City of Sacramento
City Council - 2PM Report
915 I Street Sacramento, CA 95814
www.cityofsacramento.org
File ID: 2022-02033 12/6/2022 Consent Item 13.

Agreement: Trash Full Capture System Design
File ID: 2022-02033
Location: Citywide
Recommendation: Adopt a Resolution: authorizing 1) the City Manager or the City Manager’s designee to execute a professional services agreement with Wood Rodgers, Inc. to provide professional design and engineering services for Trash Full Capture Systems Design, for an amount not-to-exceed $585,829; and 2) a budget transfer from the NPDES Stormwater Program MYOP (I14010200, Fund 6011) in the amount of $200,000 and from the Base CIP Contingency-Drainage Program (W14000200, Fund 6011) in the amount of $400,000 to the Drainage Trash Capture Program (W14230100, Fund 6011).

Contact: Bryan Mahoney, Project Manager, (916) 808-1914, [email protected]; Lisa Moretti, Supervising Engineer, (916) 808-5390, [email protected]; Sherill Huun, Engineering & Water Resources Division Manager, (916) 808-1455, [email protected]; Department of Utilities
Presenter: None
Attachments:
1-Description/Analysis
2-Agreement
3-Resolution
Description/Analysis
Issue Detail: Staff recommends Council approve an agreement with Wood Rodgers, Inc., for professional design and engineering services to support the City’s objective in meeting the interim water quality milestone to achieve at least 30% Full Capture System Equivalency (FCSE) by 2027 and 100% FCSE by 2030 through the implementation of State-certified Full Capture System (FCS) devices in high priority areas.

The State Water Resource Control Board adopted statewide Trash Provisions to address the impacts

Page 1 of 3 ends

File ID: 2022-02033 12/6/2022 Consent Item 13.
of trash on the beneficial uses of surface waters. As a result, the Central Valley Regional Water Quality Control Board issued the Water Code Section 13383 Order to implement the Trash Provisions. The Trash Provisions required the City of Sacramento, as a Phase 1 Municipal Separate Storm Sewer System (MS4) permittee, to select a method of compliance to the trash prohibition for Priority Land Uses (PLUs).

The City of Sacramento (City) prepared a Track 2 Trash Implementation Plan to meet the requirements of the Order, which was submitted in November 2018 to the Central Valley Water Board. Per the Trash Provisions, the City must achieve FCSE by 2030. The City has elected to install State-certified FCS devices that capture trash down to 5 millimeters in size for 1-hour, 1-year storm events in areas where it was feasible for installation and maintenance and within drainage areas with the high trash loads identified through the baseline trash surveys. City Staff has reviewed the baseline trash survey results to determine which drainage areas with high potential for trash load reduction are suitable for the installation of State-certified FCS devices. Three preferred project locations were identified by City Staff as being feasible for siting of large capacity FCS devices that meet the City’s priorities.

Policy Considerations: City Council approval is required for professional service agreements of $250,000 or more per City Code 3.64.020.

Economic Impacts: None.

Environmental Considerations: This report concerns administrative activities that will not have a significant effect on the environment and does not constitute a “project” as defined by CEQA [CEQA Guidelines Sections 15378(b)(2 and 5)] and is therefore, not subject to CEQA [CEQA Guidelines Section 15060(c)(3)].

Sustainability: The proposed project is consistent with the 2035 General Plan Citywide Utility and Stormwater Drainage policies as it reduces impacts to environmentally sensitive lands and provides adequate drainage facilities by reducing the quantity of trash that reaches the Sacramento River and provide appropriately sized bypass facilities for the Trash FCS devices.

Commission/Committee Action: Not applicable.

Rationale for Recommendation: On July 7, 2022, a Request for Proposals (RFP) (P23141311007) was advertised and issued on PlanetBids for design and engineering services for certified Full Capture Systems (FCS) that prevent trash greater than 5 mm from discharging to receiving waters.

On the due date of July 28, 2022, four proposals were received from the following firms:

1. CSG Consultants, Inc.

2. CWE

3. Schaaf & Wheeler

Page 2 of 3 ends

File ID: 2022-02033 12/6/2022 Consent Item 13.

4. Wood Rodgers, Inc.

A 3-member evaluation team that included staff from DOU, evaluated the proposals and interviewed 2 firms. Wood Rodgers, Inc. was the top-ranked firm.

Financial Considerations: The total estimated cost for the project is $600,000. To provide sufficient funding for this project, staff recommends transferring $200,000 from the NPDES Stormwater Program MYOP (I14010200, Fund 6011) and $400,000 from the Base CIP Contingency-Drainage Program to the Drainage Trash Capture Program (W14230100, Fund 6011).

There are no General Funds allocated or planned for this project.

Local Business Enterprise (LBE): Wood Rodgers, Inc. is an LBE.

Page 3 of 3 ends

Form Approved by City Attorney 9‐1‐2020  Page 1
CONTRACT #:

CONTRACT NAME:  Trash Full Capture System Design
CONTRACT PROJECT #:

DEPARTMENT: Department of Utilities
DIVISION:  Environmental and Regulatory Compliance
CITY OF SACRAMENTO
PROFESSIONAL SERVICES AGREEMENT
FOR ARCHITECTS, LANDSCAPE ARCHITECTS,
ENGINEERS, AND LAND SURVEYORS
THIS CONTRACT is made at Sacramento, Californ
ia, by and between the CITY OF SACRAMENTO,
a charter city and municipal corporation (“CITY”), and
Wood Rodgers, Inc.
3301 C Street, Building 100‐B
Sacramento, CA 95816
916‐341‐7760 (Phone)/ 916‐341‐7767 (Fax)
[email protected]
(“CONTRACTOR”), as of the Effective Date, as defined below.

The Cit
y and Contractor agree as follows:

1. Effective Date.   This Contract shall be effective beginning  December 13, 2022.

2. Contract Documents.   All exhibits and documents attached or referred to in this Contract are incorporated as if set forth herein, Including Exhibit A (titled “Scope of Services”) and Exhibit B (titled “Payment”).

If there is a confli
ct between the terms and conditions of any document prepared or provided by the Contractor and made a part of this Contract and the other terms or conditions of the Contract, the other terms and conditions of the Contract control.

3. Servic es.  Subject  to  the  terms  and  conditions  set  forth  in  this  Contract,  CONTRACTOR  shall provide to CITY the services described in Exhibit A (“Services”).

CONTRACTOR will not be compensated for services outside the scope of Exhibit A (“Additional Services”) unless, before providing Additional Services: (a) CONTRACTOR notifies CITY and CITY agrees that the Additional Services ar
e outside the scope of Exhibit A; (b) CONTRACTOR estimates the additional compensation required for these Additional Services; and (c) CITY, after notice, approves in writing a Supplemental Contract specifying the Additional Services and the amount of additional compensation to be paid Contractor.

CITY  will  have  no  obligations  whatsoever  under  this  Cont ract  or  any  Supplemental  Contract, unless and until this Contract or any Supplemental Contract is approved by the City as required W14230100
Form Approved by City Attorney 9‐1‐2020  Page 2
by the Sacramento City Code. As used in this Contract, the term “Services” includes both Services and Additional Services as applicable.

4.  Payment.   CITY shall pay CONTRACTOR at the times and in the manner set forth in Exhibit B.

CONTRACTOR shall submit all invoices to CITY in the manner specified in Exhibit B.

5.  Facilities  and  Equipment.   Except  as  set  forth  below,  CONTRACTOR  shall,  at  its  sole  cost  and expense, furnish all facilities and equipment required for CONTRACTOR to perform this Contract.

CITY shall furnish to CONTRACTOR only the facilities and equipment listed below, if any.

6.  Insurance.  Contractor  shall,  at  its  sole  cost  and  expense,  maintain  the  insurance  coverage described in the attached Exhibit C.

7.          General  Conditions.   Contractor  shall  comply  with  the  terms  and  conditions  set  forth  in  the attached Exhibit D.

8.  Additional Requirements for Surveying, Material Testing, and Inspection Services. If this Contract includes any land surveying, material testing, or inspection services provided for a City construction project, during the design, pre‐construction, construction, or post‐ construction phases of the project, the Contractor and any subcontractor or subconsultant performing any such services shall comply with the provisions specified in Exhibit E.

9.   Non‐Discrimination in Employee Benefits. This Contract may be subject to Sacramento City Code chapter 3.54, Non‐  Discrimination in Employee Benefits by City Contractors. A summary of the  requirements, entitled "Requirements of the Non‐Discrimination in Employee Benefits Code (Equal Benefits Ordinance),” can be viewed at:
https://www.cityofsacramento.org/Finance/Procurement/Contract‐Ordinances.

Contractor acknowledges and represents that Contractor has read and understands the requirements and shall fully comply with all applicable requirements of Sacramento City  Code chapter 3.54. If requested by City, Contractor shall promptly provide any  documents and information required by City to verify Contractor's compliance.

Contractor's violation of Sacramento City Code chapter 3.54 constitutes a material  breach of this Contract, for which the City may terminate the Contract and pursue all  available legal and equitable remedies.

10.  Considering  Criminal  Conviction  Information  in  the  Employment  Application  Process.  This Contract may be subject to the requirements of Sacramento City Code chapter 3.62, Procedures for  Considering  Criminal  Conviction  Information  in  the  Employment  Application  Process.   A summary of the requirements, entitled “Ban‐The‐Box Requirements,” can be viewed at:

https://www.cityofsacramento.org/Finance/Procurement/Contract‐Ordinances.

Form Approved by City Attorney 9‐1‐2020  Page 3
The Ban‐The‐Box Requirements are applicable to certain contracts with the City in an  amount of $250,000 or more (either initial value or total value after amendment) or if the  total value of all Contractor's contracts with the City is $250,000 or more over a 12‐month period.

Contractor acknowledges and represents that Contractor has read and understands  these requirements and shall fully comply with all applicable requirements of  Sacramento City Code chapter 3.62. If requested by City, Contractor shall promptly  provide any documents and information required by City to verify Contractor's  compliance. Contractor shall require applicable subcontractors to fully comply with all  applicable requirements of Sacramento City Code chapter 3.62 and include these  requirements in all subcontracts covered by Sacramento City Code chapter 3.62.

Contractor's violation of Sacramento City Code chapter 3.62 constitutes a material  breach of this Contract,  for  which  the  City  may  terminate  the  Contract  and  pursue  all  available  legal  and equitable remedies.

11.  Local  Business  Enterprise  Program.  The  Local  Business  Enterprise  Program  Participation Requirements ("LBE Participation  Requirements") may be applicable to this Contract. A summary of the requirements, entitled  "LBE Participation Requirements," can be viewed at:

https://www.cityofsacramento.org/Finance/Procurement/Contract‐Ordinances.

Contractor acknowledges and represents that Contractor has read and understands  these requirements and shall fully comply with all applicable requirements of  Sacramento City Code chapter 3.60. If requested by City, Contractor shall promptly  provide any documents and information required by City to verify Contractor's  compliance. Contractor shall require applicable subcontractors to fully comply with all  applicable requirements of Sacramento City Code chapter 3.60 and include these  requirements in all subcontracts covered by Sacramento City Code chapter 3.60.

Contractor's violation of Sacramento City Code chapter 3.60 constitutes a material  breach of this Contract, for which the City may terminate the Contract and pursue all  available legal and equitable remedies.

12.  Authority.  The person signing this Contract for CONTRACTOR represents and warrants that he or she has read, understands, and agrees to all the Contract terms and is fully authorized to sign this Contract on behalf of the CONTRACTOR and to bind the CONTRACTOR to the performance of the Contract’s
obligations.

[Signature Pages Follow Exhibits]

Form Approved by City Attorney 9‐1‐2020  Exhibit A ‐ Page 1 EXHIBIT A

SCOPE OF SERVICES

1.  Representatives.

The CITY Representative for this Agreement is:

Bryan Mahoney, City of Sacramento, Department of Utilities 1395 35th Ave
Sacramento, CA 95822
Phone: 916‐808‐1914, Email: [email protected]

The CONTRACTOR Representative for this Agreement is:

Jeffrey Lodge
3301 C Street, Building 100‐B
Sacramento, CA 95816
916‐341‐7421
[email protected]

Unless  otherwise  provided  in  this  Contract,  all  Contractor  questions  and  correspondence pertaining to this Contract must be addressed to the City Representative. All City questions and correspondence must be addressed to the Contractor Representative.

2.   Scope of Services. Contractor shall provide Services to City as set forth in Attachment 1 to this
Exhibit A.

3.   Time of Performance.  The Services described in this Contract shall be provided for one year.

The City may extend this Contract for up to 4 additional one‐year terms, for a maximum five‐ year term. Contractor shall provide the Services in accordance with any schedule in Attachment 1 to this Exhibit A. Contractor shall immediately notify the City if Contractor is unable to make delivery of Goods or perform Services in compliance with this Contract.

4.   Conflict of Interest Requirements. The individual(s) who will provide Services pursuant to this Contract are “Consultants” within the meaning of the Political Reform Act and the City’s Conflict of Interest Code:  ____ yes  __X__ no   [check one]

Contractor shall cause the following to occur within 30 days after execution of this Contract:

(A)       Identify the individuals who will provide Services or perform Work under this Contract as "Consultants"; and
(B)       Cause these individuals to file with the City Representative the "assuming office" statements of economic interests required by the City's Conflict of Interest Code.

Thereafter, throughout the term of the Contract, Contractor shall cause these individuals to file with the City Representative annual statements of economic interests and "leaving office" statements of economic interests, as required by the City's Conflict of Interest Code. The City

Form Approved by City Attorney 9‐1‐2020  Exhibit A ‐ Page 2 may withhold all or a portion of any payment due under this Contract or impose fines on the individuals until all required statements are filed.

P a g e | 1
Proposal | Trash Full Capture System Design
Bid Transaction | #P2314311007
Scope of Work
Task 1 | Project Management + Coordination
Wood Rodgers will provide project management to include facilitation of meetings, coordination, scheduling of activities, and performance of work tasks necessary to progress the design. The overall project management will also facilitate communication between the design team, the City, and pertinent agencies for continuity during the various phases of the work and act as an extension of City staff as appropriate. Our project manager will also be responsible for ensuring Quality Assurance and Quality Control (QA/QC) protocols are implemented. For design projects our protocols include:
• Identification of key design elements requiring prog
ress review prior to submittal milestones
• Internal progress and coordination meetings
• Discipline lead checks
• Interdisciplinary review and cross checks
• Drafting presentation and callout reference review
• Bid-ability/Constructability review (includes out of service considerations for tie-ins and retrofits) • Cost/value review
• Operation and maintenance, and repair/replacement ac cess review • Wood Rodgers will provide technical information, con ceptual design, cost estimates and maps for Caltrans grant applications and coordination
QA/QC reviews will be performed for each design submittal milestone, and at interim stages for key design and coordination elements as identified.

Deliverables
• Initial + Updated Project Schedules (electronic PDF)
• Meeting Agendas & Minutes (electronic PDF)
• Monthly Invoices
• Status Reports (electronic PDF)
Task 2 | Preliminary Design Report
Wood Rodgers will perform an evaluation of the City’s three proposed full trash capture projects to assist the City in meeting its goal of 30-percent full trash capture equivalency. Efforts under this task will include feasibility review, hydraulic modeling based on available trash capture system technologies, and reviewing specific aspects of each project site. Wood Rodgers will also investigate potential alternatives capable of achieving the City’s desired goals, and the State’s requirements for trash capture equivalency. Site visits will be conducted for the project locations to obtain an understanding of access, available space and property / right-of-way constraints, utility conflicts, environmental concerns, drainage, and other pertinent aspects. Considerations explored during design will include:
• Design and constructability
• Access for maintenance
• Frequency and extent of maintenance required
• Site security and resistance to vandalism
• Influence on upstream water levels during storm flow
A
s a part of this task, Wood Rodgers will coordinate with full trash capture system device representatives, evaluate alternative systems for suitability for each project site based on the above considerations, and provide recommendations tailored to the specifics of each site. Alternative trash capture options will also be explored and identified where more cost efficient, which may include certified multi-benefit systems or catchment-size certified full capture system devices.

Attachment 1 to Exhibit A

P a g e | 2
Proposal | Trash Full Capture System Design
Bid Transaction | #P2314311007

The City’s approved selection of the alternatives presented will be further developed into final design as described in Task 3 and Task 4 in this proposal.

Task 2.1 | Data Collection
Wood Rodgers will collect and review any available information such as: GIS storm drain network data, drainage areas, hydrologic and hydraulic models, as-builts, land use data, utility data, and geotechnical data. Wood Rodgers will document the collected data and request any missing data. Wood Rodgers will compile the collected data into a geodatabase.

Deliverables
• Updated Geodatabase
Task 2.2 | Desktop Utility Investigation
Wood Rodgers will perform a desktop utility investi gation to identify underground utilities present in the vicinity of the proposed sites and further refine the sites based on the findings of the investigation. Wood Rodgers will georeference the collected as-builts and utility GIS shape files to identify any utilities in the vicinity of the sites.

Preliminary pothole locations will be identified ar ound the vicinity of the proposed sites and will th en be further refined based on the findings of the field utility locating investigation in Task 3.3.

Deliverables
• Georeferenced utilities and preliminary pothole locations Task 2.3 | Preliminary Assessment + Site Refinement
Wood Rodgers will perform preliminary feasibility assessments of the three sites based on available information and data.

They include the utility information investigated in Task 2.2 , TMAs already developed by DOU, State-certified Full Capture System (FCS) device types, multi-benefit treatment opportunities, site constraints from Google Street views, maintenance considerations, and easements/rights-of-way from the City’s GIS database. These assessment are to determine high-level performance of the devices and potential impacts of the project.

Wood Rodgers will also develop a high-level hydrolo gic and hydraulic analysis for the existing storm d rain systems based on TMAs and existing storm drain geometries and pro perties. The findings of the analysis could be used to assess the capacity of the existing storm drain system and the potential impacts of the proposed FCS.

Wood Rodgers will then refine the proposed site locations based on the information above. If any of the preselected sites are deemed infeasible, Wood Rodgers will work close ly with the City to investigate other sites after r eviewing the model results and all other available collected data.

Task 2.4 | Site Visit
Wood Rodgers will perform site visits to determine potential issues and site constraints for the three FCS sites refined in Task 2.3 . Wood Rodgers will inspect the drainage facilities at the proposed sites to determine structural inte grity, sediment, potential backwater effects and other mai ntenance issues. The inspection data will be used t o determine the improvement extent when there are any other deficiencies found.

Deliverables
• Inspection photos, updated GIS database properties, and field forms summarizing visual findings from s ite field visits
Task 2.5 | Hydraulic Modeling
Wood Rodgers will develop existing condition hydrologic (catchment) and hydraulic (pipes + pumps) models (dynamic) to generate one-year, one-hour water quality flow for FCS device sizing. The dynamic models provide more realistic and accurate hydraulic performance of the facility than simplified hand calculations or the Rational Method by accounting for pipe storage, flow routing, backwater effects, and pipe diversion. This approach generally yields smaller water qualit y flows than the simplified Rational Method for large trash capture device sizing, which results in smal ler and less expensive devices. The Regional Board has accepted this method. The modeled one-year, one-hour flows and annual

P a g e | 3
Proposal | Trash Full Capture System Design
Bid Transaction | #P2314311007

trash volumes provided by the City will be used to size FCS devices. Up to two different FCS devices will be recommended for each TMA location.

