File ID: 2023-00421 5/9/2023 Consent Item 4.
Supplemental Agreement and Budgetary Adjustments: Richards Boulevard/ I-5 Interchange (T15165100)
File ID: 2023-00421
Location: District 4, Represented by Councilmember Valenzuela; District 4, Represented by Mayor Steinberg
Recommendation: Adopt a Resolution : 1) authorizing the City Manager or the City Manager’s designee to execute Supplemental Agreement No. 12 to City Agreement No. 2019-0042 with WSP USA for an amount not to exceed $211,962, for a new not-to-exceed amount of $3,948,627; 2) authorizing the City Manager or the City Manager’s designee to execute Amendment No. 5 to the New Measure A Capital Project Allocation and Expenditure Contract with the Sacramento Transportation Authority; 3) authorizing the City Manager or City Manager’s designee to increase the revenue and expenditure budget of the Richards Boulevard/I-5 Interchange project (T15165100) by $1,615,862 (New Measure A Capital, Fund 2023) and decrease the revenue and expenditure budget of the Cosumnes River Boulevard /I-5 Interchange and Extension Project (T15018000) by $1,615,862 (New Measure A Capital, Fund 2023); and 4) resetting the City Manager’s authority to issue Supplemental Agreements for City Agreement No. 2019-0042.
Contact: William Shunk, Senior Engineer , (916) 808-2986, [email protected]; Ofelia Avalos, Engineering Services Manager, (916) 808-5054, [email protected], Department of Public Works
Presenter: None.
Attachments:
1-Description/Analysis
2-Resolution
3-Supplemental Agreement No. 12 - WSP
4-Amendment 5 to New Measure A Capital Project Allocation and Expenditure Contract
File ID: 2023-00421 5/9/2023 Consent Item 4.
Additional Description/Analysis
Issue Detail: The Richards Boulevard/I-5 Interchange provides primary access to the Railyards and River District areas from Interstate 5. Development consistent with the adopted Specific Plans for these areas will add a significant number of higher density housing, retail, entertainment venues, a hospital, and businesses, resulting in a substantial increase of traffic in the area even though these areas will be well served by transit and are located adjacent to the urban core. The Richards Boulevard/I-5 interchange ramps currently operate at deficient levels, as indicated by lengthy traffic queues onto mainline Interstate 5 and Richards Boulevard during peak hours. The situation will continue to degrade as development occurs in the area unless improvements are made to the interchange.
On January 8, 2019, a professional services agreement was executed with WSP USA (City Agreement 2019-0042) to provide professional services to complete preliminary engineering and environmental documentation for the Richards Boulevard/ I-5 Interchange project (T15165100) .
The
project is intended to improve existing and anticipated operational deficiencies and provide for better bicycle and pedestrian access through the interchange along Richards Boulevard to the waterfront and existing trails. Without the improvements, traffic congestion levels are anticipated to result in gridlock throughout the River District. The preferred alternative for the new interchange was established through community engagement and interagency coordination with Caltrans and the Federal Highway Administration (FHWA). The proposed improvements are available for viewing online at
<http://www.cityofsacramento.org/Public-Works/Engineering-Services/Projects/Current- Projects/Interstate-5-Richards-Boulevard-Interchange-Project>.
As a federally-funded project on the Interstate Highway System, Caltrans is assigned to provide National Environmental Policy Act (NEPA) oversight. Caltrans’ technical staff has directed the City to modify the level of NEPA clearance from a Categorical Exclusion (CE) to an Environmental Assessment (EA) given the complexity of the project. This level of environmental documentation effort was not included in the original professional services agreement and requires a supplemental agreement for the increase in scope of services.
The Richards Boulevard/I-5 Interchange Project (T15165100) and the Cosumnes River Boulevard / I -5 Interchange and Extension Project (T15018000) were both included as capital projects identified in the Measure A countywide transportation sales tax ballot measure approved by voters in 2004.
The Measure A capital plan provides partial funding towards specific large capital projects. The City completed the Cosumnes River Boulevard project several years ago and was able to save $1,615,862 in Measure A funding to reallocate to the Richards Boulevard/I-5 project. On March 9, 2023, the STA Board approved an amendment to the New Measure A Capital Project Allocation and Expenditure contract (City Agreement No. 2015-1737) to reflect this the transfer and make the funding available to the Richards Boulevard/I-5 Interchange project.
Policy Considerations: The project is consistent with the City General Plan goals and key policies of providing a comprehensive transportation system that supports the social, economic, and environmental vision, goals, and objectives of the City that is effectively planned, funded, managed, operated, and maintained. The project promotes improved level of service operations at the Richards Boulevard/I-5 Interchange (General Plan M1.2.2), cooperation with Caltrans to address cumulative effects of planned development on the freeway system (General Plan M1.5.7), and the
File ID: 2023-00421 5/9/2023 Consent Item 4.
maintenance of transportation facilities to preserve the quality of the system (General Plan M1.1.4).
This project is also included in the River District Specific Plan and the Railyards Specific Plan.
Economic Impacts: None.
