the Engineer as to any road closures, the expected duration , and detours . City staff will not ify law enforcement and fire district personnel.

Driveways shall be usable at all times, unless the Contractor has made special arrangements with the property owner to close a driveway.

The Contractor shall be solely responsible for pedestrian and vehicular movement through the project area and shall assume full liability for any and all claims arising out of the construction of the project.

All traffic control devices including, but not limited to, traffic cones or portable delineators, telescopin g flag trees, arrow boards, barricades, and signs shall be placed before beginning work and shall be removed from the right-of-way at the end of each day or shift, or, for long-term closures, when no longer needed, and shall be placed so as to not obstruct bicycle lanes and pedestrian facilities. All traffic control devices left in the right-of-way by the Contractor are subject to removal by the City.

The Contractor shall be required to pay any costs incurred by the City associated with the removal of these devices. No equipment shall be parked within any traffic lanes, medians, or within the public right of way at any time of day or night, including holidays and weekends, without an approved lane or road closure. The Contractor shall notify the City a minimum of three (3) Working Days in advance of any lane closure and twenty (20) Working Days in advance of any road closure.

Flagging
Flaggers shall perform their duties and shall be provided with the necessary equipment in accordance with Manual and the curre nt “Flagging Handbook” published by the American Traffic Safety Services 322

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 13
Association (ATSSA). The equipment shall be furnished and kept clean and in good repair by the Contractor at the Contractor's expense. All flaggers shall be trained as required by Cal /OSHA Title 8, Section 1599, and proof of such training shall be made available by the Contractor upon request by the City. Any flagger, in the opinion of the City, not performing in a safe manner or in a manner conducive to public safety must be removed and replaced by the Contractor immediately.

Flaggers shall be used where necessary to control the flow of traffic through the construction site and shall be used in all cases where traffic is being routed through the construction zone under one -lane, two-way traffic controls, or when ordered by the City.

Flagging Costs
Unless specified elsewhere in the se Special Provisions, the cost of furnishing all flaggers, including transporting flaggers to provide for passage of public traffic through the construction site shall be considered included in the Traffic Control System bid item and no additional compensation will be made.

3.03 PUBLIC ACCESSIBILITY
The Contractor shall provide access to the public through the project site at all times. The Contractor shall provide access to adjacent properties at all times. The Contractor shall maintain access to properties and pedestrian access even after hours for the life of the construction. Temporary access ramps shall be installed to maintain access and shall be shown on the Contractors staging plan.

The Contractor shall be responsible for designing working drawings, constructing and providing a safe and adequate continuous, accessible and safe path of travel around or through localized construction work zones and to ea ch building, business and property utilized by the public. The Contractor shall use temporary asphalt, aggregate base, wood/metal ramps, signs, cones, barricades, flashers, and flaggers to direct and channel the public during and after construction. All proposed closures of a pedestrian access path shall be submitted in writing to the Engineer for review and approval. Advance warning shall be provided to the public should an access path be closed. All safe paths of travel shall be in compliance with Americans with Disabilities Act Accessibility Guidelines (ADAAG), Americans with Disabilities Act (ADA) regulations and the California Manual on Uniform Traffic Control Devices (CAMUTCD).

Materials
Materials used for public accessibility during construction include, but is not limited to:
▪ Temporary Hot-mix Asphalt Concrete (cut back asphalt concrete not permitted) ▪ Temporary Wood Ramp
▪ Aluminum Modular Ramps. EZ-Access, or approved equal.

Contact info: www.ezaccess.com, Phone 800-451-1903.
▪ Four (4) foot wide minimum walking surface with running slope not to exceed eight (8) percent. ▪ Barricade materials: Delineators, A-Frames, Barrier Caution Tape, Fencing Material ▪ Non-skid tape
▪ Four (4) inch timber, or equivalent, at the bottom of any railing to provide for the sight impaired

Installation
Temporary ramps shall be constructed so installation and removal will not damage existing pavement, curb and/or gutter.

Temporary ramps shall have a minimum four (4) foot wide walking surface and a running slope not to exceed eight (8) percent.

Temporary ramps shall meet existing surfaces without gaps. When required for drainage, a Schedule 40 PVC pipe, with minimum 2-inch diameter, shall be installed under or through ramp in gutter or flow line.

323

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 14
Transitions between temporary ramps and the street or sidewalk surfaces shall be smooth.

Sides of the temporary ramps shall be protected where drop-offs exceed six (6) inches.

Temporary ramps shall have appropriate detectable warning surfaces in conformance with ADAAG.

Temporary ramps shall be provided to the public leading to businesses. Temporary ramps at the corners of the intersections shall be made of temporary AC pavement to ensure that a smooth transition is provided for the public as well as auto traffic. All temporary wooden ramps shall be maintained throughout the construction project. The Contractor shall maintain the structural integrity of the ramps. No loose, splintered boards or nails will be acceptable.

Maintenance of a Clear and Accessible Public Corridor
The Contractor shall maintain a four (4) foot accessible corridor that provides at least one safe path of travel for the public at all times for the duration of the project. Conversely, if a safe path of travel is not available, the Contractor shall post the sidewalk as being closed, however, access must still be maintained to each business. Signage shall be placed at the location of closure and at the next intersection in both directions, advising of the closure but noting that access is still available to all businesses. All proposed closures of a pedestrian access path shall be submitted in writing to the Engineer for review and approval.

The Contractor shall provide a path to the businesses and residents, using aggregate base to backfill, after demolition of the concrete sidewalk, curb and gutter. The aggregate base shall be firmly packed to establish a safe and ADA compliant path, along the entire work zone.

Installation of Barricades
Barricades, which will provide protection for the public from traffic or construction operations, shall be installed in the following locations:
▪ Between the access route and any adjacent construction site. ▪ Between the alternate circulation path and any adjacent construction site. ▪ Between the alternate circulatio n path and the vehicular way, if the alternate circulation path is diverted into the street.
▪ Between the alternate circulation path and any protruding objects, drop-offs, or other hazards to the public.
▪ At the down curb ramp of an intersection, if opposite up curb ramp is temporarily or completely blocked, and no adjacent alternative circulation path is provided.

Surfacing of Public Corridors
During construction, tripping hazards and barriers must be removed to maintain an accessible safe path of travel. The surface of the path of travel shall be skid resistant and free of irregularities.

Opened crosswalks, ramps and walkways in general shall be kept free of debris and obstructions.

Identification of Safe Path of Travel
If alternate circulation routes are provided for the public to bypass the construction site, the route shall be clearly defined and advance warning shall be provided to clearly delineate the alternate circulation route.

Any change of level in a path of travel that is over ¼ inch (1/2” maximu m) height must be beveled at 45 degrees to provide a smooth, non-tripping transition. The Engineer shall review and approve any public access limitations and notification requirements for pedestrians with mobility or vision impairments.

When using A-frames for defining a path of travel, A-frames shall be placed end to end (no spacing between barricades) to provide a continuous guide for individuals using canes. A-frames shall be connected with 2x4’s that are continuous and are attached to the base of the barricade system at two (2) to four (4) inches from the ground.
324

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 15

Caution tapes shall not be used as barricades or to define a path of travel but may be used to highlight danger or in conjunction with barricades. Excavated areas shall be secured by means of barricades or temporary fences.

The bottom three (3) inches of any fencing material used shall be made solid to act as a guide for canes used by the visually impaired. Wood, sheet metal, railings, or other approved material may be used at the bottom portion of the fence.

Curb ramps leading to closed crosswalks shall be appropriately barricaded. Temporary ramps shall be provided at temporary crosswalks and shall be able to direct blind pedestrians to and through the temporary path of travel. R9-3a and R9-3b signs shall be mounted on the barricade to advise pedestrians of closed sidewalk and directed routes.

No trucks or equipment shall be parked or obstructing the public path of travel at any time.

Warning Signs
The Contractor shall provide warning signs for temporary ramps and barricades. Warning signs shall be located at both the near side and the far side of the intersection preceding a temporarily completely blocked public way.

Restoration of Public Routes
After construction, the site shall be restored to its former condition, or new condition as required.

3.04 ON-STREET PARKING
Contractor shall furnish, install, maintain and remove “No Parking” signs in areas where the Contractor’s work will require restricted parking. The Contractor shall place notification for the elimination of on-street parking, if required, at least forty-eight (48) hours, but not more than seventy-two (72) hours prior to the start of work. The signs shall clearly show the date(s) and hours of the parking prohibition, as well as the date and time the signs were posted. The notification shall include the Contractor's phone number and the phrase "VEHICLES WILL BE TOWED PURSUANT TO CVC SECTION 22654 (d)". This notice shall be affixed to a Type II barricade that is placed in the lane of the road, near lip of gutter, (max. 200 ft. spacing) used for on -street parking. No other location or method of placement is acceptable. The notification shall be in a form approved by the Engineer. Non -compliance with any st ipulation of this section will be justification for the City to stop work.

In the event that towing is required after proper notifications have been delivered and posted, and reasonable attempt have been made to the property owner or resident, the Contrac tor shall be responsible for contacting the Rocklin Police Department to dispatch a towing company. It will be the Contractor’s responsibility to determine if towing is required. The City will not be responsible for any claims made as a result of towing from the Contractor.

3.05 PORTABLE CHANGEABLE MESSAGE SIGNS
Portable Changeable Message Signs (CMS) shall be furnished, placed, operated, and maintained at locations designated by the Engineer and shall conform to the provisions in Section 12, “Temporary Traffic Control,” of the State Standard Specifications and these Special Provisions. Messages displayed on the portable changeable message signs shall be as directed by the Engineer and shall conform to Section 12-3.32 “Portable Changeable Message Signs,” of the State Standard Specifications and “Traffic Control System” of these Special Provisions.

A minimum of two (2) CMS boards shall be placed on Blue Oaks Boulevard, a minimum of one (1) CMS board on southbound Sierra College Boulevard, and a minimum of two (2) CMS boards shall be placed 325

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 16
on Crest Drive at least 7 calendar days prior to any construction activity and shall remain in place until project completion. A portable changeable message sign shall be placed in advance of the first warning sign for each stationary lane closure.

Should the CMS boards need to be located on private property due to lack of room within the public right of way, the Contractor shall coordinate this effort with private property owners and furnish written pro of to the City of the property owner’s acceptance.

A message displayed on a portable changeable message sign shall first be approved by the City.

3.06 MEASUREMENT AND PAYMENT
Traffic Control System shall be measured and paid for as LUMP SUM and shall include full compensation for furnishing all labor, material, tools, equipment and incidentals, including but not limited to private property coordination as necessary, preparing and maintaining an adequate traffic control plan, furnishing portable changeable message signs, furnishing, placing, removing storing, maintaining, moving to new locations, replacing, and disposing of the components of the temporary traffic control system, as specified in these Special Provisions, and as directed by the Engi neer and no additional compensation will be allowed therefore.

The City shall not pay additional traffic control compensation for a change work order or for a second mobilization if the project is extended due to weather. Payment for traffic control will be subject to retention.

The adjustment provisions in Section 4 -1.05, “Changes and Extra Work,” of the State Standard Specifications, shall not apply to the item of Traffic Control System. Adjustments in the compensation for Traffic Control System will be made only for increased or decreased traffic control system required by changes ordered by the Engineer and will be made on the basis of the cost of the increased or decreased traffic control necessary. Such adjustment will be made on a force account basis as provided in Section 9-1.04, “Force Account,” of the State Standard Specifications for increased work, and estimated on the same basis in the case of decreased work.
326

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 17

4.00 CONSTRUCTION STAKING
The contractor shall provide a copy of staking notes to the Engineer prior to any stakes being used. The Contractor shall furnish and set all construction stakes and marks to establish the line s, grades, and sections required for the completion of the work as shown on the plans and as specified in the State Standard Specifications and these Special Provisions.

Prior to any construction work, the Contractor shall adequately survey the existing horizontal and vertical control points of all facilities that are to be restored to their original locations at the end of construction.

Before starting any survey work, the Contractor shall submit in writing for approval to the Engineer, the proposed procedures, methods, equipment, and typical stake markings to be u sed. All procedures, methods, and typical markings shall be in accordance with the Caltrans Surveys Manual, Chapter 12, “Construction Surveys,” and which is available at https://dot.ca.gov/programs/right-of-way/surveys- manual-and-interim-guidelines.

In the event the Contractor's operations destroy any of the project control points or construction staking, the Contractor shall replace project control points and co nstruction staking at Contractor’s expense, subject to verification by the Engineer. The cost of any such verification by the Engineer will be deducted from any moneys due or to become due the Contractor. The Contractor will not be allowed any adjustment in contract time for such verification of project control points by the Engineer.

Construction stakes shall be removed from the site of the work when no longer needed.

It shall be the Contractor’s responsibility to notify the Engineer of any discrepancies found between the field conditions and grades and notes shown on the Plans.

4.01 MEASUREMENT AND PAYMENT
Full compensation for conforming to the requirements of this section of these Special Provisions shall be considered as included in the prices paid for the various items of work involved and no additional compensation will be allowed therefore.

327

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 18

5.00 POTHOLING
Attention is directed to Section 15, “Existing Facilities,” of the State Standard Specifications and these Special Provisions.

The Contractor’s attention is directed to the existence of certain underground facilities that may require special precautions be taken by the Contractor to protect the health, safety and welfare of workmen and of the public.

The Contractor shall notify the Engineer and the appropriate regional notification center for operators of subsurface installations not less than two working days, but not more than 14 calendar days, prior to performing any excavation or other work close to any underground pipeline, conduit, duct, wire or other structure. Regional notification centers include but are not limited to the following:

Notification Center
Underground Service Alert - Northern California (USA)
1(800) 227-2600

It is not the intent of the plans to show the exact location of existing or relocated utilities, and the Engineer assumes no responsibility therefore. Whenever any such utilities are indicated thereon and identified through the Underground Service Alert process, the Contractor shall be responsible for positively verifying their actual location and depth in the field. The Contractor shall notify USA prior to any excavation. The Contractor shall provide the City with the results of potholing activity.