Wood Rodgers will perform hydraulic impact analyses using the models developed in this task to determi ne any adverse hydraulic inefficiencies of the proposed large FCS devices to the existing upstream storm drainage sys tem and to subsequently develop improvements to mitigate the i nefficiencies. Aside from meeting the NPDES permit a nd maintenance requirements, the hydraulic impact anal ysis will be the most instrumental factor in select ing the trash capture device and its system configuration.

Wood Rodgers will modify the hydraulic models to in clude the hydraulic features of large FCS devices a t the three TMAs.

Wood Rodgers will perform a comprehensive hydraulic analysis for the upstream storm drain systems to a ssess the system-wide impact of the large FCS devices on storm drain facilities based on the pre- and post-large FCS devices model results. Wood Rodgers will model and assess the performance of two different device types of large FCS devices to address any requirements and considerations from different stakeholders.

Wood Rodgers will develop a post-project hydraulic model and compare the hydraulic performances of the pre- and post- project conditions for 2-, 10-, and 100-year design storms. The FCS devices will be modeled with a deb ris clogging factor and reduced performance efficiency to simulate the worst-case scenario.

If significant adverse hydraulic impacts are found for the proposed FCS devices, Wood Rodgers will ide ntify and quantify the additional floodplain and the increased hydraul ic grade lines along the main storm drain system in the post-project conditions. We will then propose additional improve ments to mitigate adverse impacts in the post-proje ct condition.

Wood Rodgers will rerun the 2-, 10-, and 100-year p ost-project models with the additional improvements . Potential additional improvements include upstream/downstream pipe upsizing, diversion pipe systems, and underground storage structures.

Wood Rodgers will then recommend the optimal FCS de vice type, location, and additional improvements by considering the hydraulic impacts, ease of maintenance, and acc ess. Wood Rodgers will iterate and optimize the imp rovement configurations required to reduce the post- FCS water surface elevations to the pre-FCS conditions in the 2-, 10-, and 100- year design storms to maintain or minimize existing storm drain system capacity.

Deliverables
• Modeled one-year, one-hour flow; FCS sizes and models for three TMA locations • Pre- and Post-FCS hydraulic results for 2-, 10-, and 100-year design storms Task 2.6 | Life-Cycle Cost Analysis
Wood Rodgers will develop a life-cycle cost analysi s, which includes construction, and operation and m aintenance cost estimates. The construction elements will be devel oped and organized in units, lump sum costs and qua ntities as applicable for all work items. A manufacturer’s quo te will be included for the selected FCS devices. T he construction cost estimates will be developed based on the contractor bids for approximately 50 trash capture devices co nstructed in the City of San Jose and City of Oakland. Wood Rodgers will also develop operation and maintenance costs for a 20-year period of the FCS devices. Wood Rodgers will also develop operation and maintenance costs as well as vandalism and replacement costs for a 20-year period of the FCS d evices. Vandalism frequency will be provided by the City for this analysis.

Deliverables
• Construction, and operation and maintenance costs
Task 2.7 | Preliminary Design Report
A Preliminary Design Report will be prepared to sum marize the findings of the analyses, which include the study area descriptions, life cycle cost analysis, utility inv estigation, existing facility inspection, large FCS device facility sizing, hydraulic analysis, and will include plan layouts and alternative full trash capture systems explored, and recommendations for each. The Preliminary Design Report will inclu de discussions and comparisons of alternatives on m ultiple aspects,

P a g e | 4
Proposal | Trash Full Capture System Design
Bid Transaction | #P2314311007

including, but not limited to, site constraints, right of way constraints, and utility conflicts, in addition to those listed above.

Conceptual design schematics will be included for r ecommended full capture system alternatives. Proje ct background and descriptions, cost vs. benefit analyses includi ng for both construction and life cycle operations and maintenance, as well as design and Class 4 Opinion of Probable Construction Cost (OPCC) estimates and recommendations will be included in the report. Efforts in the development of the report will cover:
• Operation and Maintenance | City operation and maintenance staff will be consulted to ensure ease of maintenance of the devices, including concerns of:
o Access of equipment for FCS Device maintenance
o Regular drainage system collection maintenance activities are not inhibited o Minimized maintenance and frequency to the extent possible, including resistance to clogging from organic debris, sedimentation fill
o Disposal of wastewater generated during maintenance activities • Vector Control | Sacramento-Yolo Mosquito and Vector Control District will be consulted with to ensure vector control issues are adequately addressed
• Security Issues | City DOU’s Security Section will be consulted with to ensure measures are in place to prevent vandalism
Deliverables
• Draft and Final Preliminary Design Reports (electronic PDF) • Meeting Agendas & Minutes (electronic PDF)
• Class 4 OPCC’s and Life Cycle Cost Analyses (electronic PDF) Task 3 | Design
Task 3.1 | Preliminary Design
Wood Rodgers will develop the City’s selected full trash capture system improvements for each site to a 30-percent level of design under this task. The preliminary design will be based upon the coordination efforts with th e selected full trash capture system vendor, and the manufacturer’s speci fications for required operation and maintenance. The 30-percent design will incorporate survey information provided by the City of Sacramento’s surveying department, and geotechnical information from the geotechnical investigations and report prepared by Wood Rodgers. The 30-percent design drawings will present improvements for all three project sites and will include:
• Existing site and demolition plans
• Site grading, paving, and improvement plan and profile drawings • Plans, sections, and details as applicable of:
o Diversion weirs or bypass structure improvements
o Full capture system device installation improvements
Elements crucial for design in the preliminary design submittal will be taken into consideration including the following:
• Site constraints, operational requirements and maintenance access • Site aesthetics and equipment visibility
• All weather vehicular access and turn-around
City standards and requirements will be incorporated into the design drawings.

Deliverables
• 30-Percent Plans, Preliminary Specifications List, and Class 3 Opinion of Probable Cost of Constructio n (electronic PDFs)

P a g e | 5
Proposal | Trash Full Capture System Design
Bid Transaction | #P2314311007

Task 3.2 | Geotechnical Investigation
The proposed exploration program includes site reconnaissance, permitting, verification of utility clearances through USA, geotechnical exploration, field and laboratory test ing, and engineering analyses to allow formulation of geotechnical recommendations for design and construction of the project. The deliverables for this task are anticip ated to be a draft and final geotechnical investigation report.

Wood Rodgers has performed a review of documents pr ovided in the RFP and assumes the invert depth of t he trash capture systems to be a maximum of approximately 10 feet below the invert of the existing channels.

Geotechnical Investigation
Exploration will be performed by drilling six geote chnical borings up to a maximum depth of 35 feet be low the existing ground surface, with two borings at each of the pro posed trash capture system locations. A geotechnic al boring permit will be obtained from the Sacramento County Environ mental Management Department. Wood Rodgers assumes all locations will be on City of Sacramento owned prope rty and traffic control is not required. Wood Rodge rs assumes no other permits are required. On 2 ½-feet to 10-foot centers, samples will be obtained to aid in subsurface characterization.

Soils will be sampled with a two-inch OD split-spoo n sampler driven by a standard 140-pound drive hamm er with at 30- inch stroke. The number of blows to drive the samp ler one foot into undisturbed soil (Standard Penetr ation Test) is an indication of the density and shear strength of the material. Free water depth will be measured were encountered. Wood Rodgers geotechnical personnel will log material encountered during exploration. Representative samples will be returned to our Reno laboratory for testing. It is assumed with this proposal that access is available for exploration equipment and will be provided by the City of Sacramento staff. W ood Rodgers has assumed all three proposed trash ca pture locations will be accessible under one mobilization.

Upon completion of geotechnical exploration, borings will be backfilled with neat cement grout or bentonite in accordance with Sacramento County Environmental Management Dep artment and California Department of Water Resource s standards. Soil cuttings and fluid from drilling wi ll be contained in 55-gallon DOT-approved drums and off hauled by our drilling contractor for disposal. Wood Rodgers assu mes the geotechnical investigation will not encount er any hazardous or toxic substances. In the event that suspected ha zardous materials are encountered, visually or by o dor in any geotechnical test boring, we will immediately termi nate the exploration and make arrangements to backf ill the boring with cement grout. Added costs incurred as a result of suspected hazardous substances shall be invoice d on a time and expense basis and requires a properly executed Change Order.

In addition to advancing geotechnical borings, a sh ear wave velocity profile will be measured to a dep th of 100 feet; this information will allow for Site Class determination as required by the International Building Code (IBC) and can serve as a screening mechanism for liquefaction potential.

Geotechnical Laboratory Testing
Representative samples of significant soil types wi ll be tested in the laboratory for index properties , such as moisture content (ASTM D2216), grain size distribution (ASTM D6913) and plasticity (ASTM D4318). These index pr operties are indicative of mechanical behavior of the soils and aid in determining design parameters. Consolidation (ASTM D2435) and corrosion testing will also be performed to analyze settlement and to assess the environment regarding the potential for corrosivity, respectively.

Geotechnical Data Review, Engineering Analysis, and Reporting Upon completion of our exploration, laboratory, and office studies a geotechnical investigation report, consistent with the requirements of the 2019 California Building Code (CBC), will be completed for the project and will present the following:
• Description of the project site with the approximate locations of our explorations, shown on a Site Plan.

P a g e | 6
Proposal | Trash Full Capture System Design
Bid Transaction | #P2314311007

• Descriptive logs of the explorations performed for this study, approximate grade at the time and locat ion of our exploration will be provided.
• General summary of the site soils and geology.
• Summary of seismic hazards including site seismicit y, design parameters, potential for surface fault r upture, and landslides.
• A description of the site subsurface and ground water conditions encountered. • Seismic Design values based on the most current CBC requirements and including a discussion regarding site seismicity and parameters for design.
• Site Class will be determined based on Refraction M icroTremor or ReMi® surveys, scaled to a depth of 1 00 feet.
• A preliminary assessment of liquefaction susceptibi lity based on results of geophysical testing sand geotechnical drilling data. A proposal for a site-s pecific liquefaction assessment will be presented i f the site soil and groundwater conditions present a significant potential for liquefaction based on our initial screening. • Site preparation and grading recommendations. Settlement potential of existing and imported fill soils will be discussed. Subgrade stabilization and excavation co nsiderations due to high groundwater will be discus sed.

Overexcavation requirements due to adverse soil conditions will be addressed. Compaction requirements will be stipulated.
• Recommendations for shallow foundations, including allowable bearing capacity, anticipated settlement (static and short-term seismic loading), and lateral earth design values. • Recommendations for temporary shoring, bracing, and dewatering. • Concrete and concrete slab-on-grade support options.
• Drainage considerations that may affect foundation and concrete slab-on-grade performance. • Pavement design parameters will be formulated for access drives. • Recommendations for additional exploration as appropriate.

A draft geotechnical investigation report will be p rovided for review and comment before a final repor t is issued. One (1 hour) meeting with the City of Sacramento is assumed following submittal of the draft report.

Depending on the availability of the drill rig, fie ld exploration can typically begin within one to tw o weeks of receiving written authorization to proceed. A written draft report will be available within about four to six w eeks after the completion of all field exploration. Two wet-stamped copies and one electronic copy will be provided.

Deliverables
• Draft + Final Geotechnical Reports for the Project (in electronic PDF format) Task 3.3 | Utility Coordination
Wood Rodgers will perform utility coordination as required for all utilities which may be within the areas of impact for the project sites. Based on a preliminary site visit to each of the proposed project sites, Wood Rodgers will observe the existing conditions, notate the location of key facilities a nd utilities and verify access for subsequent field work. We will contact and coordinate with local utilities that provide se rvices in the project areas to identify all known u tilities. Wood Rodgers will prepare and submit plans for coordination with utility companies and in conforming to the America n Public Works Association procedures for utility coordination (“A, B, C” letters).

Deliverables
• Utility response information

P a g e | 7
Proposal | Trash Full Capture System Design
Bid Transaction | #P2314311007

Task 4 | Final Engineering + Construction Document Preparation Task 4.1 | 65-Percent Design
The 65-percent design will advance the development of the project from the efforts in Task 2 and Task 3, with the completion of construction plans for the facility i mprovements to a 65-percent level of design develop ment. Design documents will be prepared in AutoCAD Civil 3D form at, based on the criteria established in the approv ed PDR and preliminary design, incorporating City comments and preferences. Drawings at this level will include: necessary demolition and site improvement plans; equipment sizing; structural plans; and supporting sections and details. A survey control plan for each project site will also be dev eloped based on the information provided by the Cit y’s survey. The design will consider construction sequencing to ens ure flood protection is not severely compromised. Instrument monitoring and security features in accordance with the City’s operational needs and the Security Mast er Plan as requested for the facilities will be incorporated to balance the desire for security and monitoring at the sites, while limiting aspects which may be enticing to vandal destruction . The 65-percent design will include a list of spe cifications planned, key specifications, as well as a Class 3 Opinion of Probable Cost of Construction.

A meeting led by Wood Rodgers will be conducted wit h City staff following the City’s review of the 65- percent design submittal.

Deliverables
• 65-Percent Plans, Key Specifications, and Opinion of Probable Cost of Construction (electronic PDFs) • Draft construction schedule (electronic PDF)
Task 4.2 | 90-Percent Design
The 90-percent design will advance the development of the project with additional calculations and ana lyses, cross- discipline coordination, equipment coordination per formed, and previous comments incorporated. Specifi cations will be provided for 90-percent design based on Constructio n Specifications Institute standards. Front-end sp ecifications provided by the City will be customized for the specifics of the project. The Opinion of Probable Cost of Construction will be refined to match the 90-percent design.

A meeting led by Wood Rodgers will be conducted wit h City staff following the City’s review of the 90- percent design submittal.

Deliverables
• 90-Percent Plans, Specifications, and Opinion of Probable Cost of Construction (electronic PDFs) Task 4.3 | Final Design
Based upon comments received from the City’s review of the 90-percent design submittal, the design will be advanced to a 100-percent final level of completion with any re maining comments, details, specification updates, a nd remaining information required for a biddable set of construc tion documents. The Opinion of Probable Cost of Con struction will be revised and provided as a final Class 1 level estimate.

Deliverables
• 100-Percent Plans, Specifications, and Opinion of Probable Cost of Construction (electronic PDFs) Task 5 | Environmental Study (CEQA) + Environmental Permitting Wood Rodgers in-house environmental team has determ ined that an Initial Study with Mitigated Negative D eclaration (IS/MND) would be the appropriate level of documenta tion to satisfy the California Environmental Qualit y Act (CEQA) guidelines. This determination was made because the trash capture structures would include temporary a nd permanent effects to jurisdictional waters of the United Stat es, waters of the state of California, and Californ ia Department of Fish and Wildlife (CDFW) jurisdictional habitats. Though the project would cause potentially significant effects to these aquatic resources, Wood Rodgers is confident any project ef fects can be reduced to a less than significant lev el through the incorporation of suitable and cost-effective mitigation measures within the IS/MND.

P a g e | 8
Proposal | Trash Full Capture System Design
Bid Transaction | #P2314311007

In addition, Wood Rodgers’ environmental team of pe rmitting specialists understands these project effe cts to aquatic resources would require regulatory permitting with the U.S. Army Corps of Engineers (USACE), the Central Valley Regional Water Quality Control Board (RWQCB), and the CDFW. Wood Rodgers’ recognizes these permitting requireme nts can be time consuming; whereas, Wood Rodgers is confident project effects to Section 404 waters of the U.S would qualify for a USACE Nationwide Permit (NWP) 43 for “Stormwater Management Facilities”. The NWP process will help to expedite the permitting process with the USACE, rather than conducting a letter of permission individual permit. Additionally, the Wood Rodgers’ team is highly knowledgeable and successfu l in securing Section 401 water quality certificati ons within the last two years, in the wake of the new RWQCB waters of t he state discharge procedures. Further, Wood Rodger s environmental team has extensive working relationsh ips with the USACE, RWQCB, and CDFW, which provide clear and concise communications, proving to expedite the permitting process.

Wood Rodgers is highly qualified to complete the environmental clearance and permitting requirements of the proposed project The proposed scope of work will prepare all necessary technical analysis in support of the IS/MND and permitting requirements and complete all necessary tasks for e nvironmental clearance of the proposed project on a n effective schedule, proficiently, and within budget. The scope of work for this task may include:
• Cultural Resources Inventory Report and Native American Consultation • Biological Resources Report
• Draft and Final Initial Study with Proposed Mitigated Negative Declaration • Mitigation Monitoring and Reporting Program and Notice of Determination • Environmental Permits, including Section 401 and 404
Task 6 | Depth Gage Installation, Hydraulic Analysis and Documentation Wood Rodgers, Inc. (Wood Rodgers) is providing desi gn services for a large trash capture device. To as sess the performance of the storm drain system upstream of the proposed large trash capture device, Wood Rodgers proposes to purchase and install a depth gage, collect rain and the depth gage data, and perform a hydraulic analy sis. Wood Rodgers has developed the following scope of work.

Task 6.1 | Furnish and Install Depth Gage
Wood Rodgers will furnish and install a depth measuring gage (ADS Echo or equal) at a manhole/ bridge crossing upstream of the selected trash capture location. Figure 1 shows a typical installation of a depth gage mount ed to an adjustable tension bar within a manhole. The depth gage will i nclude a cellular antenna, sim card, modem and one- year AT&T communication plan for upload of depth data measure ments cloud-based software system as described in Task 6.2. The City will have to renew the AT&T communication plan upon the expiration and replace the battery for co ntinuing monitoring. One day of traffic control will be provided during the installation.

Removal of the depth measuring gage is not included in the scope and fee; however, Wood Rodgers can pr ovide this service upon request.

P a g e | 9
Proposal | Trash Full Capture System Design
Bid Transaction | #P2314311007

Figure 1 - Depth Gage (ADS Echo or equal) Typical Installation Deliverable(s) : Furnishing and Installation of depth gage with cellular telemetry system.

Task 6.2 | Collect and Process Rain and Depth Gage Data Wood Rodgers will collect, review, and process the depth gage and adjacent rain gage data. A one-year subscription to a cloud-based data software PRISM TM will be included for real-time viewing of depth ga ge analytics through an online dashboard and downloading CSV or DSS file with depth gage readings. The data will be processed into and easily readable format.

Deliverable(s) : CSV or DSS file with depth gage readings Task 6.3 | Hydraulic Analysis
Wood Rodgers will use the collected data in Task 6.2 to evaluate the pre- and post- large trash capture device hydraulic impact of the device to the upstream storm drain system. Wood Rodgers will perform hydrologic and hydraulic calibration for the storm drain system model to match the collected gage data and to replicate the actual performance. Wood Rodgers will modify the existing XPSWMM model already devel oped to match the recorded gage data before and aft er the trash capture device is installed. Wood Rodgers will simu late one season of the collected storm events each for the pre- and post- trash capture conditions.

Once the model is calibrated, Wood Rodgers will ass ess the impact of the trash capture device on the u pstream storm drain system by comparing the system’s performance pre- and post- installation. The assessed performan ce or impact of the device will be used for future large trash capture device design and maintenance.

