City of Sacramento
City Council Report
915 I Street, 1st Floor
Sacramento, CA 95814
www.cityofsacramento.org
File ID: 2022-01328 7/26/2022 Consent Item 02.

Title: Change Order: Matsui Park Access Project
File ID: 2022-01328
Location: District 4
Recommendation: Pass a Motion: 1) authorizing the City Manager or the City Manager’s designee to execute Change Order No. 5 to City Contract No. 2021-1257 in an amount of $10,652 with TJR Resources, Inc. for a new total amount of $886,993; and 2) resetting the City Manager’s change order authority.

Contact: Dennis Day, Landscape Architect, (916) 808-7633, [email protected]; Raymond Costantino, Division Manager, (916) 808-1941, [email protected]; Park Planning and Development Services, Department of Youth, Parks, & Community Enrichment Presenter: None
Attachments:
1-Description/Analysis
2-Change Order No. 5 to Contract No. 2021-1257
Description/Analysis
Issue Detail: Matsui Robert T. Matsui Waterfront Park is a 2.1-acre community park located at 450 Jibboom Street, in Council District 4.

On November 16, 2021, the contract with TJR Resources, Inc. for the Matsui Park Access Project (L19911200) for 0.34-acre of park renovation in the amount of $798,332 was executed. The work consists of renovation of 0.34 +/- acres of the existing park and will include temporary construction City of Sacramento Page 1 of 3
File ID: 2022-01328 7/26/2022 Consent Item 02.
fencing, erosion control, clearing and grubbing, demolition, grading and drainage, concrete retaining walls, access ramps, concrete walkways, stairs, decorative guard rails and handrails, water efficient irrigation system, no-mow fescue, low water use landscaping, bark mulch areas, three ornamental flowering cherry trees, an electrical system, and flush mounted LED wall lighting along the stairs and access ramps.

Change Order No. 5 in the amount of $10,652 is needed for the contractor to place a 3” irrigation mainline to the point of connection and to modify guard rail panels due to retaining wall layout revisions which was changed due to site conditions and is needed to complete the access improvements.

An additional amount of $10,652 will increase the contract amount to $886,993 which requires Council approval because the total amount of this fifth change order exceeds the City Manager’s change order authority of 10% of the original contract price or a total of $79,833. Change orders 1-4 totaling $78,009 was within the City Manager’s authority. The Access improvements are expected to be complete by the end of July 2022.

Policy Considerations: City Code Chapter 3.60 provides that City Council approval is required for change orders in total that exceed 10% of the original contract amount.

Economic Impacts: Not applicable.

Environmental Considerations:

California Environmental Quality Act (CEQA): The community park project has been reviewed for compliance with the requirements of the CEQA as part of the Robert T. Matsui Waterfront Park Master Plan Amendment project.

Sustainability: The Matsui Park Access Project has been reviewed for consistency with the goals, policies, and targets of the City’s Climate Action Plan for Internal Operations 2016 Update, the 2035 General Plan, the 2018 YPCE Strategic Plan, and the Parks and Recreation Master Plan 2005-2010. The park will advance the goals, policies, and targets of these plans by reducing greenhouse gas emissions and air pollution through the addition of trees, including native and drought-tolerant plantings, and improving the health of all residents through access to a diverse mix of wellness activities. The park development will include sustainable design and maintenance guidelines, including the City’s Model Water Efficient Landscape Ordinance (MWELO), low impact development (LID) strategies to infiltrate stormwater and reduce run-off, and River Friendly Landscaping Program practices by using water efficient irrigation controlled by the centralized irrigation system, and water/energy efficient appliances.

Commission/Committee Action: Not applicable.

City of Sacramento Page 2 of 3
File ID: 2022-01328 7/26/2022 Consent Item 02.

Rationale for Recommendation: Approval of Change Order No. 5 is necessary to complete the access improvement project.

Financial Considerations: Sufficient funding is available in the Matsui Park Access Project (L19911200) to execute Change Order No. 5 in the amount of $10,652 with TJR Resources, Inc.