The Contractor is responsible for potholing where potential conflicts exist between existing utilities, identified through USA, and proposed improvements. Potholing shall consist of excavating to fully expose underground utilities and facilities so that their exact horizontal and vertical alignment can be determined.

The location and number of potholes shall be determined in the field by the Contractor after the underground facilities have been marked in the field through USA. It is the Contractor’s responsibility to coordinate any potholing work with the necessary utilities.

The Contractor shall backfill and replace the street section in place following potholing activity in a manner acceptable to the City and the utility.

The Contractor will not be entitl ed to damages or additional payment for delays, mobilization or demobilization caused by a utility conflict with any of the proposed improvements or the utility company’s failure to appear on site at the designated date and time whether for potholing or any other private utility work.

In the event existing and proposed facilities are found to be in conflict after potholing, the Engineer reserves the right to change the alignment and grade of the proposed improvements.

5.01 MEASUREMENT AND PAYMENT
Full compensation for conforming to the requirements of this section , including backfilling and street surface restoration, utility coordination, as necessary for the Contractor to complete the work as designed shall be considered as included in the prices paid for the various items of work involved and no additional compensation will be allowed therefore.
328

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 19

6.00 WATER POLLUTION CONTROL PLAN (WPCP)
The Contractor shall develop and implement a WPCP in accordance with Section 13, “Water Pollution Control,” of the State Standard Specifications, and these Special Provisions.

The Contractor shall generate the WPCP and submit to the Engineer for review and approval.

Within this section, references to Water Pollution Control shall be consistent with content and requirements of the Project WPCP preparation, execution, and final stabilization requirements.

Unless arrangements for disturbance of areas outside the project limits are made by the City and made part of the contract, it is expressly agreed that the City assumes no responsibility whatsoever to the Contractor or property owner with respect to any arrangements made between the Contractor and property owner to allow disturbance of areas outside the project limits.

The Contractor shall be responsible for the costs and for liabilities imposed by law as a result of the Contractor’s failure to comply with the provisions set forth in these Special Provisions, including but not limited to, compliance with the provisions of the 2009 Approved Stormwater Quality Improvement Plan (SQIP), the Permit, and Federal, State, and local regulations. For the purposes of this paragraph, costs and liabilities include, but are not limited to, fines, penalties, and damages whether assessed against the City or Contractor, including those levied under the Federal Clean Water Act and the State Porter Cologne Water Quality Act.

At reasonable times and upon presentation of credent ials and other documents as may be required by law, the Contractor shall allow authorized agents of the California Regional Water Quality Control Board, State Water Resources Control Board, United States Environmental Protection Agency and the local storm water management agency to:

A. Enter upon the construction site and the Contractor’s facilities pertinent to the work; and B. Inspect the construction site and related soil stabilization practices and sediment control measures.

The Contractor shall notify the Engineer immediately upon request from the regulatory agencies to enter, inspect, sample, monitor or otherwise access the project site or the Contractor’s records.

6.01 WPCP PREPARATION, APPROVAL, AND UPDATES
The Contractor must provide a Qualified SWPPP Developer (QSD) to prepare the WPCP. The Contractor will provide a QSD and Qualified SWPPP Practitioner (QSP) to perform the testing and inspection. This does not relieve the Contractor from their duties to amend and follow the WPCP to include inspections and implementing corrections.

The Contractor shall be required to amend the WPCP and submit to the Engineer for review and comment. Erosion and sediment control shall conform to the requirements of the current edition of the “Storm Water Quality Design Manual, Sacramento Region,” which is available at the following website:
https://www.beriverfriendly.net/stormwater-quality-design-manual/ Within 20 working days of receiving a copy of the fully executed contra ct, the Contractor shall submit a copy of the WPCP to the Engineer. The Engineer will have 10 days to review the WPCP. If revisions are required, as determined by the Engineer, the Contractor shall revise and resubmit the WPCP to the Engineer within 15 days of receipt of the Engineer’s comments. The Engineer will have 5 days to review the revisions. A copy of the WPCP shall be kept on the job site (in the job trailer) at all times. 329

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 20
Soil stabilization Best Management Practices (BMPs) shall be maintained on any area disturbed. All BMPs shall be installed/implemented and maintained throughout the duration of construction.

The Contractor shall provide a QSP to perform regular inspection of the site and the installed BMPs. The Contractor’s QSP shall place a re cord of all inspections in the project WPCP binder within 24 hours of any inspection. The project WPCP binder shall be made available to the City for review at any time during normal working hours.

Erosion and sediment control BMPs shall be placed, monito red for effectiveness, and maintained throughout the construction process.

The following precautions shall be implemented regardless of the season:

1. A stabilized construction site access should be constructed at any construction staging and/or stockpile site as determined appropriate by the Engineer.

2. Temporary stockpiling of construction materials, including vehicles and portable equipment, supplies, fuels and chemicals, will be restricted to designated construction staging areas within the project area.

3. Any wet season requirement shall be implemented if conditions exist which may cause erosion and sedimentation.

4. The Contractor shall not be limited to the requirements listed above but shall be responsible for implementing whatever measures are necessary to prevent erosion and sedimentation.

The Contractor shall recommend amendments to the WPCP, graphically and in narrative form, whenever there is a change in construction activities or operations which may affect the discharge of significant quantities of pollutants to surface waters, ground waters, municipal storm drain systems or when deemed necessary by the Engineer. The WPCP shall be amended by the Contractor’s QSD if the WPCP is in violation of any condition of the Permit or has not effectively achieved the objective of reducing pollutants in storm water discharges. Amendments shall show add itional control measures or revised operations, including those in areas not shown in the initially approved WPCP, which are required on the project to control water pollution effectively. Amendments to the WPCP shall be submitted to the Engineer for review and approval in the same manner specified for the initially approved WPCP. Approved amendments shall be dated and logged in the WPCP. Upon approval of the amendment, the Contractor shall implement the additional control measures or revised operations within 3 business days or prior to any forecast rain event of 50% or greater per National Oceanic and Atmospheric Administration (NOAA).

If the project is in non-compliance at any time, the Contractor shall make a written report to the Engineer within 15 calendar days of identification of non-compliance.

6.02 WPCP IMPLEMENTATION AND MAINTENANCE
Upon approval of the WPCP, the Contractor shall be responsible throughout the duration of the project for installing, constructing, inspecting, and maintaining the control measures included in the WPCP and any amendments thereto and for removing and disposing of temporary control measures. Unless otherwise directed by the Engineer or specified in these Special Provisions, the Contractor's responsibility for WPCP implementation shall continue throughout any temporary suspension of work.

Soil-disturbed area of the project site shall be not more than 1 acre. The Engineer may approve, on a case-by-case basis, expansions of the active, soil-disturbed area limit. The Contractor shall demonstrate the ability and preparedness to fully deploy soil stabilization practices and sediment control measures to protect soil -disturbed areas on the project site before the onset of precipitation. A quantity of soil 330

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 21
stabilization and sediment control materials shall be maintained on site equal to 100 percent of that sufficient to protect unprotected, soil -disturbed areas on the project site. A detailed plan for the mobilization of sufficient labor and equipment shall be maintained to fully deploy control measures required for the protection of soil-disturbed areas on the project site prior to the onset of precipitation. A current inventory of control measure materials and the detailed mobilization plan shall be included as part of the WPCP.

Soil-disturbed areas of the project site shall be considered to be non-active whenever soil disturbance activities are to be discontinued for a period of 20 or more days and the areas are fully protected. Areas that will become non-active during the wet season shall be fully protected with soil stabilization practices and sediment control measures within 10 days of the discontinuance of soil disturbing activities or prior to the onset of precipitation, whichever is first to occur.

Soil-disturbed areas of the project site shall be fully protected at the end of each day with soil stabilization practices and sediment control measures unless fair weather is predicted through the following workday.

The Contractor shall monitor the weather forecast on a daily basis. The NOAA forecast shall be used .

Construction scheduling shal l be modified, as required, and functioning control measures shall be deployed prior to the onset of the precipitation.

The Contractor shall comply with all provisions of the WPCP, including inspection and maintenance during the life of the project, includ ing any work stoppages for any reason, including weather, holidays, moratorium, utility conflicts, etc.

If the Contractor or the Engineer identifies a deficiency in the deployment or functioning of an identified control measure, the deficiency shall be cor rected immediately. The deficiency may be corrected at a later date and time if requested by the Contractor and approved by the Engineer in writing, but not later than the onset of subsequent precipitation. The correction of deficiencies shall be at no a dditional cost to the City.

6.03 MEASUREMENT AND PAYMENT
Water Pollution Control Plan (WPCP) shall be measured and paid for as LUMP SUM and shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all the work involved in preparing the WPCP , and installing Best Management Practices (BMP). This bid item includes implementing measures prescribed in amendments, and installing, constructing, maintaining, removing, and disposing of control measures , as shown in the plans, as specified in the State Standard Specifications and these Special Provisions, and as directed by the Engineer.

The City of Rocklin pays a total of 40% of the lump sum price upon approval of the WPCP by the City, 55% of the lump s um price as determined by the Engineer spread across monthly pay estimates, and the final 5% as part of retention.

There shall be a single Water Pollution Control Plan which encompasses all bid schedules. For payment purposes, the Water Pollution Control Plan is part of the Blue Oaks Boulevard Pedestrian Signal Project.

331

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 22

7.00 CLEARING AND GRUBBING
Clearing and grubbing shall conform to Section 17 -2, “Clearing and Grubbing,” of the State Standard Specifications and these Special Provisions.

The Contractor shall remove and dispose of trash from the site work area. Objectionable materials removed shall be disposed of outside the street right of way in accordance with the State Standard Specifications.

The Contractor shall repair any private, landscaped areas damaged by construction activities that are not identified on the plans for removal. The repair s shall be considered incidental to the work and included in the lump sum price paid for clearing and grubbing with no additional payment allowed therefore.

If ground disturbance or vegetation removal is to take place during the breeding season (February t o August), a pre -construction nesting bird survey shall be conducted in accordance with the provisions identified in the “Remove Tree” section of these Special Provisions.

The Contractor shall coordinate with the City of Rocklin’s Landscape Inspector, Carl Miller, whose contact information is 916-625-5577, or [email protected] prior to any work on or near City maintained landscaping.

All mulch to be placed in existing and new mulch area s shall be included in the price paid for Clearing and Grubbing and no additional payment allowed therefore.

7.01 EXISTING IRRIGATION SYSTEM
The removal and repair of any existing irrigation/sprinkler systems (private or public) shall be conducted in accordance with these Special Provisions and that the Contractor shall relocate, repair or replace as necessary any irrigation lines, sprinkler heads, etc. which interfere with the clearing and grubbing, sidewalk construction, or any other improvements on the plans to the satisfaction of the Engineer. The Contractor shall adjust irrigation valves to grade that are not identified to be moved or relocated if they conflict with new proposed slopes.

The Contractor shall repair any irrigation systems damaged by con struction activities. The irrigation systems shall be reinstalled within 48 hours unless approved by the Engineer. The Contractor shall water existing landscaping in the interim using alternate methods, as directed by the Engineer. The price paid for meeting the existing irrigation system provisions of this section, including furnishing all water, shall be included in the price paid for Clearing and Grubbing with no additional payment allowed therefore.

7.02 EXISTING VEGETATION
Clearing and grubbing does not include the removal of existing trees, but does include the removal of shrubs, sod and other ground cover necessary to prosecute the work. Trees to remain shall be protected and any root cutting of trees to remain shall be done under the direction of a Contractor-provided arborist certified by the International Society of Arboriculture (I.S.A.). Roots shall be removed to a minimum depth of 12 inches below the grading plane, typically.

The Contractor shall submit to the City, in writing, the name of the I.S.A. certified arborist, a minimum of five (5) working days prior to the start of Clearing and Grubbing operations.

All work by the Contractor -furnished certified arborist shall be considered incidental to the work and included in the price paid for Clearing and Grubbing and no additional payment will be allowed therefore.

This includes support from the certified arborist for work performed under the Remove Tree or other bid items necessitating a certified arborist.
332

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 23
Tree trimming shall be limited to tree limbs required to be removed to allow for Project construction activities, minimum required vehicular clearance, and tree root cutting required for earthwork and trenching. All roots 6 inches in diameter or greater shall be cut cle anly and sealed by the arborist or by the arborist's staff.

All work within oak tree driplines shall be supervised by a certified arborist. The arborist shall conduct (or direct and supervise) all necessary root pruning of the oak trees. No limb pruning sh all occur unless absolutely necessary to avoid limb damage.

The price paid for meeting the existing vegetation provisions of this section, shall be included in the price paid for Clearing and Grubbing with no additional payment allowed therefore.

7.03 MEASUREMENT AND PAYMENT
Clearing and Grubbing shall be measured and paid as LUMP SUM and shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all the work involved in clearing and grubbing as specified in these Special Provisions, and as directed by the Engineer and no additional compensation will be allowed therefore.
333

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 24

8.00 REMOVE TREE
Remove Tree shall conform to the provisions in Section 17 -2.03D, “Disposal of Materials,” of the State Standard Specifications, and Section 7, “Clearing and Grubbing,” of these Special Provisions.

Tree roots that interfere with construction shall be cut off in a workmanlike manner only after consulting with the Contractor-provided certified arborist.

The Contractor shall field mark trees to be removed. These field markings of trees to be removed shall be verified by the Engineer prior to any tree removals.

The Contractor shall submit to the City, in writing, the name of the I.S.A. certified arborist, a minimum of ten (10) working days prior to the start of clearing and grubbing and/or tree removal operations.

8.01 NESTING BIRD SURVEY
If tree removal for construction will occur during the nesting season (February through August), a pre- construction survey sh all be conducted in construction areas for nesting birds. Surveys shall be conducted by a Contractor-provided qualified wildlife biologist.

Surveys should be conducted no more than 14 calendar days prior to the initiation of tree removal activities during the early part of the breeding season (February through April) and no more than 30 days prior to the initiation of these activities during the late part of the breeding season (May through July).