Deliverable(s) : Calibrated pre and post large trash capture device hydraulic model (XPSWMM format) Task 6.4 | Documentation
Wood Rodgers will document the collected data, calibration, hydraulic analysis and any recommendations in a technical memorandum.

Deliverable(s) : Technical Memorandum

Form Approved by City Attorney 9‐1‐2020  Exhibit B ‐ Page 1 EXHIBIT B

PAYMENT

1.  CONTRACTOR’s Compensation.  The total of all fees paid to the CONTRACTOR for the provision of  Services as set forth in Exhibit A, including any authorized reimbursable expenses, shall not exceed the total sum of $ 585,829. The payments specified in this Exhibit B shall be the only payments made to Contractor unless the City approves a Supplemental Contract.

2.  Billable Rates. Contractor shall be paid for the performance of Services on an hourly rate, daily rate, flat fee, lump sum, or other basis, as set forth in Exhibit A or Attachment 1 to this Exhibit B
and any applicable special provisions included in the request for bids or proposals. If there is a conflict between Exhibit A or Exhibit B and the Special Provisions, Exhibit A or Exhibit B controls.

3.  CONTRACTOR’s  Reimbursable  Expenses.   “Reimbursable  Expenses”  are  limited  to  actual expenditures of CONTRACTOR for expenses that are necessary for the proper satisfaction of the Contract  and  are  only  payable  if  specifically  authorized  in  advance  in  writing  by  the  City.  No charges or markup will be allowed unless specified in the Contract, including charges for travel and transportation.

4.   Payments to CONTRACTOR. Contractor is responsible for supplying all documentation necessary to verify invoices to the City’s satisfaction.

A.  Payments  to  CONTRACTOR  shall  be  made  within  a  reasonable  time  after  receipt  of CONTRACTOR’s invoice, in proportion to services performed or as otherwise specified in Attachment  1  to  Exhibit  B.   CONTRACTOR  may  request  payment  on  a  monthly  basis.

CONTRACTOR shall be responsible for the cost of supplying all documentation necessary to verify the monthly billings to the satisfaction of CITY.

B.  Invoices must be submitted to either of the addresses specified below. (1) Email. Submit email invoices and any attachments to:
[email protected]

(2) Postal Mail. If emailing is not an option, mail to:

A/P Processing Center
City of Sacramento
915 I Street, Floor 4
Sacramento, CA 95814‐2608
C.   All invoices submitted by CONTRACTOR must contain the following information:

(1)  Job/Project Name
(2)  CITY’s current Purchase Order Number
(3)  CONTRACTOR’s Invoice Number
(4)  Date of Invoice Issuance
(5)  Work Order Number (if applicable)
(6)  CITY representative identified on the Purchase Order

Form Approved by City Attorney 9‐1‐2020  Exhibit B ‐ Page 2 (7)  CONTRACTOR’s remit address
(8)  Description of services billed under Invoice
(9)  Amount of Invoice (itemize all authorized Reimbursable Expenses) (10)  Total Billed to Date under Contract (if applicable)

D.  Items must be separated into Services and Reimbursable Expenses.  Invoices that do not conform to the format outlined above will be returned to CONTRACTOR for correction.

CITY  is  not  responsible  for  delays  in  payment  to  CONTRACTOR  resulting  from CONTRACTOR’s failure to comply with the invoice format described above.

5.  Additional Services.   Additional Services shall be provided only when a Supplemental Contract authorizing the Additional Services is approved in writing by the City in accordance with the City’s contract amendment procedures. The City reserves the right to perform any Additional Services with its own staff or to retain other contractors to perform the Additional Services.

6.  Accounting Records of CONTRACTOR.  During performance of this Contract and for a period of three years after completion of  performance, CONTRACTOR  shall  maintain  all  accounting  and financial  records  related  to  this  Contract,  in  accordance  with  generally  accepted  accounting practices,  including  records  of  Contractor’s  costs  for  performance  under  this  Contract  and records  of  Contractor’s  Reimbursable  Expenses.  Contractor  shall  keep  and  make  records available for inspection and audit by representatives of the CITY upon reasonable written notice.

7.  Tax Payments.  CONTRACTOR shall pay, when and as due, any and all taxes incurred as a result of CONTRACTOR’s compensation hereunder, including estimated taxes, and shall provide CITY with proof of the payment upon request.  CONTRACTOR hereby agrees to indemnify CITY for any
claims,  losses,  costs,  fees,  liabilities,  damages  or  injuries  suffered  by  CITY  arising  out  of CONTRACTOR’s breach of this section.

Client City of Sacramento Date
Project Name Trash Full Capture System Design Job Number Task 1 - Project Management Estimate By
Rate Units Quantity Cost
275.00 $ Hours -$
245.00 $ Hours 136 33,320$
225.00 $ Hours -$
215.00 $ Hours -$
205.00 $ Hours -$
195.00 $ Hours -$
185.00 $ Hours -$
170.00 $ Hours -$
220.00 $ Hours -$
320.00 $ Hours -$
135.00 $ Hours -$
115.00 $ Hours -$

0.625 $ Miles -$

30.00 $ Days -$
120.00 $ Nights -$

25.00 $ Days -$
+10% Total -$
-$
-$
-$
-$
$33,320
$0
Labor
$33,320$0
CAD Tech
Admin Assistant
Engineer I
Principal II
Principal I
Project Engineer I
Engineer II

COST ESTIMATE WORKSHEET
Subsistence, Overnight
Subsistence, Days
9/19/2022
8064
DMM
Project Engineer II
Senior Engineer II
2-Person Survey Crew
3-Person Survey Crew

TOTAL FOR TASK
Senior Engineer III
Outside
Expenses
Ground Travel
Transducer Rental
Materials
Overhead (10%)
Direct Expenses
Attachment 1 to Exhibit B
Client City of Sacramento Date
Project Name Trash Full Capture System Design Job Number Task 2.1 - Data Collection Estimate By
Rate Units Quantity Cost
275.00 $ Hours - $
245.00 $ Hours 2 490 $
225.00 $ Hours 24 5,400 $
215.00 $ Hours - $
205.00 $ Hours 10 2,050 $
195.00 $ Hours 6 1,170 $
185.00 $ Hours 10 1,850 $
170.00 $ Hours - $
220.00 $ Hours - $
320.00 $ Hours - $
135.00 $ Hours - $
115.00 $ Hours - $

0.625 $ Miles - $

30.00 $ Days - $
120.00 $ Nights - $

25.00 $ Days - $
+10% Total - $
-$
-$
-$
-$
10,960 $

COST ESTIMATE WORKSHEET
9/19/2022
8064
DMM
Labor
Principal II
$10,960
Principal I
Senior Engineer III
Senior Engineer II
Project Engineer II
Project Engineer I
Engineer II
Engineer I
2-Person Survey Crew
3-Person Survey Crew
CAD Tech
Admin Assistant
Direct Expenses
Ground Travel
$0
Subsistence, Days
Subsistence, Overnight
Transducer Rental
Materials

TOTAL FOR TASK
Outside
Expenses
$0
Overhead (10%)
Client City of Sacramento Date
Project Name Trash Full Capture System Design Job Number Task 2.2 – Desktop Utility Investigation Estimate By
Rate Units Quantity Cost
275.00 $ Hours - $
245.00 $ Hours 1 245 $
225.00 $ Hours 3 675 $
215.00 $ Hours - $
205.00 $ Hours 18 3,690 $
195.00 $ Hours 4 780 $
185.00 $ Hours 20 3,700 $
170.00 $ Hours - $
220.00 $ Hours - $
320.00 $ Hours - $
135.00 $ Hours - $
115.00 $ Hours - $

0.625 $ Miles - $

30.00 $ Days - $
120.00 $ Nights - $

25.00 $ Days - $
+10% Total - $
-$
-$
-$
-$
9,090 $ TOTAL FOR TASK
Outside
Expenses
$0
Overhead (10%)
$0
Subsistence, Days
Subsistence, Overnight
Transducer Rental
Materials
3-Person Survey Crew
CAD Tech
Admin Assistant
Direct Expenses
Ground Travel
Senior Engineer II
Project Engineer II
Project Engineer I
Engineer II
Engineer I
2-Person Survey Crew

COST ESTIMATE WORKSHEET
9/19/2022
8064
DMM
Labor
Principal II
$9,090
Principal I
Senior Engineer III
Client City of Sacramento Date
Project Name Trash Full Capture System Design Job Number Task 2.3 – Prelim Assess + Site Refinement Estimate By
Rate Units Quantity Cost
275.00 $ Hours - $
245.00 $ Hours 6 1,470 $
225.00 $ Hours 12 2,700 $
215.00 $ Hours - $
205.00 $ Hours 6 1,230 $
195.00 $ Hours 2 390 $
185.00 $ Hours 3 555 $
170.00 $ Hours - $
220.00 $ Hours - $
320.00 $ Hours - $
135.00 $ Hours - $
115.00 $ Hours - $

0.625 $ Miles - $

30.00 $ Days - $
120.00 $ Nights - $

25.00 $ Days - $
+10% Total - $
-$
-$
-$
-$
6,345 $

COST ESTIMATE WORKSHEET
9/19/2022
8064
DMM
Labor
Principal II
$6,345
Principal I
Senior Engineer III
Senior Engineer II
Project Engineer II
Project Engineer I
Engineer II
Engineer I
2-Person Survey Crew
3-Person Survey Crew
CAD Tech
Admin Assistant
Direct Expenses
Ground Travel
$0
Subsistence, Days
Subsistence, Overnight
Transducer Rental
Materials

TOTAL FOR TASK
Outside
Expenses
$0
Overhead (10%)
Client City of Sacramento Date
Project Name Trash Full Capture System Design Job Number Task 2.4 –Site Visit Estimate By
Rate Units Quantity Cost
275.00 $ Hours - $
245.00 $ Hours 4 980 $
225.00 $ Hours 8 1,800 $
215.00 $ Hours - $
205.00 $ Hours 4 820 $
195.00 $ Hours - $
185.00 $ Hours - $
170.00 $ Hours - $
220.00 $ Hours - $
320.00 $ Hours - $
135.00 $ Hours - $
115.00 $ Hours - $

0.625 $ Miles 60 38 $

30.00 $ Days - $
120.00 $ Nights - $

25.00 $ Days - $
+10% Total - $
1,075 $
-$
-$
108 $
4,820 $

COST ESTIMATE WORKSHEET
9/19/2022
8064
DMM
Labor
Principal II
$3,600
Principal I
Senior Engineer III
Senior Engineer II
Project Engineer II
Project Engineer I
Engineer II
Engineer I
2-Person Survey Crew
3-Person Survey Crew
CAD Tech
Admin Assistant
Direct Expenses
Ground Travel
$38
Subsistence, Days
Subsistence, Overnight
Transducer Rental
Materials

TOTAL FOR TASK
Outside
Expenses
J Calton Engineering (Electrical)
$1,183
Overhead (10%)
Client City of Sacramento Date
Project Name Trash Full Capture System Design Job Number Task 2.5 – Hydraulic Modeling Estimate By
Rate Units Quantity Cost
275.00 $ Hours - $
245.00 $ Hours 6 1,470 $
225.00 $ Hours 18 4,050 $
215.00 $ Hours - $
205.00 $ Hours 48 9,840 $
195.00 $ Hours - $
185.00 $ Hours 98 18,130 $
170.00 $ Hours - $
220.00 $ Hours - $
320.00 $ Hours - $
135.00 $ Hours - $
115.00 $ Hours - $

0.625 $ Miles - $

30.00 $ Days - $
120.00 $ Nights - $

25.00 $ Days - $
+10% Total - $
-$
-$
-$
-$
33,490 $

COST ESTIMATE WORKSHEET
9/19/2022
8064
DMM
Labor
Principal II
$33,490
Principal I
Senior Engineer III
Senior Engineer II
Project Engineer II
Project Engineer I
Engineer II
Engineer I
2-Person Survey Crew
3-Person Survey Crew
CAD Tech
Admin Assistant
Direct Expenses
Ground Travel
$0
Subsistence, Days
Subsistence, Overnight
Transducer Rental
Materials

TOTAL FOR TASK
Outside
Expenses
$0
Overhead (10%)
Client City of Sacramento Date
Project Name Trash Full Capture System Design Job Number Task 2.6 – Life-Cycle Cost Analysis Estimate By
Rate Units Quantity Cost
275.00 $ Hours - $
245.00 $ Hours 16 3,920 $
225.00 $ Hours - $
215.00 $ Hours 8 1,720 $
205.00 $ Hours 16 3,280 $
195.00 $ Hours - $
185.00 $ Hours - $
170.00 $ Hours - $
220.00 $ Hours - $
320.00 $ Hours - $
135.00 $ Hours - $
115.00 $ Hours - $

0.625 $ Miles - $

30.00 $ Days - $
120.00 $ Nights - $

25.00 $ Days - $
+10% Total - $
820 $
-$
-$
82 $
9,822 $

COST ESTIMATE WORKSHEET
9/19/2022
8064
DMM
Labor
Principal II
$8,920
Principal I
Senior Engineer III
Senior Engineer II
Project Engineer II
Project Engineer I
Engineer II
Engineer I
2-Person Survey Crew
3-Person Survey Crew
CAD Tech
Admin Assistant
Direct Expenses
Ground Travel
$0
Subsistence, Days
Subsistence, Overnight
Transducer Rental
Materials

TOTAL FOR TASK
Outside
Expenses
J Calton Engineering (Electrical)
$902
Overhead (10%)
Client City of Sacramento Date
Project Name Trash Full Capture System Design Job Number Task 2.7 – Preliminary Design Report Estimate By
Rate Units Quantity Cost
275.00 $ Hours - $
245.00 $ Hours 16 3,920 $
225.00 $ Hours 16 3,600 $
215.00 $ Hours - $
205.00 $ Hours 28 5,740 $
195.00 $ Hours - $
185.00 $ Hours 16 2,960 $
170.00 $ Hours - $
220.00 $ Hours - $
320.00 $ Hours - $
135.00 $ Hours - $
115.00 $ Hours 12 1,380 $

0.625 $ Miles - $

30.00 $ Days - $
120.00 $ Nights - $

25.00 $ Days - $
+10% Total - $
1,230 $
-$
-$
123 $
18,953 $

COST ESTIMATE WORKSHEET
9/19/2022
8064
DMM
Labor
Principal II
$17,600
Principal I
Senior Engineer III
Senior Engineer II
Project Engineer II
Project Engineer I
Engineer II
Engineer I
2-Person Survey Crew
3-Person Survey Crew
CAD Tech
Admin Assistant
Direct Expenses
Ground Travel
$0
Subsistence, Days
Subsistence, Overnight
Transducer Rental
Materials

TOTAL FOR TASK
Outside
Expenses
J Calton Engineering (Electrical)
$1,353
Overhead (10%)
Client City of Sacramento Date
Project Name Trash Full Capture System Design Job Number Task 3.1 - Preliminary Design Estimate By
Rate Units Quantity Cost
275.00 $ Hours - $
245.00 $ Hours 12 2,940 $
225.00 $ Hours - $
215.00 $ Hours 12 2,580 $
205.00 $ Hours 40 8,200 $
195.00 $ Hours - $
185.00 $ Hours - $
170.00 $ Hours 24 4,080 $
220.00 $ Hours - $
320.00 $ Hours - $
135.00 $ Hours - $
115.00 $ Hours - $

0.625 $ Miles - $

30.00 $ Days - $
120.00 $ Nights - $

25.00 $ Days - $
+10% Total - $
2,300 $
-$
-$
230 $
20,330 $

COST ESTIMATE WORKSHEET
9/19/2022
8064
DMM
Labor
Principal II
$17,800
Principal I
Senior Engineer III
Senior Engineer II
Project Engineer II
Project Engineer I
Engineer II
Engineer I
2-Person Survey Crew
3-Person Survey Crew
CAD Tech
Admin Assistant
Direct Expenses
Ground Travel
$0
Subsistence, Days
Subsistence, Overnight
Transducer Rental
Materials

TOTAL FOR TASK
Outside
Expenses
J Calton Engineering (Electrical)
$2,530
Overhead (10%)
Client City of Sacramento Date
Project Name Trash Full Capture System Design Job Number Task 3.2 - Geotechnical Investigation Estimate By
Rate Units Quantity Cost
275.00 $ Hours - $
245.00 $ Hours - $
225.00 $ Hours 12 2,700 $
215.00 $ Hours 14 3,010 $
205.00 $ Hours - $
195.00 $ Hours - $
185.00 $ Hours - $
170.00 $ Hours 100 17,000 $
220.00 $ Hours - $
320.00 $ Hours - $
135.00 $ Hours 8 1,080 $
115.00 $ Hours - $

0.625 $ Miles - $

30.00 $ Days - $
120.00 $ Nights - $

25.00 $ Days - $
+10% Total 1500 1,650 $
16,500 $
5,553 $
-$
2,205 $
49,698 $

COST ESTIMATE WORKSHEET
9/19/2022
8064
DMM
Labor
Principal II
$23,790
Principal I
Senior Engineer III
Senior Engineer II
Project Engineer II
Project Engineer I
Engineer II
Engineer I
2-Person Survey Crew
3-Person Survey Crew
CAD Tech
Admin Assistant
Direct Expenses
Ground Travel
$1,650
Subsistence, Days
Subsistence, Overnight
Transducer Rental
Materials

TOTAL FOR TASK
Outside
Expenses
Drilling Equipment
$24,258
Lab
Overhead (10%)
Client City of Sacramento Date
Project Name Trash Full Capture System Design Job Number Task 3.3 - Utility Coordination Estimate By
Rate Units Quantity Cost
275.00 $ Hours - $
245.00 $ Hours 2 490 $
225.00 $ Hours 4 900 $
215.00 $ Hours - $
205.00 $ Hours - $
195.00 $ Hours 16 3,120 $
185.00 $ Hours - $
170.00 $ Hours - $
220.00 $ Hours - $
320.00 $ Hours - $
135.00 $ Hours - $
115.00 $ Hours - $

0.625 $ Miles - $

30.00 $ Days - $
120.00 $ Nights - $

25.00 $ Days - $
+10% Total - $
-$
-$
-$
-$
4,510 $ TOTAL FOR TASK
Outside
Expenses
$0
Overhead (10%)
$0
Subsistence, Days
Subsistence, Overnight
Transducer Rental
Materials
3-Person Survey Crew
CAD Tech
Admin Assistant
Direct Expenses
Ground Travel
Senior Engineer II
Project Engineer II
Project Engineer I
Engineer II
Engineer I
2-Person Survey Crew

COST ESTIMATE WORKSHEET
9/19/2022
8064
DMM
Labor
Principal II
$4,510
Principal I
Senior Engineer III
Client City of Sacramento Date
Project Name Trash Full Capture System Design Job Number Task 4.1 - 65% Design Estimate By
Rate Units Quantity Cost
275.00 $ Hours - $
245.00 $ Hours 12 2,940 $
225.00 $ Hours - $
215.00 $ Hours 120 25,800 $
205.00 $ Hours - $
195.00 $ Hours 24 4,680 $
185.00 $ Hours 36 6,660 $
170.00 $ Hours 32 5,440 $
220.00 $ Hours - $
320.00 $ Hours - $
135.00 $ Hours - $
115.00 $ Hours - $