Environmental Considerations:
California Environmental Quality Act (CEQA ): The proposed actions to increase budget and amend contracts are administrative activities and are therefore not a project as defined in CEQA per CEQA Guidelines section 15378(b)(2). The Richards Boulevard/I-5 Interchange project (T15165100) is currently under environmental review and is anticipating an Initial Study - Mitigated Negative Declaration (IS-MND) for CEQA and an Environmental Assessment - Finding of no Significant Impact (EA - FONSI) for NEPA. WSP USA is preparing a joint CEQA/NEPA environmental document per Caltrans guidelines.
Sustainability: The project supports development of higher density infill and transit-oriented development in the Railyards and River District Specific Plans, and therefore supports development that uses less land, is located near the urban center, and will result in reduced per-capita vehicle miles travelled (VMT), allowing the City to accommodate new growth in a more sustainable manner.
Commission/Committee Action: The project was presented to the Disability Advisory Committee on March 3, 2021. They supported the project but had some minor comments on ADA-accessibility which have been incorporated in the preliminary design.
Rationale for Recommendation: While preparing environmental technical studies for the project, Caltrans Headquarters staff directed the City to prepare a publicly circulated Environmental Assessment instead of a NEPA Categorical Exclusion as originally scoped. Approval of Supplemental Agreement No. 12 is needed to include the additional scope of services as part of the Project Approval and Environmental Document (PA&ED) phase of the project.
Approval of the amendment to the New Measure A Capital Project Allocation and Expenditure contract (City Agreement No. 2015-1737) allows for savings in Measure A funds from the Cosumnes River Boulevard Extension project to be transferred to the Richards Boulevard/I-5 Interchange project.
Financial Considerations: At this time, the City has only obtained full funding for the planning and environmental phase of the Richards Boulevard/ I-5 Interchange (T15165100). The total estimated cost for this phase is approximately $6.2 million. The proposed budgetary actions will provide an additional $1,615,862 (New Measure A Capital, Fund 2023). There is sufficient funding within the Richards Boulevard/I-5 Interchange Project to execute Supplemental Agreement No. 12 with WSP USA for $211,962 for a new not-to-exceed amount of $3,948,627, complete this phase of work, and support the design phase if the City is awarded design funds through a pending grant application with the Sacramento Area Council of Governments (SACOG).
File ID: 2023-00421 5/9/2023 Consent Item 4.
Full funding for construction of the project has not yet been secured. It is expected that it will require a combination of Measure A funds, development fees, and significant future grant funding.
There are currently no General Funds allocated or planned for this project.
Local Business Enterprise (LBE): This is a federally-funded project so Disadvantaged Business Enterprise (DBE) requirements apply. LBE requirements are held in abeyance.
RESOLUTION NO.
Adopted by the Sacramento City Council
Supplemental Agreement and Budgetary Adjustments:
Richards Boulevard/I-5 Interchange Project (T15165100)
BACKGROUND
A. The Richards Boulevard/I-5 Interchange provides primary access to the Railyards and River District areas from Interstate 5. Operation of the Richards Boulevard/I-5 interchange ramps is currently deficient as indicated by lengthy traffic queues onto mainline Interstate 5 and Richards Boulevard during peak hours.
B. On January 8, 2019, a professional services agreement was executed with WSP USA (City Agreement 2019-0042) to provide professional services to complete preliminary engineering and environmental documentation for the Richards Boulevard/I-5 Interchange Project (T15165100). The project will improve existing and anticipated operational deficiencies and provide for better bicycle and pedestrian access through the interchange along Richards Boulevard and Jibboom Street to the waterfront and trails. Without the project the congestion levels are anticipated to result in gridlock throughout the River District. The project team is developing the preferred alternative through community and agency coordination with Caltrans and the Federal Highways Administration.
C. This is a Federal-Aid project on the Interstate Highway System. As the assigned National Environmental Policy Act (NEPA) oversight agency, Caltrans, through technical staff review, has directed the City to modify the level of National Environmental Policy Act (NEPA) clearance from a Categorical Exclusion (CE) to an Environmental Assessment (EA) given the complexity of the project. This level of environmental work was not included in the original agreement and requires a supplemental agreement.
D. The Richards Boulevard/I-5 Interchange Project and the Cosumnes River Boulevard / I-5 Interchange and Extension project (T15018000) were both included as capital projects in the Measure A countywide sales tax ballot measure approved by voters in 2004. The Cosumnes River Boulevard / I-5 Interchange and Extension project is complete with a savings of $1,615,862 in Measure A funding. On March 9, 2023, the Sacramento Transportation Authority (STA) Board approved the fifth amendment to the New Measure A Capital Project Allocation and Expenditure contract (City Agreement No. 2015-1737) to authorize the transfer of this funding to the Richards Boulevard/I-5 Interchange project.
BASED ON THE FACTS SET FORTH IN THE BACKGROUND, THE CITY COUNCIL RESOLVES AS FOLLOWS:
Section 1. The City Manager or the City Manager’s designee is authorized to execute Supplemental Agreement No. 12 to City Agreement No. 2019- 0042 with WSP USA for an amount not to exceed $211,962, for a new not-to-exceed amount of $3,948,627.