If the wildlife biologist deems that an active bird nest is close enough to the construction area to be disturbed, they should determine the extent of the construction-free buffer zone to be established around the nest. However, if an active raptor nest is located, a minimum 500 foot no-disturbance buffer shall be established with no work occurring within the buffer until a qualified biologist determines the young have fledged.

8.02 MEASUREMENT AND PAYMENT
Remove Tree shall be measured and paid for per EACH tree removed and shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for doing all the work involved in tree, complete in place, inc luding, removal, disposal, and a wildlife biologist to perform nesting bird surveys, as shown on the plans, as specified in the State Standard Specifications and these Special Provisions, and as directed by the Engineer.

334

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 25

9.00 REMOVE CONCRETE
Existing concrete curb, gutter, sidewalk, and curb ramp shall be removed to the limits as shown on the plans and in accordance with Section 15 -1.03B, “Removing Concrete,” of the State Standard Specifications.

Sidewalk, and gutter, estimated to be between 6” and 8” thick, designated on the plans to be removed or which conflicts with the proposed improvements under this contract shall be removed.

Concrete shall be cut with a concrete saw to a minimum depth of 2-inches before removing concrete so that the visible edge of the remaining concrete form a neat, straight line. Concrete saw cuts shall be at score marks.

Pedestrian access through the construction areas shall be provided as specified in the Traffic Control System bid item of these Special Provisions.

Concrete material removed shall be properly disposed offsite by the Contractor in accordance with the State Standard Specifications.

Concrete removal shall be staged to present the least amount of disruption to the general public and to maintain at least one accessible path of travel through the job site at all times. Removal of all curb ramps at one intersection at the same time shall not be allowed.

Sidewalk, curb, gutter, or other miscellaneous concrete not identified on the plans for removal which is damaged as a result of the Contractor’s operations shall be removed and replaced in kind at the Contractor’s expense.

No demolished concrete shall remain on the job site overnight.

Removed items shall become the property of the Contractor and shall be disposed of outside the City’s right of way.

9.01 MEASUREMENT AND PAYMENT
Remove Concrete (Curb, Gutter, Sidewalk, and Curb Ramp) shall be measured and paid for per SQUARE FOOT and shall include full compensation for all labor, materials, tools, equipment, and incidentals, and for doing all work involved with sawcutting and removing concrete of the various types shown on the Plans, as specified in the State Standard Specifications, these Special Provisions, and as directed by the Engineer and no additional compensation shall be paid therefore.

335

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 26

10.00 ROADWAY EXCAVATION
Roadway Excavation shall conform to Section 19 -2, “Roadway Excavation,” of the State Standard Specifications and these Special Provisions. Roadway Excavation shall consist of removal of existing pavement section, asphalt concrete dike, and other materials necessary to construct the improvements on the plans.

Existing asphalt concrete pavement/dike, aggregate base, subbase, and native material shall be removed to the limits shown on the project plans. On the line at which the asphalt concrete is to be removed, a straight, neat cut, with a power driven saw (or other acceptable means) shall be made to the full depth of the existing asphalt concrete prior to the removal of the asphalt concrete pavement.

Removal operations shall be performed with minimum damage to any portion of the asphalt concrete pavement that is to remain in place. All damage to the existing asphalt concrete to remain in place shall be repaired to a condition equal to or superior to that existing prior to the beginning of removal operations at the Contractor’s own expense.

Residue from cutting operations shall not be permitted to flow into storm drains or across lanes occupied by traffic and shall be removed from the pavement surface, concurrent with the cutting operation. All excavated material shall be removed and disposed of outside the street right of way in accordance with the State Standard Specifications.

Surplus excavated materials are the property of the Contractor and must be disposed of away from the project site. No excavated material will be allowed to be stockpiled overnight in or adjacent to public right of way, or on private property, unless approved by the City.

Unless otherwise provided for in these Special Provisions, the excavation may not be left without backfill during non-working hours except with prior written approval from the Engineer. Excavations left without backfill shall be barricaded and covered or otherwise protected to ensure public safety.

The Contractor shall assume that existing concrete flatwork is poured on native material, and which native material will not be permitted to remain. As such, excavation required to install aggregate base beneath all minor concrete as shown on the plans shall be included in the bid item for Roadway Excavation.

All quantities and bid items are assumed to have no rock within the project limit. Therefore, in bidding the items, contractor shall assume no rock excavation.

10.01 MEASUREMENT AND PAYMENT
Roadway Excavation shall be measured and paid for per CUBIC YARD and shall include full compensation for all labor, materials, tools, equipment, and incidentals, and for doing all work involved with removing asphalt concrete, aggregate base, subbase, and native material of the various types shown on the Plans, including sawcutting and grading the subbase for the proposed improvements, as specified in the State Standard Specifications, these Special Provisions, and as directed by the Engineer and no additional compensation shall be paid therefore.

336

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 27

11.00 COLD PLANING
Cold planing activities shall conform to Section 39-3.04, “Cold Planing Asphalt Concrete Pavement,” of the State Standard Specifications, and these Special Provisions. Cold Planing shall consist of removal of existing pavement section where shown on the Plans, and to the depth shown on the Plans.

Contractor shall schedule cold planing activities such that the pavement is cold planed and HMA is placed during the same work shift.

Contractor shall remove cold planed material concurrently with planing activities such that the removal does not lag more than 50 feet behind the planer.

A heating device may not be used to soften the pavement.

Cold Planing Machine
The cold planing machine, must be equipped with automatic controls for the longitudinal grade and transverse slope of the cutter head and:

1. If a ski device is used, it must be at least 30 feet long, rigid, and a 1-piece unit. The entire length must be used in activating the sensor.

2. If referencing from existing pavement, the cold planing machine must be controlled by a self- contained grade reference system. The system must be used at or near the centerline of the roadway. On the adjacent pass with the cold planing machine, a joint-matching shoe may be used.

The cold planing machine must be equipped to effectively control dust generated by the planing operation and operated such that no fumes or smoke is produced.

Grade Control and Surface Smoothness
Contractor shall install and maintain grade and transverse slope references.

The planed depth may be adjusted up to ± 0.03 feet from the depth shown on the plans to achieve uniform pavement profile, cross slope, and surface smoothness. The average cold planed depth must be equal to or greater than the depth shown on the Plans. The final cut must result in a neat and uniform surface.

The completed surface of the planed pavement must not vary more than 0.02 feet when measured with a 12-foot straightedge parallel with the centerline. With the straightedge at right angles to the centerline, the transverse slope of the planed surface must not vary more than 0.03 feet.

Contractor shall notify the Engineer immediately if delaminations are encountered during planing operations.

11.01 MEASUREMENT AND PAYMENT
Cold Planing shall be measured and paid for per SQUARE FOOT and shall include full compensation for all labor, materials, tools, equipment, and incidentals, and for doing all work involved with cold planing, where shown on the plans, to the depth shown on the plans, as specified in the State Standard Specifications, these Special Provisions, and as directed by the Engineer and no additional compensation shall be paid therefore.

337

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 28

12.00 AGGREGATE BASE
Aggregate Base shall be Class 2 and shall be furnished and installed in accordance with Section 26, “Aggregate Bases,” of the State Standard Specifications, and these Special Provisions.

Aggregate base shall be produced from commercial quality aggregate consisting of broken stone, crushed gravel, clean, rough-surfaced gravel and sand, or a combination thereof. The grading of the material shall be three -fourth inch (3/4”) maximum. Spreading and compacting shall be performed by methods that will produce a uniform base when firmly and properly compac ted free from pockets and coarse or fine material.

Class 2 Aggregate Base material shall contain sufficient moisture to prevent segregation. Aggregate base materials shall be immediately spread to its planned grade and cross section. Segregation or excessive drifting or spotting material will not be permitted.

The surface of the finished aggregate base at any point shall not vary more than 0.05-foot above or below the grade established by the City.

The Engineer shall have the option of leaving existing ag gregate base in place if deemed suitable and compacted to meet specifications. The Contractor shall not assume there is existing aggregate base under existing flatwork. If existing aggregate base exist s and is reused, t he bid item quantity shall be reduced accordingly.

The Contractor shall install aggregate base rock from one source to the greatest extent practical to ensure compaction testing results are reliable and consistent for the duration of the project. If additional suppliers are to be considered, the Contractor shall provide material submittals for review and approval. The Contractor shall coordinate with the Engineer to agree upon where a particular type of base rock is to be installed thereby avoiding the mixing of aggregate base rock from multiple suppliers in one area.

The Contractor shall achieve at a minimum 95% relative compaction as outlined in the City’s Quality Assurance Program. The Contractor shall refer to the Quality Assurance Program sec tion of these Special Provisions for information related to materials testing requirements.

The Contractor shall provide a material submittal to the City with laboratory test data no more than six weeks old certifying that the proposed materials meet all the quality requirements of Section 25 , “Aggregate Subbases,” and 26 , “Aggregate Bases,” of the State Standard Specifications. Proposed recycled materials shall not be used in the work unless a material submittal is approved in writing by the City.

The Contractor shall verify that the mix design, with ID number written on weighmaster tags, delivered to the job site matches the approved mix design. If the mix design ID numbers do not match, the product shall be rejected at no cost to the City.

12.01 DAILY SUBMITTAL
The Contractor shall submit tickets indicating the quantity of material delivered as the material arrives at the job site, or at any time upon request of the Engineer. If the Contractor does not submit the tickets at the end of each day wh en aggregate base is installed, a temporary stop work order may be issued on the construction activity with no associated cost incurred by the City. The construction activity may resume with the Engineer’s written approval upon receiving and reviewing all tickets. 338

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 29

12.02 MEASUREMENT AND PAYMENT
Aggregate Base shall be measured and paid for per CUBIC YARD and shall include full compensation for furnishing all labor, materials, tools, equipment, incidentals, and for doing all work involved in installation of aggregate base rock complete in place, including compaction and all incidental work, all as specified in the State Standard Specifications, these Special Provisions, and as directed by the Engineer and no additional compensation will be made therefore.
339

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 30

13.00 CONCRETE
All Minor Concrete for sidewalk, driveway, band, curb, gutter, and retaining curb shall be constructed in accordance with Section 73 , “Concrete Curbs and Sidewalks,” of the State Standard Specifications unless otherwise directed in these Special Provision s. Minor Concrete shall be in accordance with Section 90-2, “Minor Concrete,” of the State Standard Specifications and shall achieve a minimum of 3,000 psi compressive strength by 28-calendar days after placement.

The Contractor shall coordinate with the City for material sampling and testing. The City’s independent consultant shall have full access to all areas of the wo rksite necessary to sample and test required materials. Any material tested which does not meet the minimum design standards as outlined in this Special Provision or the City’s approved Quality Assurance Plan shall be removed and replaced at no cost to the City. The City will assume the cost of the quality assurance testing.

The Engineer shall be notified 24 hours prior to concrete pour. The Contractor shall provide string lines and forms delineating the proposed concrete surface for Engineer observation a minimum of 4 (four) hours prior to concrete pour. No concrete shall be poured until the Engineer has approved the forms.

All oil, paint, tire, graffiti and other marks shall be removed from all minor concrete construction by sandblasting or complete replacement prior to acceptance by the Engineer. Cement mortar will not be an acceptable substitute for sandblasting or complete replacement.

13.01 EXECUTION
A. Curb Ramps

1. No utility pull box, traffic signal pull box, traffic signal pole foundation, or any other facility that is visible on or above the surface of a curb ramp may be located within the area of a curb ramp without prior approval of the Engineer. For the purpose of these Special Provisions, the area of the curb ramp shall be the area of curb, gutter, sidewalk , and retainer curb (back of walk) including and bounded by the 4-foot transition adjacent to the inclined portions of the ramp.

2. All Curb Ramps shall be constructed in accordance with this section, State Standard Plan A88A and A88B, except as noted on the plans, and all Federal, State and local codes and regulations.

Any variations from the details or code requirements must be approved in writing by the Engineer, prior to placing concrete.

If a ramp constructed by the Contractor is not in full compliance with the requirements of this section, as determined by the Engineer, the Contractor shall remove and reconstruct the entire ramp at their sole cost and expense. Note: To ensure full compliance of all curb ramps with the standard details and codes, the City’s Inspector shall use appropriate means including, but not limited to, a 2-foot smart level and a tape measure.

3. The Contractor shall form, place concrete , and re-open each new curb ramp to full and safe pedestrian use by 5:00 p.m. on Friday of the same week demolition/removal is performed unless previously agreed to by the Engineer.

To the greatest extent practical, curb ramp locations shall be open for pe destrian use on weekends and holidays. For the purpose of this project “full and safe pedestrian use” means removal of all formwork, restoration of pavement or placement of properly compacted temporary patch material in front of ramp, removal of construction debris and elimination of all other barriers to pedestrian travel.

340

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 31
B. Doweling

1. When pouring new concrete to existing concrete, the existing concrete vertical face shall be doweled two feet on center with 16-inch long, grade 60, #4 rebar penetrating four-inches into the existing curb, four-inches below top of curb. The dowel hole shall be 5/8-inch diameter at a light angle horizontally. The penetrating portion the dowel and adjoining existing concrete shall be 95% coated with two-part epoxy.

2. Abutting curb and gutter ends shall be doweled twice, 18-inches apart, centered on the curb and gutter section.

3. If the existing edge is damaged during doweling, the concrete shall be saw cut again at the Engineer's discretion, at no additional cost to the City.

C. Concrete

1. Before placing concrete, subgrade shall be well dampened.

2. All curb and gutter shall be poured monolithically with adjoining sidewalk.

3. Extruded curb will not be allowed.

4. All newly placed concrete shall be finished and cured in accordance with Section 90 -1.03B, “Curing Concrete,” of the State Standard Specifications and these Special Provisions.

5. Exposed surfaces of all minor concrete shall be coated with a pigmented curing compound immediately following surface finishing prior to the moisture sheen disappearing from the surface.