0.625 $ Miles - $

30.00 $ Days - $
120.00 $ Nights - $

25.00 $ Days - $
+10% Total - $
4,600 $
-$
-$
460 $
50,580 $

COST ESTIMATE WORKSHEET
9/19/2022
8064
DMM
Labor
Principal II
$45,520
Principal I
Senior Engineer III
Senior Engineer II
Project Engineer II
Project Engineer I
Engineer II
Engineer I
2-Person Survey Crew
3-Person Survey Crew
CAD Tech
Admin Assistant
Direct Expenses
Ground Travel
$0
Subsistence, Days
Subsistence, Overnight
Transducer Rental
Materials

TOTAL FOR TASK
Outside
Expenses
J Calton Engineering (Electrical)
$5,060
Overhead (10%)
Client City of Sacramento Date
Project Name Trash Full Capture System Design Job Number Task 4.2 - 90% Design Estimate By
Rate Units Quantity Cost
275.00 $ Hours 2 550 $
245.00 $ Hours 16 3,920 $
225.00 $ Hours - $
215.00 $ Hours 240 51,600 $
205.00 $ Hours - $
195.00 $ Hours 24 4,680 $
185.00 $ Hours 36 6,660 $
170.00 $ Hours 40 6,800 $
220.00 $ Hours - $
320.00 $ Hours - $
135.00 $ Hours - $
115.00 $ Hours - $

0.625 $ Miles - $

30.00 $ Days - $
120.00 $ Nights - $

25.00 $ Days - $
+10% Total - $
19,230 $
-$
-$
1,923 $
95,363 $

COST ESTIMATE WORKSHEET
9/19/2022
8064
DMM
Labor
Principal II
$74,210
Principal I
Senior Engineer III
Senior Engineer II
Project Engineer II
Project Engineer I
Engineer II
Engineer I
2-Person Survey Crew
3-Person Survey Crew
CAD Tech
Admin Assistant
Direct Expenses
Ground Travel
$0
Subsistence, Days
Subsistence, Overnight
Transducer Rental
Materials

TOTAL FOR TASK
Outside
Expenses
J Calton Engineering (Electrical)
$21,153
Overhead (10%)
Client City of Sacramento Date
Project Name Trash Full Capture System Design Job Number Task 4.3 - Final Design Estimate By
Rate Units Quantity Cost
275.00 $ Hours 2 550 $
245.00 $ Hours 16 3,920 $
225.00 $ Hours - $
215.00 $ Hours 72 15,480 $
205.00 $ Hours - $
195.00 $ Hours 16 3,120 $
185.00 $ Hours 24 4,440 $
170.00 $ Hours 32 5,440 $
220.00 $ Hours - $
320.00 $ Hours - $
135.00 $ Hours - $
115.00 $ Hours - $

0.625 $ Miles - $

30.00 $ Days - $
120.00 $ Nights - $

25.00 $ Days - $
+10% Total - $
12,080 $
-$
-$
1,208 $
46,238 $

COST ESTIMATE WORKSHEET
9/19/2022
8064
DMM
Labor
Principal II
$32,950
Principal I
Senior Engineer III
Senior Engineer II
Project Engineer II
Project Engineer I
Engineer II
Engineer I
2-Person Survey Crew
3-Person Survey Crew
CAD Tech
Admin Assistant
Direct Expenses
Ground Travel
$0
Subsistence, Days
Subsistence, Overnight
Transducer Rental
Materials

TOTAL FOR TASK
Outside
Expenses
$13,288
Overhead (10%)
J Calton Engineering (Electrical)
Client City of Sacramento Date
Project Name Trash Full Capture System Design Job Number Task 5.1 - Environmental Project Management Estimate By Rate Units Quantity Cost
275.00 $ Hours - $
245.00 $ Hours - $
225.00 $ Hours - $
215.00 $ Hours - $
205.00 $ Hours 24 4,920 $
195.00 $ Hours - $
185.00 $ Hours 16 2,960 $
170.00 $ Hours - $
220.00 $ Hours - $
320.00 $ Hours - $
135.00 $ Hours - $
115.00 $ Hours - $

0.625 $ Miles - $

30.00 $ Days - $
120.00 $ Nights - $

25.00 $ Days - $
+10% Total - $
-$
-$
-$
-$
7,880 $

COST ESTIMATE WORKSHEET
9/19/2022
8064
DMM
Labor
Principal II
$7,880
Principal I
Senior Engineer III
Senior Engineer II
Project Engineer II
Project Engineer I
Engineer II
Engineer I
2-Person Survey Crew
3-Person Survey Crew
CAD Tech
Admin Assistant
Direct Expenses
Ground Travel
$0
Subsistence, Days
Subsistence, Overnight
Transducer Rental
Materials

TOTAL FOR TASK
Outside
Expenses
$0
Overhead (10%)
Client City of Sacramento Date
Project Name Trash Full Capture System Design Job Number Task 5.2.1 - Env Cultural Resources Inv Report Estimate By Rate Units Quantity Cost
275.00 $ Hours - $
245.00 $ Hours - $
225.00 $ Hours - $
215.00 $ Hours - $
205.00 $ Hours 8 1,640 $
195.00 $ Hours - $
185.00 $ Hours 10 1,850 $
170.00 $ Hours - $
220.00 $ Hours - $
320.00 $ Hours - $
135.00 $ Hours - $
115.00 $ Hours - $

0.625 $ Miles - $

30.00 $ Days - $
120.00 $ Nights - $

25.00 $ Days - $
+10% Total - $
10,450 $
-$
-$
1,045 $
14,985 $

COST ESTIMATE WORKSHEET
9/19/2022
8064
DMM
Labor
Principal II
$3,490
Principal I
Senior Engineer III
Senior Engineer II
Project Engineer II
Project Engineer I
Engineer II
Engineer I
2-Person Survey Crew
3-Person Survey Crew
CAD Tech
Admin Assistant
Direct Expenses
Ground Travel
$0
Subsistence, Days
Subsistence, Overnight
Transducer Rental
Materials

TOTAL FOR TASK
Outside
Expenses
Subconsultant
$11,495
Overhead (10%)
Client City of Sacramento Date
Project Name Trash Full Capture System Design Job Number Task 5.2.2 - Env Biological Resources Report Estimate By Rate Units Quantity Cost
275.00 $ Hours - $
245.00 $ Hours - $
225.00 $ Hours - $
215.00 $ Hours - $
205.00 $ Hours 10 2,050 $
195.00 $ Hours - $
185.00 $ Hours 68 12,580 $
170.00 $ Hours - $
220.00 $ Hours - $
320.00 $ Hours - $
135.00 $ Hours - $
115.00 $ Hours - $

0.625 $ Miles - $

30.00 $ Days - $
120.00 $ Nights - $

25.00 $ Days - $
+10% Total - $
-$
-$
-$
-$
14,630 $

COST ESTIMATE WORKSHEET
9/19/2022
8064
DMM
Labor
Principal II
$14,630
Principal I
Senior Engineer III
Senior Engineer II
Project Engineer II
Project Engineer I
Engineer II
Engineer I
2-Person Survey Crew
3-Person Survey Crew
CAD Tech
Admin Assistant
Direct Expenses
Ground Travel
$0
Subsistence, Days
Subsistence, Overnight
Transducer Rental
Materials

TOTAL FOR TASK
Outside
Expenses
$0
Overhead (10%)
Client City of Sacramento Date
Project Name Trash Full Capture System Design Job Number Task 5.3.1 - Draft IS/MND Estimate By
Rate Units Quantity Cost
275.00 $ Hours - $
245.00 $ Hours - $
225.00 $ Hours - $
215.00 $ Hours - $
205.00 $ Hours 16 3,280 $
195.00 $ Hours - $
185.00 $ Hours 88 16,280 $
170.00 $ Hours - $
220.00 $ Hours - $
320.00 $ Hours - $
135.00 $ Hours - $
115.00 $ Hours - $

0.625 $ Miles - $

30.00 $ Days - $
120.00 $ Nights - $

25.00 $ Days - $
+10% Total - $
-$
-$
-$
-$
19,560 $

COST ESTIMATE WORKSHEET
9/19/2022
8064
DMM
Labor
Principal II
$19,560
Principal I
Senior Engineer III
Senior Engineer II
Project Engineer II
Project Engineer I
Engineer II
Engineer I
2-Person Survey Crew
3-Person Survey Crew
CAD Tech
Admin Assistant
Direct Expenses
Ground Travel
$0
Subsistence, Days
Subsistence, Overnight
Transducer Rental
Materials

TOTAL FOR TASK
Outside
Expenses
$0
Overhead (10%)
Client City of Sacramento Date
Project Name Trash Full Capture System Design Job Number Task 5.3.2 - Notice of Avail and IS/MND Circulation Estimate By Rate Units Quantity Cost
275.00 $ Hours - $
245.00 $ Hours - $
225.00 $ Hours - $
215.00 $ Hours - $
205.00 $ Hours 8 1,640 $
195.00 $ Hours - $
185.00 $ Hours 28 5,180 $
170.00 $ Hours - $
220.00 $ Hours - $
320.00 $ Hours - $
135.00 $ Hours - $
115.00 $ Hours - $

0.625 $ Miles - $

30.00 $ Days - $
120.00 $ Nights - $

25.00 $ Days - $
+10% Total - $
-$
-$
-$
-$
6,820 $

COST ESTIMATE WORKSHEET
9/19/2022
8064
DMM
Labor
Principal II
$6,820
Principal I
Senior Engineer III
Senior Engineer II
Project Engineer II
Project Engineer I
Engineer II
Engineer I
2-Person Survey Crew
3-Person Survey Crew
CAD Tech
Admin Assistant
Direct Expenses
Ground Travel
$0
Subsistence, Days
Subsistence, Overnight
Transducer Rental
Materials

TOTAL FOR TASK
Outside
Expenses
$0
Overhead (10%)
Client City of Sacramento Date
Project Name Trash Full Capture System Design Job Number Task 5.3.3 - Environmental Document Workshops Estimate By Rate Units Quantity Cost
275.00 $ Hours - $
245.00 $ Hours - $
225.00 $ Hours - $
215.00 $ Hours - $
205.00 $ Hours 30 6,150 $
195.00 $ Hours - $
185.00 $ Hours 68 12,580 $
170.00 $ Hours - $
220.00 $ Hours - $
320.00 $ Hours - $
135.00 $ Hours - $
115.00 $ Hours - $

0.625 $ Miles - $

30.00 $ Days - $
120.00 $ Nights - $

25.00 $ Days - $
+10% Total - $
-$
-$
-$
-$
18,730 $

COST ESTIMATE WORKSHEET
9/19/2022
8064
DMM
Labor
Principal II
$18,730
Principal I
Senior Engineer III
Senior Engineer II
Project Engineer II
Project Engineer I
Engineer II
Engineer I
2-Person Survey Crew
3-Person Survey Crew
CAD Tech
Admin Assistant
Direct Expenses
Ground Travel
$0
Subsistence, Days
Subsistence, Overnight
Transducer Rental
Materials

TOTAL FOR TASK
Outside
Expenses
$0
Overhead (10%)
Client City of Sacramento Date
Project Name Trash Full Capture System Design Job Number Task 5.3.4 - Resp to Pub Comment, Final IS/MND Estimate By Rate Units Quantity Cost
275.00 $ Hours - $
245.00 $ Hours - $
225.00 $ Hours - $
215.00 $ Hours - $
205.00 $ Hours 12 2,460 $
195.00 $ Hours - $
185.00 $ Hours 34 6,290 $
170.00 $ Hours - $
220.00 $ Hours - $
320.00 $ Hours - $
135.00 $ Hours - $
115.00 $ Hours - $

0.625 $ Miles - $

30.00 $ Days - $
120.00 $ Nights - $

25.00 $ Days - $
+10% Total - $
-$
-$
-$
-$
8,750 $

COST ESTIMATE WORKSHEET
9/19/2022
8064
DMM
Labor
Principal II
$8,750
Principal I
Senior Engineer III
Senior Engineer II
Project Engineer II
Project Engineer I
Engineer II
Engineer I
2-Person Survey Crew
3-Person Survey Crew
CAD Tech
Admin Assistant
Direct Expenses
Ground Travel
$0
Subsistence, Days
Subsistence, Overnight
Transducer Rental
Materials

TOTAL FOR TASK
Outside
Expenses
$0
Overhead (10%)
Client City of Sacramento Date
Project Name Trash Full Capture System Design Job Number Task 5.3.5 - MMRP & NOD Estimate By
Rate Units Quantity Cost
275.00 $ Hours - $
245.00 $ Hours - $
225.00 $ Hours - $
215.00 $ Hours - $
205.00 $ Hours 10 2,050 $
195.00 $ Hours - $
185.00 $ Hours 16 2,960 $
170.00 $ Hours - $
220.00 $ Hours - $
320.00 $ Hours - $
135.00 $ Hours - $
115.00 $ Hours - $

0.625 $ Miles - $

30.00 $ Days - $
120.00 $ Nights - $

25.00 $ Days - $
+10% Total - $
-$
-$
-$
-$
5,010 $

COST ESTIMATE WORKSHEET
9/19/2022
8064
DMM
Labor
Principal II
$5,010
Principal I
Senior Engineer III
Senior Engineer II
Project Engineer II
Project Engineer I
Engineer II
Engineer I
2-Person Survey Crew
3-Person Survey Crew
CAD Tech
Admin Assistant
Direct Expenses
Ground Travel
$0
Subsistence, Days
Subsistence, Overnight
Transducer Rental
Materials

TOTAL FOR TASK
Outside
Expenses
$0
Overhead (10%)
Client City of Sacramento Date
Project Name Trash Full Capture System Design Job Number Task 5.4.1 - Section 404 Nationwide Permit Estimate By
Rate Units Quantity Cost
275.00 $ Hours - $
245.00 $ Hours - $
225.00 $ Hours - $
215.00 $ Hours - $
205.00 $ Hours 20 4,100 $
195.00 $ Hours - $
185.00 $ Hours 86 15,910 $
170.00 $ Hours - $
220.00 $ Hours - $
320.00 $ Hours - $
135.00 $ Hours - $
115.00 $ Hours - $

0.625 $ Miles - $

30.00 $ Days - $
120.00 $ Nights - $

25.00 $ Days - $
+10% Total - $
-$
-$
-$
-$
20,010 $

COST ESTIMATE WORKSHEET
9/19/2022
8064
DMM
Labor
Principal II
$20,010
Principal I
Senior Engineer III
Senior Engineer II
Project Engineer II
Project Engineer I
Engineer II
Engineer I
2-Person Survey Crew
3-Person Survey Crew
CAD Tech
Admin Assistant
Direct Expenses
Ground Travel
$0
Subsistence, Days
Subsistence, Overnight
Transducer Rental
Materials

TOTAL FOR TASK
Outside
Expenses
$0
Overhead (10%)
Client City of Sacramento Date
Project Name Trash Full Capture System Design Job Number Task 5.4.2 - Section 401 Water Quality Certification Estimate By Rate Units Quantity Cost
275.00 $ Hours - $
245.00 $ Hours - $
225.00 $ Hours - $
215.00 $ Hours - $
205.00 $ Hours 20 4,100 $
195.00 $ Hours - $
185.00 $ Hours 86 15,910 $
170.00 $ Hours - $
220.00 $ Hours - $
320.00 $ Hours - $
135.00 $ Hours - $
115.00 $ Hours - $

0.625 $ Miles - $

30.00 $ Days - $
120.00 $ Nights - $

25.00 $ Days - $
+10% Total - $
-$
-$
-$
-$
20,010 $

COST ESTIMATE WORKSHEET
9/19/2022
8064
DMM
Labor
Principal II
$20,010
Principal I
Senior Engineer III
Senior Engineer II
Project Engineer II
Project Engineer I
Engineer II
Engineer I
2-Person Survey Crew
3-Person Survey Crew
CAD Tech
Admin Assistant
Direct Expenses
Ground Travel
$0
Subsistence, Days
Subsistence, Overnight
Transducer Rental
Materials

TOTAL FOR TASK
Outside
Expenses
$0
Overhead (10%)
Client City of Sacramento Date
Project Name Trash Full Capture System Design Job Number Task 5.4.3 - CDFW Streambed Alt Agrmnt/Tree Survey Estimate By Rate Units Quantity Cost
275.00 $ Hours - $
245.00 $ Hours - $
225.00 $ Hours - $
215.00 $ Hours - $
205.00 $ Hours 20 4,100 $
195.00 $ Hours - $
185.00 $ Hours 86 15,910 $
170.00 $ Hours - $
220.00 $ Hours - $
320.00 $ Hours - $
135.00 $ Hours - $
115.00 $ Hours - $

0.625 $ Miles - $

30.00 $ Days - $
120.00 $ Nights - $

25.00 $ Days - $
+10% Total - $
-$
-$
-$
-$
20,010 $

COST ESTIMATE WORKSHEET
9/19/2022
8064
DMM
Labor
Principal II
$20,010
Principal I
Senior Engineer III
Senior Engineer II
Project Engineer II
Project Engineer I
Engineer II
Engineer I
2-Person Survey Crew
3-Person Survey Crew
CAD Tech
Admin Assistant
Direct Expenses
Ground Travel
$0
Subsistence, Days
Subsistence, Overnight
Transducer Rental
Materials

TOTAL FOR TASK
Outside
Expenses
$0
Overhead (10%)
Client City of Sacramento Date
Project Name Trash Full Capture System Design Job Number Task 6.1 - Furnish and Install Depth Gage Estimate By
Rate Units Quantity Cost
275.00 $ Hours - $
245.00 $ Hours 10 2,450 $
225.00 $ Hours - $
215.00 $ Hours 12 2,580 $
205.00 $ Hours - $
195.00 $ Hours - $
185.00 $ Hours - $
170.00 $ Hours - $
220.00 $ Hours - $
320.00 $ Hours - $
135.00 $ Hours - $
115.00 $ Hours - $

0.625 $ Miles - $

30.00 $ Days - $
120.00 $ Nights - $

25.00 $ Days - $
+10% Total 4000 4,400 $
1,500 $
-$
-$
150 $
11,080 $ TOTAL FOR TASK
Outside
Expenses
Traffic Control Sub
$1,650
Overhead (10%)
$4,400
Subsistence, Days
Subsistence, Overnight
Transducer Rental
Materials
3-Person Survey Crew
CAD Tech
Admin Assistant
Direct Expenses
Ground Travel
Senior Engineer II
Project Engineer II
Project Engineer I
Engineer II
Engineer I
2-Person Survey Crew

COST ESTIMATE WORKSHEET
9/19/2022
8064
DMM
Labor
Principal II
$5,030
Principal I
Senior Engineer III
Client City of Sacramento Date
Project Name Trash Full Capture System Design Job Number Task 6.2 - Collect & Process Rain Gage Data Estimate By Rate Units Quantity Cost
275.00 $ Hours - $
245.00 $ Hours 8 1,960 $
225.00 $ Hours - $
215.00 $ Hours - $
205.00 $ Hours 24 4,920 $
195.00 $ Hours - $
185.00 $ Hours - $
170.00 $ Hours - $
220.00 $ Hours - $
320.00 $ Hours - $
135.00 $ Hours - $
115.00 $ Hours - $