Local Business Enterprise (LBE): TJR Resources, Inc. exceeded the 5% LBE participation requirement.

City of Sacramento Page 3 of 3
C2021-1257 Change Order # 5
63779
TO:

Contract for:

Approval Recommended by: Approved as to Form by:

Project Manager City Attorney
Approved by: Approved by:

Contractor Director or Assistant City Manager
Approved by:

City Clerk
Contract #
Purchase Order #

CHANGE ORDER
Budget #
2031-L19911200-4820
TJR Resources Inc.

MATSUI PARK ACCESS IMPROVEMENTS
Description:
$78,008.84
$876,340.84
Upon mutual acceptance of this document the City of Sacramento, hereinafter referred to as "City"' and your firm, hereinafter referred to a "Contractor", in accordance with the terms and conditions of the original contract documents, you are hereby directed to make the following change or changes for the consideration set forth below:

Additional work: 1) Place 85 ft. of new 3" irrigation main line to Point of connection, due to existing irrigation main cut and not functioning. $2,358.30; and 2) Additional cost to change railing panels due to change is retaining wall footprint to avoid MOSAC outdoor patio, which was not per plan. $8,294.13. Total $10,652.43 $798,332.00The original contract sum was:

The contract sum prior to this Change Order was:

The contract sum will be increased by this Change Order:

New contract sum including all Change Orders:

Net change by previous Change Orders:

CONTRACTOR agrees that the amount of increase or decrease in the contract sum specified in this change order shall constitute full compensation for the work required by this change order, including but not limited to all compensation for the additional and/or revised work specified herein, and shall fully compensate CONTRACTOR for any and all direct and indirect costs that may be incurred by CONTRACTOR in connection with such additional and/or revised work, including any changes, disruptions or delays in work schedules or in the performance of other work by CONTRACTOR. The time for performance of the Contract will increase 2 working days by reason of the work
described by this Change Order. Except as herein above expressly provided, CONTRACTOR further agrees that the performance of the work specified in this Change Order or the rescheduling of other project work made necessary by this Change Order, shall not constitute a delay which will extend the time limit for completion of the work as said term is used in the Contract between CITY and CONTRACTOR for the project. $10,652.43
$886,993.27

FR
OM: TJR Resources, Inc. 20 Jun 2022
TO: City of Sacramento Dept of Parks & Recreation
ATTN: Dennis Day
915 I Street
Sacramento, CA 95814
SUBJ: Matsui Park Access (Area A) – Change Order Proposal – Decorative Panel Changes Dennis,

1. Change Order Information:
a. CHANGE DESCRIPTION:

De
corative Panel Changes due to change in retaining wall footprint. b. COST IMPACT: Addition of $8,294.13 (Breakout attached) c. TI
ME IMPACT: 0 days
2 . NET TOTAL OF CHANGE ORDER: Net Contract decrease of $8,294.13 and project extension of working days – not including production time of decorative panels.

3. If you have any questions, please call me at 916.752.6019 or email at [email protected].

R
espectfully Submitted,

THOMAS MURPHY USAF, RET
President/CEO
TJR Resources, Inc
“palma non sine pulvere”
PO Box 637
Rancho Cordova, CA 95741
Office/Fax: 888.423.7789
CA DVBE #1759799
CSLB # 989449
Job: Matsui Park Access (Area A) CONTRACTOR: TJR RESOURCES, INC LS $7,212.29
$0.00
$0.00
$0.00
$8,294.13
$8,294.13
HOURLY

RATE EXTENDED AMOUNTS

MATERIAL AND/OR SPECIALISTS
DESCRIPTION # UNITS UNIT PRICE EXTENDED AMOUNTS

LABOR HOURS
Equip
No. EQUIPMENT HOURS HOURLY

RATE EXTENDED AMOUNTS

TOTAL COST LABOR, MATERIALS & EQUIPMENT
Total Cost of Materials & Equipment
Change Order 7: Changes to decorative
panels due to change in retaining wall
footprint Total Labor
15% Markup
Subtotal
$0.00
$0.00
Subtotal
15% Markup
15% Markup
Total Materials
Total Equipment $0.00
$1,081.84
$7,212.29
Decorative Panels Changes $7,212.29
$8,294.13
Subtotal
1 6/20/2022
EQUIP.