Curing compound shall be uniformly applied at a rate of one gallon per 150 square feet per the manufacturer’s recommendations, whichever is greater, unless otherwise specified. The Contractor shall use caution that the pigmented compound is contained within the intended area of work and does not discolor asphalt concrete or other adjoining improvements.

6. Median island concrete shall have Davis Colors Brick Red color integrated per manufacturer recommendations.

D. Expansion Joints, Weakened Plane Joints, and Score Marks

1. In sidewalks, an expansion joint shall be placed at the end of round corners and at major structures such as utility vaults, at portions of sidewalk that include a manhole, and at other as shown on the Plans or as directed by the Engineer. In addition, expansion joints shall be placed at sixty-foot (60’) intervals of all sidewalks, and concrete median pavement.

2. Expansion joint material shall be one-half inch (1/2”) thick, be shaped to fit the geometry of the sidewalks and extend for the full depth of the sidewalks. Expansion joint material shall conform to Section 73-1.02, “Materials”, of the State Standard Specifications. Expansion joints shall be at right angles to the line of the work. Sealant shall be placed over the expansion joint material if directed by the City. Contractor shall not place “Felt” in expansion joints of sidewalk or curb and gutter.

3. Weakened plane joints and score marks shall be placed through the curbs and gutter section at the following intervals for the sidewalk widths indicated:
i. All four-foot (4’) wide sidewalk/ramp shall be scored at four-foot (4’) intervals. In lieu of every third score mark, at twelve-foot (12’) intervals, weakened plane joints shall be constructed. ii. All five-foot (5’) wide sidewalk/ramp shall be scored at five-foot (5’) intervals. In lieu of every third score mark, at fifteen-foot (15’) intervals, weakened plane joints shall be constructed. iii. All six-foot (6’) wide sidewalk/ramp shall be scored at six -foot (6’) intervals. In lieu of every third score mark, at eighteen-foot (18’) intervals, weakened plane joints shall be constructed. 341

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 32

4. Weakened plane joints shall extend through both the sidewalk and the curb and gutter when constructed at the same time and monolithically.

5. All score marks shall be placed at the back of the curb for the total length of all monolithic curb, gutter and sidewalk.

E. Concrete Finish

1. Concrete shall not be placed or finished in the rain.

2. Curb and gutter shall be free from humps, sags, or other irregularities. The surface shall be uniform to a degree such that no depressions greater than 0.02 foot are present when tested with a ten-foot (10’) straightedge, except at grade changes.

3. All concrete surfaces shall be completed with a medium broom finish transverse to the line of work unless otherwise specified.

4. All gutters shall be flow tested with water post concrete pour to assure proper drainage. If positive drainage is not achieved, the Contractor shall remove and reconstruct gutter/bus pad to achieve positive flow at their sole cost and expense.

5. All exposed surfaces of minor concrete shall be free from rock pockets, discoloration, graffiti, and blemishes. Surfaces shall have a uniform texture and appearance free of bulges, depressions, or other imperfections. Surfaces shall not vary by more than one quarter of an inch (1/4") from a ten-foot (10’) straight edge except at grade changes.

6. Median island concrete shall be stamped with an “offset brick” pattern.

F. Damage Repairs
All damage done or openings cut in concrete walks, curbs or gutters during the progress of the work shall be repaired by the Contractor to the satisfaction of the City. Patching of damaged areas may be allowed at the discretion of the Engineer. Partial rem oval and replacement of sections of sidewalk, portions of curbs and/or gutters less than four (4’) feet in length will not be allowed.

All removal of damaged sidewalk, curb and gutter sections shall extend to the nearest score marks, weakened plane joint, construction joint within three (3’) feet of the limit of damage concrete. All damaged areas shall be removed and replaced as specified by the Engineer without compensation.

All voids behind back of walk created by the installation of minor concrete shall be backfilled with suitable material and properly compacted within 10 working days of concrete placement.

13.02 DETECTABLE WARNING SURFACE
Detectable Warning Surfaces shall be installed in each curb ramp in accordance with State Standard Plan A88A, Section 73, “Concrete Curbs and Sidewalks,” of the State Standard Specifications, these Special Provisions, and as directed by the Engineer.

A detectable warning surface must be on the Caltran s Authorized Material List for detectable warning surfaces and must match yellow color no. 33538 of AMS-STD-595.

13.03 DAILY SUBMITTAL
The Contractor shall provide delivery tickets at the time of delivery of each load of concrete. Each delivery ticket shall state the total yield in cubic yards, date, and time of day corresponding to when the batch was loaded, when it was dispatched, when it arrived at the job, and the time that unloading began. Each delivery 342

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 33
ticket shall include the mix design number such that the Engineer can confirm the placed concrete matches the approved material submittal.

13.04 MEASUREMENT AND PAYMENT
Curb Ramps – Payment for the work required to construct the Curb Ramps, complete in place, shall be considered as included in other bid items that make up the work including, but not limited to , Minor Concrete Sidewalk, Minor Concrete Curb and Gutter of the various types shown on the plans, and Detectable Warning System, and no additional compensation will be allowed, therefore.

Minor Concrete (Median) shall be measured and paid for per SQUARE FOOT and shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals and for doing all work involved in sawcutting, constructing the flatwork, complete in place, including preparing the subgrade, all form work, integrating color, finishing and curing the concrete, scoring, placing dowels and epoxy, water testing, and repairing any damage as shown on the Plans, as specified in the State Standard Specifications, these Special Provisions, and as directed by the Engineer and no additional compensation shall be allowed therefore.

Minor Concrete (Sidewalk) shall be measured and paid for per SQUARE FOOT and shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals and for doing all work involved in sawcutting, constructing the flatwork, complete in place, including preparing the subgrade, all form work, finishing and curing the concrete, scoring , placing dowels and epoxy, water testing, and repairing any damage as shown on the Plans , as specified in the State Standard Specifications, these Special Provisions, and as directed by the Engineer and no additional compensation shall be allowed therefore.

Minor Concrete (Driveway) shall be meas ured and paid for per SQUARE FOOT and shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals and for doing all work involved in sawcutting, constructing the flatwork, complete in place, including preparing the subgrade, all form work, finishing and curing the concrete, scoring, placing dowels and epoxy, water testing, and repairing any damage as shown on the Plans, as specified in the State Standard Specifications, these Special Provisions, and as directed by the Engineer and no additional compensation shall be allowed therefore.

Minor Concrete (Type 2 Curb & Gutter) shall be measured and paid for per LINEAR FOOT and shall include full compensation for furnishing all labor, materials, to ols, equipment, and incidentals and for doing all work involved in sawcutting, constructing curb and gutter, complete in place, including preparing the subgrade, all form work, furnishing and curing the concrete, scoring, placing dowels and epoxy, curb and gutter water testing, and repairing any damage as shown on the Plans, as specified in the State Standard Specifications, these Special Provisions, and as directed by the Engi neer and no additional compensation shall be allowed therefore.

Minor Concrete (Type 5 Curb) shall be measured and paid for per LINEAR FOOT and shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals and for doing all work involved in sawcutting, constructing curb and gutter, complete in place, including preparing the subgrade, all form work, furnishing and curing the concrete, scoring, placing dowels and epoxy, curb and gutter water testing, and repairing any damage as shown on the Plans, as specified in the State Standard Specifications, these Special Provisions, and as directed by the Engineer and no additional compensation shall be allowed therefore.

Minor Concrete (18” and 6” Retaining Curb) shall be measured and paid for per LINEAR FOOT and shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals and for doing all work involved in sawcutting, constructing the retaining curb , complete in place , including preparing the subgrade, all form work, furnishing and curing the concrete, scoring, installing steel rebar, 343

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 34
placing dowels and epoxy, water testing, and repairing any damage as shown on the Plans, as specified in the State Standard Specifications, these Special Provisions, and as directed by the Eng ineer and no additional compensation shall be allowed therefore.

Minor Concrete (Mow Band) shall be measured and paid for per LINEAR FOOT and shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals and for doing all work involved in sawcutting, constructing the mow band, complete in place, including preparing the subgrade, all form work, furnishing and curing the concrete, scoring, installing steel rebar, placing dowels and epoxy, water testing, and repairing any damage as shown on the Plans, as specified in the State Standard Specifications, these Special Provisions, and as directed by the Engineer and no additional compensation shall be allowed therefore.

Detectable Warning Surface shall be measured and paid for per SQUARE FOOT and shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all work involved in constructing detectable warning system, complete in place, as shown on the Plans, as specified in the State Standard Specifications, these Special Provisions, and as directed by the Engineer and no additional compensation shall be allowed therefore. This bid item is strictly for the DWS and does not include the concrete or aggregate base rock beneath the DWS.

344

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 35

14.00 HOT MIX ASPHALT
The Contractor shall furnish and install hot mix asphalt (HMA) at the locations and to the depths shown on the plans in accordance with Section 39-2, “Hot Mix Asphalt,” of the State Standard Specifications, and these Special Provisions.

14.01 MATERIALS
The Contractor shall submit in writing to the Engineer a complete mix design as described in Section 39-

2.01A(3)(b), “Job Mix Formula,” of the State Standard Specifications. Mix designs must include the name of the material plant, the product name, a mix d esign ID number, and item of work in which it is to be used.

HMA shall be type A.

All asphalt binder shall be PG 64 -10 and shall conform to the requirements of Section 92, “Asphalt Binders,” of the State Standard Specifications. Aggregate shall be ½” aggregate.

The Contractor shall furnish and install an emulsified asphalt (Type SSI) tack coat conforming to Sections 39-2.01C(3)(f), “Tack Coat,” and 94, “Asphaltic Emulsions,” of the State Standard Specifications.

The Contractor shall submit certificat ion from the supplier that the material he is furnishing has been properly tested within the last 6 weeks and designed so as to meet the aforementioned specifications.

Cost of any such testing shall be the responsibility of the Contractor and/or supplier. Once a supplier's material has been found acceptable, the Contractor shall furnish material from no other source without the prior approval of the Engineer in writing.

The Contractor shall verify that the mix design, with ID number written on weighmaster tags, delivered to the job site matches the approved mix design. If the mix design ID numbers do not match, the product shall be rejected at no cost to the City.

14.02 EXECUTION
The HMA structural section in areas of roadway widening shall be brought to the elevation of the adjacent existing pavement before overlay is placed. The overlay joints on the top lift shall overlap the joint between the new and the existing pavement.

Surface p reparation and tack coat application shall be in accordance with the State Standard Specifications. The surfaces upon which asphalt concrete is to be placed shall be thoroughly cleaned of all dirt, vegetation, and debris.

Prior to application of tack coat, the street shall be cleaned with a vacuum street sweeper and be clean of all dust.

Existing paved surfaces shall be given a tack coat by spraying with penetration type emulsified asphalt at the rate of 0.05 to 0.10 gallon per square yard as directed by the Engineer.

The HMA shall be placed in 3 -inch maximum lifts after compaction. Conform sections shall be squared off and hand raked to a neat straight line. Edges at curb shall be hand raked and rolled with a small roller or tamper when larger roller cannot be used.

Spreading and Compaction
345

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 36

1. Vehicles used for hauling HMA mixtures must have tight, smooth, metal beds, and must be free from dust, screenings, excessive petroleum oils, volatiles, or other mineral spirits that may affect the mix being hauled. Trucks must be provided with tarpaulins or cargo covers of sufficient size and weight to protect the entire load.

2. Should the methods and equipment furnished by the Contractor fail to produce a layer of HMA conforming to the requirements, including straightedge tolerance, of Section 39 -2.01C(2), “Spreading and Compacting Equipment,” of the State Standard Specifications, the paving operations shall be discontinued, and the Contractor shall modify his equipment or furnish substitute equipment.

Finishing Roadway

1. The completed surface shall be thoroughly compacted, smooth, and true to grade and cross section, free from ruts, humps, depressions or irregularities. When a straight edge 1 2 feet long is laid on the finished surface and parallel with the center line of the highway, the surface shall not vary more than 0.01 feet from the lower edge of the straight edge . When tested transversely to traffic, the surface shall incline continuously in the direction of the drainage so that no depressions, which will not drain, remain in the surface after rolling. Any ridges, indentations or other objectionable marks left in the surface of the HMA by equipment shall be elimin ated by rolling or other means. The use of any equipment that leaves ridges, indentations or other objectionable marks in the HMA shall be discontinued and other acceptable equipment shall be furnished by the Contractor.

2. A drop-off of more than 2 inches will not be allowed at any time between adjacent lanes open to public traffic.

3. Half-width surfacing operations shall be conducted in such manner that, at the end of each day’s work, the distance between the ends of adjacent surfaced lanes shall not be greater than can be completed in the following day of normal surfacing operations.

4. Finishing roadway shall conform to Section 22 , “Finishing Roadway,” of the State Standard Specifications. The entire roadway and right -of-way shall be left in a neat and pre sentable condition to the satisfaction of the Engineer.

5. Temporary pavement markings shall be installed for all roadway centerlines, stop lines and channelizing lines following the final lift of HMA overlay . Temporary pavement markers shall be the same color as the lane line or centerline markers being replaced. Temporary pavement markings shall comply with ‘Temporary pavement markers for short term day/night use (14 days or less) of Section 12 -6, “Temporary Pavement Delineatio n,” of the State Standard Specifications. The costs of temporary pavement markings or floppies are included in the asphalt concrete bid item.

Testing and Certification
During the work, the City may periodically sample and test the furnished material to en sure quality assurance in accordance with the City’s Quality Assurance Program. The Contractor will perform all required quality control testing. The City will assume the cost of all quality assurance testing, however, the Contractor will be required to pay for all failing tests.

14.03 DAILY SUBMITTAL
The Contractor shall submit HMA Weighmaster’s Certificates as the material arrives at the job site, or at any time upon request of the Engineer. If the Contractor does not submit the Certificates at the end of the day when HMA is installed, a temporary stop work order may be issued on the paving operation with 346

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 37
no associated cost incurred by the City. The paving operation may resume with the Engineer’s written approval upon receiving and reviewing the Certificates.