0.625 $ Miles - $

30.00 $ Days - $
120.00 $ Nights - $

25.00 $ Days - $
+10% Total - $
-$
-$
-$
-$
6,880 $ TOTAL FOR TASK
Outside
Expenses
$0
Overhead (10%)
$0
Subsistence, Days
Subsistence, Overnight
Transducer Rental
Materials
3-Person Survey Crew
CAD Tech
Admin Assistant
Direct Expenses
Ground Travel
Senior Engineer II
Project Engineer II
Project Engineer I
Engineer II
Engineer I
2-Person Survey Crew

COST ESTIMATE WORKSHEET
9/19/2022
8064
DMM
Labor
Principal II
$6,880
Principal I
Senior Engineer III
Client City of Sacramento Date
Project Name Trash Full Capture System Design Job Number Task 6.3.1 - Hydraulic Analysis Calibrate Pre Model Estimate By Rate Units Quantity Cost
275.00 $ Hours - $
245.00 $ Hours 6 1,470 $
225.00 $ Hours - $
215.00 $ Hours - $
205.00 $ Hours - $
195.00 $ Hours - $
185.00 $ Hours 12 2,220 $
170.00 $ Hours - $
220.00 $ Hours - $
320.00 $ Hours - $
135.00 $ Hours - $
115.00 $ Hours - $

0.625 $ Miles - $

30.00 $ Days - $
120.00 $ Nights - $

25.00 $ Days - $
+10% Total - $
-$
-$
-$
-$
3,690 $ TOTAL FOR TASK
Outside
Expenses
$0
Overhead (10%)
$0
Subsistence, Days
Subsistence, Overnight
Transducer Rental
Materials
3-Person Survey Crew
CAD Tech
Admin Assistant
Direct Expenses
Ground Travel
Senior Engineer II
Project Engineer II
Project Engineer I
Engineer II
Engineer I
2-Person Survey Crew

COST ESTIMATE WORKSHEET
9/19/2022
8064
DMM
Labor
Principal II
$3,690
Principal I
Senior Engineer III
Client City of Sacramento Date
Project Name Trash Full Capture System Design Job Number Task 6.3.2 - Hydraulic Analysis Calibrate Post Model Estimate By Rate Units Quantity Cost
275.00 $ Hours - $
245.00 $ Hours 6 1,470 $
225.00 $ Hours - $
215.00 $ Hours - $
205.00 $ Hours - $
195.00 $ Hours - $
185.00 $ Hours 12 2,220 $
170.00 $ Hours - $
220.00 $ Hours - $
320.00 $ Hours - $
135.00 $ Hours - $
115.00 $ Hours - $

0.625 $ Miles - $

30.00 $ Days - $
120.00 $ Nights - $

25.00 $ Days - $
+10% Total - $
-$
-$
-$
-$
3,690 $ TOTAL FOR TASK
Outside
Expenses
$0
Overhead (10%)
$0
Subsistence, Days
Subsistence, Overnight
Transducer Rental
Materials
3-Person Survey Crew
CAD Tech
Admin Assistant
Direct Expenses
Ground Travel
Senior Engineer II
Project Engineer II
Project Engineer I
Engineer II
Engineer I
2-Person Survey Crew

COST ESTIMATE WORKSHEET
9/19/2022
8064
DMM
Labor
Principal II
$3,690
Principal I
Senior Engineer III
Client City of Sacramento Date
Project Name Trash Full Capture System Design Job Number Task 6.3.3 - Hydraulic Analysis Evaluate Impact Estimate By Rate Units Quantity Cost
275.00 $ Hours - $
245.00 $ Hours 4 980 $
225.00 $ Hours - $
215.00 $ Hours - $
205.00 $ Hours - $
195.00 $ Hours - $
185.00 $ Hours 7 1,295 $
170.00 $ Hours - $
220.00 $ Hours - $
320.00 $ Hours - $
135.00 $ Hours - $
115.00 $ Hours - $

0.625 $ Miles - $

30.00 $ Days - $
120.00 $ Nights - $

25.00 $ Days - $
+10% Total - $
-$
-$
-$
-$
2,275 $ TOTAL FOR TASK
Outside
Expenses
$0
Overhead (10%)
$0
Subsistence, Days
Subsistence, Overnight
Transducer Rental
Materials
3-Person Survey Crew
CAD Tech
Admin Assistant
Direct Expenses
Ground Travel
Senior Engineer II
Project Engineer II
Project Engineer I
Engineer II
Engineer I
2-Person Survey Crew

COST ESTIMATE WORKSHEET
9/19/2022
8064
DMM
Labor
Principal II
$2,275
Principal I
Senior Engineer III
Client City of Sacramento Date
Project Name Trash Full Capture System Design Job Number Task 6.4 - Depth Gage Documentation Estimate By
Rate Units Quantity Cost
275.00 $ Hours 4 1,100 $
245.00 $ Hours 16 3,920 $
225.00 $ Hours - $
215.00 $ Hours - $
205.00 $ Hours 16 3,280 $
195.00 $ Hours - $
185.00 $ Hours - $
170.00 $ Hours - $
220.00 $ Hours - $
320.00 $ Hours - $
135.00 $ Hours - $
115.00 $ Hours - $

0.625 $ Miles - $

30.00 $ Days - $
120.00 $ Nights - $

25.00 $ Days - $
+10% Total - $
-$
-$
-$
-$
8,300 $ TOTAL FOR TASK
Outside
Expenses
$0
Overhead (10%)
$0
Subsistence, Days
Subsistence, Overnight
Transducer Rental
Materials
3-Person Survey Crew
CAD Tech
Admin Assistant
Direct Expenses
Ground Travel
Senior Engineer II
Project Engineer II
Project Engineer I
Engineer II
Engineer I
2-Person Survey Crew

COST ESTIMATE WORKSHEET
9/19/2022
8064
DMM
Labor
Principal II
$8,300
Principal I
Senior Engineer III
Client City of Sacramento Date
Project Name Trash Full Capture System Design Job Number Estimate By
Labor Direct Expenses
Outside
Expenses
$33,320 $0 $0 $33,320
$10,960 $0 $0 $10,960
$9,090 $0 $0 $9,090
$6,345 $0 $0 $6,345
$3,600 $38 $1,183 $4,820
$33,490 $0 $0 $33,490
$8,920 $0 $902 $9,822
$17,600 $0 $1,353 $18,953
$17,800 $0 $2,530 $20,330
$23,790 $1,650 $24,258 $49,698
$4,510 $0 $0 $4,510
$45,520 $0 $5,060 $50,580
$74,210 $0 $21,153 $95,363
$32,950 $0 $13,288 $46,238
$7,880 $0 $0 $7,880
$3,490 $0 $11,495 $14,985
$14,630 $0 $0 $14,630
$19,560 $0 $0 $19,560
$6,820 $0 $0 $6,820
$18,730 $0 $0 $18,730
$8,750 $0 $0 $8,750
$5,010 $0 $0 $5,010
$20,010 $0 $0 $20,010
$20,010 $0 $0 $20,010
$20,010 $0 $0 $20,010
$5,030 $4,400 $1,650 $11,080
$6,880 $0 $0 $6,880
$3,690 $0 $0 $3,690
$3,690 $0 $0 $3,690
$2,275 $0 $0 $2,275
$8,300 $0 $0 $8,300
$467,005 $1,688 $81,222 $549,914
$496,870 $6,088 $82,872 $585,829
- Optional tasks.

TOTAL w/Optional Tasks 6.1 - 6.4

5.4.3 - CDFW Streambed Alt Agrmnt/Tree Survey

6.4 - Depth Gage Documentation
TOTAL Tasks 1 - 5.4.3
9/19/2022

3.2 - Geotechnical Investigation

4.1 - 65% Design

6.1 - Furnish and Install Depth Gage

6.2 - Collect & Process Rain Gage Data

3.3 - Utility Coordination

2.3 – Prelim Assess + Site Refinement

2.4 –Site Visit

2.5 – Hydraulic Modeling

SUMMARY OF COSTS BY TASK
8064
DMM
Tasks
1 - Project Management

2.2 – Desktop Utility Investigation
Total
for Task

2.1 - Data Collection

3.1 - Preliminary Design

4.2 - 90% Design

2.6 – Life-Cycle Cost Analysis

2.7 – Preliminary Design Report

4.3 - Final Design

5.1 - Environmental Project Management

5.2.1 - Env Cultural Resources Inv Report

5.2.2 - Env Biological Resources Report

5.3.1 - Draft IS/MND

6.3.1 - Hydraulic Analysis Calibrate Pre Model

6.3.2 - Hydraulic Analysis Calibrate Post Model

6.3.3 - Hydraulic Analysis Evaluate Impact

5.3.4 - Resp to Pub Comment, Final IS/MND

5.3.2 - Notice of Avail and IS/MND Circulation

5.3.3 - Environmental Document Workshops

5.3.5 - MMRP & NOD

5.4.1 - Section 404 Nationwide Permit

5.4.2 - Section 401 Water Quality Certification

CLASSIFICATION STANDARD RATE
Principal Engineer/Geologist/Surveyor/Planner/GIS/LA* II $275 Principal Engineer/Geologist/Surveyor/Planner/GIS/LA* I $245 Senior Engineer/Geologist/Surveyor/Planner/GIS/LA* II $225 Senior Engineer/Geologist/Surveyor/Planner/GIS/LA* I $215 Project Engineer/Geologist/Surveyor/Planner/GIS/LA* II $205 Project Engineer/Geologist/Surveyor/Planner/GIS/LA* I $195 Engineer/Geologist/Surveyor/Planner/GIS/LA* II $185
Engineer/Geologist/Surveyor/Planner/GIS/LA* I $170
Assistant Engineer/Geologist/Surveyor/Planner/GIS/LA* $135 Designer $90
Senior CAD Technician/Graphics Designer II $170
Senior CAD Technician/Graphics Designer I $150
CAD Technician/Graphics Designer $135
Project Coordinator $150
Administrative Assistant $115
1 Person Survey Crew $220
2 Person Survey Crew $320
3 Person Survey Crew $410
Consultants, Outside Services, Materials & Direct Charges Cost Plus 10% *LA = Landscape Architect.

Fee Schedule subject to change January 1, 2023.

WOOD RODGERS, INC.

FEE SCHEDULE
Effective January 1, 2022
Blueprints, reproduction, and travel expenses will be charged at vendor invoice.

Auto mileage will be charged at the IRS standard rate, currently 62.5 cents per mile.

Form Approved by City Attorney 9‐1‐2020  Exhibit C ‐ Page 1 EXHIBIT C

INSURANCE

1.   Insurance Requirements. During the entire term of this Contract, Contractor shall maintain the insurance coverage  described in the Insurance Terms below. Full compensation for all premiums that Contractor is required to pay for the insurance  coverage described herein shall be included in the compensation specified under this  Contract. No additional compensation will be provided for Contractor's insurance  premiums. Any available insurance proceeds in excess of the specified minimum limits  and coverages shall be available to the City.

Contractor's liability to the City is not in any way limited to or affected by the amount of insurance coverage required or carried by the Contractor in connection with this  Contract.

2.   General Liability Minimum Scope and Limits of Insurance Coverage. Commercial General Liability Insurance is required providing coverage at least as broad  as ISO CGL Form 00 01 on an occurrence basis for bodily injury, including death, of  one or more persons, property damage, and personal injury, arising out of activities  performed by or on behalf of the Contractor and subcontractors, products and  completed operations of Contractor and subcontractors, and premises owned, leased,  or used by Contractor and subcontractors, with limits of not less than one million dollars  ($1,000,000) per occurrence. The policy shall provide contractual liability and products  and completed operations coverage for the term of the policy.

The City, its officials, employees and volunteers shall be covered by policy terms or endorsement as additional insureds as respects general liability arising out of: activities performed by or on behalf of Contractor and subcontractors; products and completed operations of Contractor and subcontractors; and premises owned, leased, or used by Contractor and subcontractors.

3.  Automobile Liability Minimum Scope and Limits of Insurance Coverage. (Check the applicable provision.)

_X_   Automobile Liability Insurance is required providing coverage at least as broad as ISO
Form CA 00 01 for bodily injury, including death, of one or more persons, property damage and personal injury, with limits of not less than one million dollars ($1,000,000) per occurrence. The policy shall provide coverage for owned, non‐owned and/or hired autos as appropriate to the operations of the Contractor.

The City, its officials, employees and volunteers shall be covered by policy terms or endorsement as additional insureds as respects auto liability.

___  No  automobile  liability  insurance  is  required,  and  by  signing  this  Contract,  Contractor certifies as follows:

“Contractor certifies that a motor vehicle will not be used in the performance of any work or services under this agreement. If, however, Contractor does transport items under this Contract, or this Contract is amended to require any employees of Contractor to use a

Form Approved by City Attorney 9‐1‐2020  Exhibit C ‐ Page 2 vehicle  to  perform  services  under  the  Contract,  Contractor  understands  that  it  must maintain and provide evidence of Automobile Liability Insurance providing coverage at least as broad as ISO Form CA 00 01 for bodily injury, including death, of one or more persons, property damage and personal injury, with limits of not less than one million dollars ($1,000,000) per occurrence. The policy shall provide coverage for owned, non‐ owned and/or hired autos as appropriate to the operations of the Contractor.”

4.  Excess  Insurance.   The  minimum  limits  of  insurance  required  above  may  be  satisfied  by  a combination of  primary and umbrella or excess insurance coverage, provided that any umbrella or  excess insurance contains, or is endorsed to contain, a provision that it will apply on a  primary basis  for  the  benefit  of  the  City,  and  any  insurance  or  self‐insurance  maintained  by  City,  its officials, employees, or volunteers will be in excess of Contractor's umbrella  or excess coverage and will not contribute to it.

5.  Workers’ Compensation Minimum Scope and Limits of Insurance Coverage. (Check the applicable provision.)

_X_   Workers’ Compensation Insurance is required with statutory limits and Employers' Liability Insurance with limits of not less than one million dollars ($1,000,000). The Workers' Compensation policy shall include a waiver of subrogation in favor of the City.

___   No work or services will be performed on or at CITY facilities or CITY Property, therefore a Workers’ Compensation waiver of subrogation in favor of the CITY is not required.

___   No Workers’ Compensation insurance is required, and by signing this Contract, Contractor certifies as follows:

“Contractor  certifies  that  its  business  has  no  employees,  and  that  it  does  not  employ anyone,  and  is  therefore  exempt  from  the  legal  requirements  to  provide  Workers' Compensation insurance. If, however, Contractor hires any employee during the term of this Contract, Contractor understands that Workers’ Compensation with statutory limits and  Employer’s  Liability  Insurance  with  a  limit  of  not  less  than  one  million  dollars ($1,000,000)  is  required.  The  Workers’  Compensation  policy  will  include  a  waiver  of subrogation in favor of the City.”

6.   Professional Liability Minimum Scope and Limits of Insurance Coverage. Professional Liability Insurance providing coverage on a claims‐made basis for errors and omissions, or malpractice with limits of not less than one million dollars ($1,000,000):

Is __X___   Is not _____ [check one] required for this Agreement.

If required, such coverage must be continued for at least 3 year(s) following the completion of all Services under this Contract. The retroactive date must be prior to the date this Contract is approved or any Services are performed.

Form Approved by City Attorney 9‐1‐2020  Exhibit C ‐ Page 3

7.   Other Insurance Provisions. The policies must contain, or be endorsed to contain, the following provisions:

A. Contractor's insurance coverage, including excess insurance, shall be  primary insurance as respects the City, its officials, employees and  volunteers. Any insurance or self‐insurance maintained by the City, its  officials, employees or volunteers will be in excess of Contractor's  insurance and will not contribute with it.

B. Any failure to comply with reporting provisions of the policies will not affect  coverage provided to the City, its officials, employees or volunteers.

C. Coverage shall state that Contractor's insurance applies separately to  each insured against whom claim is made or suit is brought, except with  respect to the limits of the insurer's liability.

D. Contractor shall provide the City with 30 days written notice of cancellation or material change in the policy language or terms.

8.  Acceptability of Insurance. Insurance must be placed with insurers with a Bests' rating of not less than A:VI. Self‐insured retentions, policy terms or other variations that do not comply with the  requirements of this Exhibit C must be declared to and approved by the City in  writing before execution of this Contract.

9.   Verification of Coverage.

A.  Contractor shall furnish City with certificates and required endorsements evidencing  the insurance required. Certificates of insurance must be signed by an authorized representative of the insurance carrier. Copies of policies shall be delivered to the City Representative on demand.

B. Contractor shall send all insurance certificates and endorsements, including policy renewals, during the term of this Contract directly to:

City of Sacramento
c/o Exigis LLC
PO Box 947
Murrieta, CA 92564

C. Certificate Holder must be listed as:

City of Sacramento
c/o Exigis LLC
PO Box 947
Murrieta, CA 92564

D. The City may withdraw its offer of Contract or cancel this Contract if the certificates  of insurance and endorsements required have not been provided before execution of  this Contract. The City may withhold payments to Contractor and/or cancel the Contract  if the insurance is canceled or Contractor otherwise ceases to be insured as required  herein.

Form Approved by City Attorney 9‐1‐2020  Exhibit C ‐ Page 4

10.  Subcontractor  Insurance  Coverage.  Contractor  shall  require  and  verify  that  all  subcontractors maintain insurance coverage  that meets the minimum  scope and limits of insurance coverage specified in this Exhibit C.

Form Approved by City Attorney 9‐1‐2020  Exhibit D ‐ Page 1 EXHIBIT D

GENERAL CONDITIONS

1.  Independent Contractor.

A.  It is understood and agreed that CONTRACTOR (including CONTRACTOR’s employees) is an  independent  contractor  and  that  no  relationship  of  employer‐employee  exists between  the  parties  hereto  for  any  purpose  whatsoever.   Neither  CONTRACTOR  nor CONTRACTOR’s  assigned  personnel  will  be  entitled  to  any  benefits  payable  to  CITY employees.   CITY  is  not  required  to  make  any  deductions  or  withholdings  from  the compensation  payable  to  CONTRACTOR  under  the  provisions  of  this  Contract,  and CONTRACTOR will be issued a Form 1099 for its services hereunder.  As an independent contractor, CONTRACTOR hereby agrees to indemnify and hold CITY harmless from any and  all  claims  that  may  be  made  against  CITY  based  upon  any  contention  by  any  of CONTRACTOR’s employees or by any third party, including any state or federal agency, that an employer‐employee relationship or a substitute therefor exists for any purpose whatsoever by reason of this Contract or by reason of the nature and/or performance under this Contract.

B.  It is further understood and agreed by the parties that CONTRACTOR, in the performance of its obligations, is subject to the City’s control and direction   as to the designation of tasks to be performed and the results to be accomplished under this Contract, but not as to the means, methods, or sequence used by CONTRACTOR for accomplishing the results.

To  the  extent  that  CONTRACTOR  obtains  permission  to,  and  does,  use  CITY  facilities, space, equipment or support services in the performance of this Contract, this use will be at the CONTRACTOR’s sole discretion based on the CONTRACTOR’s determination that the  use  will  promote  CONTRACTOR’s  efficiency  and  effectiveness.   Except  as  may  be specifically  provided  elsewhere  in  this  Contract,  the  CITY  does  not  require  that CONTRACTOR use CITY facilities, equipment or support services or work in CITY locations in the performance of this Contract. As used in this Contract, "sole discretion" or "sole judgment" means that the party authorized to exercise its discretion or judgment may do so based on an unfettered assessment of its own interests, without considering how its decision affects the other party, and unconstrained by the implied covenant of good faith and fair dealing.