NO. HOURS LABOR
1 0 Foreman O. T. 0
21 6 REG. 16
3 0 Laborer #1 O. T. 0
4 Superintendent Truck 0 REG. 16
5 0 Laborer #2 O. T. 0
6 Jack Hammer 0 REG. 0
7 Welder 0 Laborer #3 O. T. 0
8 Concrete saw 0 REG. 0
9 Material trailer 0 O. T. 0
10 Back Hoe/Mini ex 0 REG. 0
11 0 O. T. 0
12 0 REG. 0
13 0 Superintendent O. T. 0
14 0 REG. 0
Office support REG. 0
SHOP REG. 24
NO. UNIT
0 1 per man $150.00
5 varies
0 varies
0 0 A
B
+1 5 % ON LABOR COST ( A
)
+1 5 ( B )
+0 ( C )

0.00 % tax on material

TOTAL THIS REPORT
425.00

0.00 0.00

25.04 19.25

0.00 0.00

18.00 0.00

0.00 HOURLY RATE
113.01

75.34 0.00

0.00 72.45
108.68
108.68
Man lift

11.78 17.50

17.50 27.14
Dump truck
compressor

0.00 HOURS
DATE :

Owner/General Contractor
DESCRIPTION OF WORK:

Monday, 20 Jun 2022 FIELD INSTRUCTION
City of Sacramento / TJR Resources
JOB NAMEDecorative Panel Changes Matsui Park
2346.92

0.00 0.00

0.00 EXTENDED AMOUNTS

0.00 0.00

0.00 1,205.44
352.04

0.00 588.70
Powdercoating Posts
3924.64

DELIVERY

CRUSADER FENCE REPRESENTATIVE

0.00 TOTAL COST OF EQUIPMENT, MATERIALS
$7,212.29

0.00Daniel Boek
% ON EQUIPMENT, MATERIAL
% BONDS & INSURANCE

DESCRIPTION
-$
TOTAL COST OF LABORPart load charge on concret
-$
Material

UNIT COST
Powdercoating panels TRAVEL EXPENSE

0.00 0.00

85.00$

35.00$
-$

80.00 70.00
1,392.00$ 1,392.00

65.00 0.00
$529.92TOTAL FOR EQUIPMENT

SUBSISTENCE
1,560.00

SUB-TOTAL

LABOR EXPENSES
$3,924.64MATERIAL

0.00 80.00

51.72 108.68

24.12 Asphalt cutter
1,159.20

0.00 0.00

0.00 0.00

0.00 0.00

72.45 0.00

72.45 0.00

0.00 0.00

0.00 0.00 0.00

25.72 Fork lift

50.00 EXTENDED

AMOUNTS
529.92

EQUIPMENT
(Cal trans rates)
Bobcat c/w auger
Crew truck

25.72 33.12
Cal Trans

HOURLY RATE

0.00 Crusader Fence Co., LLC 3115 GOLD VALLEY DRIVE
Rancho Cordova, CA 95742-6588 (916) 631-9191 FAX (916) 631-8989

ITEMIZED ESTIMATE
22-152 Matsui - adjustements due to wall changes
QTY. SOURCE # ITEM AMOUNT
4 NONE 2-1/2" PRE-GALV SQUARE x 11GA x 20' TUBE STEEL
@ 235.00 = 940.00
4 NONE Infill panels for guard rail @ 85.00 = 340.00
--------
MATERIALS TOTAL: $ 1280.00

8.75% STATE SALES TAX: 112.00
--------
TOTAL: $ 1392.00
06/20/2022

FROM: TJR Resources, Inc. 20 Jun 2022

TO: City of Sacramento Dept of Parks & Recreation
ATTN: Dennis Day
915 I Street
Sacramento, CA 95814