14.04 MEASUREMENT AND PAYMENT
Hot Mix Asph alt as determined by Weighmaster’s Certificates, shall be per TON and shall include full compensation for furnishing all the labor, materials, tools, equipment, incidentals, and for doing all the work involved in furnishing and installing hot mix asphalt, including production, delivery, placement, and compaction of HMA, complete in place, including tack coat, pre -overlay preparation, and all incidental work, as shown on the project plans, as specified in the State Standard Specifications, these Special Provisions, and as directed by the Engineer, and no additional compensation will be made therefore.

Hot Mix Asphalt Plug Pave as determined by Weighmaster’s Certificates, shall be per TON and shall include full compensation for furnishing all the labo r, materials, tools, equipment, incidentals, and for doing all the work involved in furnishing and installing hot mix asphalt, including production, delivery, placement, and compaction of HMA, complete in place, including tack coat, and all incidental work , as shown on the project plans, as specified in the State Standard Specifications, these Special Provisions, and as directed by the Engineer, and no additional compensation will be made therefore.

Quantities of material wasted or disposed of in a manner not called for under the contract, or rejected loads of materi al, including material rejected after it has been placed by reason of the failure of the Contractor to conform to the provisions of the contract, or materials placed outside the lines indi cated from the transporting vehicle, or material remaining on hand after completion of the work, will not be paid for and such quantities will be deducted from the final total quanti ties. No compensation will be allowed for hauling rejected material. The final weighmaster tag shall note the amount of tonnage to be deducted from the pay estimate and be signed by the Engineer or the Engineer’s representative and the Contractor.

347

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 38

15.00 TRAFFIC STRIPING AND PAVEMENT MARKINGS
Traffic stripes and pavement markings, of the various colors indicated on the plans (white or yellow), shall be installed in accordance with these Special Provision s and Section 84 , “Markings,” of the State Standard Specifications.

The Contractor shall install cat-tracks at least two (2) working days ahead of, and receive approval from the Engineer prior to, installation of any permanent striping and pavement markings.

New, permanent traffic striping shall be installed on the roadway within five (5) working days after final paving operations.

Thermoplastic stripes and pavement markings shall not be placed over utility covers including, but not limited to, manhole covers, utility boxes, traffic signal detector hand holes, or water valves covers.

Thermoplastic traffic stripes and pavement markings shall be free of runs, bubbles, craters, drag marks, stretch marks, and debris.

Retroreflectivity of the thermoplastic traffic stripes and pavement markings shall conform to the requirements in ASTM Designation: D6359 -99. White thermoplastic traffic stripes and pavement markings shall have a minimum initial retroreflectivity of 250 mcd ⋅m-2⋅lx-1. Yellow thermoplastic traffic stripes and pavement markings shall have a minimum initial retroreflectivity of 150 mcd⋅m-2⋅lx-1.

15.01 PAVEMENT MARKERS/DELINEATORS/STRIPING/PAVEMENT MARKINGS The Contractor shall remove all existing traffic stripes and pavement markings in conflict with new traffic stripes and pavement markings in accordance with Section 84 -9, “Existing Markings,” of the State Standard Specifications.

Sandblasting of traffic stripes shall not be permitted. Removal of traffic stripes shall be by grinding, or by other methods approved in writing by the Engineer. Drain inlets adjacent to areas to be ground shall be protected from grinding entering the storm drain system.

For removal of pavement markings, a rectangular area shall be ground to prevent ghosting of the original markings. Conflicting striping shall be removed completely.

All striping or pavement markings damaged during construction shall be repaired at the Contractor’s expense. Repairs shall consist of complete replacement of markings or legends, replacement of sections of striping, and replacement of damaged or missing markers as directed by the Engineer.

15.02 TEMPORARY STRIPING AND PAVEMENT MARKINGS
The Contractor shall supply and install temporary stripi ng to control traffic until permanent striping and pavement markings are installed. All temporary striping, pavement markings, tape, floppies, etc. shall be removed when no longer needed to safely direct traffic.

Painted white striping/pavement markings shall conform to Section 84-2.03B(6), “Paint,” of the State Standard Specifications.

The Contractor is not required to remove painted temporary traffic stripes that will be covered by paving work.

348

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 39
Full compensation for furnishing and installing temporary striping and pavement markings is included in the prices paid for the various items of work involved and no additional compensation will be allowed therefore.

15.03 MATERIAL
Thermoplastic shall be Alkyd type for extrusion application and shall produce an adherent reflectorized strip capable of resisting deformation by traffic.

Thermoplastic material shall be free of lead and chromium and shall conform to the requirements in State Specification PTH-02ALKYD.

The thermoplastic material shall be 100 percent solids. The binder shall consist of synthetic alkyd resins and shall be homogeneously incorporated with all the necessary prime pigments, fillers, and glass beads to produce a traffic coating to meet the requirements as specified herein.

Characteristics of Finished Thermoplastic:

White Yellow
Glass Beads, AASHTO M -247, Type I, percent by
weight, min. (Cal. Test Method 423)
30 30
Titanium Dioxode (TiO2), percent by weight, min.
(AASHTO T250-77)
10 Lead Chromate, Medium Heat Stability, percent by
weight, min.

2.5 Specific Gravity, max. (Cal. Test Method 423) 2.15 2.15 Binder, percent by weight, min.
(Cal. Test Method 423)
18 18
Ring & Ball Softening Point, °F (ASTM E28) 200-240 200-240

Bond Strength to Concrete, 0.125-inch-thick film
drawdown at 425°F test at 75°F + 2°F, psi, min
(Cal. Test Method 423)
180 180
Brookfield Thermosel Viscosity, Spindle SC4 -27, 20
RPM at 425°F, Poise (Cal. Test Method 423)
30 – 45 30 – 45
Impact Resistance, Falling Ball Method, 0.125-inch-thick film drawdown at 425°F on concrete. Test at 75°F + 2°F
inch-lbs., (ASTM D2794)
10 10
Daylight Luminous Reflectance, min. (ASTM E97) 75 40 Yellowness Index, max., (ASTM E313) .15 Hardness, Shore A-2 Durometer with 2-kilogram weight
at 115°F (Cal. Test 423)
60 – 80 60 – 80
Low Temperature Stress Cracking, Resistance at 25°
(AASHTO)
No Crack No Crack
Color Match, Federal Std. No. 595a, Color No. 33538 Passes

15.04 APPLICATION
Thermoplastic Traffic Striping Material, Alkyd Binder, White and Yellow. All thermoplastic must be applied per Section 84-2.03B(2)(b), “Extruded Thermoplastic,” of the State Standard Specifications.

349

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 40
The Contractor shall apply an adhesive primer base coat prior to the application of any thermoplastic material on treated pavement, stamped pavement, colored pavement, concrete surfaces, or pavement older than 30 days.

Unless otherwise specified in these Special Provisions, the thermoplastic material for traffic stripes shall be applied at a minimum thickness of 0.075-inch. Thermoplastic Material for pavement markings shall be applied at a minimum thickness of 0.125 -inch. Glass beads shall be applied imme diately to the surface of the molten thermoplastic material, at a rate of not less than 8 lbs. per 100 sq. ft. The amount of glass beads applied shall be measured by stabbing the glass beads tank with a calibrated rod.

15.05 TOLERANCES AND APPEARANCE
The completed traffic stripes and markings shall have clean and well-defined edges without deformations and shall be free of tears or other disfigurements. Improperly placed, defective, or disfigured traffic stripes and markings shall be immediately removed fr om the pavement surface by methods approved by the Engineer. All such removal work shall be at the Contractor's expense.

Completed traffic stripes shall be uniform, shall be straight on tangent alignment, and shall be on a true arc on curved alignment. On tangent alignment, when a 100' string line is stretched taught and placed directly on the outer edge of the completed traffic stripe, the distance between the string and the edge of the traffic stripe shall not exceed three -fourths of one inch (3/4") when measured anywhere along any 100' interval of the tangent alignment. On curved alignment, the outer edge of the traffic stripe shall not deviate more than three-fourths of one inch (3/4") from the true arc. The lengths of the gaps and individual stripes that form broken traffic stripes shall not deviate more than 2" from the lengths required to produce a uniformly repeating, broken-stripe pattern.

15.06 PAVEMENT MARKERS
Pavement markers shall be placed in conformance with the provisions in Section 84, “Markings,” of the State Standard Specifications and these Special Provisions.

Retroreflective pavement markers shall comply with the specific intensity provisions for reflectance after abrading the lens surface in conformance with the “Steel Wool Abrasion Procedure” specified for pavement markers placed in pavement recesses in Section 81-3.02C, “Retroreflective Pavement Markers,” of the State Standard Specifications.

Blue raised reflective fire hydrant markers with two reflective faces shall be included in this item of work. Hydrant markers shall be placed in the street, 6”-12” off the centerline and perpendicular to the fire hydrant.

15.07 OBJECT MARKERS
Object markers shall be placed in conformance with the provisions in Section 82, “Signs and Markers,” of the State Standard Specifications and these Special Provisions.

Type Q (CA) object markers shall be Pexco’s City Post Model Embedded Anchor Cup. Embedded anchor cups shall be installed per manufacturer recommendations.

15.08 MEASUREMENT AND PAYMENT
Thermoplastic traffic stripes (Bid Item by Detail) shall be measured and paid for by the LINEAR FOOT, for the various traffic stripes shown on the project p lans, along the line of the traffic stripes, without deductions for gaps in broken traffic stripes. The price shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals for all work involved in furnishing and installing traffic 350

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 41
stripes, including pavement markers , blue reflective pavement markers identifying fire hydrants, replacement of damaged stripes, and pavement surface preparation, all per the project p lans, State Standard Plans/Specifications, and these Special Provisions, and no additional compensation will be allowed therefore.

Red Curb Paint shall be measured and paid for by the LINEAR FOOT, for the various red curb paint shown on the project plans. The price shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals for all work involved in furnishing and installing red curb paint per the project plans, State Standard Plans/Specification s, and these Special Provision s, and no additional compensation will be allowed therefore.

Thermoplastic Pavement Markings including letters, turn arrows, symbols, limit lines, and crosswalks shall be measured and paid for by the SQUARE FOOT, which price shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals and for doing all work involved in placing pavement markings, replacement of damaged pavement markings, and pavement surface preparation, all per the p roject plans, State Standard Plans/Specifications, and these Special Provisions, and no additional compensation will be allowed therefore.

The square foot area of pavement markings will be determined from the most recent State Standard Plans.

Removal of existing traffic stripes and markings shall be included in the various items of work involved and no separate payment shall be allowed therefore.

Type Q (CA) Object Markers shall be measured and paid for per EACH, for the various Type Q (CA) object markers shown on the project plans. The price shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals for all work involved in furnishing and installing Type Q (CA) object markers, including installing aluminum embedded anchor cups, retroreflective sheeting, all per the project plans, State Standard Plans/Specifications, and these Special Provision s, and no additional compensation will be allowed therefore.

351

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 42

16.00 ROADSIDE SIGNS AND BARRICADES
The Contractor shall install and relocate roadside signs and barricades in accordance with the most recent edition of the California Supplement to the Manual o n Uniform Traffic Control Devices (CA - MUTCD), the State Standard Specifications, State Standard Plans, and these Special Provisions. Sign panels and fastening hardware shall conform to Section 82, “Signs and Markers,” of the State Standard Specifications. Signs shall be fabricated with aluminum sheeting and single sheet aluminum panels.

Reflective sheeting and legends must comply with ASTM D9465.

Signs to be removed shall be returned back to the City of Rocklin Public Works Department.

Barricades shall be type 1 pedestrian barricades, per State Standard Plan ES-7Q.

Installation of sign panels shall conform to Section 82 -3, “Roadside Signs ,” of the State Standard Specifications. Signs shall be installed on metal posts.

Metal posts shall be 2 -inch by 2 -inch galvanized Telespar square posts with breakaway sleeves and installed per City of Rocklin Standard Drawing 3-28.

Metal posts shall be subject to review and approval by the City prior to installation. Wood posts are not permitted.

Back braces for signs must be commercial quality, mild steel, and hot-dip galvanized after fabrication.

Straps and saddle brackets for mounting sign panels on sign posts must be stainless steel under ASTM A167, Type 302 or 304. Bolts must be stainless steel with a chromium content of at least 16 percent and a nickel content of at last 8 percent.

The lag screws, metal washer, and nuts must be commercial quality steel and hot -dip galvanized after fabrication. Fiber washers must be commercial quality.

All sign locations shall be approved by the Engineer prior to installation.

16.01 MEASUREMENT AND PAYMENT
Install Roadside Sign shall be paid for as EACH and shall include full compensation for furnishing all labor, material, tools, equipment, and incidentals for doing all work involved in furnishing and installing new roadside sign(s) and new post, complete in place, including excavation, disposal of spoils, concrete footing, as shown on the Plans, as specified in the State Standard Specifications, these Special Provisions, and as directed by the Engineer and no additional compensation shall be allowed.

Relocate Roadside Sign shall be paid for as EACH and shall include full compensation for furnishing all labor, material, tools, equipment, and incidentals for doing all work involved in relocating roadside sign, post, and footing complete in place, including excavation, disposal of spoils, backfilling void spaces with approved material , as shown on the Plans, as specified in the State Standard Specifications, these Special Provisions, and as directed by the Engineer and no additional compensation shall be allowed.

Remove Roadside Sign shall be paid for as EACH and shall include full compensation for furnishing all labor, material, tools, equipment, and incidentals for doing all work involved in removing roadside sign, post, and footing complete in place, including excavation, disposal of spoils, backfilling void spaces with approved material , as shown on the Plans, as specified in the State Standard Specifications, these Special Provisions, and as directed by the Engineer and no additional compensation shall be allowed. 352

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 43

Install Pedestrian Barricade shall be measured and paid for per EACH and shall include full compensation for furnishing all labor, material, tools, equipment, and incidentals for doing all work involved in installing type 1 pedestrian barricades as shown on the Plans, as specified in the State Standard Specifications , these Special Provisions, State Standard Plan ES-7Q and as directed by the Engineer and no additional compensation shall be allowed therefore.
353

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 44

17.00 METAL FENCE
Contractor shall temporarily remove existing wrought iron fence as necessary to prevent damage to the fence and in order to construct the adjacent concrete pad, where shown on the Plans. Should the fence not need to be temporarily removed, the Contractor will not be paid for this bid item.