C.   If, in the performance of this Contract, any third persons are employed by CONTRACTOR, such persons will be entirely and exclusively under the direction, supervision, and control of CONTRACTOR.  Except as otherwise provided in this Contract, all terms of employment, including  hours,  wages,  working  conditions,  discipline,  hiring,  and  discharging,  or  any other  terms  of  employment  or  requirements  of  law,  shall  be  determined  by CONTRACTOR.  It is further understood and agreed that CONTRACTOR will issue W‐2 or 1099  Forms  for  income  and  employment  tax  purposes  for all  CONTRACTOR’s  assigned personnel and subcontractors.

D.  The provisions of this section will survive any expiration or termination of this Contract.

Nothing  in  this  Contract  creates  an  exclusive  relationship  between  CITY  and CONTRACTOR.   CONTRACTOR may represent, perform services for, or be employed by

Form Approved by City Attorney 9‐1‐2020  Exhibit D ‐ Page 2 any  additional  persons  or  companies  so  long  as  CONTRACTOR  does  not  violate  the provisions of Section 5, below.

2.  Licenses; Permits, Etc.  CONTRACTOR represents and warrants that CONTRACTOR has, and shall maintain at all times during the term of this Contract at its sole cost and expense, all licenses, permits, qualifications,
and approvals of any nature that are legally required for CONTRACTOR to practice its profession or fulfill the terms of this Contract, including a City Business Operations Tax Certificate and any required certification issued by the California Secretary of State.

3.  Time.  Time is off the essence in the performance
of this Contract. CONTRACTOR shall devote the
necessary time and effort to its performance under this Contract. Neither party will be considered in default of this Contract, to the extent that party’s performance is prevented or delayed by any cause, present or future, that is beyond the reasonable control of that party.

4.  CONTRACTOR  Not  Agent.   Except  as  CITY  may  specify  in  writing,  CONTRACTOR  and CONTRACTOR’s personnel have no authority, express or implied, to act on behalf of CITY in any capacity  whatsoever  as  an  agent.   CONTRACTOR  and  CONTRACTOR’s  personnel  shall  have  no authority, express or implied, to bind CITY to any obligations whatsoever.

5.  Conflicts of Interest.  CONTRACTOR covenants that neither it, nor any officer or principal of its firm, has or will acquire any interest, directly or indirectly, that would conflict in any manner with the  CITY’s  interests  or  that  would  in  any  way  hinder  CONTRACTOR’s  performance  under  this Contract.  CONTRACTOR further covenants that in the performance of this Contract, no person having any such interest will be employed by it as an officer, employee, agent or subcontractor, without the City’s written consent.

CONTRACTOR agrees to avoid conflicts of interest or the appearance of any conflicts of interest with
the City’s interests during the performance of this Contract.  If CONTRACTOR is or employs a former officer or employee of the CITY, CONTRACTOR and any former City officer or employee shall  comply  with  the  provisions  of  Sacramento  City  Code  Section  2.16.090  pertaining  to appearances before the City Council or any CITY department, board, commission, or committee.

6.  Hazardous Substances. "Hazardous Substances" means any substance, material, waste, or other pollutant or  contaminant that is or becomes designated, classified, or regulated as hazardous or  toxic under any law, regulation, rule, order, decree, or other governmental requirement  now in effect or later enacted. If
Contractor is shipping Hazardous Substances,
Contractor must supply a Safety Data Sheet ("SDS") with the first shipment of  Hazardous Substances to each City location receiving the Hazardous Substances. If the content of an SDS is revised, Contractor must provide a revised SDS to each City  location receiving Hazardous Substances.

7.  Confidentiality of CITY Information.   During performance of this Contract, CONTRACTOR may gain  access  to  and  use  CITY  information  regarding  inventions,  machinery,  products,  prices, apparatus, costs, discounts, future plans, business affairs, governmental affairs, processes, trade secrets, technical matters, systems, facilities, customer lists, product design, copyright, data, and other vital information (hereafter collectively referred to as “City Information”) that are valuable, special and unique assets of the CITY.

Form Approved by City Attorney 9‐1‐2020  Exhibit D ‐ Page 3 CONTRACTOR  agrees  to  protect  all  City  Information  and  treat  it  as  strictly  confidential,  and further  agrees  that  CONTRACTOR  shall  not  at  any  time,  either  directly  or  indirectly,  divulge, disclose or communicate in any manner any City Information to any third party without the City’s prior written consent.

In  addition,  CONTRACTOR  must  comply  with  all  CITY  policies  governing  the  use  of  the  CITY network and technology systems, as set forth in applicable provisions of the City of Sacramento Administrative Policy Instructions # 30.  A violation by CONTRACTOR of this section is a material violation of this Contract and shall justify legal and equitable relief.

8.  CONTRACTOR Information.

A.  CITY shall have full ownership and control, including ownership of any copyrights, of all information prepared, produced, or provided by CONTRACTOR under this Contract.   In this  Contract,  the  term  “information”  means  and  includes:  any  and  all  work  product, submittals, reports, plans, specifications, and other
deliverables consisting of documents,
writings,  handwritings,  typewriting,  printing,  photostatting,  photographing,  computer models, and any other computerized data and every other means of recording any form of  information,  communications,  or  representation,  including  letters,  works,  pictures, drawings, sounds, or symbols, or any combination thereof.   CONTRACTOR shall not be responsible for any unauthorized modification or use of such information for other than its intended purpose by CITY.

B.  CONTRACTOR  shall  fully  defend,  indemnify  and  hold  harmless  CITY,  its  officers  and employees, and each of them, from and against any and all claims, actions, lawsuits or other proceedings alleging that all or any part of the information prepared, produced, or provided by CONTRACTOR under this Contract infringes upon any third party’s trademark, trade  name,  copyright,  patent  or  other  intellectual  property  rights.   CITY  shall  make reasonable efforts to notify CONTRACTOR not later than ten days after CITY is served with any  such  claim,  action,  lawsuit  or  other  proceeding.  However,  City’s  failure  to  provide notice  within  the  ten‐day  period  does  not  relieve  CONTRACTOR  of  its  obligations hereunder, which survive any termination or expiration of this Contract.

C.  All  proprietary  and  other  information  received  from  CONTRACTOR  by  CITY,  whether received  in  connection  with  CONTRACTOR’s  proposal  to  CITY  or  in  connection  with Contractor’s performance, will be disclosed upon receipt of a request for disclosure, in accordance  with  the  California  Public  Records  Act;  provided,  however,  that,  if  any information is set apart and clearly marked “trade secret” when it is provided to CITY, CITY  shall  give  notice  to  CONTRACTOR  of  any  request  for  the  disclosure  of  such information.  The CONTRACTOR will then have five days from the date it receives notice to petition the court for a protective order to prevent the  disclosure of the information.

The CONTRACTOR shall have sole responsibility for defense of the actual “trade secret” designation of such information.

D.  The  parties  understand  and  agree  that  any  failure  by  CONTRACTOR  to  respond  to  the notice provided by CITY and seek a protective order, in accordance with the provisions of subsection  C,  above,  constitutes  a  complete  waiver  by  CONTRACTOR  of  any  rights regarding  the  information  designated  “trade  secret”  by  CONTRACTOR,  and  the

Form Approved by City Attorney 9‐1‐2020  Exhibit D ‐ Page 4 information will be disclosed by CITY in accordance with the Public Records Act.

9.  Notification of Material Changes in Business. Contractor agrees that if it experiences any material changes in its business, including a  reorganization, refinancing, restructuring, leveraged buyout, bankruptcy, name change,  or loss of key personnel, it will immediately notify the City of the changes. Contractor  also agrees to immediately notify the City of any condition that may jeopardize the  scheduled delivery or fulfillment of Contractor's obligations to the City under this  Contract.

10.  Standard  of  Performance.   CONTRACTOR  shall  perform  in  the  manner  and  according  to  the standards  currently  observed  by  a  competent  practitioner  of  CONTRACTOR’s  profession  in California  and  in  compliance  with  all  requirements  of  this  Contract.   All  products  that CONTRACTOR delivers to CITY under this Contract must be prepared in a professional manner and conform to the standards of quality normally observed by a person currently practicing in CONTRACTOR’s profession.

CONTRACTOR shall assign only competent personnel to perform on its behalf under this Contract.

CONTRACTOR must notify the CITY in writing of any changes in CONTRACTOR’s staff assigned to perform under this Contract, before any performance by the new staff member.  If the CITY, in its sole discretion, determines that any person assigned by the Contractor to perform under this Contract is not performing in accordance with the standards required herein, City shall provide notice to Contractor. CONTRACTOR shall immediately remove the assigned person upon receipt of the notice.

11.  Performance or Different Terms and Conditions. The City's subsequent performance will not
be construed as either acceptance of  additional or different terms and conditions or a counteroffer by the Contractor, nor will  the City's subsequent performance be viewed as acceptance of any provision of the  Uniform Commercial Code, as adopted by any State, that is contrary to the terms and  conditions contained herein. Contractor's performance shall conform to the applicable  requirements of the Sacramento City Charter, Sacramento City Code, and all applicable  State and Federal laws, and all the requirements of this Contract. The California  Commercial Code will apply except as otherwise provided in the Contract.

12.  Emergency/Declared Disaster Requirements.

If an emergency is declared by the City Manager,
or if any portion of the City is declared  a disaster area by the county, state or federal government, this Contract may be  subjected to increased usage. The Contractor shall serve the City during a declared  emergency or disaster, subject to the same terms and conditions that apply during non‐ emergency / non‐disaster conditions. The pricing set forth in this Contract will apply,  without mark‐up, regardless of the circumstances. If the Contractor is unable to fulfill the  terms of the Contract because of a disruption in its chain of supply or service, then the  Contractor shall provide proof  of  the  disruption.  Acceptable  forms  of  proof  will  include  a  letter  or  notice  from  the Contractor's source stating the reason for the disruption

13.  Term; Suspension; Termination.

A.  This Contract is effective on the Effective Date and continues in effect until both parties have  fully  performed  their  respective  obligations  under  this  Contract,  unless  sooner terminated as provided herein.

Form Approved by City Attorney 9-1-2020 Exhibit D - Page 5

B. CITY shall have the right at any time to suspend CONTRACTOR’s performance hereunder, in whole or in part, by giving a written notice of suspension to CONTRACTOR. Upon receipt of such notice , CONTRACTOR shall immediately suspend its activities under this Contract, as specified in the notice.

C. The CITY shall have the right to terminate this Contract at any time by giving a written notice of termination to CONTRACTOR. Upon receipt of such notice , CONTRACTOR shall immediately cease performance under this Contract as specified in the notice. If the CITY terminates this Contract:

(1) CONTRACTOR shall, not later than five days after receipt of the notice, deliver all information prepared under this Contract to the City.

(2) The CITY shall pay CONTRACTOR the reasonable value of Goods or Services provided by CONTRACTOR before termination; provided, however, CITY shall not in any manner be liable for lost profits that might have been made by CONTRACTOR had the Contract not been terminated or had CONTRACTOR completed performance required by this Contract. CONTRACTOR shall furnish to the CITY any financial information r equested by the City to determine the reasonable value of the Goods or Services provided by CONTRACTOR. The foregoing is cumulative and does not affect any right or remedy that CITY may have in law or equity.

14. Default by Contractor. In case of default by the Contractor, the City reserves the right to procure the Goods or Services from other sources and deduct from any monies due, or that may thereafter become due to the Contractor, the difference between the price named in this Contract and the actual cost to the City to procure from an alternate source. Prices paid by the City will be considered the prevailing market price at the time such purchase is made.

15. Indemnity.

A. Indemnity : Contractor shall defend, hold harmless, and indemnify City, its officers, and employees, and each and every one of them, to the fullest extent permitted under law, from and against all actions, damages, costs, liabilities, claims, demands, losses, judgments, penalties, and expenses of every type and description, whether arising on or off the site of the work or services performed under this Contract, including any fees and costs reasonably incurred by City’s staff attorneys or outside attorneys and any fees and expenses incurred in enforcing this provision (hereafter collectively referred to as “Claims”), including Claims for personal injury or death, damage to personal, real, or intellectual property, damage to the environment, contractual or other economic damages, or regulatory penalties, that to the extent arise out of, pertain to, or relate to any negligent act or omission, recklessness, or willful misconduct related in any way to the performance of or failure to perform this Contract by Contractor, any subcontractor (including lower-tier subcontractors) or agent of Contractor, their respective officers and employees, and anyone else for whose acts of omissions any of them may be liable, whether or not the Claims are litigated, settled, or reduced to judgment; provided that the foregoing indemnity does not apply to liability for damages for death or bodily injury

Form Approved by City Attorney 9‐1‐2020  Exhibit D ‐ Page 6 to persons, injury to property, or other loss, damage, or expense, to the extent arising from the active negligence or willful misconduct of, or defects in design furnished by, City, its agents, servants, or independent contractors who are directly responsible to City, except when such agents, servants, or independent contractors are under the supervision and control of Contractor or any subcontractor (including lower‐tier subcontractors) or agent of Contractor.  While Contractor’s defense costs ordinarily cannot exceed Contractor’s proportionate percentage of fault, if one or more defendants is unable to pay its share of defense costs due to bankruptcy or dissolution, the Contractor shall meet and confer with the City and other parties regarding the unpaid defense costs.

B.   Insurance Policies; Intellectual Property Claims:  The existence or acceptance by City of any of the insurance policies or coverages described in this Contract will not affect or limit any of City’s rights under this Section, nor will the limits of any insurance limit the liability of Contractor hereunder.  This Section will not apply to any intellectual property claims, actions, lawsuits or other proceedings subject to the provisions of the Contractor Information Section, above.

C.  Survival. The provisions of this section will survive any expiration or termination of this Contract.

16.  Funding Availability.

A.    This Contract is subject to the budget and fiscal provisions of the Charter and the Sacramento City Code.

B.    The City’s payment obligation under this Contract will not exceed the amount of funds appropriated and approved for this Contract by the Sacramento City Council.

C.    This Section shall govern over any other contrary provision of the Contract.

17.  Equal  Employment  Opportunity.   During  the  performance  of  this  Contract,  CONTRACTOR,  for itself, its assignees and successors in interest, agrees as follows:

A.  Compliance With Regulations: CONTRACTOR shall comply with all state, local, and federal anti‐discrimination  laws  and  regulations,  including  the  Executive  Order  11246  entitled “Equal  Opportunity  in  Federal  Employment”,  as  amended  by  Executive  Order  11375, 12086,  and  13672,  and  as  supplemented  in  Department  of  Labor  regulations  (41  CFR Chapter 60), referred to collectively as the “Regulations.”

B.  Nondiscrimination: CONTRACTOR, with regards to the work performed by it after award and  before  completion  of  the  work  under  this  Contract,  shall  not  discriminate  on  the ground of race, color, religion, sex, national origin, age, marital status, physical handicap or sexual orientation in selection and retention of subcontractors, including procurement of materials and leases of equipment.  CONTRACTOR shall not participate either directly or indirectly in discrimination prohibited by the Regulations.

C.  Solicitations for Subcontractors, Including Procurement of Materials and Equipment: In

Form Approved by City Attorney 9‐1‐2020  Exhibit D ‐ Page 7 all solicitations either by competitive bidding or negotiations made by CONTRACTOR for work to be performed under any subcontract, including all procurement of materials or equipment, each potential subcontractor or supplier shall be notified by CONTRACTOR of CONTRACTOR’s  obligation  under  this  Contract  and  the  Regulations  relative  to nondiscrimination on the ground of race, color, religion, sex, national origin, age, marital status, physical handicap or sexual orientation.

D.  Information and Reports: CONTRACTOR shall provide all information and reports required by the Regulations, or by any orders or instructions issued pursuant thereto, and shall permit  access  to  its  books,  records,  accounts,  other  sources  of  information  and  its facilities as may be determined by the CITY to be pertinent to ascertain compliance with the  Regulations,  orders  and  instructions.   Where  any  information  required  of CONTRACTOR is in the exclusive possession of another who fails or refuses to furnish this information, CONTRACTOR shall so certify to the CITY, and shall set forth what efforts it has made to obtain the information.

E.  Sanctions for Noncompliance: In the event of noncompliance by CONTRACTOR with the nondiscrimination  provisions  of  this  Contract,  the  CITY  shall  impose  any  sanctions  it determines are appropriate including:

(1)  Withholding of payments to CONTRACTOR under this Contract until CONTRACTOR complies;
(2)  Cancellation, termination, or suspension of this Contract, in whole or in part.

F.  Incorporation of Provisions: CONTRACTOR shall include the provisions of subsections A through E, above, in every subcontract, including procurement of materials and leases of equipment, unless exempted by the Regulations, or by any order or instructions issued pursuant thereto.   The City may direct CONTRACTOR to take specific actions to enforce these  provisions,  including  sanctions  for  noncompliance;  provided,  however,  that  if CONTRACTOR becomes involved in, or is threatened with, litigation with a subcontractor or supplier as a result of such direction, CONTRACTOR may request that the CITY join such litigation to protect the City’s interests.

18.  Entire  Agreement.   This  Contract,  including  all  Exhibits  and  documents  referenced  herein, contains  the  entire  agreement  between  the
parties  and  supersedes  whatever  oral  or  written
understanding they may have had before the execution of this Contract.   No alteration to the terms of this Contract shall be valid unless approved in writing by CONTRACTOR, and by CITY, in accordance with applicable provisions of the Sacramento City Code.

19. Modification of Contract.   The Contractor shall take no direction from any City employee that changes the executed terms and conditions of the Contract, including Exhibit A, or any change that impacts the cost, price, or schedule, before receiving a written, signed modification to the Contract.

20. Severability.  If a court with jurisdiction rules that any portion of this Contract or its application to any person or circumstance is invalid or unenforceable, the remainder of this Contract will not be  affected  thereby  and  will  remain  valid  and  enforceable  as  written,  to  the  greatest  extent permitted by law.

Form Approved by City Attorney 9‐1‐2020  Exhibit D ‐ Page 8

21. Waiver.  Neither the CITY’s acceptance of, or payment for, any Goods or Services, nor any waiver by either party of any default, breach or condition precedent, will be construed as a waiver of any provision of this Contract, nor as a waiver of any other default, breach or condition precedent or any other right hereunder. No waiver will be effective unless it is in writing and signed by the waiving party.

22. Governing Law.  This Contract shall be governed, construed and enforced in accordance with the laws  of  the  State  of  California,  except  that  the  rule  of  interpretation  in  California  Civil  Code section 1654 will not apply.  Venue of any litigation arising out of this Contract will lie exclusively in  the  state  trial  court  or  Federal  District  Court  located  in  Sacramento  County  in  the  State  of California, and the parties consent to jurisdiction over their persons and over the subject matter of any such litigation in such courts, and consent to service of process issued by such courts.