SUBJ: Matsui Park Access (Area A) – Change Order Proposal – Install Water Line to POC

Dennis,

1. Change Order Information:

a. CHANGE DESCRIPTION:

The water line that was supposed to be used to feed the irrigation is dead and cutoff from the POC on the plans. Will have to run 85’ of new 3” water from the irrigation to the existing POC

b. COST IMPACT: Addition of $2,358.30 (Sub-Contractor Breakout attached)

c. TIME IMPACT: 2 days

2. NET TOTAL OF CHANGE ORDER: Net Contract decrease of $2,358.30 and project extension of 2 working days

3. If you have any questions, please call me at 916.752.6019 or email at [email protected].

Respectfully Submitted,

THOMAS MURPHY USAF, RET
President/CEO
TJR Resources, Inc

“palma non sine pulvere”
PO Box 637
Rancho Cordova, CA 95741
Office/Fax: 888.423.7789
CA DVBE #1759799
CSLB # 989449
Job: Matsui Park Access (Area A) CONTRACTOR: TJR RESOURCES, INC LS $2,246.00
$0.00
$0.00
$0.00
$2,358.30
$2,358.30
HOURLY

RATE EXTENDED AMOUNTS

MATERIAL AND/OR SPECIALISTS
DESCRIPTION # UNITS UNIT PRICE EXTENDED AMOUNTS

LABOR HOURS
Equip
No. EQUIPMENT HOURS HOURLY

RATE EXTENDED AMOUNTS

TOTAL COST LABOR, MATERIALS & EQUIPMENT
Total Cost of Materials & Equipment
Change Order 5: Install Additional water
line for irrigation system
Total Labor
15% Markup
Subtotal
$0.00
$0.00
Subtotal
15% Markup
5% Markup
Total Materials
Total Equipment $0.00
$112.30
$2,246.00
Parker Landscape
$2,358.30
Subtotal
$2,246.00
1 6/20/2022

“palma non sine pulvere”
PO Box 637
Rancho Cordova, CA 95741
Office/Fax: 888.423.7789
CSLB #989449
CA DVBE #1759799

REQUEST FOR INFORMATION
FROM: Tom Murphy RFI NUMBER: 10
TO: D
ennis Day
Project Name: Matsui P ark Access (Area A)
Project Number: L19911200
In reference to the above contract, we are hereby requesting a clarification, determination and/or information concerning the following:

Specification Section No(s):

Drawing No(s): Drawings.

Request: Please reference attached RFI from Crusader for the layout of the replacement panels due to wall change.

Once a decision is made Crusader can submit a change order for the additional work.

Requested by: Tom Murphy – TJR R esources
Title: Replacement Decorative Panel Layout
Date of Request: 10 Jun 2022
Date Reply Required: 17 June 2022
NOTE: Please reply and return this form to the originator. I understand that a reply to this RFI does not authorize changes to contract specifications that involve a change in cost or time. If a change in cost or time is involved, I will submit a written proposal prior to initiating any work and will await written authorization from the Contracting Officer.

In reply to your request, be
advised:____________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ ___________________________________________________________________________________________________________ _________________________________________________________________________ Reply by: __________________________ Date of Reply: _______ Title
: ______________________________ Date reply returned to originator: ____________ Dennis Day
6/13/22
Split the two large panels into two equal sized panels. 1 Tom Murphy
From: Daniel Boek <[email protected]>
Sent: Friday, June 10, 2022 11:42 AM
To: Tom Murphy
Cc: Tom Nordyke; Nick Brown; Ed Korte
Subject: remaining panels at Matsui
Hi guys,
Below is a picture of 1 of the 2 larger areas that need to be made due to the wall change. My question is do you want me to split the large section in 2 and have 2 equal panels at these two locations or would you rather I put a full size panel and then 1 custom panel at the end that is smaller.

If we have 2 equal size panels this will result in 5 panels being made. Or using the full size then 1 small panel would result in 3 panels made. Let me know.

Daniel Boek

Direct:

916-809-2300

|

Main:

916-631-9191