The fence shall be removed and stored in complete, post-post, sections. Cuts to remove the fence shall be made at the posts and no intermediate cuts, between posts, will be allowed.

Prior to the removal of the wrought iron fence, the Contractor shall document the existing conditions of the fence to be removed.

Contractor shall protect and store the removed fence until completion of the concrete pad. Upon completion of the concrete p ad, the contractor shall reinstall the wrought iron fence to the existing conditions, and to the satisfaction of the Engineer.

17.01 MEASUREMENT AND PAYMENT
Reset Metal Fence shall be measured and paid fo r by the LINEAR FOOT and shall include full compensation for furnishing all labor, material, tools, equipment, and incidentals for doing all work involved in removing, storing and reinstalling the wrought iron fence, as shown on the Plans, as specified in the State Standard Specifications, these Special Provisions, and as directed by the Engineer and no additional compensation shall be allowed therefore.

354

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 45

18.00 ELECTRICAL SYSTEMS
Traffic Signal and Street Light work shall conform to the provisions of Sections 86, "Electrical Work," and 87, “Electrical Systems,” of the State Standard Specifications, the information shown on the Plans, and these Special Provisions.

In general, the work consists of the following items:

1. Installation of one new traffic signal on Blue Oaks Boulevard; and

2. Installation of two new street lights on Blue Oaks Boulevard; and

3. Traffic signal modification on Sierra College Boulevard at Dominguez Road; and

4. Traffic signal modification on Sierra College Boulevard at Schriber Way; and

5. Installation of a new rectangular rapid flashing beacon system on Crest Drive; and

6. Installation of new blinker sign systems at various school crossings

The traffic signal installation shall include, where shown on the plans, furnishing and installing new traffic signal poles with mast arms, pedestrian traffic signal, vehicle/pedestrian heads, flashing beacon poles, foundations, loop detectors, loop detector handholes, CCTV camera, controller cabinet , service equipment enclosure, pull boxes, conduit, and conductors.

The traffic signal modifications shall include, where shown on the plans, removal and relocation of existing signal pole and vehicle/pedestrian heads on new foundation, removal and replacement of existing signal pole with new traffic signal pole with mast arm on new foundation, furnishing and installing loop detectors, loop detector handholes, pull boxes, conduit, and conductors.

The street light installation shall include, where shown on the plans, furnishing and installing new street light standards with luminaire mast arms, foundation, pull boxes, conduit, and conductors.

The rectangular rapid flashing beacon system installation shall include, where shown on the plans, furnishing and installing new traffic signal poles with foundations, push button posts with foundations, pedestrian push button assemblies, rectangular rapid flashing beacon light bars, solar panels, controllers, and enclosures.

The Contractor shall be responsible for locating and marking the positions of all traffic signal equipment, pull boxes, and conduit. All locations shall be approved by the Engineer before any work is performed.

18.01 TRAFFIC SIGNAL SCHEDULE OF VALUES
The Contractor shall prepare a schedule of values for each lump sum item of work covered by this Electrical Systems specification per Section 9 -1.16B, “Schedule of Values,” of the State Standard Specifications.

18.02 SALVAGING ELECTRICAL EQUIPMENT
The Contractor shall remove, handle, transport, store, and dispose of all existing electrical equipment, including light bulbs, and all other construction or installation related refuse in compliance with City’s current practice and all applicable laws and regulations in such a manner as to minimize potential adverse environmental impacts on this project at no additional cost to the City. The City encourages recycling where possible.

Ballasts and transformers that contain poly chlorinated biphenyls (PCB’s) are designated as extremely hazardous wastes and fluorescent tubing and mercury lamps are designated as hazardous wastes under Title 22, Division 4.5, Chapter 11, Article 4.1 and Article 5, of the California Code of Regulations.

Contractor shall provide evidence of proper disposal of hazardous waste. 355

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 46
All traffic signal and street lighting equipment shown on the Plans as salvaged shall be salvaged to the City of Rocklin Corporation Yard.

The salvaged material shall be delivered, in the same condition as before removal, by the Contractor to the site as directed by the City. The Contractor is responsible for unloading of equipment.

The Contractor shall call (916) 625-5567 and confirm drop-off at least 48 hours in advance of delivery.

All other equipment shown on the Contract plans to be removed or discarded shall become the property of the Contractor and shall be removed from the right-of-way and disposed of by the Contractor.

Full compensation for salvage and delivery to the site as directed by the City and for disposal shall be considered as included in the lump sum price paid for the traffic signal modifications and street lighting and no separate payment will be made therefore.

18.03 MAINTAINING EXISTING AND TEMPORARY ELECTRICAL SYSTEMS The Contractor shall maintain existing and temporary electrical systems per Section 87 -21.03B, “Maintaining Existing Electrical Systems,” of the State Standard Specifications, and these Special Provisions.

All traffic signal and stree t lighting systems are to remain in operation at all times during construction unless otherwise approved by the Engineer. Temporary traffic signal installation s may be required at various locations to accommodate the Contractor’s construction staging at the Contractor’s expense.

Temporary traffic signal systems shall meet all Californian MUTCD and Caltrans requirements.

Full compensation for the preparation, submittal, review, and approval of temporary traffic signal plans, and for the Contractor to furnish, install, activate, and later remove said temporary traffic signal installation, shall be included in the lump sum bid item necessitating said temporary traffic signal system, and no additional compensation will be allowed therefore.

Traffic signal shutdown is allowed, and must be limited to nighttime hours as defined elsewhere in these Special Provisions. The Engineer will notify life safety personnel of full signal shutdowns.

18.04 SIGNAL ACTIVATION
On the day of signal activation, the Contractor shall be required to have in his possession at the job site all tools, equipment and parts necessary to repair a signal malfunction. These items shall include, but not be limited to, a bucket truck, replacement LED’s, wire, etc.

Immediately prior to the activation of a new traffic signal, the Contractor shall install two (2) orange flags on the “Signal Ahead” signs. Flags shall remain in place for two (2) weeks. The Contractor shall also provide two (2) changeable message sign (CMS) boards on Blue Oaks Boulevard a minimum of 5 working days ahead of the signal turn on. CMS board messages shall be approved by the Engineer for a message before turn on and a separate message updated the day of the turn on. CMS boards shall remain in place for two (2) weeks following turn on. The cost of CMS boards for this purpose is included in the Traffic Control System bid item.

Prior to activation of a new traffic signal, the Contractor shall provide a minimum of two (2) flaggers to control traffic. The number of flaggers may be increased at the request of the Engineer at no additional cost to the City. Each flagger shall wear ap propriate safety gear and carry a stop paddle for controlling traffic. The flaggers shall completely stop traffic prior to the signal changing from red flash to full operation. 356

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 47

18.05 FOUNDATIONS
The Contractor shall construct foundations for traffic signal and street light poles, and push button posts per the State Standard Plans and Section 87-1.03E(3), “Concrete Pads, Foundations, and Pedestals,” of the State Standard Specifications.

The Contractor shall verify all existing underground and overhead utilities within the project site prior to constructing foundations for the street lighting and signal standards.

Unless otherwise directed by the Engineer, the Contractor is not required to place inspection tubes in the foundations per Caltrans Standard Plan ES-7N.

The layout of the service equipment e nclosure and traffic signal controller cabinet shall be per City of Rocklin Standard Drawing 8-4. The foundations themselves shall be per Caltrans Standard Plans, latest edition.

18.06 STANDARDS, POLES, PEDESTALS, AND POSTS
The Contractor shall furnish and install traffic signal and street lighting poles, and push button posts per the State Standard Plans, Section 87 -1.03J, “Standards, Poles, Pedestals, and Posts,” of the State Standard Specifications.

18.07 CONDUIT
Conduit to be installed underground shall be Type 1 or Type 3 as defined in Section 86-1.02B, “Conduit and Accessories,” of the State Standard Specifications unless otherwise specified herein.

The conduit in a foundation and between a foundation and the nearest pull box shall be Type 1. Conduit sizes shown on the plans and specified in the State Standard Specifications and these Special Provisions are referenced to metallic type conduit.

When a standard coupling cannot be used for joining Type 1 conduit, a UL listed threaded union coupling conforming to the provisions in Section 87 -1.03B, “Conduit Installation,” of the State Standard Specifications, or a concrete-tight split coupling, or concrete-tight set screw coupling shall be used.

If Type 3 conduit is placed in a trench, not in the pavement or under concrete sidewalk after the bedding material is placed and the conduit is installed, backfill the trench to not less than 4 inches above the conduit with minor concrete under Section 90-2, “Minor Concrete,” except the concrete must contain not less than 421 pounds of cementitious material per cubic yard. Backfill the remaining trench to finished grade with backfill material.

Conduit placed in a trench, in the pavement, shall be installed and backfilled per Section 87 -

1.03B(3)(b)(iii) “Trench-In-Pavement Method,” of the State Standard Specifications.

After conductors have been installed, the ends of conduits terminating in pull boxes and the service equipment enclosure shall be sealed with an approved type of sealing compound.

At those locations where conduit is required to be installed under pavement and underground facilities designated as high priority subsurface installation under Government Code § 4216 et seq. exist, conduit must be placed per Section 87-1.03B(3)(b)(iii), “Trenching-In-Pavement Method,” of the State Standard Specifications.

The conduit shall have a 45-degree sweep (measured in the vertical plane) with a minimum bend radius of 36 inches when entering the pull box.
357

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 48
The conduit shall have a safe working pull strength greater than 3,000 pounds.

18.08 PULL BOXES
Pull boxes shall be concrete utility boxes. Pull boxes shall be as shown on the plans and in accordance with Section 86 -1.02C, “Pull Boxes,” and Section 87 -1.03C, "Installation of Pull Boxes" of the State Standard Specifications.

The pull boxes shall be installed per City of Rocklin Standard Drawings 7-5 and 7-6.

Existing and new electrical pull boxes shall be adjusted to grade as shown on the Plans or directed by the Engineer, and included in the cost for each traffic signal system bid item.

The Contractor shall ensure that traffic box covers are not covered with concrete or landscaping materials during construction operations.

Pull boxes shall be marked “Traffic Signal” or “City Communications” depending on the purpose for which the pull box will serve.

Pull boxes for PG&E service connections shall meet all PG&E Greenbook requirements and shall be marked “Service.”

Pull boxes shall be a minimum of No. 5 or larger as shown on the Plans. No. 3 -1/2 pull boxes shall not be used in the public right of way for traffic signals.

All pull boxes shall have non-slip lids. Pull boxes shall not be installed in a curb ramp.

Where an existing pull box or splice vault is damaged by the Contractor’s operations, the pull box shall be reconstructed to match existing, and if the sump was grouted, the old grout shall be removed and new grout placed at the sole cost of the Contractor.

All pull boxes to be abandoned shall have conductors removed from the pull boxes and conduits and the pull box shall be removed. The remaining hole shall be backfilled and compacted with similar material as the surrounding material. If within a sidewalk, the entire square of sidewalk shall be removed and replaced as part of the traffic signal installation bid item, unless within the limits of proposed sidewalk as shown on the civil sheets, in which case the cost is measured and paid for under the sidewalk bid item.

The concrete flatwork shown on City of Rocklin Standard Drawing 7 -6 shall be included in the traffic signal installation bid item unless within the limits of proposed sidewalk as shown on the civil sheets, in which case the cost is measured and paid for under the sidewalk bid item.

18.09 CONDUCTORS AND WIRING
The Contractor shall furnish and install all conductors and wiring as shown on the plans per Section 86-1.02F, “Conductors and Cables,” of the State Standard Specifications.

Splices shall be insulated by “Method B” or, at the Contractor’s option, splice s of conductors shall be insulated with heat-shrink tubing of the appropriate size after thoroughly painting the spliced conductors with electrical insulating coating.

Wiring for traffic signal indications or equipment shall not be daisy-chained.

358

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 49
Conductors shall be wrapped around projecting end of conduit in pull boxes as shown on the plans.

Cables shall be secured to the projecting end of conduit in pull boxes to prevent pulling of cables without removing the securing device.

All conductors shall be labeled and identified in each and every pull box. A minimum of 6 feet (3 feet up and 3 feet down) of service loop shall be provided in each pull box.

The minimum insulation thickness, at any point, for Type USE, RHH or RHW wire shall be 0.039 inches for conductor sizes No. 14 to No. 10, inclusive, and 0.051 inches for No. 8 to No. 2, inclusive. The minimum insulation thickness, at any point, for Type THW and TW wires shall be 0.03 -inches for conductor sizes No. 14 to No. 10, inclusive, 0.04 -inches for No. 8, and 0.053 inches for No. 6 to No. 2, inclusive.

Testing
The Contractor shall perform a high -voltage series lighting test consisting of the open circuit voltage of the connected constant current transformer between conductors and ground. The high-voltage test shall not be performed on existing circuits or equipment. Non -testing of existing circuits and equipment shall not relieve the Contractor from the responsibility for malfunctioning of existing lighting circuits due to the Contractor making splices in or connecting to the circuits and such malfunctions shall be corrected at the Contractor’s expense.

18.10 SIGNAL FACES AND SIGNAL HEADS
The Contractor shall furnish and install all signal faces, lamps and signal heads as shown on the plans per Section 86-1.02R, “Signal Heads,” of the State Standard Specifications. All 12-inch red, yellow, and green ball/arrow sections shall be furnished with LED modules. LED modules shall be Type 1. Signal heads, visors and backplates shall be black. Backpla tes shall include retroreflective strip per the Plans and State Standard Plans.

18.11 PEDESTRIAN SIGNALS
The Contractor shall supply and install pedestrian signals per Section 86-1.02S, “Pedestrian Signal Heads,” of the State Standard Specifications.