23. Assignment  Prohibited.   The  expertise  and  experience  of  CONTRACTOR  are  material considerations for this Contract.  CITY has a strong interest in the qualifications and capability of the  persons  and  entities  that  will  fulfill  the  obligations  imposed  on  CONTRACTOR  under  this Agreement. In recognition of this interest, CONTRACTOR shall not assign any right or obligation pursuant to this Contract without the written consent of the CITY.  Any attempted or purported assignment without CITY’s written consent shall be void and of no effect.

24. Binding Effect.  This Contract is binding on the heirs, executors, administrators, successors and assigns of the parties, subject to the provisions of Section 23, above.

25. Compliance with Laws. The Contractor shall be responsible for strict compliance with all applicable laws, regulations, court orders and other legal requirements applicable to the work to be accomplished under the Contract, including the California Occupational Safety and Health Act and all applicable safety orders issued by the Division of Occupational Safety and Health, Department of Industrial Relations, State of California, and all applicable requirements of Underwriters Laboratories and the Federal Communication Commission.

26.  Debarment Certification
A.  Pursuant to 2 CFR, Part 200, and applicable Executive Orders, the City is restricted in its ability  to  contract  with  certain  parties  that  are  debarred,  suspended,  or  otherwise excluded  or  ineligible  for  participating  in  Federal  assistance  programs  or  activities.  By signing  this  Agreement,  CONTRACTOR  warrants  and  certifies  under  penalty  of  perjury under the laws of the State of California that Contractor, including any owner, partner, director,  officer,  or  principal  of  the  CONTRACTOR,  or  any  person  in  a  position  with management responsibility or responsibility for the administration of federal funds:

(1)   Is  not  presently  debarred,  suspended,  proposed  for  debarment,  declared ineligible,  or  voluntarily  excluded  from  covered  transactions  by  any  federal  or  state department/agency;

(2)   Has not within a three‐year period preceding this certification been convicted of or had a civil judgment rendered against it for: commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public transaction or contract  (federal,  state,  or  local);  violation  of  federal  or  state  antitrust  statutes;  or

Form Approved by City Attorney 9‐1‐2020  Exhibit D ‐ Page 9 commission  of  embezzlement,  theft,  forgery,  bribery,  falsification  or  destruction  of records, making false statements, receiving stolen property, or other criminal felony;

(3)   Is  not  presently  indicted  for  or  otherwise  criminally  or  civilly  charged  by  a governmental  entity  (federal,  state,  or  local)  with  commission  of  any  of  the  offenses enumerated in paragraph (b) above; or

(4)   Has not, within a three‐year period preceding this certification, had one or more public contracts (federal, state, or local) or transactions terminated for cause or default.

(5)    Has not been notified, within a three‐year period preceding this certification, been notified of any delinquent Federal taxes in an amount that exceeds $3,500 for which the liability remains unsatisfied. Federal taxes are considered delinquent if the tax liability has been finally determined and the taxpayer is delinquent in making payment, as defined in Section 52.209‐5 of the Federal Acquisition Regulations.

B.  CONTRACTOR  further  warrants  and  certifies  that  it  shall  not  knowingly  enter  into  any transaction with any subcontractor, material supplier, or vendor who is debarred, suspended, declared  ineligible,  or  voluntarily  excluded  from  covered  transactions  by  any  federal  or  state department/agency. Any exceptions to the warranties and certifications in this Section must be disclosed to the City.

C.  Exceptions will not necessarily result in denial of recommendation for award, but will be considered  in  determining  Contractor’s  responsibility.  Disclosures  must  indicate  to  whom exceptions apply, the initiating agency, and dates of action.

D.  City  will  review  the  Federal  Government’s  System  for  Award  Management  Exclusions maintained by the General Services Administration for eligibility, prior to the execution of this Agreement. The CONTRACTOR shall provide immediate written notice to the City if, at any time prior  to  execution,  the  CONTRACTOR  learns  this  certification  is  erroneous  or  has  become erroneous  by  reason of changed  circumstances.  If  it  is  later  determined  that  the Contractor’s warranties  and  certification  in  this  Section  were  erroneous,  the  City  may  terminate  this Agreement for default.

Form Approved by City Attorney 9‐1‐2020  Exhibit E ‐ Page 1 EXHIBIT E

ADDITIONAL REQUIREMENTS FOR SURVEYING, MATERIAL TESTING, AND INSPECTION SERVICES

The Services provided under this Contract include  land surveying, material testing, or inspection services provided  for  a  City  construction  project  during  the  design,  pre‐construction,  construction,  or  post‐ construction phases of the project. Therefore, the services include “Public Work” under the California Labor Code and is subject to the following requirements:

A.  Payment of Prevailing Wages: Contractor and any subcontractor(s) performing any Public Work  shall  comply  with  the  provisions  of  Sacramento  City  Code  section  3.60.180   and applicable provisions of the California Labor Code, which require, among other things, that CONTRACTOR and all subcontractors pay not less than the prevailing rate of wages, as determined by the Director of the California Department of Industrial Relations (“DIR”) in  accordance  with  California  Labor  Code  section  1773.   CONTRACTOR  and  every subcontractor shall maintain payroll records and submit certified payrolls and other labor compliance  documentation  electronically  when  and  as  required  by  CITY.  In  addition, Labor Code Section 1771.4 requires the CONTRACTOR and any subcontractor performing any Public Work to furnish electronic payroll records directly to the Labor Commissioner.

Contractor shall include these requirements in every subcontract.

This  Agreement  is  subject  to  compliance  monitoring  and  enforcement  by  the  DIR,  as specified in California Labor Code section 1771.4. The Contractor and any subcontractor will be subject to withholding and penalties for violation of prevailing wage requirements in accordance with applicable law, including Labor Code Sections 1726, 1741, 1771.5, and 1775, and City Code Section 3.60.180. Questions regarding the City’s Labor Compliance Program should be directed to the City Representative.

B.  DIR Registration: California Labor Code Section 1725.5 requires the CONTRACTOR and all

subcontractors performing Public Works services to be currently registered with the DIR, as specified in California Labor Code Section 1725.5. California Labor Code Section 1771.1 provides that a contractor or subcontractor shall not be qualified to bid on, be listed in a bid proposal (subject to the requirements of Section 4104 of the California Public Contract Code), or engage in the performance of any contract for Public Work, unless currently registered and qualified to perform Public Work in accordance with California Labor Code Section 1725.5.

Further  information  can  be  found  on  DIR’s  website  at  http://www.dir.ca.gov/Public‐ Works/Contractors.html.   The  above  summary  is  provided  solely  for  informational purposes  and  does  not  in  any  way  affect  the  CONTRACTOR’s  and  subcontractors’ obligation to comply in all respects with all other applicable laws and regulations. The CONTRACTOR shall disseminate these provisions to all subcontractors.

Before the performance of work by Contractor or any subcontractor(s) under this Contract,
Contractor shall furnish Contractor’s and any subcontractors’ current DIR

Form Approved by City Attorney 9‐1‐2020  Exhibit E ‐ Page 2 registration number(s). The Contractor’s current DIR registration number and the current DIR registration number of all subcontractors will be listed on the Subcontractor and LBE Participation Verification Form, incorporated herein.

To be completed by the City Representative if this Agreement is for the performance of any Public Work:

Contractor DIR registration #: _________________________________________

C.  Workers’ Compensation Certification. In accordance with California Labor Code Section 1861, by signing this Contract, Contractor acknowledges and represents that Contractor is aware of the provisions of section 3700 of the California Labor Code which requires every employer to be insured against liability for workers' compensation or to undertake self‐insurance in accordance with the provisions of that code, and that Contractor will comply with the provisions of the Labor Code before commencing performance   under this Contract.

D.  Apprentices. If this Contract is for the performance of any Public Work, and the amount of the Contract is $30,000 or more, the Contractor and any subcontractors performing any Public Work under this Contract must comply with and be subject to enforcement under, the provisions of Sacramento City Code Section 3.60.190, Section 1777.5 et seq. of the California Labor Code, and implementing regulations set forth in Title 8 of the California Code of Regulations, governing the employment of apprentices. The Contractor and any subcontractors performing Public Work will be subject to penalties for apprenticeship violations in accordance with Labor Code Section 1777.7.

E.   Working Hours. If this Contract is for the performance of any Public Work, Contractor
and any subcontractors performing any Public Work under this Contract must comply with and be subject to enforcement under, the provisions of Sacramento City Code Section 3.60.180 and California Labor Code Section 1810 et seq., governing the working hours of employees performing Public Work.

F.   Failure to Comply with Labor Compliance.

If all applicable labor compliance
requirements are not met, the City will have the right to withhold or reject a payment request and/or invoice, in whole or in part, without in any way relieving Contractor or its subcontractors of any obligations under this Contract.

G. Subcontractors.  The  Contractor  shall  include  these  provisions  A  through  F  in  every subcontract  or  sub‐agreement  for  any  subcontractors  performing  work  under  this Contract.

SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE

THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN ACCORDANCE WITH THE POLICY PROVISIONS.

INSURER(S) AFFORDING COVERAGE
INSURER F :

INSURER E :

INSURER D :

INSURER C :

INSURER B :

INSURER A :

NAIC #
NAME:

CONTACT
(A/C, No):

FAX
E-MAIL
ADDRESS:

PRODUCER
(A/C, No, Ext):

PHONE

INSURED
REVISION NUMBER:CERTIFICATE NUMBER:COVERAGES
IMPORTANT: If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must have ADDITIONAL INSURED provisions or be endorsed.

If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may require an endorsement. A statement on this certificate does not confer rights to the certificate holder in lieu of such endorsement(s).

THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS

CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHORIZED REPRESENTATIVE OR PRODUCER, AND THE CERTIFICATE HOLDER.

OTHER:
(Per accident)
(Ea accident)
$
$
N / A
SUBR
WVD
ADDL
INSD

THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS

CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS. $ $
$
$PROPERTY DAMAGE
BODILY INJURY (Per accident)
BODILY INJURY (Per person)

COMBINED SINGLE LIMIT

AUTOS ONLY

AUTOSAUTOS ONLY

NON-OWNED

SCHEDULEDOWNED

ANY AUTO

AUTOMOBILE LIABILITY
Y / N

WORKERS COMPENSATION

AND EMPLOYERS' LIABILITY
OFFICER/MEMBER EXCLUDED?
(Mandatory in NH)
DESCRIPTION OF OPERATIONS below
If yes, describe under

ANY PROPRIETOR/PARTNER/EXECUTIVE
$
$
$
E.L. DISEASE - POLICY LIMIT
E.L. DISEASE - EA EMPLOYEE
E.L. EACH ACCIDENT
ER
OTH-

STATUTE
PER

LIMITS(MM/DD/YYYY)

POLICY EXP
(MM/DD/YYYY)

POLICY EFF

POLICY NUMBERTYPE OF INSURANCELTR
INSR
DESCRIPTION OF OPERATIONS / LOCATIONS / VEHICLES (ACORD 101, Additional Remarks Schedule, may be attached if more space is required)

EXCESS LIAB
UMBRELLA LIAB $EACH OCCURRENCE
$AGGREGATE
$
OCCUR

CLAIMS-MADE
DED RETENTION $
$PRODUCTS - COMP/OP AGG
$GENERAL AGGREGATE
$PERSONAL & ADV INJURY
$MED EXP (Any one person)
$EACH OCCURRENCE

DAMAGE TO RENTED
$PREMISES (Ea occurrence)

COMMERCIAL GENERAL LIABILITY

CLAIMS-MADE OCCUR
GEN'L AGGREGATE LIMIT APPLIES PER:

POLICY PRO-

JECT LOC

CERTIFICATE OF LIABILITY INSURANCE

DATE (MM/DD/YYYY)

CANCELLATION

AUTHORIZED REPRESENTATIVE
ACORD 25 (2016/03)
© 1988-2015 ACORD CORPORATION. All rights reserved.

CERTIFICATE HOLDER
The ACORD name and logo are registered marks of ACORD
HIRED

AUTOS ONLY
9/27/2022
AssuredPartners Design Professionals Insurance Services, LLC 3697 Mt. Diablo Blvd., Suite 230
Lafayette CA 94549
Nancy Ferrick
510-272-1400
[email protected]
License#: 6003745
Valley Forge Insurance Company
20508
WOODROD-01
Continental Casualty Company
20443
Wood Rodgers, Inc.
3301 C Street, Bldg 100B
Sacramento CA 95816-3342
Continental Insurance Company
35289
American Casualty Company of Reading,
20427
XL Specialty Insurance Company
37885
1119766098
A
X
1,000,000
X
1,000,000
X
Contractual Liab
15,000
X
Sev. of Interest
1,000,000
2,000,000
X
Y
Y
7034275106
10/1/2022
10/1/2023
2,000,000
B
1,000,000
X
Y
Y
7034275090
10/1/2022
10/1/2023
C
X
X
5,000,000
Y
7034275087
10/1/2022
Y
10/1/2023
5,000,000
D
D
X
N
Y
7034275123
7034275137
10/1/2022
10/1/2022
10/1/2023
10/1/2023
1,000,000
1,000,000
1,000,000
E
Professional Liability
(Includes Pollution Liability)
DPR5002083
10/1/2022
10/1/2023
Per Claim
Annual Aggregate
$5,000,000
$7,000,000
Umbrella Liability policy is follow-form underlying General Liability/Auto Liability/Employer's Liability.

REF ID: Z328053 - ALL OPERATIONS OF THE NAMED INSURED. The City of Sacramento, its officials, employees, and volunteers are named as Additional Insured as respects General Liability and Auto Liability coverage. Insurance is Primary/Non-Contributory and a Severability of Interest clause applies per policy form wording. A Waiver of Subrogation applies to Workers' Compensation. Should any of the above described policies be cancelled before the expiration date thereof, the issuing insurer will mail 30 days written notice to the Certificate Holder. Professional Liability Policy is Claims Made. Professional Liability Retroactive Date: 04/01/1996.
30 Days Notice of Cancellation
City of Sacramento
c/o EXIGIS Risk Management Services
P.O. Box 947
Murrita, CA 92564

CNA PARAMOUNT
BlanketAdditionalInsured- Owners,Lesseesor
Contractors- with Products-Completed
OperationsCoverageEndorsement
This endorsementmodifiesinsuranceprovidedunderthe following:

COMMERCIALGENERALLIABILITYCOVERAGEPART
It is understoodand agreedas follows:

I. WHO IS AN INSUREDis amendedto include asan Insuredany personor organizationwhomyou are requiredby writtencontractto addas an additionalinsuredon this coveragepart, but only with respectto liabilityfor bodily injury, propertydamageor personaland advertisinginjurycausedin whole or in part by your acts or omissions,or the acts or omissionsof those actingon your behalf:

A. in the performanceof your ongoingoperationssubjectto such writtencontract; or B. in the performanceof yourworksubjectto such writtencontract, but only with respectto bodilyinjuryor propertydamageincludedin the products-completedoperationshazard, and only if:

1. the writtencontractrequiresyou to providethe additionalinsuredsuch coverage;and

2. this coveragepart providessuch coverage.

II. But if the writtencontractrequires:

A. additionalinsuredcoverageunderthe 11-85edition,10-93edition,or 10-01editionof CG2010,or underthe 10- 01 editionof CG2037;or
B. additionalinsuredcoveragewith "arisingout of" language;or C. additionalinsuredcoverageto thegreatestextentpermissibleby law; then paragraphI. aboveis deletedin its entiretyand replacedby the following:

WHO IS AN INSUREDis amendedto include asan Insuredany personor organizationwhomyou are requiredby writtencontractto addas an additionalinsuredon this coveragepart, but only with respectto liabilityfor bodily injury, propertydamageor personaland advertisinginjuryarisingout ofyourworkthat is subjectto such written contract.

III. Subjectalwaysto thetermsand conditionsof this policy,includingthe limits of insurance,the Insurerwill not provide such additionalinsuredwith:

A. coveragebroaderthan requiredby the writtencontract; or B. a higherlimit of insurancethan requiredby the writtencontract.

IV. The insurancegrantedby this endorsementto theadditionalinsureddoes not apply to bodilyinjury, property damage, or personaland advertisinginjuryarisingout of:

A. the renderingof, or the failureto render,any professionalarchitectural,engineering,or surveyingservices, including:

1. the preparing,approving,or failing to prepareor approvemaps,shop drawings,opinions,reports,surveys, field orders,changeordersor drawingsand specifications;and

2. supervisory,inspection,architecturalor engineeringactivities;or B. any premisesor work for which the additionalinsuredis specifically listedas an additionalinsuredon another endorsementattachedto this coveragepart.

V. UnderCOMMERCIALGENERALLIABILITYCONDITIONS,the ConditionentitledOther Insuranceis amendedto add thefollowing,which supersedesany provisionto thecontraryin this Conditionor elsewherein this coverage part:

Policy No: 7034275106 CNA75079XX (10-16)

Page 1 of 2 ends

Nat'l Fire Ins Co of Hartford
Insured Name: WOOD RODGERS, INC.

CopyrightCNA All Rights Reserved. Includes copyrightedmaterialof Insurance ServicesOffice, Inc., with its permission. 20020005460755215544738

CNA PARAMOUNT
BlanketAdditionalInsured- Owners,Lesseesor
Contractors- with Products-Completed
OperationsCoverageEndorsement
Primaryand NoncontributoryInsurance
With respectto other insuranceavailableto theadditionalinsuredunderwhich the additionalinsuredis a named insured,this insuranceis primaryto andwill not seek contributionfrom such other insurance,providedthat awritten contractrequiresthe insuranceprovidedby this policy to be:

1. primaryand non-contributingwith other insuranceavailableto theadditionalinsured;or

2. primaryand to notseek contributionfrom any other insuranceavailableto theadditionalinsured.

But exceptas specifiedabove,this insurancewill be excessof all other insuranceavailableto theadditionalinsured.

VI. Solelywith respectto theinsurancegrantedby this endorsement,the sectionentitledCOMMERCIALGENERAL LIABILITYCONDITIONSis amendedas follows:

The ConditionentitledDutiesIn TheEventof Occurrence,Offense,Claimor Suit is amendedwith the additionof the following:

Any additionalinsuredpursuantto this endorsementwill as soon as practicable:

1. give the Insurerwrittennoticeof any claim, or any occurrenceor offensewhich may result in a claim;

2. send the Insurercopiesof all legal papersreceived,and otherwisecooperatewith the Insurerin the investigation, defense,or settlementof theclaim; and

3. make availableany other insurance,and tenderthe defenseand indemnityof any claimto any other insureror self-insurer,whosepolicy or programappliesto a loss that theInsurercoversunderthis coveragepart. However, if the writtencontractrequiresthis insuranceto be primaryand non-contributory,this paragraph3. does not apply to insuranceon which the additionalinsuredis a namedinsured.

The Insurerhas no duty to defendor indemnifyan additionalinsuredunderthis endorsementuntil the Insurerreceives writtennoticeof a claimfrom the additionalinsured.

VII. Solelywith respectto theinsurancegrantedby this endorsement,the sectionentitledDEFINITIONSis amendedto add thefollowingdefinition:

Writtencontractmeansa writtencontractor writtenagreementthat requiresyou to make a personor organizationan additionalinsuredon this coveragepart, providedthe contractor agreement:

A. is currentlyin effect or becomeseffectiveduringthe term of this policy;and B. was executedprior to:

1. the bodilyinjuryor propertydamage; or

2. the offensethat causedthe personaland advertisinginjury; for which the additionalinsuredseeks coverage.