Section 2. The City Manager or the City Manager’s designee is authorized to execute the fifth amendment to the Sacramento Transportation Authority New Measure A Capital Project Allocation and Expenditure Contract, City Agreement No. 2015-1737.
Section 3. The City Manager or the City Manager’s designee is authorized to increase the revenue and expenditure budget of the Richards Boulevard/I-5 Interchange project (T15165100) by $1,615,862 (Measure A Capital, Fund 2023) and decrease the revenue and expense budget of the Cosumnes River Boulevard /I-5 Interchange and Extension Project (T15018000) by $1,615,862 (Measure A Capital, Fund 2023).
Section 4. Administrative authority to issue supplemental agreements for City Agreement No. 2019-0042 is reset.
AMENDMENT OF THE AUGUST 27, 2015
CAPITAL PROJECT ALLOCATION AND EXPENDITURE CONTRACT
BETWEEN THE SACRAMENTO TRANSPORTATION AUTHORITY
AND THE CITY OF SACRAMENTO REGARDING THE
DOWNTOWN INTERMODAL STATION (II/III) AND THE RICHARDS
BOULEVARD/INTERSTATE 5 INTERCHANGE PROJECTS
THIS FIFTH AMENDMENT TO SACRAMENTO TRANSPORTATION AUTHORITY NEW MEASURE A CAPITAL PROJECT ALLOCATION AND EXPENDITURE CONTRACT is made and entered into this 9th day of March 2023, by and between the SACRAMENTO TRANSPORTATION AUTHORITY, a local transportation authority formed pursuant to the provisions of Public Utilities Code section 180000, et seq. (hereinafter referred to as “AUTHORITY”), and the CITY OF SACRAMENTO, a municipal corporation (hereinafter referred to as “ENTITY”).
RECITALS
WHEREAS, in 2004, the electors of Sacramento County approved, by two-thirds vote, sales tax Measure ‘A’ and Authority Ordinance No. 04-01 (“Measure A Ordinance”); and WHEREAS, the Measure A Ordinance includes the “Sacramento County Transportation Expenditure Plan 2009–2039” (“Expenditure Plan”); and
WHEREAS, the Expenditure Plan includes the following two capital improvement projects: Downtown Intermodal Station and Richards Boulevard/Interstate 5 Interchange (“Project”); and
WHEREAS, AUTHORITY and ENTITY are parties to that certain Capital Project Allocation and Expenditure Contract for the Project (“Contract”) dated August 27, 2015; and WHEREAS, AUTHORITY took action to allocate $1,615,862 in savings from the Capital Project Allocation And Expenditure Contract for the Cosumnes River Blvd Extension to the to the Richards Blvd / I-5 Interchange project, but no formal contract amendment was processed at that time; and
WHEREAS, Section 4 of the Contract requires that ENTITY expend its capital allocation prior to June 30, 2018; and
WHEREAS, AUTHORITY and ENTITY, on June 14, 2018, amended Contract by adding an additional twelve (12) months to the length of the term to June 30, 2019; and WHEREAS, AUTHORITY and ENTITY, on May 9, 2019, amended Contract by adding an additional twelve (12) months to the length of the term to June 30, 2020; and Contract Amendment No. 5 March 9, 2023
Sacramento Transportation Authority/City of Sacramento Page 2 WHEREAS, AUTHORITY and ENTITY, on May 14, 2020, amended Contract by adding an additional twelve (12) months to the length of the term to June 30, 2021: and WHEREAS, AUTHORITY and ENTITY, on March 11, 2021, amended Contract by adding an additional thirty-six (36) months to the length of the term to June 30, 2024: and WHEREAS, ENTITY requires additional time to expend the funds allocated in the Contract on eligible Project costs.
NOW, THEREFORE, in consideration of the conditions herein contained, AUTHORITY and ENTITY do hereby agree to amend the Contract as follows:
AGREEMENT
1. Section 4 of the Contract is amended to add an additional thirty-six (36) months to the length of the term, thereby changing the end date of the Period of Expenditure to June 30, 2027; and
2. Section 4 of the Contract is amended to specifically allocate project funding as follows:
$19,823,000 for the Downtown Intermodal Station (II/III) and $1,500,000 for Richards Blvd / I-5 Interchange; and
3. Section 4 of the Contract is further amended to add an additional $1,615,862 for the Richards Boulevard / I-5 Interchange, thereby changing the maximum sum of expenditure to $3,115,862 for the Richards Boulevard / I-5 Interchange Project; and
4. All other terms and conditions not changed by this Amendment remain in full force and effect.
Contract Amendment No. 5 March 9, 2023
Sacramento Transportation Authority/City of Sacramento Page 3 IN WITNESS THEREOF, the parties hereto have executed this Amendment as of the date indicated below.
CITY OF SACRAMENTO SACRAMENTO TRANSPORTATION
AUTHORITY
Authorized Signature Kevin Bewsey
Executive Director
Printed Name and Title
Date Date