All pedestrian signals shall be furnished with a combination Portland Orange “Up-Raised Hand”, and Lunar White “Walking Man” LED modules with self-contained “countdown” timer, and shall conform to Sections 4E.04 and 4E.07 of the latest edition of the California Manual on Uniform Traffic Control Devices (CAMUTCD).

All pedestrian indication symbols shall be completely filled in, outlined indications shall not be allowed.

Signal housing shall be black.

18.12 PHOTOELECTRIC CONTROLS
Photoelectric control shal l be Type II and pole top mounted in accordance with Section 86 -1.02M, “Photoelectric Controls,” of the State Standard Specifications.

The Contractor shall supply all equipment, supplies, and material required for mounting the photoelectric cell.

359

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 50

18.13 SERVICE EQUIPMENT ENCLOSURE
All service equipment enclosures/service pedestals shall conform to Section 86 -1.02P(2), “Service Equipment Enclosures,” of the State Standard Specifications, and shall not be painted.

Service equipment enclosures located within the City of Rocklin shall be installed in conformance with the PG&E Greenbook, latest edition and City of Rocklin Standard Drawing 8-4.

Service equipment enclosures for traffic signals shall be Tesco Type III-AF metered with battery backup system as shown on the plans.

If a service equipment enclosure will have power of 120/208v, the Contractor shall provide the required 5th clip meter socket configuration.

18.14 ACCESSIBLE PESDESTRIAN SIGNAL
The Contractor shall furnish and install accessible pedestrian signals (APS) where shown on the plans.

APS shall conform to the State Standard Plan ES -5C and Section 86-1.02T, “Accessible Pedestrian Signals,” of the State Standard Specifications.

Crest Drive RRFB APS push button assemblies shall be the Polara “iNX” iNavigator system.

APS push button assemblies for the blinker sign systems shown on the plans shall be the Polara “iNX” iNavigator system.

Blue Oaks Boulevard APS push button assemblies shall be a 3-wire APS push button assembly which shall include a push button station and a pedestrian head control unit. The APS shall be the Polara “iNS” iNavigator system.

Contractor shall supply all cabling including any and all cabling associated with the connections between each of the push button assemblies.

Pedestrian push buttons shall be 2” ADA pushbuttons, mounted 4 2” above finished grade to center of button, and meet reach requirements per Section 308.3, Side Reach, of the 2010 ADA Standards for Accessible Design, and which is available at the following website:
https://www.ada.gov/law-and-regs/design-standards/2010-stds/#top Terminal screws shall be used for all bare wire terminations. Crimp terminals are not allowed.

Audible messages shall conform to the latest CA-MUTCD Section 4E. Pedestrian push buttons shall be within 5 feet from the edge of the access ramp pan (CAMUTCD Figure 4E-2).

Contractor shall submit Voice on Location and Walk Message (VOL) sheet –with proper English phonetic pronunciation for approval by the Engineer prior to proceeding with the purchase of the equipment.

The accessible pedestrian signal system must be manufactured within 6 months of delivery.

18.15 LOOP DETECTION SYSTEM
The work shall conform to the provisions of Sections 86, "Electrical Work," and 87, “Electrical Systems,” of the State Standard Specifications, the information shown on the Plans, City of Rocklin Standard Drawing #8-5, and these Special Provisions.

360

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 51
The contractor shall furnish and install a model 2070LX Intelight controller in a type 332 cabinet with a Tesco battery backup system per City of Rocklin Standard Drawing #8-4, where shown on the plans.

The Contractor shall be responsible for locating and marking the positions of all traffic signal loops, detector handholes, and conduit. All locations shall be approved by the Engineer before any work is performed.

The Contractor shall coordinate with the City of Rocklin’s Traffic Supervisor, Naz Lazar, whose contact information is 916-625-5567, or [email protected]. Work on or near existing traffic loops shall be meticulously planned and coordinated to identify the minimal impact necessary. If the t raffic signal is to be placed into flash at any time to accommodate loop installation, all loop work shall be performed during nighttime hours as defined elsewhere in these Special Provisions.

All vehicle detectors shall be cut in and be inductive loop de tector Type “A” and “D”. Bicycle loops shall be Type “B”- 5’x5’ with 5 turns.

Loop wire shall be Type 1 as noted in Section 86 -1.02F(2)(c)(iii), “Inductive Loop Conductors,” of the State Standard Specifications and be RHW -USE, neoprene -jacketed, cross -linked polyethylene, insulated, # 12 stranded copper.

Lead-in cable shall be Type B copper per Section 86 -1.02F(3)(d)(iii), “Detector Lead-in Cables,” of the State Standard Specifications.

Inductive loop detector includes a completely installed loop or group of loops in the roadway, and a lead- in cable installed and connected inside a controller cabinet. Vehicle detection loops shall be cut into the newly paved asphalt surface within 72 hours following paving operations. Contractor shall furnish loop continuity test results to the City within 24 hours of splicing.

Verify in the presence of the Engineer or Traffic Supervisor that the loops are operational before making the final splices between loop conductors and the lead-in cable.

Identify and tag each lead-in cable with the detector designation at the cabinet and pull box adjacent to the loops.

Where shown on the plans, the Contractor shall install new conduit and detector handholes per Caltrans standard.

18.16 LUMINAIRES
The contractor shall furnish and install luminaires where shown on the Plans, luminaires shall conform to Section 86-1.02K “Luminaires” of the State Standard Specifications, the information shown on the Plans, City of Rocklin Standard Drawing #7-10, and these Special Provisions.

18.17 FLASHING BEACON SYSTEMS
The contractor shall furnish and install flashing beacon systems where shown on the Plans, flashing beacon systems shall conform to Section 87 -7 “Flashing Beacon Systems” of the State Standard Specifications, the most recent edition of the California Supplement to the Manual o n Uniform Traffic Control Devices (CA-MUTCD), the information shown on the Plans, and these Special Provisions.

Crest Drive flashing beacon system shall be a solar powered TAPCO RRFB Pedestrian C rosswalk System, compatible with the Polara “iNX” APS push button assembly. Rectangular rapid flashing beacon light bars shall be TAPCO RRFB-XL2 light bars.

361

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 52

18.18 BLINKER SIGN SYSTEMS
The contractor shall furnish and install blinker sign systems where sho wn on the Plans, blinker sign systems shall conform to Section 87-7 “Flashing Beacon Systems” of the State Standard Specifications, the most recent edition of the California Supplement to the Manual o n Uniform Traffic Control Devices (CA-MUTCD), the information shown on the Plans, and these Special Provisions.

Blinker sign systems shall be a Tapco Self-Contained Solar Powered Blinker Sign Pedestrian Crosswalk Systems, compatible with the Polara “iNX” APS push button assembly . The blinking sign shall be a SW24-2 (CA) sign or an S1-1 sign with a supplemental arrow plaque.

All existing blinker sign systems to be removed, where shown on the plans, shall be salvaged to the City of Rocklin Corporation Yard.

The salvaged equipment shall be delivered, in the same condition as before removal, by the Contractor to the site as directed by the City. The Contractor is responsible for unloading of equipment.

The Contractor shall call (916) 625-5567 and confirm drop-off at least 48 hours in advance of delivery

18.19 PG&E SERVICE CONNECTION
The City will provide the Contractor with the PG&E service connection design, upon completion by PG&E. The Contractor shall construct the PG&E service connection in accordance with PG&E Greenbook requirements.

18.20 MEASUREMENT AND PAYMENT
The LUMP SUM price paid for Blue Oaks Pedestrian Signal and Street Lighting as shown on the plans shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals for doing all the work involved to construct a complete and functioning traffic signal and street lighting , complete and in place. The work shall include, but is not limited to, supplying and installing traffic signal poles with foundations, street light poles with foundations, flashing beacon poles with foundations, controller cabinet, luminaires, vehicle heads, pedestrian signal heads, conductors/cables, conduits, pull boxes, service enclosure, supplying and installing traffic signal loops, loop detector handholes, loop wire, detector lead-in cables (DLCs) , detector loop card inside the controller cabinet, photoelectric controls, roadway or street name signs mounted to mast arms, brackets for roadway or street name signs, pole numbers, temporary traffic signal systems, pedestrian push button post, accessible pedestrian signals, replacement of concrete flatwork when outside the limits of proposed concrete flatwork, and coordination with PG&E, and all incidentals, as shown on the plans, as detailed in the State Standard Specifications, these Special Provisions and as directed by the Engineer and no additional payment shall be allowed therefore.

The LUMP SUM price paid for Sierra College Blvd/Dominguez Rd Signal Modification as shown on the plans shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals for doing all the work involved in modifying the existing traffic signal system, complete and in place. The work shall include, but is not limited to, relocating traffic signal pole and signal heads on new foundation, installing pull boxes, supplying and installing traffic signal loops, loop detector handholes, loop wire, detector lead-in cables (DLCs), termination inside controller cabinets, conduits, pull boxes as well as removal of existing detector handhole s, replacement of concrete flatwork when outside the limits of proposed concrete fla twork, and coordination with Rocklin to confirm proper vehicle detection, and all incidentals, as shown on the plans, as detailed in the State Standard Specifications, these Special Provisions and as directed by the Engineer and no additional payment shall be allowed therefore.

362

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 53
The LUMP SUM price paid for Sierra College Blvd/Schriber Way Signal Modification as shown on the plans shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals for doing all the work involved in modifying the existing traffic signal system, complete and in place. The work shall include, but is not limited to, replacement of traffic signal pole with new traffic signal pole and mast arm and signal heads on new foundation, installing pull box es, conduits, replacement of concrete flatwork when outside the limits of proposed concrete flatwork, and coordination with Rocklin, and all incidentals, as shown on the plans, as detailed in the State Standard Specifications, these Special Provisions and as directed by the Engineer and no additional payment shall be allowed therefore.

The LUMP SUM price paid for Crest Drive Rectangular Rapid Flashing Beacon System as shown on the plans shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals for doing all the work involved to construct a complete and functioning rectangular rapid flashing beacon system, complete and in place. The work shall include, but is not limited to, supplying and installing flashing beacon poles with foundations, pedestrian push button posts with foundations , solar panels, RRFB light bars, controller enclosures, conductors/cables, APS push button assemblies, roadside signs and plaques mounted to poles, brackets for mounting roadside signs, and all incidentals, as shown on the plans, as detailed in the State Standard Specifications, these Special Provisions and as directed by the Engineer and no additional payment shall be allowed therefore.

Blinker Sign Systems shall be paid for as EACH as shown on the plans and shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals for doing all the work involved to construct a complete and functioning blinker sign system , complete and in place. The work shall include, but is not limited to, supplying and installing solar panels, self-contained solar cabinet , conductors/cables, APS push button assemblies, blinker signs and plaques mounted to existing poles, brackets for mounting blinker signs, and all incidentals, as shown on the plans, as detailed in the State Standard Specifications, these Special Provisions and as directed by the Engineer and no additional payment shall be allowed therefore.

PG&E Service Connection bid item shall be an ALLOWANCE from which the City and Contractor will negotiate a fair and reasonable price formalized in a contract change order. A ll labor, materials, tools, equipment, and incidentals involved in constructing a complete and functioning PG&E electrical service connection, including conduit, conductors/cables, and pull boxes, complete in place, shall be included in this bid item per PG&E standards, and as directed by the Engineer and no additional compensation will be made therefore.
363

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 54

19.00 QUALITY ASSURANCE PROGRAM
The City has a Caltrans approved Quality Assurance Program (QAP), which can be made available upon request, that will ensure the materials and workmanship incorporated into the construction project conform to the requirements of the contract plans and Special Provisions, including approved changes.

Material testing and sampling noted in the QAP shall be done in accordance with California Test Method (CTM) procedures. The QAP specifies which CTM to follow depending upon the material in question.

19.01 ACCEPTANCE TESTING
At a minimum, and as outlined in the City’s QAP, the following materials shall be sampled and tested for acceptance into the project:

1. Hot Mix Asphalt

2. Hot Mix Asphalt (Aggregates)

3. Aggregate Base

4. Structural Concrete

5. Soil Subgrade

See Attachment 1, Acceptance Sampling and Testing Frequencies, in the QAP for frequency tables.

The Contractor shall coordinate with the Engineer or batch plant for material sampling and testing. The City’s independent consultant shall h ave full access to all areas of the worksite necessary to fulfill the requirements of the City’s QAP.

Whenever failing tests occur, sufficient additional acceptance tests must be taken to isolate the affected work. Documentation of the results of such additional tests must be included in the City’s records, including a description of the corrective measures taken by the Contractor. Any material tested and found out of compliance with these Special Provisions and the QAP shall be removed and replaced at no cost to the City.

For clarification purposes, the City’s materials testing consultant will complete Local Assistance Procedures Manual (LAPM) Exhibit 16 -Z2, Acceptance Testing Results Summary Log, outlining the results of all testing, a copy of which can be provided to the Contractor upon request.

Compaction testing of hot mix asphalt shall be per State Standard Specifications and while aggregate base shall achieve 95% relative compaction.

Minor concrete will be accepted via a certificate of compliance, however, concrete cylinder samples will be collected and tested in accordance with CTM procedures.

19.02 CERTIFICATE OF COMPLIANCE
The Contractor shall review Local Assistance Proce dures Manual (LAPM) Exhibit 16 -T1, Materials Requiring a Certificate of Compliance per Caltrans Standard Specifications, and submit certificates of compliance (COCs) for all materials listed which are to be used in the construction of this project. The current version of this form is locate d at the following website: https://dot.ca.gov/programs/local- assistance/forms/local-assistance-procedures-manual-forms.

COCs shall be project specific (no generic forms accepted), approved before material is incorporated into the project, and include, at a minimum, the following information:

364

SPECIAL PROVISIONS

SPECIAL PROVISIONS - 55
• Federal Project Number;
• Statement that the material complies with the specifications; • Certified material lot number matching lot tags affixed or stenciled to the released materials; and • Signature of authorized manufacturer representative.

COCs shall be approved by the City prior to any progress payments being made to the Contractor for the material covered by the COC.