Any coveragegrantedby this endorsementshall apply solely to theextentpermissibleby law.

All other termsand conditionsof thePolicyremainunchanged.

This endorsement,which formsa part of andis for attachmentto thePolicyissuedby the designatedInsurers,takes effect on theeffectivedate ofsaid Policyat thehour statedin said Policy,unlessanothereffectivedate is shown below,and expiresconcurrentlywith said Policy.

Policy No: 7034275106 CNA75079XX (10-16)

Page 2 of 2 ends

Nat'l Fire Ins Co of Hartford
Insured Name: WOOD RODGERS, INC.

CopyrightCNA All Rights Reserved. Includes copyrightedmaterialof Insurance ServicesOffice, Inc., with its permission.

CNA PARAMOUNT
Architects,Engineersand SurveyorsGeneralLiability
Extension Endorsement
by the indemniteeat the Insurer'srequestwill be paid as defensecosts. Such paymentswill not be deemed to be damagesfor personaland advertisinginjuryand will not reducethe limits of insurance.

C. This PERSONALAND ADVERTISINGINJURY- LIMITEDCONTRACTUALLIABILITYProvisiondoes not apply if CoverageB –Personaland AdvertisingInjury Liabilityis excludedby anotherendorsementattachedto this CoveragePart.

This PERSONAL AND ADVERTISING INJURY - CONTRACTUAL LIABILITY Provision does not apply to any personor organizationwho otherwisequalifiesas an additionalinsuredon this CoveragePart.

22. PROPERTYDAMAGE– ELEVATORS
A. Under COVERAGES, Coverage A – Bodily Injury and Property Damage Liability, the paragraph entitled Exclusionsis amendedsuch that theDamageto Your ProductExclusionand subparagraphs(3), (4) and (6) of the Damageto PropertyExclusiondo notapply to propertydamagethat resultsfrom the use of elevators.

B. Solely for the purpose of the coverage provided by this PROPERTYDAMAGE – ELEVATORSProvision, the Other Insuranceconditionsis amendedto add thefollowingparagraph:

This insurance is excess over any of the other insurance,whether primary, excess, contingent or on any other basis that is Propertyinsurancecoveringpropertyof othersdamagedfrom the use of elevators.

23. RETIREDPARTNERS,MEMBERS,DIRECTORSAND EMPLOYEES
WHO IS INSUREDis amendedto include as Insuredsnatural personswho are retired partners,members,directors or employees, but only for bodily injury, property damage or personal and advertisinginjury that results from servicesperformedfor the NamedInsuredunderthe NamedInsured'sdirect supervision. All limitationsthat apply to employeesand volunteerworkersalso apply to anyonequalifying asan Insuredunderthis Provision.

24. SUPPLEMENTARYPAYMENTS
The sectionentitledSUPPLEMENTARYPAYMENTS– COVERAGESA AND Bis amendedas follows:

A. Paragraph1.b. is amendedto delete the $250limit shown for the cost of bail bonds and replace it with a $5,000. limit; and
B. Paragraph 1.d. is amended to delete the limit of $250 shown for daily loss of earnings and replace it with a $1,000.limit.

25. UNINTENTIONALFAILURETO DISCLOSEHAZARDS
If the Named Insured unintentionally fails to disclose all existing hazards at the inception date of the Named Insured'sCoveragePart, the Insurerwill not deny coverageunderthis CoveragePart becauseof such failure.

26. WAIVEROF SUBROGATION- BLANKET
Under CONDITIONS, the conditionentitled TransferOf Rights Of RecoveryAgainst Others To Us is amendedto add thefollowing:

The Insurer waives any right of recovery the Insurer may have against any person or organization because of paymentsthe Insurermakesfor injury or damagearisingout of:

1. the NamedInsured'songoingoperations;or

2. yourworkincludedin the products-completedoperationshazard.

However,this waiver appliesonly when the Named Insuredhas agreed in writing to waive such rights of recoveryin a writtencontractor writtenagreement,and only if such contractor agreement:

Policy No: 7034275106 CNA74858XX (1-15)
Nat'l Fire Ins Co of Hartford
Insured Name: WOOD RODGERS, INC.

CopyrightCNA All Rights Reserved. Includes copyrightedmaterialof Insurance ServicesOffice, Inc., with its permission.

Business Auto Policy
Policy Endorsement

DESIGNATED INSURED FOR COVERED AUTOS LIABILITY COVERAGE THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.

This endorsement modifies insurance provided under the following:

AUTO DEALERS COVERAGE FORM

BUSINESS AUTO COVERAGE FORM

MOTOR CARRIER COVERAGE FORM
With respect to coverage provided by this endorsement, the provisions of the Coverage Form apply unless modified by this endorsement.

This endorsement identifies person(s) or organization(s) who are "insureds" for Covered Autos Liability Coverage under the Who Is An Insured provision of the Coverage Form. This endorsement does not alter coverage provided in the Coverage Form.

This endorsement changes the policy effective on the inception date of the policy unless another date is indicated below.

Named Insured: WOOD RODGERS, INC.

Endorsement Effective Date: 10/01/2022

SCHEDULE
Name Of Person(s) Or Organization(s):

ANY PERSON OR ORGANIZATION THAT THE NAMED INSURED IS OBLIGATED TO PROVIDE INSURANCE

WHERE REQUIRED BY A WRITTEN CONTRACT OR AGREEMENT IS AN INSURED,BUT ONLY WITH RESPECT

TO LEGAL RESPONSIBILITY FOR ACTS OR OMISSIONS OF A PERSON/ORGANIZATION FOR WHOM

LIABILITY COVERAGE IS AFFORDED UNDER THIS POLICY
Information required to complete this Schedule, if not shown above, will be shown in the Declarations.

Each person or organization shown in the Schedule is an "insured" for Covered Autos Liability Coverage, but only to the extent that person or organization qualifies as an "insured" under the Who Is An Insured provision contained in Paragraph A.1. of Section II - Covered Autos Liability Coverage in the Business Auto and Motor Carrier Coverage Forms and Paragraph D.2. of Section I - Covered Autos Coverages of the Auto Dealers Coverage Form.

Policy No: 7034275090Form No: CA 20 48 10 13
Endorsement No: 7; Page: 1 of 1
Underwriting Company: Valley Forge Insurance Company, 151 N Franklin St, Chicago, IL 60606 © Copyright Insurance Services Office, Inc., 2011
Business Auto Policy
Policy Endorsement

CONTRACTORS EXTENDED COVERAGE ENDORSEMENT - BUSINESS AUTO PLUS I.

A.

1. 2.
a.
b.
(1)
(2)

3. 4.

1. 2.

B.

1. 2.

THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.

This endorsement modifies insurance provided under the following:

BUSINESS AUTO COVERAGE FORM

LIABILITY COVERAGE
Who Is An Insured
The following is added to Section II, Paragraph A.1., Who Is An Insured:
a. Any incorporated entity of which the Named Insured owns a majority of the voting stock on the date of inception of this Coverage Form; provided that, b. The insurance afforded by this provision A.1. does not apply to any such entity that is an insured under any other liability "policy" providing auto coverage.

Any organization you newly acquire or form, other than a limited liability company, partnership or joint venture, and over which you maintain majority ownership interest.

The insurance afforded by this provision A.2.:

Is effective on the acquisition or formation date, and is afforded only until the end of the policy period of this Coverage Form, or the next anniversary of its inception date, whichever is earlier.

Does not apply to:

Bodily injury or property damage caused by an accident that occurred before you acquired or formed the organization; or
Any such organization that is an insured
under any other liability "policy" providing auto
coverage.

Any person or organization that you are required by a written contract to name as an additional insured is an insured but only with respect to their legal liability for acts or omissions of a person, who qualifies as an insured under SECTION II – WHO IS AN INSURED and for whom Liability Coverage is afforded under this policy. If required by written contract, this insurance will be primary and non-contributory to insurance on which the additional insured is a Named Insured.

An employee of yours is an insured while operating an auto hired or rented under a contract or agreement in that employee's name, with your permission, while performing duties related to the conduct of your business.
"Policy", as used in this provision A. Who Is An Insured, includes those policies that were in force on the inception date of this Coverage Form but:

Which are no longer in force; or
Whose limits have been exhausted.

Bail Bonds and Loss of Earnings
Section II, Paragraphs A.2. (2) and A.2. (4) are revised as follows:

In a.(2), the limit for the cost of bail bonds is changed from $2,000 to $5,000; and In a.(4), the limit for the loss of earnings is changed from $250 to $500 a day.

Policy No: 7034275090Form No: CNA63359XX (04-2012)
Endorsement No: 18
Underwriting Company: Valley Forge Insurance Company, 151 N Franklin St, Chicago, IL 60606 © Copyright CNA All Rights Reserved. Includes copyrighted material of the Insurance Services Office, Inc., used with its permission.

Business Auto Policy
Policy Endorsement

WAIVER OF TRANSFER OF RIGHTS OF RECOVERY

AGAINST OTHERS TO US (WAIVER OF SUBROGATION)
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.

This endorsement modifies insurance provided under the following:

AUTO DEALERS COVERAGE FORM

BUSINESS AUTO COVERAGE FORM

MOTOR CARRIER COVERAGE FORM
With respect to coverage provided by this endorsement, the provisions of the Coverage Form apply unless modified by the endorsement.

This endorsement changes the policy effective on the inception date of the policy unless another date is indicated below.

Named Insured: WOOD RODGERS, INC.

Endorsement Effective Date: 10/01/2022

SCHEDULE
Name(s) Of Person(s) Or Organization(s):

ANY PERSON OR ORGANIZATION FOR WHOM OR WHICH YOU ARE REQUIRED BY WRITTEN CONTRACT OR AGREEMENT TO OBTAIN THIS WAIVER FROM US. YOU MUST AGREE TO THAT REQUIREMENT PRIOR TO LOSS.

Information required to complete this Schedule, if not shown above, will be shown in the Declarations.

The Transfer Of Rights Of Recovery Against Others To Us condition does not apply to the person(s) or organization(s) shown in the Schedule, but only to the extent that subrogation is waived prior to the "accident" or the "loss" under a contract with that person or organization.

Policy No: 7034275090Form No: CA 04 44 10 13
Endorsement No: 5; Page: 1 of 1
Underwriting Company: Valley Forge Insurance Company, 151 N Franklin St, Chicago, IL 60606 © Copyright Insurance Services Office, Inc., 2011
Workers Compensation And Employers Liability Insurance
Policy Endorsement

WAIVER OF OUR RIGHT TO RECOVER FROM OTHERS ENDORSEMENT
We have the right to recover our payments from anyone liable for an injury covered by this policy. We will not enforce our right against the person or organization named in the Schedule.

This agreement shall not operate directly or indirectly to benefit anyone not named in the Schedule.

Schedule
Any Person or Organization on whose behalf you are required to obtain this waiver of our right to recover from under a written contract or agreement.

The premium charge for the endorsement is reflected in the Schedule of Operations.

All other terms and conditions of the policy remain unchanged.

This endorsement, which forms a part of and is for attachment to the policy issued by the designated Insurers, takes effect on the Policy Effective Date of said policy at the hour stated in said policy, unless another effective date (the Endorsement Effective Date) is shown below, and expires concurrently with said policy unless another expiration date is shown below.

Policy No: 7034275123Form No: WC 00 03 13 (04-1984)
Endorsement No: 5; Page: 1 of 1
Underwriting Company: American Casualty Company Of Reading, PA Copyright 1983 National Council on Compensation Insurance.

Named Insured: Wood Rodgers, Inc.

Workers Compensation And Employers Liability Insurance
Policy Endorsement

BLANKET WAIVER OF OUR RIGHT TO RECOVER FROM OTHERS
This endorsement changes the policy to which it is attached.

It is agreed that Part One - Workers’ Compensation Insurance G. Recovery From Others and Part Two - Employers’ Liability Insurance H. Recovery From Others are amended by adding the following:

We will not enforce our right to recover against persons or organizations. (This agreement applies only to the extent that you perform work under a written contract that requires you to obtain this agreement from us.) PREMIUM CHARGE - Refer to the Schedule of Operations
The charge will be an amount to which you and we agree that is a percentage of the total standard premium for California exposure. The amount is 2%.

All other terms and conditions of the policy remain unchanged.

This endorsement, which forms a part of and is for attachment to the policy issued by the designated Insurers, takes effect on the Policy Effective Date of said policy at the hour stated in said policy, unless another effective date (the Endorsement Effective Date) is shown below, and expires concurrently with said policy unless another expiration date is shown below.

Policy No: 7034275137 Form No: G-19160-B (11-1997)
Endorsement No: 4; Page: 1 of 1
Underwriting Company: American Casualty Company Of Reading, PA © Copyright CNA All Rights Reserved.

Named Insured: Wood Rodgers, Inc.

Form 590 2021
7061223

TAXABLE YEAR
2022 Withholding Exemption Certificate

CALIFORNIA FORM
590
The payee completes this form and submits it to the withholding agent. The withholding agent keeps this form with their records.

Withholding Agent Information
Name
Name □ SSN or ITIN □ FEIN □ CA Corp no. □ CA SOS file no.

Address (apt./ste., room, PO box, or PMB no.)
City (If you have a foreign address, see instructions.) State ZIP code Exemption Reason
Check only one box.

By checking the appropriate box below, the payee certifies the reason for the exemption from the California income tax withholding requirements on payment(s) made to the entity or individual.

CERTIFICATE OF PAYEE: Payee must complete and sign below.

Our privacy notice can be found in annual tax booklets or online. Go to ftb.ca.gov/privacy to learn about our privacy policy statement, or go to ftb.ca.gov/forms and search for 1131 to locate FTB 1131 EN-SP , Franchise Tax Board Privacy Notice on Collection. To request this notice by mail, call 800.338.0505 and enter form code 948 when instructed.

Under penalties of perjury, I declare that I have examined the information on this form, including accompanying schedules and statements, and to the best of my knowledge and belief, it is true, correct, and complete. I further declare under penalties of perjury that if the facts upon which this form are based change, I will promptly notify the withholding agent.

Type or print payee’s name and title ___________________________________________________ Telephone _________________ Payee Information
□ Individuals — Certification of Residency:

I am a resident of California and I reside at the address shown above. If I become a nonresident at any time, I will promptly notify the withholding agent. See instructions for General Information D, Definitions.

Payee’s signature ▶ Date ______________________
□ Corporations:

The corporation has a permanent place of business in California at the address shown above or is qualified through the California Secretary of State (SOS) to do business in California. The corporation will file a California tax return. If this corporation ceases to have a permanent place of business in California or ceases to do any of the above, I will promptly notify the withholding agent. See instructions for General Information D, Definitions. □ Partnerships or Limited Liability Companies (LLCs):

The partnership or LLC has a permanent place of business in California at the address shown above or is registered with the California SOS, and is subject to the laws of California. The partnership or LLC will file a California tax return. If the partnership or LLC ceases to do any of the above, I will promptly inform the withholding agent. For withholding purposes, a limited liability partnership (LLP) is treated like any other partnership. □ Insurance Companies, Individual Retirement Arrangements (IRAs), or Qualified Pension/Profit-Sharing Plans:

The entity is an insurance company, IRA, or a federally qualified pension or profit-sharing plan. □ California Trusts:

At least one trustee and one noncontingent beneficiary of the above-named trust is a California resident. The trust will file a California fiduciary tax return. If the trustee or noncontingent beneficiary becomes a nonresident at any time, I will promptly notify the withholding agent.
□ Estates — Certification of Residency of Deceased Person:

I am the executor of the above-named person’s estate or trust. The decedent was a California resident at the time of death.

The estate will file a California fiduciary tax return. □ Nonmilitary Spouse of a Military Servicemember:

I am a nonmilitary spouse of a military servicemember and I meet the Military Spouse Residency Relief Act (MSRRA) requirements. See instructions for General Information E, MSRRA. □ Tax-Exempt Entities:

The entity is exempt from tax under California Revenue and Taxation Code (R&TC) Section 23701 ______ Internal Revenue Code Section 501(c) _____
the withholding agent. Individuals cannot be tax-exempt entities. (insert letter) or
(insert number). If this entity ceases to be exempt from tax, I will promptly notify Wood Rodgers, Inc.

Wood Rodgers, Inc.
✔
91-1762478
3301 C Street, Bldg 100B
Sacramento
CA
95816
✔

@BCL@9C1BA199, Rev. 09/09/2020
RESOLUTION NO. 2022-

Adopted by the Sacramento City Council

December 13, 2022

Trash Full Capture System Design

BACKGROUND
A. The State Water Resource Control Board adopted statewide Trash Provisions to address the impacts of trash on the beneficial uses of surface waters. As a result, the Central Valley Regional Water Quality Control Board issued a Water Code Section 13383 Order to implement the Trash Provisions. The Trash Provisions required the City of Sacramento as a Phase 1 Municipal Separate Storm Sewer System (MS4) permittee to select a method of compliance to the trash prohibition for Priority Land Uses (PLUs).

The City of Sacramento (City) prepared a Track 2 Trash Implementation Plan to meet the requirements of the Order, which was submitted in November 2018 to the Central Valley Water Board. Per the Trash Provisions, the City must achieve Full Capture System Equivalency by 2030.

The City has elected to install State-certified Full Capture Systems (FCS) that capture trash down to 5 millimeters in size for 1-hour, 1-year storm events in areas where it was feasible for installation and maintenance and within drainage areas with the high trash loads identified through the baseline trash surveys. City Staff has reviewed the baseline trash survey results to determine which drainage areas with high potential for trash load reduction are suitable for the installation of State-certified FCS devices. Three preferred project locations were identified by City Staff as being feasible for siting of large capacity FCS devices that meet the City’s priorities.

B. To meet the requirements of the order, professional design and engineering services are required to site, design, model, permit, and develop construction plans for the three large capacity FCS devices. The City does not have the expertise and experience to develop FCS devices and adequately model the impacts to the City’s existing storm drainage conveyance systems.

C. City Council approval is required to authorize execution of agreements for professional services of $250,000 or more.

D. A budget augmentation of $600,000 is required to transfer $200,000 from the NPDES Stormwater Program MYOP (I14010200, Fund 6011) and $400,000 from the Base CIP Contingency-Drainage Program (W14000200, Fund 6011) for the Trash Full Capture System Design project.

@BCL@9C1BA199, Rev. 09/09/2020

BASED ON THE FACTS SET FORTH IN THE BACKGROUND, THE CITY COUNCIL RESOLVES AS FOLLOWS:

Section 1. The City Manager or the City Manager’s designee is authorized to execute a contract with Wood Rodgers, Inc. for Trash Full Capture System Design for an amount not–to-exceed $585,829.

Section 2. The City Manager or the City Manager’s designee is authorized to transfer $200,000 from the NPDES Stormwater Program MYOP (I14010200, Fund 6011) and $400,000 from the Base CIP Contingency-Drainage Program (W14000200, Fund 6011) to the Drainage Trash Capture Program (W14230100, Fund 6011).

Adopted by the City of Sacramento City Council on December 16, 2022, by the following vote:

Ayes:

Noes:

Abstain:

Absent:

Attest:

The presence of an electronic signature certifies that the foregoing is a true and correct copy as approved by the Sacramento City Council.