Northwest Community Parks
Master Plan
Rocklin, CA
August 12, 2026

3 -
in
-
1 MASTER PLAN

You Spoke & We Listened !
#2 Shade
#3 Balance uses of sports complex
vs community park space
#4 Demand for Wellness, Walking & Nature
#5 More Spaces to Stay & Gather
#6 Identity & Beauty
#7 Recreation Gaps
#1 Functional Improvements
Elements are prioritized in order of demand:

September 12, 2025
COMMUNITY WORKSHOP # 1
(In-Person, All Parks)
September 2025 – March 2026

ONLINE SURVEY OPEN THROUGH

PROCESS
121 Responses!
November 2025 - December 2025
COMMUNITY WORKSHOP # 2
(Virtual Meetings, Individual Parks)
April 13, 2026

MASTER PLAN PRESENTATION
(In-Person, All Parks)
In-Person Community Workshop
Whitney Community Park:
• #1 Soccer Fields & Multi-Use Open
Grass Area
• Add Recreation, Enlarge Pump Track
• Synthetic Fields, Soccer & Softball
• More Shade, especially at Pump Track
• Shaded Gathering Areas, Passive Spaces
• More Community Programming, Seniors
• Improve Garden Area & Walking Trails
Summary:

People like the park and want to have more
soccer fields that also serve as a multi-use
open grass area for large community events.

To feel more balanced with more amenities for
all ages and programming that is community-
oriented.

Feedback Summary
Kathy Lund Community Park:
• #1 Maximize Softball Fields, Regional
Complex/Tournaments
• Balance Parking vs Field Space
• Storage Building Space
• Concessions & Restrooms
• Warm Up Areas
• Gated Parking Access
• Renovated Sprayground
Summary:

Residents want Kathy Lund to evolve into a
softball sports complex, that is equipped to
host tournaments and to also serve the
community as a Park that is well-rounded
with playgrounds, walking trails and natural
elements.

Margaret Azevedo Park:
• #1 Maximize Full-Size Soccer Fields
• On-Grade Slides & Climbers
• Multi-Use Courts
• Fencing along the Creek/Marsh
• More Gathering Spaces
• Concessions & Restrooms
• Overlooks/Shaded Picnic Areas
• Grading/Terracing of Site
Summary:

People said they wanted to maximize the
use of full-size soccer fields so, the park
feels more like a destination with more
amenities for both activity and relaxation,
not only organized sports.

Community
-
Driven Elements
(Future Improvements)
As funding becomes available for undeveloped areas across Rocklin, we will look to this community-driven list to guide future improvements. Below are the ideas we heard and the parks we are exploring as potential homes for them.

Sports and Recreation - The community expressed strong interest in active recreation options.

We are exploring opportunities to bring the following to future park developments:
• Cricket field (Potential Location: Twin Oaks Park)
• Grass Volleyball court
• Bocce Ball Court
• Futsal Court
• Multi-Use Court
• Fitness Area
Nature and Passive Recreation - Residents made it clear that quieter, restorative spaces matter just as much as active ones.

Future undeveloped areas may offer opportunities for:
• Meditation Areas
• Labyrinth
• Bird and Nature Trail
• Passive Recreation Areas
Play and Family - Families asked for more imaginative
play experiences. We are looking at ways to incorporate:
• Incorporate More Themed Play Areas
Gathering and Social - Community connection was a
consistent theme throughout the feedback process.

Ideas that were explored include:
• Picnic Tables and Gathering spaces
• Interactive and Public Art Installations
Dog Amenities - Our four-legged community members
were not forgotten. We heard the demand for more dog-
friendly spaces:
• Dog Park (Potential Location: Sonora Park)
Infrastructure and Amenities
Accessibility was an important value expressed by our
community. Future developments will to be
implemented:
• Accessible and Universal Design Features
Throughout Park Spaces

Whitney
Community Park
Whitney Park
–

Existing Conditions

2026
-
06 -
10 2026
-
06 -
10 AMENITY AREA 1 … $ 10 – 15 MILLION
AMENITY AREA 2 … $ 4 – 5 MILLION
AMENITY AREA 3 … $ 2 – 3 MILLION
TOTAL: $ 16 - 23 MILLION

AMENITIES:

AMENITIES:

AMENITIES:

Kathy Lund
Community Park
Kathy Lund
–

Existing Conditions

AMENITY AREA 1 … $ 17 – 20 MILLION
AMENITY AREA 2 … $ 10 – 13 MILLION
AMENITY AREA 3 … $ 5 – 8 MILLION
TOTAL: $ 32 - 41 MILLION

AMENITIES:

AMENITIES:

AMENITIES:

Margaret Azevedo
Community Park
Margaret Azevedo
–

Existing Conditions

Margaret Azevedo
–

Existing Conditions

Margaret Azevedo
–

Existing Conditions

Margaret Azevedo

AMENITY AREA 1 … $ 10 – 15 MILLION
AMENITY AREA 2 … $ 5 – 7 MILLION
AMENITY AREA 3 … $ 8 – 10 MILLION
TOTAL: $ 23 - 32 MILLION

AMENITIES:

AMENITIES:

AMENITIES:

Consolidation
Kathy Lund – Softball
Whitney Park – All Sport
Margaret Azevedo – Soccer
Existing NEW TOTAL
• (4) SB (4) SB (8) SB
• (2) Soccer X X
Existing NEW TOTAL
• (1) BB X X
• (2) Soccer (2) SOC (4) SOC
Existing NEW TOTAL
• (2) SB X (2) SB
• (2) BB X (2) BB
• (0) Soccer (3) SOC (3) SOC

Park Priority & Phasing
Building Our Parks in Phases
Projects will be sequenced to minimize disruption to existing park uses and league operations.

Here is the order we would like to build:

Phase 1: Whitney Park
• First in line because it offers the most flexibility due to the undeveloped area • Construction can move forward without impacting active league operations Phase 2: Kathy Lund Park
• Softball programs can expand into Margaret Azevedo Park during construction • League space is maintained as best as it can be throughout the process Phase 3: Margaret Azevedo Park
• Soccer programs will have expanded space at Whitney prior to construction beginning • Allows for the removal of the softball field and addition of new amenities with minimal disruption Why this order?
Our goal is to keep Rocklin's parks active and accessible throughout the entire construction process. This sequence ensures every program, league, and community user has space to continue while improvements are underway.

Thank You For Your
Collaboration!