19.03 MEASUREMENT AND PAYMENT
Full compensation for conforming to the requirements of this section of these Special Provisions shall be considered as included in the prices paid for the various items of work involved and no additional compensation will be allowed therefore.

365
RESOLUTION NO. 2024-

RESOLUTION OF THE CITY COUNCIL

OF THE CITY OF ROCKLIN

APPROVING A NOTICE OF EXEMPTION
(Blue Oaks Boulevard Pedestrian Traffic Signal Project) WHEREAS, the City of Rocklin’s Environmental Coordinator has reviewed the Blue Oaks Boulevard Pedestrian Traffic Signal Project (“Project”) and determined that it is exempt from review under the California Environmental Quality Act pursuant to California Code of Regulations Section 15301-Existing Facilities; and WHEREAS, a Notice of Exemption has been prepared for the Project.

NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Rocklin as follows:

Section 1. Based on the review and determination of the Environmental Coordinator, and for the reasons stated in the Notice of Exemption, attached hereto and incorporated by reference herein as Exhibit A, the City Council of the City of Rocklin finds that the Project is exempt from review under the California Environmental Quality Act.

Section 2. The City Council approves the Notice of Exemption for the Project.

Section 3. Upon approval of the Project by the City Council, the Environmental Coordinator may file the Notice of Exemption with the County Clerk of Placer County and with the State Office of Planning and Research, pursuant to the provisions of Section 21152(b) of the Public Resources Code and the State EIR Guidelines adopted pursuant thereto.

PASSED AND ADOPTED this 14th day of May, 2024, by the following vote:

AYES: Councilmembers:

NOES: Councilmembers:

ABSENT: Councilmembers:

ABSTAIN: Councilmembers:
____________________________________
Greg Janda, Mayor
ATTEST:
______________________________
Avinta Singh, City Clerk
366

EXHIBIT A

NOTICE OF EXEMPTION
TO: County Clerk, County of Placer FROM: City of Rocklin 2954 Richardson Blvd. Community Development Department Auburn, CA 95604-5228 3970 Rocklin Road
Rocklin, CA 95677
Project Title: Blue Oaks Boulevard Pedestrian Traffic Signal Project Project Location - Specific: The project site is located along Blue Oaks Boulevard, between the intersections of Hannah Way/Cassia Way and Tanager Way/Westmeath Way, at approximately 800 feet north of the Tanager Way/Westmeath Way intersection.

Project Location - City: Rocklin, CA; County: Placer
Description of Nature, Purpose and Beneficiaries of Project: The project will install a new traffic signal on Blue Oaks Boulevard at the open space areas, to connect existing multi-use pathways that terminate at Blue Oaks Boulevard. The project will also involve the installation of associated concrete sidewalks, electrical equipment, signage and striping and the removal of existing roadway improvements and landscaping, including approximately 21 trees, along the sides and within the median of Blue Oaks Boulevard to accommodate project equipment and to provide needed visibility for motorists.

Name of Public Agency Approving Project: City of Rocklin Name of Person or Agency Carrying Out Project: City of Rocklin, Engineering Division, 3970 Rocklin Road, Rocklin, CA, 95677, Attn: Hunter Young, (916) 625-5581.

Exempt Status (Check one)
_X_ Categorical Exemption (California Code of Regulations Sec. 15300 et seq.): Section 15301 (Existing Facilities)
Reasons why the project is exempt. Class 1 consists of the operation, repair, maintenance, permitting, leasing, licensing, or minor alteration of existing public or private structures, facilities, mechanical equipment, or topographical features, involving negligible or no expansion of existing or former use. The types of “existing facilities” itemized below are not intended to be all-inclusive of the types of projects which might fall within Class 1. The key consideration is whether the project involves negligible or no expansion of use. Examples include but are not limited to:
(c) Existing highways and streets, sidewalks, gutters, bicycle and pedestrian trails, and similar facilities (this includes road grading for the purposes of public safety, and other alterations such as the addition of bicycle facilities, including but not limited to bicycle parking, bicycle-share facilities and bicycle lanes, transit improvements such as bus lanes, pedestrian crossings, street trees, and other similar alterations that do not create additional automobile lanes). 367
(f) Addition of safety or health protection devices for use during construction of or in conjunction with existing structures, facilities, or mechanical equipment, or topographical features including navigational devices.

The project as proposed is consistent with the exemption class description noted above and is exempt pursuant to Class 1 of the CEQA Guidelines.

Contact Person: David Mohlenbrok, Director of Community Development Date received for Filing:

Signature:

David Mohlenbrok, Director of Community Development
368
RESOLUTION NO. 2024-

RESOLUTION OF THE CITY COUNCIL

OF THE CITY OF ROCKLIN

APPROVING A NOTICE OF EXEMPTION
(Crest Drive at Valley View Elementary Pedestrian Improvements Project) WHEREAS, the City of Rocklin’s Environmental Coordinator has reviewed the Crest Drive at Valley View Elementary Pedestrian Improvements Project (“Project”) and determined that it is exempt from review under the California Environmental Quality Act pursuant to California Code of Regulations Section 15301-Existing Facilities; and WHEREAS, a Notice of Exemption has been prepared for the Project.

NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Rocklin as follows:

Section 1. Based on the review and determination of the Environmental Coordinator, and for the reasons stated in the Notice of Exemption, attached hereto and incorporated by reference herein as Exhibit A, the City Council of the City of Rocklin finds that the Project is exempt from review under the California Environmental Quality Act.

Section 2. The City Council approved the Notice of Exemption for the Project.

Section 3. Upon approval of the Project by the City Council, the Environmental Coordinator may file the Notice of Exemption with the County Clerk of Placer County and with the State Office of Planning and Research, pursuant to the provisions of Section 21152(b) of the Public Resources Code and the State EIR Guidelines adopted pursuant thereto.

PASSED AND ADOPTED this 14th day of May, 2024, by the following vote:

AYES: Councilmembers:

NOES: Councilmembers:

ABSENT: Councilmembers:

ABSTAIN: Councilmembers:
____________________________________
Greg Janda, Mayor
ATTEST:
______________________________
Avinta Singh, City Clerk
369

EXHIBIT A

NOTICE OF EXEMPTION
TO: County Clerk, County of Placer FROM: City of Rocklin 2954 Richardson Blvd. Community Development Department Auburn, CA 95604-5228 3970 Rocklin Road
Rocklin, CA 95677
Project Title: Crest Drive at Valley View Elementary Pedestrian Improvements Project Project Location - Specific: The project site is located along Crest Drive, at the intersection of Fox Hill Drive and the northernmost driveway to Valley View Elementary School.

Project Location - City: Rocklin, CA; County: Placer
Description of Nature, Purpose and Beneficiaries of Project: The project will install new Americans with Disabilities Act (ADA) curb ramps, rapid rectangular flashing beacons (RRFBs), pedestrian push button assemblys, and high-visibility crosswalk markings to enhance the visibility of pedestrians, and in particular students during drop off and pick up times..

Name of Public Agency Approving Project: City of Rocklin Name of Person or Agency Carrying Out Project: City of Rocklin, Engineering Division, 3970 Rocklin Road, Rocklin, CA, 95677, Attn: Hunter Young, (916) 625-5581.

Exempt Status (Check one)
_X_ Categorical Exemption (California Code of Regulations Sec. 15300 et seq.): Section 15301 (Existing Facilities)
Reasons why the project is exempt. Class 1 consists of the operation, repair, maintenance, permitting, leasing, licensing, or minor alteration of existing public or private structures, facilities, mechanical equipment, or topographical features, involving negligible or no expansion of existing or former use. The types of “existing facilities” itemized below are not intended to be all-inclusive of the types of projects which might fall within Class 1. The key consideration is whether the project involves negligible or no expansion of use. Examples include but are not limited to:
(c) Existing highways and streets, sidewalks, gutters, bicycle and pedestrian trails, and similar facilities (this includes road grading for the purposes of public safety, and other alterations such as the addition of bicycle facilities, including but not limited to bicycle parking, bicycle-share facilities and bicycle lanes, transit improvements such as bus lanes, pedestrian crossings, street trees, and other similar alterations that do not create additional automobile lanes). (f) Addition of safety or health protection devices for use during construction of or in conjunction with existing structures, facilities, or mechanical equipment, or topographical features including navigational devices.
370
The project as proposed is consistent with the exemption class description noted above and is exempt pursuant to Class 1 of the CEQA Guidelines.

Contact Person: David Mohlenbrok, Director of Community Development Date received for Filing:

Signature:

David Mohlenbrok, Director of Community Development
371
RESOLUTION NO. 2024-

RESOLUTION OF THE CITY COUNCIL

OF THE CITY OF ROCKLIN

APPROVING A NOTICE OF EXEMPTION
(School Zone Signage and Pavement Markings Project)
WHEREAS, the City of Rocklin’s Environmental Coordinator has reviewed the School Zone Signage and Pavement Markings Project (“Project”) and determined that it is exempt from review under the California Environmental Quality Act pursuant to California Code of Regulations Section 15301-Existing Facilities; and WHEREAS, a Notice of Exemption has been prepared for the Project.

NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Rocklin as follows:

Section 1. Based on the review and determination of the Environmental Coordinator, and for the reasons stated in the Notice of Exemption, attached hereto and incorporated by reference herein as Exhibit A, the City Council of the City of Rocklin finds that the Project is exempt from review under the California Environmental Quality Act.

Section 2. The City Council approved the Notice of Exemption for the Project.

Section 3. Upon approval of the Project by the City Council, the Environmental Coordinator may file the Notice of Exemption with the County Clerk of Placer County and with the State Office of Planning and Research, pursuant to the provisions of Section 21152(b) of the Public Resources Code and the State EIR Guidelines adopted pursuant thereto.

PASSED AND ADOPTED this 14th day of May, 2024, by the following vote:

AYES: Councilmembers:

NOES: Councilmembers:

ABSENT: Councilmembers:

ABSTAIN: Councilmembers:
____________________________________
Greg Janda, Mayor
ATTEST:
______________________________
Avinta Singh, City Clerk
372

EXHIBIT A

NOTICE OF EXEMPTION
TO: County Clerk, County of Placer FROM: City of Rocklin 2954 Richardson Blvd. Community Development Department Auburn, CA 95604-5228 3970 Rocklin Road
Rocklin, CA 95677
Project Title: School Zone Signage and Pavement Markings Project Project Location - Specific: The project sites are located at school sites throughout the City of Rocklin, specifically as follows:

1. Quarry Trail Elementary School, on Lazy Trail Drive and Jamboree Drive.

2. Rocklin Elementary School, on Meyers Street and Racetrack Road.

3. Whitney High School, on Ranch View Drive.

4. Springview Middle School, on 5 th Street.

5. Cobblestone Elementary School, on Cobblestone Drive.

6. Rock Creek Elementary School, on Collett Quarry Drive and Great Divide Way.

7. Antelope Creek Elementary School, on Springview Drive.

8. Ruhkala Elementary School, on Turnstone Way.

9. Sunset Ranch Elementary, on Flintlock Lane.

10.Parker Whitney Elementary, on Topaz Avenue..

Project Location - City: Rocklin, CA; County: Placer
Description of Nature, Purpose and Beneficiaries of Project: The project will install high- visibility crosswalk markings and signage improvements to conform to current standards at 10 schools throughout Rocklin, as listed above.

Name of Public Agency Approving Project: City of Rocklin Name of Person or Agency Carrying Out Project: City of Rocklin, Engineering Division, 3970 Rocklin Road, Rocklin, CA, 95677, Attn: Hunter Young, (916) 625-5581.

Exempt Status (Check one)
_X_ Categorical Exemption (California Code of Regulations Sec. 15300 et seq.): Section 15301 (Existing Facilities)
Reasons why the project is exempt. Class 1 consists of the operation, repair, maintenance, permitting, leasing, licensing, or minor alteration of existing public or private structures, facilities, mechanical equipment, or topographical features, involving negligible or no expansion of existing or former use. The types of “existing facilities” itemized below are not intended to be all-inclusive of the types of projects which might fall within Class 1. The key consideration is whether the project involves negligible or no expansion of use. Examples include but are not limited to:
(c) Existing highways and streets, sidewalks, gutters, bicycle and pedestrian trails, and similar facilities (this includes road grading for the purposes of public safety, and other alterations such 373
as the addition of bicycle facilities, including but not limited to bicycle parking, bicycle-share facilities and bicycle lanes, transit improvements such as bus lanes, pedestrian crossings, street trees, and other similar alterations that do not create additional automobile lanes). (f) Addition of safety or health protection devices for use during construction of or in conjunction with existing structures, facilities, or mechanical equipment, or topographical features including navigational devices.

The project as proposed is consistent with the exemption class description noted above and is exempt pursuant to Class 1 of the CEQA Guidelines.

Contact Person: David Mohlenbrok, Director of Community Development Date received for Filing:

Signature:

David Mohlenbrok, Director of Community Development
374
ATTACHMENT 6

CHART OF BUDGETARY TRANSFERS
Transfer to Funds
Fund 210 212 302 706 Total Project/Fund
Transfer From Funds
210

290,800

286,000

53,900

630,700
Blue Oaks Pedestrian Crossing
(50177)
210

606,800

606,800
Sierra College Boulevard
Widening (50164)
210

406,800

406,800
Uncontrolled Crosswalk
Enhancements (50158)
210

(697,600)

(697,600)
Sierra College Boulevard
Rehabilitations (50091) *
212

(100,000)

(100,000)
Aguilar Road Improvements
(50104)**
212

(186,000)

(186,000) PCTPA LTF Fund
302

(606,800)

(606,800)
Traffic Circulation Impact Fee
Fund - Fund Balance
706

(53,900)

(53,900)
Community Facilities District
No. 7 Operating Budget
*Project 50091 will be absorbed into the Citywide Pavement Management Program (50007).
**$100,000 in available funds from Project 50104 will be transferred into the Blue Oaks Pedestrian Crossing project (50177). Project 50104 will continue as planned with existing gas tax funds.
375